CN108486976A - Mountain highway, which is filled out, digs intersection road structure and its construction method - Google Patents

Mountain highway, which is filled out, digs intersection road structure and its construction method Download PDF

Info

Publication number
CN108486976A
CN108486976A CN201810406200.5A CN201810406200A CN108486976A CN 108486976 A CN108486976 A CN 108486976A CN 201810406200 A CN201810406200 A CN 201810406200A CN 108486976 A CN108486976 A CN 108486976A
Authority
CN
China
Prior art keywords
intersection
changeover portion
drain
section
french drain
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810406200.5A
Other languages
Chinese (zh)
Other versions
CN108486976B (en
Inventor
钱申春
彭申凯
孙学军
杜海峰
刘要武
任杰
刘晓晗
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anhui Road and Bridge Engineering Co Ltd
Original Assignee
Anhui Road and Bridge Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Anhui Road and Bridge Engineering Co Ltd filed Critical Anhui Road and Bridge Engineering Co Ltd
Priority to CN201810406200.5A priority Critical patent/CN108486976B/en
Publication of CN108486976A publication Critical patent/CN108486976A/en
Application granted granted Critical
Publication of CN108486976B publication Critical patent/CN108486976B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C3/00Foundations for pavings
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C11/00Details of pavings
    • E01C11/22Gutters; Kerbs ; Surface drainage of streets, roads or like traffic areas
    • E01C11/224Surface drainage of streets
    • E01C11/227Gutters; Channels ; Roof drainage discharge ducts set in sidewalks
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C3/00Foundations for pavings
    • E01C3/04Foundations produced by soil stabilisation
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/12Consolidating by placing solidifying or pore-filling substances in the soil
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C2201/00Paving elements
    • E01C2201/20Drainage details
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A30/00Adapting or protecting infrastructure or their operation
    • Y02A30/60Planning or developing urban green infrastructure

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Soil Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • Agronomy & Crop Science (AREA)
  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
  • Road Paving Structures (AREA)

Abstract

The present invention relates to a kind of mountain highways to fill out digging intersection road structure and its construction method, the road structure includes embankment section, excavation section and fill out dig intersection changeover portion, embankment section is equipped with changeover portion step and open drain, fill out dig intersection changeover portion be equipped with fill out dig intersection drainage system, it includes replaceable displacement hull assembled transverse drainage french drain to fill out and dig intersection drainage system, it longitudinally through weeper drain and fills out digging intersection is permeable combines changeover portion with water barrier, it fills out to dig in intersection drainage system and changeover portion step and is equipped with combined type draining ductule, it fills out the combined type draining ductule bottom dug on intersection drainage system and connects longitudinally through weeper drain, longitudinally through weeper drain is communicated with replaceable displacement hull assembled transverse drainage french drain.The present invention can in time be monitored soil body level of ground water in slope surface by the peephole of setting, effectively controls the leaning angle and size of cubic meter of stone section changeover portion step, accelerates speed of application, improve the overall stability of roadbed.

