CN108518013A - Frame suspended ceiling mounting structure and its mounting means - Google Patents

Frame suspended ceiling mounting structure and its mounting means Download PDF

Info

Publication number
CN108518013A
CN108518013A CN201810572607.5A CN201810572607A CN108518013A CN 108518013 A CN108518013 A CN 108518013A CN 201810572607 A CN201810572607 A CN 201810572607A CN 108518013 A CN108518013 A CN 108518013A
Authority
CN
China
Prior art keywords
frame
angle steel
slotted hole
nut group
bolt
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810572607.5A
Other languages
Chinese (zh)
Inventor
郑波波
周黎明
楼甲
陈建
于红宁
陈宇华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ZHEJIANG SHENMEI DECORATION ENGINEERING Co Ltd
Original Assignee
ZHEJIANG SHENMEI DECORATION ENGINEERING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ZHEJIANG SHENMEI DECORATION ENGINEERING Co Ltd filed Critical ZHEJIANG SHENMEI DECORATION ENGINEERING Co Ltd
Priority to CN201810572607.5A priority Critical patent/CN108518013A/en
Publication of CN108518013A publication Critical patent/CN108518013A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B9/00Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation
    • E04B9/18Means for suspending the supporting construction
    • E04B9/20Means for suspending the supporting construction adjustable
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B9/00Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation
    • E04B9/06Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation characterised by constructional features of the supporting construction, e.g. cross section or material of framework members

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Joining Of Building Structures In Genera (AREA)

Abstract

The invention discloses a kind of frame suspended ceiling mounting structure and its mounting means, including angle steel and frame, the end of the angle steel is welded with load angle steel normal thereto;The second slotted hole is offered on the load angle steel, the first slotted hole is offered on the frame, and the first slotted hole is bolted with the second slotted hole, and bolt lower part passes through the first nut group fixed frame positioned at the first slotted hole both sides;Load angle steel is fixed in bolt top by the second nut group positioned at the second slotted hole both sides;The frame is being equipped with functional hole positioned at the side of the first slotted hole.The present invention was not only easily installed and dismantled, but also was convenient for adjustment frame height, and stability is strong;It ensure that installation accuracy simultaneously, also reduce construction requirement.

Description

Frame suspended ceiling mounting structure and its mounting means
Technical field
The present invention relates to a kind of frame suspended ceiling mounting structure, more particularly to a kind of frame suspended ceiling mounting structure and its installation side Formula.
Background technology
In modem architectural ornament field, especially market, shop decoration or even house ornamentation field, finished product or semi-finished product Frame furred ceiling becomes increasingly common.According to shape-designing, these frames pass through steel wire rope, sunpender, shaped steel(Aluminium section bar)Or The modes such as conversion layer realize roof trim effect.Wherein for there is fixed desired frame furred ceiling, shaped steel is used mostly(Aluminium profiles Material)Suspension fixed form is lifted, and the shaking after installation is prevented.
Traditional shaped steel(Aluminium section bar)Fixed form, by shaped steel(Aluminium section bar)One end is fixed on civil engineering floor, another head end Portion is typically provided upper and lower directions slotted hole, the completion height for adjusting furred ceiling, and finished product or semifinished frame products back are equipped with band cross To the rib of slotted hole, then by bolt by frame and shaped steel(Aluminium section bar)It is fixed, frame furred ceiling is being carried out to complete height tune When section, it is fixed afterwards in place or take certain interim measure to need manually to lift frame, after so that frame height is adjusted in place again It is fixed, finally temporary facility is removed again, and for heavy duty metal frame, to prevent frame caused by answering slotted hole Displacement, need to also be in shaped steel(Aluminium section bar)It is welded with metal ribs fixed position, it is ensured that fixation.Obviously such installation side The installation accuracy of formula diagonal steel requires height, high-strength bolt and welding more to seem conventional mounting mode complexity, construction slowly, and not Convenient for the detachable maintaining in later stage;And bolt is by shearing force, because frame weight is larger so that vertical slotted hole is subjected to displacement change Change, and makes frame run-off the straight.
Invention content
The object of the present invention is to provide a kind of frame suspended ceiling mounting structure and its mounting means.The present invention is both convenient for peace Assembly and disassembly, and it is convenient for adjustment frame height, stability is strong;It ensure that installation accuracy simultaneously, also reduce construction requirement.
Technical scheme of the present invention:A kind of frame suspended ceiling mounting structure, including angle steel and frame, the end weldering of the angle steel It is connected to load angle steel normal thereto;The second slotted hole is offered on the load angle steel, and the first length is offered on the frame Circular hole, the first slotted hole are bolted with the second slotted hole, and bolt lower part passes through positioned at the first of the first slotted hole both sides Nut group fixed frame;Load angle steel is fixed in bolt top by the second nut group positioned at the second slotted hole both sides;The frame Frame is being equipped with functional hole positioned at the side of the first slotted hole.
In above-mentioned frame suspended ceiling mounting structure, second slotted hole and the first slotted hole are phase on same perspective plane Mutually it is vertically arranged.
In frame suspended ceiling mounting structure above-mentioned, the frame is hollow type framework.
In frame suspended ceiling mounting structure above-mentioned, the functional hole is arranged in frame lateral surface and/or medial surface.
In frame suspended ceiling mounting structure above-mentioned, the second nut group and load angle steel and the first nut group and frame Between be equipped with spring shim.
According to the mounting means of frame suspended ceiling mounting structure, it is as follows:
Step 1:Preliminary assembling before being installed;On ground, pacify by bolt by functional hole and using the first nut group activity It is attached on frame so that bolt has up and down adjustment space;
Step 2:Angle steel is fixedly installed on floor straight down according to construction drawing;
Step 3:By frame lifter to required mounting height, the bolt on frame is penetrated on the load angle steel of angle steel bottom end Second slotted hole, and be flexibly connected by the second nut group, frame is hung in realization temporarily;
Step 4:By being finely adjusted the first nut group and the second nut group, frame is adjusted to carry out after equilibrium state tight Gu installation is complete.
In the mounting means of said frame suspended ceiling mounting structure, bolt is movably arranged on frame by the first nut group Afterwards, then on bolt lower position nut in second nut group is installed, realize the peace to the lower position nut in the second nut group Dress.
In the mounting means of said frame suspended ceiling mounting structure, in step 4, needed in the second nut group according to balance Upper limit nut is fine-tuned, until after frame is adjusted to equilibrium state, is carried out to the lower position nut in the second nut group It is fixed, finally the first nut group is fastened, realizes the fixation to frame and angle steel.
Compared with prior art, the present invention is not only easily installed and dismantles, but also is convenient for adjustment frame height, and stability is strong;Together When ensure that installation accuracy, also reduce construction requirement.Pass through certain length between the load angle steel and frame of angle steel end It is vertical be bolted, to carry out firm installation to frame furred ceiling and height is adjusted, load angle steel and frame are adjusted wherein passing through Between bolt length, the height of frame to be adjusted.By offering functional hole on frame, one is easy for early period will Bolt is penetrated into frame and is fixed, and two are easy for stretching into for later stage spanner, bolt to be adjusted.By on load angle steel It opens up the second slotted hole and offers the first slotted hole on frame, the second slotted hole and the first slotted hole are combined, and are ensured Frame and angle steel have regulating error range, can be adjusted to front and back and left and right directions, reduce angle steel in connection Installation accuracy requirement.Moreover, avoid in traditional fixed form, bolt is by shearing force, because frame weight is larger so that bolt is sent out Raw change in displacement, and make frame run-off the straight.
Description of the drawings
Fig. 1 is the frame and angle steel lifting schematic diagram of the present invention;
Fig. 2 is enlarged drawing at A;
Fig. 3 is partial structurtes scheme of installation of the present invention;
Fig. 4 is steel angle structure schematic diagram;
Fig. 5 is circuit theory schematic diagram.
1- angle steel;2- frames;3- load angle steel;The first slotted holes of 4-;5 second slotted holes;6- bolts;The first nuts of 7- Group;8- the second nut groups;9- functional holes.
Specific implementation mode
The present invention is further illustrated with reference to the accompanying drawings and examples, but be not intended as to the present invention limit according to According to.
Embodiment:A kind of frame suspended ceiling mounting structure, as shown in attached drawing 1-5, including angle steel 1 and frame 2, the frame 2 For hollow type framework;The total quality for reducing frame 2, to reduce the bearing capacity of angle steel 1;The end of the angle steel 1 is welded with Load angle steel 3 normal thereto;The second slotted hole 5 is offered on the load angle steel 3, and the first length is offered on the frame 2 Circular hole 4, second slotted hole, 5 and first slotted hole 4 are arranged in a mutually vertical manner on same perspective plane;Adjustable extent is big; First slotted hole 4 is connect with the second slotted hole 5 by bolt 6, and 6 lower part of bolt passes through positioned at the first of 4 both sides of the first slotted hole 7 fixed frame 2 of nut group;Load angle steel 3 is fixed in 6 top of bolt by the second nut group 8 positioned at 5 both sides of the second slotted hole; It is equipped with spring shim between the second nut group 8 and load angle steel 3 and the first nut group 7 and frame 2;Avoid the first spiral shell Mother's group 7 is in direct contact with frame 2, and causes to wear to frame 2, is reduced the service life of frame 2, is also avoided the second nut group 8 are in direct contact with load angle steel 3, and cause to wear to load angle steel 3, and the frame 2 is set positioned at the side of the first slotted hole 4 Functional hole 9, the functional hole 9 are arranged in 2 lateral surface of frame and/or medial surface, to meet different construction demands.
According to the mounting means of frame suspended ceiling mounting structure, it is as follows:
Step 1:Preliminary assembling before being installed;On ground, pacify by bolt by functional hole and using the first nut group activity It is attached on frame so that bolt has up and down adjustment space;
Step 2:Angle steel is fixedly installed on floor straight down according to construction drawing;
Step 3:By frame lifter to required mounting height, the bolt on frame is penetrated on the load angle steel of angle steel bottom end Second slotted hole, and be flexibly connected by the second nut group, frame is hung in realization temporarily;
Step 4:By being finely adjusted the first nut group and the second nut group, frame is adjusted to carry out after equilibrium state tight Gu installation is complete.
In step 2, after bolt being movably arranged on frame by the first nut group, then the second nut is installed on bolt Lower position nut in group realizes the installation to the lower position nut in the second nut group.
In step 4, it needs to fine-tune the upper limit nut in the second nut group according to balance, until frame tune It is whole that the lower position nut in the second nut group is fixed, finally the first nut group is fastened to after equilibrium state, it is real Now to the fixation of frame and angle steel.
It during actual use, is installed first, bolt 6 is utilized into 7 activity of the first nut group by functional hole 9 It installs on the frame 2, and the lower position nut installed in the second nut group 8 consolidates angle steel 1 then according to construction drawing Dingan County then carries out elevated height, when frame 2 is promoted to desired height, along the first slotted hole 4 on floor to frame 2 Sliding, the position of adjusting bolt 6 so that bolt 6 passes through the second slotted hole 5 on load angle steel 3, then screws on the second nut group Upper limit nut in 8, to be hung to frame 2 temporarily, finally according to construction requirement, height to frame 2 and flat Weighing apparatus state is adjusted, and during adjusting, spanner is extend into frame 2 by functional hole 9, to bolt 6 into fixation, It then proceedes to adjust the upper limit nut in the second nut group 8, carrys out the spacing between adjustment frame 2 and load angle steel 3, until frame After frame 2 is in desired height and equilibrium state, the lower position nut in the second nut group 8 is then tightened, diagonal steel 1 is consolidated It is fixed, the first nut group 7 is finally tightened, realizes the fixation to frame 2, avoids generating opposite fortune between frame 2 and load angle steel 3 It is dynamic, and frame 2 is made to shake or tilt.
Compared with traditional installation fixed form, this mounting structure and mounting means effectively avoid bolt 6 by When shearing force, because 2 weight of frame is larger so that bolt 6 is subjected to displacement variation, and makes 2 run-off the straight of frame.

Claims (8)

1. frame suspended ceiling mounting structure, it is characterised in that:Including angle steel(1)And frame(2), the angle steel(1)End welding There is load angle steel normal thereto(3);The load angle steel(3)On offer the second slotted hole(5), the frame(2)On open Equipped with the first slotted hole(4), the first slotted hole(4)With the second slotted hole(5)Pass through bolt(6)Connection, bolt(6)Lower part passes through Positioned at the first slotted hole(4)First nut group of both sides(7)Fixed frame(2);Bolt(6)Top is by being located at the second slotted hole (5)Second nut group of both sides(8)Fixed load angle steel(3);The frame(2)Positioned at the first slotted hole(4)Side set Functional hole(9).
2. frame suspended ceiling mounting structure according to claim 1, it is characterised in that:Second slotted hole(5)With first Slotted hole(4)It is to be arranged in a mutually vertical manner on same perspective plane.
3. according to claim 1, it is characterised in that:The frame(2)For hollow type framework.
4. frame suspended ceiling mounting structure according to claim 1, it is characterised in that:The functional hole(9)It is arranged in frame (2)Lateral surface and/or medial surface.
5. frame suspended ceiling mounting structure according to claim 1, it is characterised in that:The second nut group(8)With load Angle steel(3)And the first nut group(7)With frame(2)Between be equipped with spring shim.
6. according to the mounting means of claim 1-5 any one of them frame suspended ceiling mounting structures, it is characterised in that:Including with Lower step:
Step 1:Preliminary assembling before being installed;On ground, pacify by bolt by functional hole and using the first nut group activity It is attached on frame so that bolt has up and down adjustment space;
Step 2:Angle steel is fixedly installed on floor straight down according to construction drawing;
Step 3:By frame lifter to required mounting height, the bolt on frame is penetrated on the load angle steel of angle steel bottom end Second slotted hole, and be flexibly connected by the second nut group, frame is hung in realization temporarily;
Step 4:By being finely adjusted the first nut group and the second nut group, frame is adjusted to carry out after equilibrium state tight Gu installation is complete.
7. the mounting means of frame suspended ceiling mounting structure according to claim 6, it is characterised in that:In step 2, by bolt After being movably arranged on frame by the first nut group, then the lower position nut in the second nut group is installed on bolt, realizes pair The installation of lower position nut in second nut group.
8. the mounting means of frame suspended ceiling mounting structure according to claim 7, it is characterised in that:In step 4, according to flat Weighing apparatus needs to fine-tune the upper limit nut in the second nut group, until after frame is adjusted to equilibrium state, to the second spiral shell Lower position nut in female group is fixed, and is finally fastened to the first nut group, realizes the fixation to frame and angle steel.
CN201810572607.5A 2018-06-06 2018-06-06 Frame suspended ceiling mounting structure and its mounting means Pending CN108518013A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810572607.5A CN108518013A (en) 2018-06-06 2018-06-06 Frame suspended ceiling mounting structure and its mounting means

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810572607.5A CN108518013A (en) 2018-06-06 2018-06-06 Frame suspended ceiling mounting structure and its mounting means

Publications (1)

Publication Number Publication Date
CN108518013A true CN108518013A (en) 2018-09-11

Family

ID=63427053

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810572607.5A Pending CN108518013A (en) 2018-06-06 2018-06-06 Frame suspended ceiling mounting structure and its mounting means

Country Status (1)

Country Link
CN (1) CN108518013A (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202430879U (en) * 2011-12-06 2012-09-12 华鼎建筑装饰工程有限公司 Perforated panel connecting mechanism
CN204299020U (en) * 2014-12-16 2015-04-29 山东天元装饰工程有限公司 A kind of mounting system of furred ceiling
EP2902559A1 (en) * 2014-01-30 2015-08-05 Saint-Gobain Ecophon AB A suspended ceiling system and a method for mounting a suspended ceiling
CN104863299A (en) * 2015-04-29 2015-08-26 苏州乔布注塑工业有限公司 Plastic suspended ceiling frame
CN204715604U (en) * 2015-05-21 2015-10-21 广州康普顿至高建材有限公司 One hangs the wide keel smallpox of boxlike
CN105464272A (en) * 2014-09-03 2016-04-06 上海西蒙幕墙吊顶板有限公司 Round pipe ceiling mounting structure
CN208267214U (en) * 2018-06-06 2018-12-21 浙江深美装饰工程有限公司 Frame suspended ceiling mounting structure

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202430879U (en) * 2011-12-06 2012-09-12 华鼎建筑装饰工程有限公司 Perforated panel connecting mechanism
EP2902559A1 (en) * 2014-01-30 2015-08-05 Saint-Gobain Ecophon AB A suspended ceiling system and a method for mounting a suspended ceiling
CN105464272A (en) * 2014-09-03 2016-04-06 上海西蒙幕墙吊顶板有限公司 Round pipe ceiling mounting structure
CN204299020U (en) * 2014-12-16 2015-04-29 山东天元装饰工程有限公司 A kind of mounting system of furred ceiling
CN104863299A (en) * 2015-04-29 2015-08-26 苏州乔布注塑工业有限公司 Plastic suspended ceiling frame
CN204715604U (en) * 2015-05-21 2015-10-21 广州康普顿至高建材有限公司 One hangs the wide keel smallpox of boxlike
CN208267214U (en) * 2018-06-06 2018-12-21 浙江深美装饰工程有限公司 Frame suspended ceiling mounting structure

Similar Documents

Publication Publication Date Title
CN203855292U (en) Escalator inclined section support device
CN208267214U (en) Frame suspended ceiling mounting structure
EP2671783A2 (en) Cabin arrangement for a crane
CN108518013A (en) Frame suspended ceiling mounting structure and its mounting means
CN113585705A (en) Construction hanging flower basket is built in room
CN210127654U (en) Large-span steel structure sliding device
KR101271760B1 (en) Supporting apparatus for heavy weight
CN209780275U (en) lifting device for large-span beam reinforcing steel bar
CN112551342A (en) Prefabricated staircase hoist
CN110805258A (en) Double-triangular-support elevator shaft operating platform and construction method
CN104787653A (en) Supporting structure capable of adjusting movable cover plate to be horizontal
CN211874002U (en) LED stage
CN209989034U (en) A hoisting frame for factory building piping erection
CN208415512U (en) A kind of new steel structure assembled architecture
CN206940162U (en) Compensated chain guider
CN114104942B (en) Lifting lug in steel spring floating slab hole
CN204643520U (en) A kind of supporting construction of adjustable removable cover level
CN216807987U (en) Fine adjustment device after steel column hoisting
CN220264918U (en) Adjustable lifting appliance and lifting system for upper loading of mixer truck
CN212715870U (en) Wall-attached seat
CN215048347U (en) Building engineering material lifting machine with safeguard function
CN207987785U (en) A kind of upper front beam suspension system of suspended pouring construction hanging basket
CN214980824U (en) Support frame for steel processing
CN207113182U (en) The air-conditioning box of balance-adjustable
CN217173012U (en) Adjusting device of metallurgical bridge crane

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination