CN108533315A - A kind of percolating water ejectment structure and construction method for wall in tunnel, tunnel - Google Patents

A kind of percolating water ejectment structure and construction method for wall in tunnel, tunnel Download PDF

Info

Publication number
CN108533315A
CN108533315A CN201810343649.1A CN201810343649A CN108533315A CN 108533315 A CN108533315 A CN 108533315A CN 201810343649 A CN201810343649 A CN 201810343649A CN 108533315 A CN108533315 A CN 108533315A
Authority
CN
China
Prior art keywords
tunnel
percolating water
wall
gutter
longitudinal
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810343649.1A
Other languages
Chinese (zh)
Inventor
付大喜
阮锦楼
安枫垒
阮飞鹏
郭炎伟
曹文文
张奇
赵慧勇
齐强
卫涛
胡晓伟
伍冬
张百岁
李浩彬
祁得运
孙玉辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Henan Provincial Communication Planning and Design Institute Co Ltd
Original Assignee
Henan Provincial Communication Planning and Design Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Henan Provincial Communication Planning and Design Institute Co Ltd filed Critical Henan Provincial Communication Planning and Design Institute Co Ltd
Priority to CN201810343649.1A priority Critical patent/CN108533315A/en
Publication of CN108533315A publication Critical patent/CN108533315A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F16/00Drainage
    • E21F16/02Drainage of tunnels

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention discloses a kind of percolating water ejectment structures and construction method for wall in tunnel, tunnel, belong to municipal works city tunnel structure design and technical field of construction, it is therefore intended that solve the problems, such as that existing tunnel percolating water by effective Path-collection and cannot be discharged into the drainage system in tunnel.The percolating water ejectment structure of middle wall is included in the longitudinal receipts ditch being arranged at the top of anticollision kerbstone, and anticollision kerbstone outer surface is provided with several drain measure ditches, longitudinal flat stone gutter is provided on the flat stone by anticollision kerbstone bottom.The percolating water ejectment structure of side wall is included in maintaining roadway bottom and is provided with the plain concrete with cross fall and slope aspect gutter, and maintaining roadway is embedded with several transverse drains consistent with the plain concrete cross fall of maintaining roadway bottom and slope aspect gutter with gutter adjacent wall.The invention also includes the construction methods of above-mentioned percolating water ejectment structure.The percolating water ejectment structure and construction method of present invention wall suitable for tunnel, tunnel.

Description

A kind of percolating water ejectment structure and construction method for wall in tunnel, tunnel
Technical field
The invention belongs to municipal works city tunnel structure design and technical field of construction, and in particular to one kind being used for tunnel The percolating water ejectment structure and construction method of wall in road, tunnel.
Background technology
City tunnel can effectively improve road passage capability, alleviate urban traffic pressure, and than elevated bridge occupied space Less, small to the influence of environment.With the utilization of urban underground space, the underground trend increasingly significant of means of transportation, city City tunnel will more enter people’s lives.
Although the design and construction technology of city tunnel are more ripe, anti-row's problem of tunnel structure percolating water is still It is the emphasis and difficult point in design and construction.Tunnel structure waterproof system include concrete structure self-waterproofing, outer waterproofing layer and The thin portions water proof structure such as deformation joint, construction joint, wall pipe, built-in fitting.Although all taking much count of tunnel in overall process of designing and constructing Waterproof and water drainage system, but percolating water phenomenon or inevitable, all possible generation in the positions such as waterproof layer, detail structure in Practical Project Different degrees of percolating water.
Tunnel structure percolating water causes humid environment in tunnel, shortens the service life of tunnel auxiliary facility, increases and safeguards Expense.Percolating water can lead to concrete structure damage, road surface large area ponding in tunnel when serious, not only influence traffic safety, The service life of structure can also be reduced.
City tunnel generally uses armored concrete single hole or multiple box culvert structure, and box culvert structure is by top plate and bottom plate, side wall And middle wall (multiple box culvert) composition.Along the longitudinally disposed maintaining roadway in tunnel and gutter, the bottoms Zhong Qiang are vertical along tunnel for side wall bottom To setting anticollision kerbstone.Fig. 1 show typical diplopore box culvert structure cross section.
At present in engineering, common anticollision kerbstone and flat stone (A drawings), maintaining roadway and gutter (B drawings) As shown in Figure 2 and Figure 3.When percolating water occurs for the detail structures such as tunnel structure waterproof layer, deformation joint, therefrom wall flows down meeting to percolating water It covers anticollision kerbstone A1 to arrange to tunnel road surface by flat stone A2, then is discharged into the longitudinal drainage gutter in tunnel by acclive road surface In B2, drainage pattern inorganization is random;Percolating water is flowed down from side wall to be directly discharged into maintaining roadway by maintaining roadway B1 cover board holes In B1, maintaining roadway internal water accumulation, no exclusion channel are caused.The percolating water of middle wall and side wall cannot be by effective Path-collection side by side Enter in the drainage system in tunnel, influence appearance quality inside and outside tunnel, may bring traffic safety hidden danger, therefore, timely and effectively arrange Except the percolating water in tunnel is very necessary.
Invention content
It is an object of the invention to:A kind of percolating water ejectment structure for wall in tunnel, tunnel is provided, existing tunnel is solved Road percolating water cannot be by effective Path-collection and the problem of be discharged into the drainage system in tunnel.
Another object of the present invention is to:A kind of percolating water ejectment structure construction side for wall in tunnel, tunnel is provided Method.
The technical solution adopted by the present invention is as follows:
A kind of percolating water ejectment structure for wall in tunnel includes along length of tunnel direction and being arranged in the bottoms Zhong Qiang Anticollision kerbstone is provided with flat stone by anticollision kerbstone, be provided at the top of anticollision kerbstone it is longitudinal receive ditch, it is longitudinal to receive ditch longitudinal slope and tunnel Road longitudinal slope is consistent, and anticollision kerbstone outer surface is provided with several drain measure ditches, is provided on the flat stone by anticollision kerbstone bottom Longitudinal flat stone gutter, longitudinal flat stone gutter longitudinal slope are consistent with tunnel longitudinal slope.
Further, it is divided into 10m between adjacent two sections of drain measure ditches.
Further, drain measure ditch is the semicircle drain measure ditch that radius is 25mm.
Further, longitudinal ditch of receiving is the longitudinal receipts ditch of semicircle that radius is 25mm.
Further, longitudinal flat stone gutter is the longitudinal flat stone gutter of semicircle that radius is 50mm.
A kind of percolating water ejectment construction method for wall in tunnel includes the following steps:
S1, wall in integrated cast structure, in the structure wall and the pre-buried water-swelling rubber water bar in joint at the top of anticollision kerbstone;
Wall in structure is in contact part dabbing by S2 with anticollision kerbstone side, surface layer brushing cement-base infiltration crystallization waterproof Agent;
S3, the binding of anticollision kerbstone reinforcing bar and formwork erection;
When formwork erection, the semicircle drain measure that radius is 25mm is reserved in anticollision kerbstone outer surface every 10m by S4 Ditch, segmentation pour anticollision kerbstone concrete;
S5 waits for anticollision kerbstone concrete initial set, and the pipe discharge by pressing radius for being 25mm with radius at the top of anticollision kerbstone is The semicircle of 25mm is longitudinal to receive ditch;
S6, after anticollision kerbstone concrete reaches intensity, form removal, external coating cement-base infiltration crystallization type water-proof Agent;
S7 after the completion of pavement structure pavement construction, paves the longitudinal flat stone gutter of the semicircle that reserved radius is 50mm.
A kind of percolating water ejectment structure for tunnel, including the percolating water ejectment structure of middle wall and the percolating water of side wall draw Structure is arranged, the percolating water ejectment structure of the middle wall is the leak ejectment knot that the middle wall described in any one of claim 1-5 oozes Structure, the percolating water ejectment structure of the side wall include being set to the maintaining roadway of side wall bottom, and maintaining roadway is also set far from side wall side It is equipped with gutter, maintaining roadway bottom is provided with the plain concrete with cross fall and slope aspect gutter, maintaining roadway and row Waterside ditch adjacent wall is embedded with several consistent with the plain concrete cross fall of maintaining roadway bottom and slope aspect gutter cross To drainpipe B4.
Further, plain concrete is C15 plain concretes, and the minimum thickness of plain concrete is 100mm, the cross of plain concrete It is 2% to the gradient.
Further, it is divided into 10m between adjacent two transverse drains.
A kind of percolating water ejectment construction method for tunnel includes the percolating water ejectment construction method of middle wall Percolating water ejectment construction method with the percolating water ejectment construction method of side wall, the middle wall is claim 6 institute The percolating water ejectment construction method of the percolating water ejectment construction method for the middle wall stated, the side wall includes following step Suddenly:
S'1 backfills C15 plain concretes, the minimum thickness 100mm of plain concrete, plain concrete transverse direction in maintaining roadway bottom The gradient 2%, plain concrete slope aspect gutter;
S'2, every 10m in maintaining roadway and gutter adjacent wall bar-mat reinforcement pre-buried installation diameter 50mmPVC materials Transverse drain, transverse drain cross fall 2%, transverse drain slope aspect gutter;
S'3, supporting module pour maintaining roadway and gutter side wall concrete;
S'4, after waiting for that concrete reaches intensity, form removal, maintaining roadway and gutter inner surface brushing cement base are oozed Saturating crystalline waterproofing agent.
In conclusion by adopting the above-described technical solution, the beneficial effects of the invention are as follows:
1, in the present invention, the percolating water ejectment structure of wall in tunnel is provided with longitudinal receipts ditch A3 at the top of anticollision kerbstone, It is provided with drain measure ditch A4 in anticollision kerbstone outer surface, longitudinal flat stone draining is provided on the flat stone of anticollision kerbstone bottom The percolating water of wall in tunnel can be collected by specific path and is discharged into the drainage system in tunnel by ditch A5, anticollision kerbstone Longitudinal ditch A3 that receives at top collects percolating water, and longitudinal receipts ditch A3 longitudinal slopes are consistent with tunnel longitudinal slope, and the percolating water of collection passes through The reserved drain measure ditch A4 of anticollision kerbstone outer surface is flowed into the flat stone gutter A5 in longitudinal direction adjacent with anticollision kerbstone bottom, Longitudinal flat stone gutter A5 longitudinal slopes are consistent with tunnel longitudinal slope, and the percolating water in longitudinal flat stone gutter A5 is discharged into tunnel with tunnel longitudinal slope In the transversal ditch of road minimum point or the inspection shaft of pre-buried transverse drain, and then it is discharged into tunnel drainage system.Tunnel Zhong Qiang Percolating water ejectment structure design it is simple, percolating water by effective Path-collection and can be discharged into the drainage system in tunnel, it is real The application of border engineering is strong.And pre-buried a large amount of drainpipe ejectment percolating water, construction need not be easier under road surface, cost is more Economy, repair are more convenient.
2, in the present invention, the percolating water ejectment structure of tunnel sidewalls, element of the bottoms the maintaining roadway B1 backfill with cross fall Concrete B3 forms difference in height with gutter bottom, and maintaining roadway cover board hole collects percolating water, then passes through maintaining roadway and draining side Percolating water of the siltation in maintaining roadway can be effectively discharged, by percolating water in the transverse drain B4 being arranged on ditch adjacent wall It has been directly discharged into tunnel drainage gutter, then has been discharged into the transversal ditch of tunnel minimum point or the inspection shaft of pre-buried transverse drain, into And it is discharged into tunnel drainage system.The percolating water ejectment structure design of the tunnel sidewalls is simpler, can be by percolating water by effective Path-collection is simultaneously discharged into the drainage system in tunnel, and the application of Practical Project is strong.And it constructs and is easier, cost is more economical, Repair is more convenient.
Description of the drawings
Fig. 1 is typical diplopore box culvert structure cross-sectional view;
Fig. 2 is common anticollision kerbstone and flat stone figure;
Fig. 3 is common maintaining roadway and gutter figure;
Fig. 4 is the anticollision kerbstone of the present invention and flat stone figure;
Fig. 5 is the maintaining roadway and gutter figure of the present invention;
It is marked in figure:Wall in wall, 5- top plates finishing layer, 6- side walls finishing layer, 7- in 1- top plates, 2- bottom plates, 3- side walls, 4- Fit up layer, 8- pavement structures, A- anticollisions kerbstone and flat stone, A1- anticollisions kerbstone, the flat stones of A2-, A3- longitudinally receipts ditch, A4- water conservancy diversion Gutter, the flat stone gutters A5-, A6- water-swelling rubber water bars, B- maintaining roadways and gutter, B1- maintaining roadways, B2- Gutter, B3- plain concretes, B4- transverse drains.
Specific implementation mode
In order to make the purpose , technical scheme and advantage of the present invention be clearer, with reference to the accompanying drawings and embodiments, right The present invention is further elaborated.It should be appreciated that described herein, specific examples are only used to explain the present invention, not For limiting the present invention.
A kind of percolating water ejectment structure for wall in tunnel includes along length of tunnel direction and being arranged in the bottoms Zhong Qiang It is provided with flat stone A2 by anticollision kerbstone A1, anticollision kerbstone A1, longitudinal receipts ditch A3 is provided at the top of anticollision kerbstone A1, it is longitudinal to receive water Ditch A3 longitudinal slopes are consistent with tunnel longitudinal slope, and anticollision kerbstone A1 outer surfaces are provided with several drain measure ditch A4, the bottoms anticollision kerbstone A1 Longitudinal flat stone gutter A5 is provided on the flat stone A2 of radical, longitudinal flat stone gutter A5 longitudinal slopes are consistent with tunnel longitudinal slope.
Further, it is divided into 10m between adjacent two sections of drain measure ditches A4.
Further, drain measure ditch A4 is the semicircle drain measure ditch A4 that radius is 25mm.
Further, longitudinal ditch A3 that receives is the longitudinal receipts ditch A3 of semicircle that radius is 25mm.
Further, longitudinal flat stone gutter A5 is the longitudinal flat stone gutter A5 of semicircle that radius is 50mm.
A kind of percolating water ejectment construction method for wall in tunnel includes the following steps:
S1, wall in integrated cast structure, in the structure wall and the pre-buried hydro-expansive rubber sealing in joint at the top of anticollision kerbstone A1 A6;
Wall in structure is in contact part dabbing by S2 with the sides anticollision kerbstone A1, and brushing cement-base infiltration crystallization in surface layer is anti- Aqua;
S3, the binding of anticollision kerbstone A1 reinforcing bars and formwork erection;
S4 when formwork erection, reserves the semicircle water conservancy diversion that radius is 25mm every 10m in anticollision kerbstone A1 outer surfaces and arranges Ditch A4, segmentation pour anticollision kerbstone A1 concrete;
S5 waits for anticollision kerbstone A1 concrete initial sets, the pipe discharge by pressing half for being 25mm with radius at the top of anticollision kerbstone A1 The longitudinal receipts ditch A3 of semicircle that diameter is 25mm;
S6, after anticollision kerbstone concrete reaches intensity, form removal, external coating cement-base infiltration crystallization type water-proof Agent;
S7 after the completion of pavement structure pavement construction, paves the longitudinal flat stone gutter of the semicircle that reserved radius is 50mm.
A kind of percolating water ejectment structure for tunnel, including the percolating water ejectment structure of middle wall and the percolating water of side wall draw Structure is arranged, the percolating water ejectment structure of the middle wall is the leak ejectment knot that the middle wall described in any one of claim 1-5 oozes Structure, the percolating water ejectment structure of the side wall include being set to the maintaining roadway of side wall bottom, and maintaining roadway is also set far from side wall side It is equipped with gutter, the bottoms maintaining roadway B1 are provided with the plain concrete B3 with cross fall and slope aspect gutter, maintaining roadway B1 is embedded with several consistent with the plain concrete B3 cross falls of maintaining roadway bottom and slope aspect with gutter adjacent wall and drains The transverse drain B4 of gutter.
Further, plain concrete is C15 plain concretes, and the minimum thickness of plain concrete is 100mm, the cross of plain concrete It is 2% to the gradient.
Further, it is divided into 10m between adjacent two transverse drains.
A kind of percolating water ejectment construction method for tunnel includes the percolating water ejectment construction method of middle wall Percolating water ejectment construction method with the percolating water ejectment construction method of side wall, the middle wall is claim 6 institute The percolating water ejectment construction method of the percolating water ejectment construction method for the middle wall stated, the side wall includes following step Suddenly:
S'1 backfills C15 plain concretes, the minimum thickness 100mm of plain concrete, plain concrete transverse direction in maintaining roadway bottom The gradient 2%, plain concrete slope aspect gutter;
S'2, every 10m in maintaining roadway and gutter adjacent wall bar-mat reinforcement pre-buried installation diameter 50mmPVC materials Transverse drain, transverse drain cross fall 2%, transverse drain slope aspect gutter;
S'3, supporting module pour maintaining roadway and gutter side wall concrete;
S'4, after waiting for that concrete reaches intensity, form removal, maintaining roadway and gutter inner surface brushing cement base are oozed Saturating crystalline waterproofing agent.
Embodiment 1
A kind of percolating water ejectment structure for wall in tunnel includes along length of tunnel direction and being arranged in the bottoms Zhong Qiang It is provided with flat stone by anticollision kerbstone A1, anticollision kerbstone A1, longitudinal receipts ditch A3 is provided at the top of anticollision kerbstone A1, it is longitudinal to receive ditch A3 longitudinal slopes are consistent with tunnel longitudinal slope, and anticollision kerbstone A1 outer surfaces are provided with several drain measure ditch A4, the bottoms anticollision kerbstone A1 Longitudinal flat stone gutter A5 is provided on other flat stone, longitudinal flat stone gutter A5 longitudinal slopes are consistent with tunnel longitudinal slope.Adjacent two sections It is divided into 10m between drain measure ditch.Drain measure ditch is the semicircle drain measure ditch that radius is 25mm.Longitudinal ditch of receiving is half The longitudinal receipts ditch of semicircle that diameter is 25mm.Longitudinal flat stone gutter is the longitudinal flat stone gutter of semicircle that radius is 50mm. It is provided with longitudinal receipts ditch A3 at the top of anticollision kerbstone A1, drain measure ditch A4 is provided in anticollision kerbstone A1 outer surfaces, It is provided with longitudinal flat stone gutter A5 on the flat stone of the bottoms anticollision kerbstone A1, the percolating water of wall in tunnel can be pressed specific path It is collected and is discharged into the drainage system in tunnel, longitudinal ditch A3 that receives at the top of anticollision kerbstone A1 collects percolating water, Zong Xiangshou Ditch A3 longitudinal slopes are consistent with tunnel longitudinal slope, and the percolating water of collection passes through the reserved drain measure ditch A4 of anticollision kerbstone A1 outer surfaces It flows into the flat stone gutter A5 in longitudinal direction adjacent with the anticollision bottoms kerbstone A1, longitudinal flat stone gutter A5 longitudinal slopes and tunnel longitudinal slope one It causes, the percolating water in longitudinal flat stone gutter A5 is discharged into the transversal ditch of tunnel minimum point or pre-buried transverse drain with tunnel longitudinal slope Inspection shaft in, and then be discharged into tunnel drainage system.The percolating water ejectment structure design of wall is simple in the tunnel, can will leak Water is by effective Path-collection and is discharged into the drainage system in tunnel, and the application of Practical Project is strong.And it need not be under road surface Pre-buried a large amount of drainpipe ejectment percolating water, construction are easier, and cost is more economical, and repair is more convenient.
Embodiment 2
A kind of percolating water ejectment structure for tunnel, including the percolating water ejectment structure of middle wall and the percolating water of side wall draw Structure is arranged, the percolating water ejectment structure of wall in tunnel includes that along length of tunnel direction and anticollision kerbstone in the bottoms Zhong Qiang is arranged Be provided with flat stone by A1, anticollision kerbstone A1, be provided at the top of anticollision kerbstone A1 it is longitudinal receive ditch A3, it is longitudinal receive ditch A3 longitudinal slopes with Tunnel longitudinal slope is consistent, and anticollision kerbstone A1 outer surfaces are provided with several drain measure ditch A4, the flat stone by the bottoms anticollision kerbstone A1 On be provided with longitudinal flat stone gutter A5, longitudinal flat stone gutter A5 longitudinal slopes are consistent with tunnel longitudinal slope.Adjacent two sections of drain measures 10m is divided between ditch.Drain measure ditch is the semicircle drain measure ditch that radius is 25mm.It is 25mm that longitudinal receipts ditch, which is radius, Semicircle longitudinal receive ditch.Longitudinal flat stone gutter is the longitudinal flat stone gutter of semicircle that radius is 50mm.Side wall oozes Leak ejectment structure includes being set to the maintaining roadway of side wall bottom, and maintaining roadway is additionally provided with gutter far from side wall side, inspection Bottoms B1 of cultivating oneself according to a religious doctrine are provided with the plain concrete B3 with cross fall and slope aspect gutter, and maintaining roadway B1 is adjacent with gutter Side wall is embedded with several consistent with the plain concrete B3 cross falls of maintaining roadway bottom and slope aspect gutter transverse drain B4., the percolating water ejectment structure of wall in tunnel, be provided at the top of anticollision kerbstone A1 it is longitudinal receive ditch A3, in anticollision kerbstone A1 Outer surface is provided with drain measure ditch A4, and longitudinal flat stone gutter A5 is provided on the flat stone of the bottoms anticollision kerbstone A1, can The percolating water of wall in tunnel is collected by specific path and is discharged into the drainage system in tunnel, at the top of anticollision kerbstone A1 Longitudinal ditch A3 that receives collects percolating water, and longitudinal receipts ditch A3 longitudinal slopes are consistent with tunnel longitudinal slope, and the percolating water of collection passes through anticollision side The reserved drain measure ditch A4 of stone A1 outer surfaces is flowed into the flat stone gutter A5 in longitudinal direction adjacent with the anticollision bottoms kerbstone A1, Longitudinal flat stone gutter A5 longitudinal slopes are consistent with tunnel longitudinal slope, and the percolating water in longitudinal flat stone gutter A5 is discharged into tunnel with tunnel longitudinal slope In the transversal ditch of road minimum point or the inspection shaft of pre-buried transverse drain, and then it is discharged into tunnel drainage system.Tunnel Zhong Qiang Percolating water ejectment structure design it is simple, percolating water by effective Path-collection and can be discharged into the drainage system in tunnel, it is real The application of border engineering is strong.And pre-buried a large amount of drainpipe ejectment percolating water, construction need not be easier under road surface, cost is more Economy, repair are more convenient.The percolating water ejectment structure of tunnel sidewalls, plain coagulation of the bottoms the maintaining roadway B1 backfill with cross fall Native B3 forms difference in height with gutter bottom, and maintaining roadway cover board hole collects percolating water, then passes through maintaining roadway and gutter phase Percolating water of the siltation in maintaining roadway can be effectively discharged in the transverse drain B4 being arranged on adjacent side wall, and percolating water is direct It has been discharged into tunnel drainage gutter, then has been discharged into the transversal ditch of tunnel minimum point or the inspection shaft of pre-buried transverse drain, Jin Erpai Enter in tunnel drainage system.The percolating water ejectment structure design of the tunnel sidewalls is simpler, can percolating water be pressed effective path It collects and is discharged into the drainage system in tunnel, the application of Practical Project is strong.And it constructs and is easier, cost is more economical, repair It is more convenient.
The foregoing is merely illustrative of the preferred embodiments of the present invention, is not intended to limit the invention, all essences in the present invention All any modification, equivalent and improvement etc., should all be included in the protection scope of the present invention made by within refreshing and principle.

Claims (10)

1. a kind of percolating water ejectment structure for wall in tunnel includes along length of tunnel direction and being arranged in the anti-of the bottoms Zhong Qiang Kerbstone is hit, flat stone is provided with by anticollision kerbstone, which is characterized in that longitudinal receipts ditch is provided at the top of anticollision kerbstone, it is longitudinal to receive water Ditch longitudinal slope is consistent with tunnel longitudinal slope, and anticollision kerbstone outer surface is provided with several drain measure ditches, flat by anticollision kerbstone bottom Longitudinal flat stone gutter is provided on stone, longitudinal flat stone gutter longitudinal slope is consistent with tunnel longitudinal slope.
2. a kind of percolating water ejectment structure for wall in tunnel described in accordance with the claim 1, which is characterized in that adjacent two sections It is divided into 10m between drain measure ditch.
3. a kind of percolating water ejectment structure for wall in tunnel according to claim 2, which is characterized in that drain measure Ditch is the semicircle drain measure ditch that radius is 25mm.
4. a kind of percolating water ejectment structure for wall in tunnel described in accordance with the claim 1, which is characterized in that longitudinal to receive water Ditch is the longitudinal receipts ditch of semicircle that radius is 25mm.
5. a kind of percolating water ejectment structure for wall in tunnel described in accordance with the claim 1, which is characterized in that longitudinal flat stone Gutter is the longitudinal flat stone gutter of semicircle that radius is 50mm.
6. a kind of percolating water ejectment construction method for wall in tunnel, which is characterized in that include the following steps:
S1, wall in integrated cast structure, in the structure wall and the pre-buried water-swelling rubber water bar in joint at the top of anticollision kerbstone;
Wall in structure is in contact part dabbing by S2 with anticollision kerbstone side, surface layer brushing cement-base infiltration crystallization waterproofing agent;
S3, the binding of anticollision kerbstone reinforcing bar and formwork erection;
When formwork erection, the semicircle drain measure ditch that radius is 25mm is reserved in anticollision kerbstone outer surface every 10m by S4, Segmentation pours anticollision kerbstone concrete;
S5 waits for anticollision kerbstone concrete initial set, and the pipe discharge by pressing radius for being 25mm with radius at the top of anticollision kerbstone is 25mm Semicircle longitudinal receive ditch;
S6, after anticollision kerbstone concrete reaches intensity, form removal, external coating cementitious capillary crystalline waterproofing agent;
S7 after the completion of pavement structure pavement construction, paves the longitudinal flat stone gutter of the semicircle that reserved radius is 50mm.
7. a kind of percolating water ejectment structure for tunnel, which is characterized in that percolating water ejectment structure and side wall including middle wall Percolating water ejectment structure, the percolating water ejectment structure of the middle wall is what the middle wall described in any one of claim 1-5 oozed The percolating water ejectment structure of leak ejectment structure, the side wall includes being set to the maintaining roadway of side wall bottom, and maintaining roadway is far from side Wall side is additionally provided with gutter, and maintaining roadway bottom is provided with the plain concrete with cross fall and slope aspect gutter, Maintaining roadway is embedded with several consistent with the plain concrete cross fall of maintaining roadway bottom and slope aspect with gutter adjacent wall and arranges The transverse drain of waterside ditch.
8. a kind of percolating water ejectment structure for tunnel according to claim 7, which is characterized in that plain concrete is The minimum thickness of C15 plain concretes, plain concrete is 100mm, and the cross fall of plain concrete is 2%.
9. a kind of percolating water ejectment structure for tunnel according to claim 7, which is characterized in that adjacent two transverse directions 10m is divided between drainpipe.
10. a kind of percolating water ejectment construction method for tunnel, which is characterized in that the percolating water ejectment knot including middle wall The percolating water ejectment construction method of the percolating water ejectment construction method of structure construction method and side wall, the middle wall is power Profit requires the percolating water ejectment construction method of the middle wall described in 6, the percolating water ejectment construction method packet of the side wall Include following steps:
S'1 backfills C15 plain concretes, the minimum thickness 100mm of plain concrete, plain concrete cross fall in maintaining roadway bottom 2%, plain concrete slope aspect gutter;
S'2, every the cross of 10m pre-buried installation diameter 50mmPVC materials in maintaining roadway and gutter adjacent wall bar-mat reinforcement To drainpipe, transverse drain cross fall 2%, transverse drain slope aspect gutter;
S'3, supporting module pour maintaining roadway and gutter side wall concrete;
S'4, after waiting for that concrete reaches intensity, form removal, maintaining roadway and gutter inner surface brushing cement-based penetrant knot Crystal form waterproofing agent.
CN201810343649.1A 2018-04-17 2018-04-17 A kind of percolating water ejectment structure and construction method for wall in tunnel, tunnel Pending CN108533315A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810343649.1A CN108533315A (en) 2018-04-17 2018-04-17 A kind of percolating water ejectment structure and construction method for wall in tunnel, tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810343649.1A CN108533315A (en) 2018-04-17 2018-04-17 A kind of percolating water ejectment structure and construction method for wall in tunnel, tunnel

Publications (1)

Publication Number Publication Date
CN108533315A true CN108533315A (en) 2018-09-14

Family

ID=63480832

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810343649.1A Pending CN108533315A (en) 2018-04-17 2018-04-17 A kind of percolating water ejectment structure and construction method for wall in tunnel, tunnel

Country Status (1)

Country Link
CN (1) CN108533315A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109989766A (en) * 2019-04-29 2019-07-09 中铁第四勘察设计院集团有限公司 Unidirectional shield tunnel construction with emergency temporary parking hole

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102434175A (en) * 2012-01-12 2012-05-02 中国市政工程西北设计研究院有限公司 Tunnel lining self waterproof drainage system
CN102587938A (en) * 2012-03-16 2012-07-18 郑州市市政工程总公司 Water seepage and leakage preventability collection system for tunnel and construction method of system
CN202493277U (en) * 2012-03-16 2012-10-17 郑州市市政工程总公司 Preventive collecting system for leaking water and seeping water in tunnel
CN204357484U (en) * 2014-12-11 2015-05-27 中铁十一局集团第五工程有限公司 The drainage system of anti-tunnel invert constuction joint infiltration
CN204476470U (en) * 2015-01-20 2015-07-15 山西省交通科学研究院 A kind of waterproof and water drainage system of applicable tunnel project seam
CN104806270A (en) * 2015-05-09 2015-07-29 西安科技大学 Double-arch tunnel modularized middle wall with waterproofing and draining functions and construction method thereof
CN204552818U (en) * 2014-12-11 2015-08-12 中铁十一局集团第五工程有限公司 The drainage system of ditch, side, anti-tunnel bottom leaky
CN208473931U (en) * 2018-04-17 2019-02-05 河南省交通规划设计研究院股份有限公司 A kind of percolating water ejectment structure for tunnel
CN208633870U (en) * 2018-04-17 2019-03-22 河南省交通规划设计研究院股份有限公司 A kind of percolating water ejectment structure for wall in tunnel

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102434175A (en) * 2012-01-12 2012-05-02 中国市政工程西北设计研究院有限公司 Tunnel lining self waterproof drainage system
CN102587938A (en) * 2012-03-16 2012-07-18 郑州市市政工程总公司 Water seepage and leakage preventability collection system for tunnel and construction method of system
CN202493277U (en) * 2012-03-16 2012-10-17 郑州市市政工程总公司 Preventive collecting system for leaking water and seeping water in tunnel
CN204357484U (en) * 2014-12-11 2015-05-27 中铁十一局集团第五工程有限公司 The drainage system of anti-tunnel invert constuction joint infiltration
CN204552818U (en) * 2014-12-11 2015-08-12 中铁十一局集团第五工程有限公司 The drainage system of ditch, side, anti-tunnel bottom leaky
CN204476470U (en) * 2015-01-20 2015-07-15 山西省交通科学研究院 A kind of waterproof and water drainage system of applicable tunnel project seam
CN104806270A (en) * 2015-05-09 2015-07-29 西安科技大学 Double-arch tunnel modularized middle wall with waterproofing and draining functions and construction method thereof
CN208473931U (en) * 2018-04-17 2019-02-05 河南省交通规划设计研究院股份有限公司 A kind of percolating water ejectment structure for tunnel
CN208633870U (en) * 2018-04-17 2019-03-22 河南省交通规划设计研究院股份有限公司 A kind of percolating water ejectment structure for wall in tunnel

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109989766A (en) * 2019-04-29 2019-07-09 中铁第四勘察设计院集团有限公司 Unidirectional shield tunnel construction with emergency temporary parking hole

Similar Documents

Publication Publication Date Title
CN104878783B (en) A kind of Super-long Basement concrete floor deformation joint anti-seepage and method for treating seepage
CN110158650A (en) A kind of underground structure that waterproof and drainage system are set
CN105756100B (en) Basement post-pouring zone system and preparation method thereof
CN108533315A (en) A kind of percolating water ejectment structure and construction method for wall in tunnel, tunnel
CN211972965U (en) Permeable pavement flat kerb drainage system
CN110295630B (en) Multilayer constraint anti-leakage post-pouring belt structure
KR20140098420A (en) Precast concrete protection wall with linear drainage functions and construction method thereof
CN216340909U (en) Novel advanced water stopping device and system for roof post-cast strip of garage
CN109577183A (en) The anti-ponding structure in overhead bridge floor edge and construction
CN208473931U (en) A kind of percolating water ejectment structure for tunnel
CN212153269U (en) Make river course view surface of water silt reducing equipment of installation fast
CN101603299B (en) Broken line type dam joint structure and construction method thereof
CN212153012U (en) Sponge city pavement that permeates water
CN208633870U (en) A kind of percolating water ejectment structure for wall in tunnel
CN207092154U (en) A kind of basement drain plate
CN208633871U (en) A kind of percolating water ejectment structure for tunnel sidewalls
CN110387908A (en) The rear pouring tape construction method of multilayer constraint antiseep
CN216838801U (en) City permeable pavement
CN216809420U (en) Combined type town road
CN220486669U (en) Drainage ditch for desert area
CN217231309U (en) Adopt building rubbish's green road structure
CN215977132U (en) Assembled regeneration waterproof concrete drainage canal mechanism and channel
CN219862984U (en) Tower crane foundation construction joint waterproof construction
CN219886513U (en) Ultra-high section escape canal and curb integration forming die
CN218779259U (en) Lightweight concrete roadbed structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20180914

RJ01 Rejection of invention patent application after publication