Description

Mountain highway, which is filled out, digs intersection road structure and its construction method
Technical field
The present invention relates to a kind of novel Subgrade in Mountain Area structure, more particularly to a kind of mountain highway fills out the road for digging intersection Based structures and its construction method.
Background technology
As building in large scale for China's highway is set to, after especially " the logical high speed in county of county " theory proposes, highway is applied Work will be shifted to mountain area, and highways in mountain areas roadbed is substantially high-fill roadbed, and be filled out digging and interlocked.High-fill roadbed is due to being conducted oneself with dignity Greatly, the duration is tight, mountain area rainy season is long, and constructs lack of standardization so that roadbed is easy to settle, and is especially filled out in transverse and longitudinal Intersection is dug, sedimentation is apparent, leads to pavement cracking, depression, strong influence is caused to traffic safety.Highways in mountain areas It has been the protrusion problem faced at present to fill out and dig intersection roadbed filling.
It is traditional fill out to dig intersection construction processing and be divided into longitudinal fill out digging digging of having a common boundary and laterally fill out and have a common boundary two kinds of processing modes.Before Person mainly carries out backfill of backbreaking in excavation section, embankment section progress bench excavation, the Construction Mode main drawback is that, The step in embankment section, which rolls, to be not enough, and it is excessive to be easy to cause posterior settlement, and intersection changeover portion is dug due to the old and new in addition, filling out Roadbed combine it is insufficient, if without consolidation process, the stability of road structure can be seriously affected;The side of the latter's Ji highways It is excavated, at the same time, the other side of highway carries out backfilling working, cross fall of the Construction Mode very dependent on highway Degree, the gradient is different, and form of construction work change is very big, therefore applicability is relatively poor, and geotechnical grid is laid on roadbed, to geotechnique The intensity of cell compartment, overlap joint requirement is all higher, and difficulty of construction is big.
Dig that intersection road structure is stable, intensity load-carrying properties are good, roll in conclusion being badly in need of searching out one kind at present and filling out Fully, it settles small novel mountain highway and fills out digging intersection roadbed and its construction method.
Invention content
For the above-mentioned problems in the prior art, fills out digging the purpose of the present invention is to provide a kind of mountain highway and have a common boundary Locate road structure and its construction method.
The mountain highway, which is filled out, digs intersection road structure, it is characterised in that:Including embankment section, excavation section and fill out Intersection changeover portion is dug, embankment section is equipped with changeover portion step and open drain, fills out digging intersection changeover portion and is handed over equipped with digging is filled out Drainage system at boundary, it includes replaceable displacement hull assembled transverse drainage french drain, longitudinally through row to fill out and dig intersection drainage system It water french drain and fills out digging intersection is permeable combines changeover portion with water barrier, fill out and dig that intersection is permeable to combine changeover portion and mistake with water barrier It crosses in section step and is equipped with combined type draining ductule, fill out and dig the permeable combined type row combined with water barrier on changeover portion of intersection Water ductule bottom connects longitudinally through weeper drain, longitudinally through weeper drain and replaceable displacement hull assembled transverse drainage French drain communicates, and the height of replaceable displacement hull assembled transverse drainage french drain is 1/3 height of excavation section height, and is arranged Excavation section bottom.
The mountain highway, which is filled out, digs intersection road structure, it is characterised in that:Replaceable displacement hull assembled is laterally arranged Water french drain includes that drawing and pulling type guide rod band end plate replaces displacement hull and prefabricated assembling type reinforced concrete french drain, prefabricated assembling type reinforced It is equipped with vertical steel plate in the middle part of concrete french drain, is two cell compartment structures, prefabricated assembling type reinforced concrete french drain top paving by it Reinforced mesh, each cell compartment bottom surface are respectively equipped with two tracks, and drawing and pulling type guide rod band end plate is replaced displacement hull and is arranged in prefabricated dress In cell compartment with formula armored concrete french drain, drawing and pulling type guide rod band end plate replaces displacement hull bottom and is equipped with idler wheel, idler wheel and rail Road matches, and can be slided in track, so that drawing and pulling type guide rod band end plate is replaced draining physical efficiency free skating and enters prefabricated assembling type reinforced mix Solidifying soil french drain.
The mountain highway, which is filled out, digs intersection road structure, it is characterised in that:It fills out digging intersection changeover portion and is located at embankment Between section and excavation section, length range is not less than 10m, and it is 4% to fill out and dig the gradient of intersection changeover portion.
The mountain highway, which is filled out, digs intersection road structure, it is characterised in that:It fills out and digs setting below intersection changeover portion Changeover portion step, inclined angle control within 4 °, and due at step rolled section it is small, therefore use annular compression, effectively disappear Except compacting blind area, soil body compactness and overall stability are improved.
The mountain highway, which is filled out, digs intersection road structure, it is characterised in that:In embankment section and fill out digging intersection It is permeable combined with water barrier be respectively set on changeover portion combined type draining ductule, combined type draining ductule include Dense mesh screen, Geotechnological cloth bag, taper pile crown, grouting pipe and expand end plate, is equipped with Dense mesh screen and geotextiles in grouting pipe successively from the inside to surface Bag is filled with rubble between Dense mesh screen and grouting pipe;Grouting pipe bottom connects taper pile crown, and top connection expands end plate, Taper pile crown opens valve equipped with circular cone, expands end plate lower surface and is equipped with peephole, the combined type draining ductule later stage does Grouting Pipe With.
The mountain highway, which is filled out, digs intersection road structure, it is characterised in that:Changeover portion step passes through static blasting Method constructs to obtain:It is first drilled with L-shaped static blasting hole in embankment section, loads Static Blasting Agent in L-shaped static blasting hole, together When installation horizontal stripes hush panel integral pressurized water water supply pipe and lateral strip hush panel integral pressurized water water supply pipe, horizontal stripes hush panel The outer end end of integral pressurized water water supply pipe and lateral strip hush panel integral pressurized water water supply pipe is solid by end anchor firmware respectively It is scheduled in slope surface, rock is burst using hydration reaction, obtains changeover portion step.
The mountain highway fills out the construction method for digging intersection road structure, it is characterised in that includes the following steps:
The first step is that the basal layer of former slope surface is cleared up and is compacted, and specifically includes the longitudinal interim ditch of excavation, and longitudinal ditch is dug Go out earthwork training and makees the ditch ridge on the outside of ditch, in case surface water is discharged into roadbed substrate on the outside of roadbed;Trees, filling within the scope of roadbed land used Wooden clump etc. is cut down before construction and uproots, and ground surface soil is removed, embankment substrate cleaning, it is smooth, dry after flatten pressure again Real, table soil 200mm is removed in embankment location, and compactness is not less than 90%;It fills out in embankment bottom and is carried out with materials such as sand, gravel, rubbles It reinforces, forms it into the good stabilized zone of water stability;
Second step is to carry out filling out the position excavation changeover portion step for digging intersection changeover portion on embankment section, and carry out annular pressure It is real;
Third step is to excavate replaceable displacement hull assembled transverse drainage french drain, replaceable displacement hull assembly in intersection changeover portion The height of formula transverse drainage french drain is 1/3 height in excavation section, after the completion of excavation, is laterally arranged in replaceable displacement hull assembled Prefabricated assembling type reinforced concrete french drain is installed on water french drain, vertical steel is installed in the middle part of prefabricated assembling type reinforced concrete french drain It is two cell compartment structures by plate, and prefabricated assembling type reinforced concrete french drain top spreads reinforced mesh, and each cell compartment bottom surface is respectively spread Equipped with two tracks;Drawing and pulling type guide rod replaces displacement hull with end plate and the cell compartment in prefabricated assembling type reinforced concrete french drain is arranged In, drawing and pulling type guide rod band end plate replaces displacement hull bottom and is equipped with idler wheel, idler wheel and Orbit Matching, and can be slided in track, makes Drawing and pulling type guide rod band end plate replaces draining physical efficiency free skating and enters prefabricated assembling type reinforced concrete french drain, completes replaceable displacement hull The construction and installation of assembled transverse drainage french drain;
4th step installs longitudinally through weeper drain above replaceable displacement hull assembled transverse drainage french drain, then is passed through longitudinally It carries out filling out digging above logical weeper drain intersection is permeable and combine Construction of Transition Section with water barrier, and carry out enhancing ftercompction, it is described to fill out The permeable transition section length that combine with water barrier of intersection is dug not less than 10m, fills out and digs that intersection is permeable to combine changeover portion with water barrier Construction is combined using hydraulic rammer and drop hammer type dynamic compaction machinery, compactness is not less than 96%, the gradient 4%;
5th step is that combined type is arranged on changeover portion step to drain ductule, and combined type drains ductule by Dense mesh screen and geotechnique Cloth bag is wrapped in outside grouting pipe and is formed, and rubble is filled between Dense mesh screen and grouting pipe, and combined type drains ductule, under End is equipped with taper pile crown, expands end plate and includes peephole, taper pile crown lower end is equipped with circular cone valve, direct with grouting pipe It is connected;It is provided with the guiding of slope surface inclined tube between each combined type draining ductule, is guided and is connected by slope surface inclined tube, water body can in slope Ductule is drained through combined type, then guides and is discharged through slope surface inclined tube;
6th step carries out slope surface construction to embankment section, and open drain etc. is arranged in embankment section bottom, then to excavation section It constructs.
The mountain highway fills out the construction method for digging intersection road structure, it is characterised in that transition is excavated in step 2 Duan Taijie detailed processes are as follows:First several L-shaped static blastings hole is drilled with successively from top to bottom in slope surface, L-shaped is static using drilling tool The width of blast hole is not less than 2.0m, is highly not more than 1.0m, internal diameter 50mm, laterally arranges one every 0.3m;And then The Static Blasting Agent configured in advance is put into the duct in L-shaped static blasting hole, in the embodiment of the present invention, according to L-shaped static state The size of blast hole takes around 2.5kg, then installs horizontal stripes hush panel integral pressurized water moisturizing on L-shaped static blasting hole Pipe and lateral strip hush panel integral pressurized water water supply pipe, two water supply pipes are utilized respectively end anchor firmware and are fixedly mounted on slope surface 36 On, by water supply pipe moisturizing into L-shaped static blasting hole, hydration reaction occurs with Static Blasting Agent, heat is released, by lithosome Cracking is burst, which generally requires 3 hours, and crack, which is 3 centimeters, to be advisable, by damaged rock mass profit after static blasting Manually pick cuts, and the control step gradient is within 4%.It is immediately begun to from top to bottom after substrate is removed as far as possible It is disposable build molding, if cannot once build from top to bottom, at least retain 3 steps more than every layer of constructing soil, then into Row placement in layers.
The mountain highway fills out the construction method for digging intersection road structure, it is characterised in that debulking methods are using annular Compacting is conducive to being abound with, uniformly for shock point in conjunction with fluid pressure type rolling apparatus, enhances overall effect, and it is blind to effectively eliminate compacting Area.
By using above-mentioned technology, compared with prior art, the present invention has following features and advantageous effect:
1)The present invention can eliminate in such a way that annular rolls and roll insufficient defect at step excavation;
2)The present invention by digging that intersection is permeable to combine changeover portion with water barrier filling out to dig intersection setting and fill out, and with it is longitudinally through Weeper drain and replaceable displacement hull assembled transverse drainage french drain link together, not only waterproof but also can drain in time, protect The load-carrying properties filled out and dig intersection are demonstrate,proved, to ensure that the stability of entire road structure;
3)The present invention has buried combined type draining ductule at changeover portion step, and coordinates the guiding of slope surface inclined tube, can supervise at any time The water level and seepage problem inside roadbed are surveyed, roadbed internal water accumulation is discharged in time, reduces water level, the geological disasters such as landslide are avoided with this Generation, and combined type draining the ductule later stage can be used as Grouting Pipe;
4)Drawing and pulling type guide rod band end plate in the present invention is replaced displacement hull and is combined with prefabricated assembling type reinforced concrete french drain, can be with The displacement hull for occurring damaging is replaced in time;
5)The static blasting construction method used in the present invention can effectively control the leaning angle and ruler of cubic meter of stone section changeover portion step It is very little, accelerate speed of application.
Description of the drawings
Fig. 1 is high embankment schematic cross-sectional view;
Fig. 2 is that mountain highway fills out digging intersection road structure schematic diagram;
Fig. 3 is combined type draining ductule structural schematic diagram;
Fig. 4 is replaceable displacement hull assembled transverse drainage french drain cross-section diagram;
Fig. 5 is static blasting construction schematic diagram;
Fig. 6 is enlarged drawing at A in Fig. 2.
Wherein:1- embankments section;2- excavations section;3-, which is filled out, digs intersection changeover portion;4- changeover portion steps;5- pervious beds; 6- cement nails;7- TGXG;The replaceable displacement hull assembled transverse drainage french drains of 8-;The open drains 9-;10- combined types drain Ductule;11- Dense mesh screens;12- geotechnique's cloth bag;13- taper pile crowns;14- rubbles;15- grouting pipes;16- expands end plate;17- Circular cone opens valve;18-, which is filled out, digs intersection drainage system;19- slope surface inclined tubes guide;The longitudinally through weeper drains of 20-;21- fills out digging and hands over It is permeable at boundary to combine changeover portion with water barrier;22- water barriers;The vertical ductules of 23- are embedded in head layer;24- reinforcement foam concrete Regulating course;25- reinforced mesh;The vertical steel plates of 26-;27- prefabricated assembling type reinforced concrete french drains;28- tracks;29- idler wheels; 30- drawing and pulling types guide rod band end plate replaces displacement hull;31- peepholes;32-L shape static blastings hole;33- horizontal stripes hush panel is whole Formula presses water water supply pipe;34- lateral strip hush panel integral pressurized water water supply pipes;35- end anchor firmwares;36- slope surfaces;37- original slope surfaces.
Specific implementation mode
Below in conjunction with Figure of description, the invention will be further described, but protection scope of the present invention is not limited in This:
As shown in figures 1 to 6, mountain highway of the invention fill out dig intersection road structure, including embankment section 1, excavation section 2 and It fills out and digs intersection changeover portion 3, embankment section 1 is equipped with changeover portion step 4 and open drain 9, fills out digging intersection changeover portion 3 and is equipped with Fill out and dig intersection drainage system 18, fill out dig intersection drainage system 18 include replaceable displacement hull assembled transverse drainage french drain 8, It longitudinally through weeper drain 20 and fills out digging intersection is permeable combines changeover portion 21 with water barrier, fill out that digging intersection is permeable and water barrier It is equipped with combined type draining ductule 10 in combination changeover portion 21 and changeover portion step 4, fills out that dig intersection permeable with water barrier group 10 bottom of combined type draining ductule closed on changeover portion 21 connects longitudinally through weeper drain 20, longitudinally through weeper drain 20 It is communicated with replaceable displacement hull assembled transverse drainage french drain 8, the height of replaceable displacement hull assembled transverse drainage french drain 8 is 1/3 height of 2 height of excavation section, and be arranged in 2 bottom of excavation section.
It is replaced as shown in figure 4, the replaceable displacement hull assembled transverse drainage french drain 8 includes drawing and pulling type guide rod band end plate Displacement hull 30 and prefabricated assembling type reinforced concrete french drain 27,27 middle part of prefabricated assembling type reinforced concrete french drain are equipped with vertical steel It is two cell compartment structures by plate 26, and 27 top of prefabricated assembling type reinforced concrete french drain spreads reinforced mesh 25, each cell compartment bottom Face is respectively equipped with two tracks 28, and it is blind in prefabricated assembling type reinforced concrete that drawing and pulling type guide rod band end plate replaces the setting of displacement hull 30 In the cell compartment of ditch 27, drawing and pulling type guide rod band end plate replaces 30 bottom of displacement hull and is equipped with idler wheel 29, and idler wheel 29 is matched with track 28, And can be slided in track 28, so that drawing and pulling type guide rod band end plate is replaced displacement hull 30 and freely slides into prefabricated assembling type reinforced concrete French drain 27.
It fills out and digs intersection changeover portion 3 between embankment section 1 and excavation section 2, length range is not less than 10m, fills out digging The gradient of intersection changeover portion 3 is 4%;It fills out and digs 3 lower section setting changeover portion step 4 of intersection changeover portion, inclined angle is controlled at 4 ° Within, and due at step rolled section it is small, therefore use annular compression, effectively eliminate compacting blind area, improve soil body compactness and Overall stability.
As shown, the present invention is in the embankment section 1 and fills out and digs intersection permeable combined with water barrier and divide on changeover portion 21 Not She Zhi combined type drain ductule 10, as shown in figure 3, the combined type draining ductule 10 include Dense mesh screen 11, geotextiles Bag 12, taper pile crown 13, grouting pipe 15 and expand end plate 16, is equipped with 11 He of Dense mesh screen in grouting pipe 15 successively from the inside to surface Geotechnological cloth bag 12 is filled with rubble 14 between Dense mesh screen 11 and grouting pipe 15;15 bottom of grouting pipe connects taper pile crown 13, Top connection expands end plate 16, and taper pile crown 13 opens valve 17 equipped with circular cone, expands 16 lower surface of end plate and is equipped with peephole 31, multiple It is effective that box-like 10 later stage of draining ductule does slip casting.
As shown in figure 5, the changeover portion step 4 constructs to obtain by the method for static blasting:First bored in embankment section 1 If L-shaped static blasting hole 32, Static Blasting Agent is loaded in L-shaped static blasting hole 32, while horizontal stripes hush panel monoblock type being installed Press water water supply pipe 33 and lateral strip hush panel integral pressurized water water supply pipe 34,33 He of horizontal stripes hush panel integral pressurized water water supply pipe The outer end end of lateral strip hush panel integral pressurized water water supply pipe 34 is fixed on by end anchor firmware 35 in slope surface 36 respectively, profit Rock is burst with hydration reaction, obtains changeover portion step 4.
As shown in Figure 1, general mountain highway construction needs to carry out filling out excavation construction to former slope surface 37, and filling out digging intersection Road structure construction when, due to fill out dig intersection road structure include embankment section 1, intersection changeover portion 3 and excavation road Section 2, specifically comprises the following steps:
The first step is that the basal layer of former slope surface 37 is cleared up and is compacted, and specifically includes the longitudinal interim ditch of excavation, longitudinal ditch It digs out earthwork training and makees the ditch ridge on the outside of ditch, in case surface water is discharged into roadbed substrate on the outside of roadbed;Trees within the scope of roadbed land used, Bushes etc. are cut down before construction and uproot, and ground surface soil is removed, embankment substrate cleaning, it is smooth, dry after flatten again Table soil 200mm is removed in compacting, embankment location, and compactness is not less than 90%;To avoid substrate by Effect of Underground Water Level, at embankment bottom Portion fills out the materials such as sand excellent with water stability, dysgeogenous, gravel, rubble and carries out consolidation process, and it is good to form it into water stability Stabilized zone.
Second step is to carry out filling out the position excavation changeover portion step 4 for digging intersection changeover portion 3 on embankment section 1, is gone forward side by side Row annular compacting, detailed process are as follows:The excavation of step is carried out according to design drawing, as shown in figure 5, using drilling tool first in slope surface 36 are drilled with several L-shaped static blastings hole 32 successively from top to bottom, and the width in L-shaped static blasting hole 32 is not less than 2.0m, and height is not More than 1.0m, internal diameter 50mm, laterally one is arranged every 0.3m;And then the Static Blasting Agent configured in advance is put into L In the duct in shape static blasting hole 32, in the embodiment of the present invention, according to the size in L-shaped static blasting hole 32, take around 2.5kg, then installation horizontal stripes hush panel integral pressurized water water supply pipe 33 and lateral strip hush panel are whole on L-shaped static blasting hole 32 Body formula presses water water supply pipe 34, and two water supply pipes are utilized respectively end anchor firmware 35 and are fixedly mounted in slope surface 36, pass through water supply pipe The moisturizing into L-shaped static blasting hole 32 occurs hydration reaction with Static Blasting Agent, releases heat, lithosome is burst cracking, should Work progress generally requires 3 hours, and crack, which is 3 centimeters, to be advisable, and digs the damaged artificial pick of rock mass utilization after static blasting It removes, the control step gradient is within 4%.Disposable build from top to bottom is immediately begun to after substrate is removed as far as possible Molding, if cannot once build from top to bottom, 3 steps are at least retained more than every layer of constructing soil, then carry out placement in layers, Debulking methods are compacted using annular, in conjunction with fluid pressure type rolling apparatus, are conducive to being abound with, uniformly for shock point, enhance whole effect Fruit effectively eliminates compacting blind area.
Third step is to excavate replaceable displacement hull assembled transverse drainage french drain 8, replaceable draining in intersection changeover portion 3 The height of body assembled transverse drainage french drain 8 is 1/3 height in excavation section 2, after the completion of excavation, is assembled in replaceable displacement hull Prefabricated assembling type reinforced concrete french drain 27 is installed, as shown in figure 4, pre- in the embodiment of the present invention on formula transverse drainage french drain 8 27 sectional dimension of assembled steel reinforced concrete french drain processed is 50*30cm, and 27 middle part of prefabricated assembling type reinforced concrete french drain is equipped with It is two cell compartment structures by vertical steel plate 26, and 27 top of prefabricated assembling type reinforced concrete french drain spreads reinforced mesh 25, each Cell compartment bottom surface is respectively equipped with two tracks 28;Drawing and pulling type guide rod band end plate replaces the setting of displacement hull 30 prefabricated assembling type reinforced mixed In the cell compartment of solidifying soil french drain 27, it is 20*18cm that drawing and pulling type guide rod band end plate, which replaces 30 sectional dimension of displacement hull, and bottom is equipped with Idler wheel 29, idler wheel 29 are matched with track 28, and can be slided in track 28, and drawing and pulling type guide rod band end plate is enable to replace displacement hull 30 certainly By slide-in prefabricated assembling type reinforced concrete french drain 27, the construction peace of replaceable displacement hull assembled transverse drainage french drain 8 is completed Dress.
4th step installs longitudinally through weeper drain 20 above replaceable displacement hull assembled transverse drainage french drain 8, such as Shown in Fig. 2 and Fig. 6, the section of longitudinally through weeper drain 20 is the circle of radius 20cm;Again on longitudinally through weeper drain 20 Fang Jinhang, which is filled out, to be dug the permeable changeover portion 21 that combine with water barrier of intersection and constructs, and carries out enhancing ftercompction, and described to fill out digging intersection saturating Water combines 21 length of changeover portion with water barrier and is not less than 10m, and compactness is not less than 96%, and it is saturating to fill out digging intersection for the gradient 4% It is the double-deck TGXG 7 of 5cm thickness respectively that water, which combines changeover portion 21 with water barrier from top to bottom, water barrier 22, pervious bed 5, is erected Cement nail 6 is used to ductule insertion head layer 23, water barrier 22 and reinforcement foam concrete regulating course 24, the double-deck TGXG 7 It is fixed on water barrier 22, should stretch smooth-going when being laid with TGXG, be close to sub-layer, must not there is fold.Sub-layer answer it is smooth, Forbid have hard projection, 22 thickness of water barrier is 3cm, and water barrier 22 uses to be filled under SBS modified pitch, water barrier 22 The rubble of 2cm thickness, constitutes pervious bed 5, and vertical ductule insertion head layer 23, the 3cm that 5 lower section of pervious bed is equipped with 3cm thickness successively are thick Water barrier 22 and 5cm thickness reinforcement foam concrete regulating course 24.Filling out digging, intersection is permeable combines changeover portion with water barrier It is good that 21 use hydraulic rammers and drop hammer type dynamic compaction machinery are combined effect.For the small region of construction section, for example at step and turn At angle, effective thickness is compacted according to hydraulic rammer, is successively tamped, the every 4 meters of progress reinforcement of drop hammer type dynamic compaction machinery is taken to other positions, For the big region of construction section, it is combined and rolls using hydraulic rammer and 32 tons of high performance strongs rammer vibratory rollers, constructed Longitudinally through weeper drain 20, slope surface inclined tube guiding 19 after and replaceable 8 groups of displacement hull assembled transverse drainage french drain The important drainage system 18 for digging intersection road structure is filled out at mountain highway.
5th step is that combined type is arranged on changeover portion step 4 to drain ductule 10, and combined type drains ductule 10 by close Mesh net 11 and geotechnological cloth bag 12 are wrapped in 15 outside of grouting pipe and are formed, and rubble is filled between Dense mesh screen 11 and grouting pipe 15 14, the visible Fig. 3 of structural schematic diagram, combined type drain diameter 42mm, the long 150mm of ductule 10, and end, which is equipped with, thereon expands End plate 16, lower end are equipped with taper pile crown 13, expand the peephole 31 that end plate 16 includes diameter 10mm, 13 lower end of taper pile crown Equipped with circular cone valve 17, it is connected directly with grouting pipe 15;Slope surface inclined tube is provided between each combined type draining ductule 10 to lead Draw 19, combined type draining ductule 10 is together in series by slope surface inclined tube guiding 19, water body can drain small through combined type in slope Conduit 10, then through 19 discharge of slope surface inclined tube guiding.The construction of slope surface 36, setting open drain 9 etc. finally are carried out to embankment section 1, It constructs again to excavation section 2.

Claims (9)

1. mountain highway, which is filled out, digs intersection road structure, it is characterised in that:Including embankment section(1), excavation section(2)And fill out digging Intersection changeover portion(3), embankment section(1)It is equipped with changeover portion step(4)The open drain and(9), fill out and dig intersection changeover portion (3)Intersection drainage system is dug equipped with filling out(18), fill out and dig intersection drainage system(18)Including replaceable displacement hull assembled cross To weeper drain(8), longitudinally through weeper drain(20)And it fills out digging intersection is permeable combines changeover portion with water barrier(21), fill out digging Intersection is permeable to combine changeover portion with water barrier(21)With changeover portion step(4)Inside it is equipped with combined type draining ductule(10), Filling out digging, intersection is permeable combines changeover portion with water barrier(21)On combined type drain ductule(10)Bottom connection is longitudinally through Weeper drain(20), longitudinally through weeper drain(20)With replaceable displacement hull assembled transverse drainage french drain(8)It communicates, it can be more Change gear water body assembled transverse drainage french drain(8)Height be excavation section(2)1/3 height of height, and be arranged on excavation road Section(2)Bottom.
2. mountain highway according to claim 1, which is filled out, digs intersection road structure, it is characterised in that:Replaceable displacement hull dress With formula transverse drainage french drain(8)Displacement hull is replaced including drawing and pulling type guide rod band end plate(30)It is blind with prefabricated assembling type reinforced concrete Ditch(27), prefabricated assembling type reinforced concrete french drain(27)Middle part is equipped with vertical steel plate(26), it is two cell compartment structures by it, in advance Assembled steel reinforced concrete french drain processed(27)Top spreads reinforced mesh(25), each cell compartment bottom surface is respectively equipped with two tracks (28), drawing and pulling type guide rod band end plate replacement displacement hull(30)It is arranged in prefabricated assembling type reinforced concrete french drain(27)Cell compartment In, drawing and pulling type guide rod band end plate replaces displacement hull(30)Bottom is equipped with idler wheel(29), idler wheel(29)With track(28)Matching, and It can be in track(28)Sliding makes drawing and pulling type guide rod band end plate replace displacement hull(30)Prefabricated assembling type reinforced coagulation can freely be slid into Native french drain(27).
3. mountain highway according to claim 1, which is filled out, digs intersection road structure, it is characterised in that:It fills out and digs intersection transition Section(3)Positioned at embankment section(1)With excavation section(2)Between, length range is not less than 10m, fills out and digs intersection changeover portion(3)'s The gradient is 4%.
4. mountain highway according to claim 1, which is filled out, digs intersection road structure, it is characterised in that:It fills out and digs intersection transition Section(3)Changeover portion step is arranged in lower section(4), inclined angle control within 4 °, and due at step rolled section it is small, therefore use Annular compression effectively eliminates compacting blind area, improves soil body compactness and overall stability.
5. mountain highway according to claim 1, which is filled out, digs intersection road structure, it is characterised in that:In embankment section(1) It is interior and fill out digging intersection is permeable combines changeover portion with water barrier(21)On be respectively set combined type draining ductule(10), combined type Drain ductule(10)Including Dense mesh screen(11), geotechnological cloth bag(12), taper pile crown(13), grouting pipe(15)And expand end plate (16), grouting pipe(15)On from the inside to surface successively be equipped with Dense mesh screen(11)With geotechnological cloth bag(12), Dense mesh screen(11)With slip casting Conduit(15)Between be filled with rubble(14);Grouting pipe(15)Bottom connects taper pile crown(13), top connection expansion end plate (16), taper pile crown(13)Valve is opened equipped with circular cone(17), expand end plate(16)Lower surface is equipped with peephole(31), combined type row Water ductule(10)It is effective that later stage does slip casting.
6. mountain highway according to claim 1, which is filled out, digs intersection road structure, it is characterised in that:Changeover portion step(4) It constructs to obtain by the method for static blasting:First in embankment section(1)Inside it is drilled with L-shaped static blasting hole(32), L-shaped static blasting Hole(32)Interior filling Static Blasting Agent, while horizontal stripes hush panel integral pressurized water water supply pipe being installed(33)With lateral strip hush panel Integral pressurized water water supply pipe(34), horizontal stripes hush panel integral pressurized water water supply pipe(33)With lateral strip hush panel integral pressurized water Water supply pipe(34)Outer end end pass through end anchor firmware respectively(35)It is fixed on slope surface(36)On, using hydration reaction rock It bursts, obtains changeover portion step(4).
7. a kind of filling out the construction method for digging intersection road structure based on mountain highway described in claim 1, it is characterised in that Include the following steps:
The first step is to former slope surface(37)Basal layer cleared up and be compacted, specifically include the longitudinal interim ditch of excavation, it is longitudinal Ditch digs out earthwork training and makees the ditch ridge on the outside of ditch, in case surface water is discharged into roadbed substrate on the outside of roadbed;Tree within the scope of roadbed land used Wood, bushes etc. are cut down before construction and uproot, and ground surface soil is removed, embankment substrate cleaning, it is smooth, dry after it is whole again Concora crush is real, and table soil 200mm is removed in embankment location, and compactness is not less than 90%;It is filled out with materials such as sand, gravel, rubbles in embankment bottom It is reinforced, forms it into the good stabilized zone of water stability;
Second step is in embankment section(1)On fill out and to dig intersection changeover portion(3)Position excavate changeover portion step(4), and Carry out annular compacting;
Third step is in intersection changeover portion(3)Excavate replaceable displacement hull assembled transverse drainage french drain(8), replaceable draining Body assembled transverse drainage french drain(8)Height be excavation section(2)1/3 height, after the completion of excavation, in replaceable displacement hull Assembled transverse drainage french drain(8)Upper installation prefabricated assembling type reinforced concrete french drain(27), prefabricated assembling type reinforced concrete French drain(27)Middle part is installed by vertical steel plate(26), it is two cell compartment structures, prefabricated assembling type reinforced concrete french drain by it(27) Top spreads reinforced mesh(25), each cell compartment bottom surface is respectively equipped with two tracks(28);Drawing and pulling type guide rod band end plate replaces draining Body(30)It is arranged in prefabricated assembling type reinforced concrete french drain(27)Cell compartment in, drawing and pulling type guide rod band end plate replaces displacement hull (30)Bottom is equipped with idler wheel(29), idler wheel(29)With track(28)Matching, and can be in track(28)Sliding, makes drawing and pulling type guide rod Band end plate replaces displacement hull(30)Prefabricated assembling type reinforced concrete french drain can freely be slid into(27), complete replaceable displacement hull dress With formula transverse drainage french drain(8)Construction and installation;
4th step is in replaceable displacement hull assembled transverse drainage french drain(8)Top is installed by longitudinally through weeper drain(20), then In longitudinally through weeper drain(20)Top fill out digging intersection is permeable combines changeover portion with water barrier(21)Construction, and carry out Enhance ftercompction, it is described to fill out digging intersection is permeable combines changeover portion with water barrier(21)Length is not less than 10m, and it is saturating to fill out digging intersection Water combines changeover portion with water barrier(21)Construction is combined using hydraulic rammer and drop hammer type dynamic compaction machinery, compactness is not less than 96%, the gradient 4%;
5th step is in changeover portion step(4)Upper setting combined type drains ductule(10), combined type draining ductule(10)By Dense mesh screen(11)With geotechnological cloth bag(12)It is wrapped in grouting pipe(15)Outside is formed, Dense mesh screen(11)And grouting pipe(15)It Between be filled with rubble(14), combined type draining ductule(10 upper ends, which are equipped with, expands end plate(16), lower end is equipped with taper pile crown (13), expand end plate(16)Include peephole(31), taper pile crown(13)Lower end is equipped with circular cone valve(17), with grouting pipe (15)It is connected directly;Each combined type drains ductule(10)Between be provided with slope surface inclined tube guiding(19), led by slope surface inclined tube Draw(19)It connects, water body can drain ductule through combined type in slope(10), then through the guiding of slope surface inclined tube(19)Discharge;
6th step is to embankment section(1)Carry out slope surface(36)Construction, and in embankment section(1)Open drain is arranged in bottom(9)Deng, Again to excavation section(2)It constructs.
8. mountain highway according to claim 7 fills out the construction method for digging intersection road structure, it is characterised in that step Changeover portion step is excavated in two(4)Detailed process is as follows:Using drilling tool first in slope surface(36)It is drilled with several L-shaped successively from top to bottom Static blasting hole(32);And then the Static Blasting Agent configured in advance is put into L-shaped static blasting hole(32)Duct in, then In L-shaped static blasting hole(32)Upper installation horizontal stripes hush panel integral pressurized water water supply pipe(33)With lateral strip hush panel monoblock type Press water water supply pipe(34), two water supply pipes are utilized respectively end anchor firmware(35)It is fixedly mounted on slope surface(36)On, pass through moisturizing Pipe is to L-shaped static blasting hole(32)Interior moisturizing occurs hydration reaction with Static Blasting Agent, releases heat, lithosome is burst out It splits, cuts the damaged artificial pick of rock mass utilization after static blasting, the control step gradient is within 4%;It is finished in substrate removing Disposable build molding from top to bottom is immediately begun to afterwards, if cannot once build from top to bottom, more than every layer of constructing soil At least retain 3 steps, then carries out placement in layers.
9. mountain highway according to claim 8 fills out the construction method for digging intersection road structure, it is characterised in that compacting Method is compacted using annular, in conjunction with fluid pressure type rolling apparatus.
CN201810406200.5A 2018-04-30 2018-04-30 Roadbed structure at mountain highway filling and digging junction and construction method thereof Active CN108486976B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810406200.5A CN108486976B (en) 2018-04-30 2018-04-30 Roadbed structure at mountain highway filling and digging junction and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810406200.5A CN108486976B (en) 2018-04-30 2018-04-30 Roadbed structure at mountain highway filling and digging junction and construction method thereof

Publications (2)

Publication Number Publication Date
CN108486976A true CN108486976A (en) 2018-09-04
CN108486976B CN108486976B (en) 2023-06-27

Family

ID=63313386

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810406200.5A Active CN108486976B (en) 2018-04-30 2018-04-30 Roadbed structure at mountain highway filling and digging junction and construction method thereof

Country Status (1)

Country Link
CN (1) CN108486976B (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109610435A (en) * 2019-01-29 2019-04-12 中国机械设备工程股份有限公司 A kind of loess high roadbed cheuch ground discharge structure and its laying method
CN110055831A (en) * 2019-04-28 2019-07-26 中铁二院工程集团有限责任公司 A kind of abrupt slope high-speed railway concrete rigid short circuit based structures and construction method
CN110172884A (en) * 2019-06-04 2019-08-27 中信国安建工集团有限公司 A kind of Subgrade in Mountain Area and construction method
CN112681043A (en) * 2020-12-18 2021-04-20 湖北省路桥集团有限公司 Roadbed splicing and widening structure and construction method
CN113403904A (en) * 2021-07-21 2021-09-17 中信国安建工集团有限公司 Highway filling and digging boundary roadbed structure and construction operation method

Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0384117A (en) * 1989-08-25 1991-04-09 Railway Technical Res Inst Steep sloping method of banking slope
AU632967B2 (en) * 1992-02-19 1993-01-14 Charles St'Clair Matheson Easy gutter cleaner
US5930923A (en) * 1996-12-26 1999-08-03 Yugenkaisha Unit Shoji Limited Method for operation to excavate underdrain in the field ground and a device for operation to excavate underdrain
US20050047866A1 (en) * 2003-09-02 2005-03-03 Chen Jui Wen Construction of environmental and water-permeable paving
JP2005097858A (en) * 2003-09-22 2005-04-14 Ito Yogyo Co Ltd Draining block, and pavement structure using the same
BRPI0902835A2 (en) * 2009-08-21 2012-06-12 Engegraut Servicos Tecnicos Ltda deep radial consolidation process or cpr for soft or peat clay soils using finite element method in process programming and control
CN203741666U (en) * 2014-01-27 2014-07-30 安徽省公路桥梁工程有限公司 Roadbed structure for preventing cut-fill section of highway in cold region from frost boiling
CN104264557A (en) * 2014-08-28 2015-01-07 杭州江润科技有限公司 Semi-filling and semi-excavating ecological subgrade structure and construction method
CN104594329A (en) * 2014-12-17 2015-05-06 河海大学 Device for treating differential settlement of road and bridge transition sections through load reducing and method of device
CN204356888U (en) * 2014-12-23 2015-05-27 中山市博见金属制品有限公司 A kind of novel gutter
CN106759792A (en) * 2016-12-02 2017-05-31 安徽省公路桥梁工程有限公司 A kind of inspection shaft construction technique
CN208455387U (en) * 2018-04-30 2019-02-01 安徽省公路桥梁工程有限公司 Mountain highway, which is filled out, digs intersection road structure

Patent Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0384117A (en) * 1989-08-25 1991-04-09 Railway Technical Res Inst Steep sloping method of banking slope
AU632967B2 (en) * 1992-02-19 1993-01-14 Charles St'Clair Matheson Easy gutter cleaner
US5930923A (en) * 1996-12-26 1999-08-03 Yugenkaisha Unit Shoji Limited Method for operation to excavate underdrain in the field ground and a device for operation to excavate underdrain
US20050047866A1 (en) * 2003-09-02 2005-03-03 Chen Jui Wen Construction of environmental and water-permeable paving
JP2005097858A (en) * 2003-09-22 2005-04-14 Ito Yogyo Co Ltd Draining block, and pavement structure using the same
BRPI0902835A2 (en) * 2009-08-21 2012-06-12 Engegraut Servicos Tecnicos Ltda deep radial consolidation process or cpr for soft or peat clay soils using finite element method in process programming and control
CN203741666U (en) * 2014-01-27 2014-07-30 安徽省公路桥梁工程有限公司 Roadbed structure for preventing cut-fill section of highway in cold region from frost boiling
CN104264557A (en) * 2014-08-28 2015-01-07 杭州江润科技有限公司 Semi-filling and semi-excavating ecological subgrade structure and construction method
CN104594329A (en) * 2014-12-17 2015-05-06 河海大学 Device for treating differential settlement of road and bridge transition sections through load reducing and method of device
CN204356888U (en) * 2014-12-23 2015-05-27 中山市博见金属制品有限公司 A kind of novel gutter
CN106759792A (en) * 2016-12-02 2017-05-31 安徽省公路桥梁工程有限公司 A kind of inspection shaft construction technique
CN208455387U (en) * 2018-04-30 2019-02-01 安徽省公路桥梁工程有限公司 Mountain highway, which is filled out, digs intersection road structure

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109610435A (en) * 2019-01-29 2019-04-12 中国机械设备工程股份有限公司 A kind of loess high roadbed cheuch ground discharge structure and its laying method
CN109610435B (en) * 2019-01-29 2023-09-12 中国机械设备工程股份有限公司 Loess high fill valley foundation drainage structure and laying method thereof
CN110055831A (en) * 2019-04-28 2019-07-26 中铁二院工程集团有限责任公司 A kind of abrupt slope high-speed railway concrete rigid short circuit based structures and construction method
CN110172884A (en) * 2019-06-04 2019-08-27 中信国安建工集团有限公司 A kind of Subgrade in Mountain Area and construction method
CN110172884B (en) * 2019-06-04 2024-02-13 中信国安建工集团有限公司 Mountain highway subgrade and construction method
CN112681043A (en) * 2020-12-18 2021-04-20 湖北省路桥集团有限公司 Roadbed splicing and widening structure and construction method
CN113403904A (en) * 2021-07-21 2021-09-17 中信国安建工集团有限公司 Highway filling and digging boundary roadbed structure and construction operation method

Also Published As

Publication number Publication date
CN108486976B (en) 2023-06-27

Similar Documents

Publication Publication Date Title
CN106499413B (en) A kind of Shallow-buried section tunnel stratum consolidation construction method
CN108486976A (en) Mountain highway, which is filled out, digs intersection road structure and its construction method
CN204059124U (en) A kind of sand drain strong rammer grouting behind shaft or drift lining foundation reinforcing structure
CN103790166B (en) Method for treating foundation of loess area saturated zone slope filling and digging joint part
CN103806432B (en) Method for treating foundations in slope filling and digging joint part of wet and soft zone in loess region
CN105862710B (en) A kind of drain bar and construction method for Tidal Flat Inning Area processing
CN104264680B (en) The method for processing foundation of Tian Wa joint portion, a kind of collapsible loess slope
CN101864960A (en) Carst region double-arch road tunnel construction method
CN106759473A (en) The constructing structure and its construction method of underground pipe gallery and road
CN107558480A (en) The construction method of the reinforced ecological slope protection structure of roadbed three-dimensional water discharge
CN106567379B (en) Method for reinforcing manual dewatering, bedding course, low-energy replacement dynamic compaction shallow foundation
CN113445396B (en) High-fill road foundation filling construction method for high liquid limit soil road section
CN110778328B (en) Loess tunnel entrance section construction method for passing through landslide body
CN113847050B (en) Construction method of ultra-long highway tunnel in lava mountain area
CN109914161B (en) Construction method of high-speed railway filling roadbed in soft soil area
CN108978385A (en) A kind of roadbed construction method on the road Tong Cun
CN110777819A (en) High and steep mine mountain reconstruction ecological restoration method
CN209039896U (en) The soft soil roadbed three-dimensional reinforced structure of convolution is knitted in a kind of stake-
CN111322087A (en) Construction method for soft soil highway tunnel entrance semi-open semi-hidden tunnel in mountainous area
CN109778625A (en) A kind of express highway roadbed structure that dregs class building castoff fills
CN111778941A (en) High-standard farmland channel construction method and structure
CN208455387U (en) Mountain highway, which is filled out, digs intersection road structure
CN205399440U (en) Inflation dirt road moat structure
CN106638684B (en) A kind of piping lane backfill soil processing method of Collapsible Loess District
CN110905529B (en) Construction method of loess tunnel penetrating through landslide mass

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant