CN108457172A - Assembling type girder bridge and construction method - Google Patents

Assembling type girder bridge and construction method Download PDF

Info

Publication number
CN108457172A
CN108457172A CN201810297853.4A CN201810297853A CN108457172A CN 108457172 A CN108457172 A CN 108457172A CN 201810297853 A CN201810297853 A CN 201810297853A CN 108457172 A CN108457172 A CN 108457172A
Authority
CN
China
Prior art keywords
pier shaft
steel plate
cushion cap
anchor bolt
ground anchor
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810297853.4A
Other languages
Chinese (zh)
Inventor
周帅
凡林
李水生
谭立新
方聪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Fifth Engineering Bureau Co Ltd
Original Assignee
China Construction Fifth Engineering Bureau Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Fifth Engineering Bureau Co Ltd filed Critical China Construction Fifth Engineering Bureau Co Ltd
Priority to CN201810297853.4A priority Critical patent/CN108457172A/en
Publication of CN108457172A publication Critical patent/CN108457172A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/02Piers; Abutments ; Protecting same against drifting ice
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention discloses a kind of assembling type girder bridges, including upper component, lower member, support system and basis, the lower member includes prefabricated pier shaft and prefabricated bent cap, the basis includes cushion cap, the top of the pier shaft connects the bent cap, and the bottom of the pier shaft connects the cushion cap with ground anchor bolt by steel plate, and the steel plate connects the reinforcing bar in the pier shaft, the ground anchor bolt connects the reinforcing bar in the cushion cap, and ground anchor bolt is adapted to one by one described in the Kong Weiyu on the steel plate.The stability of bridge pier can be enhanced using this structure, and form effective stress channel, pier shaft and the whole common stress in basis, and bolted mode enhances resistance of the pier bottom to shear action, anti-seismic performance, resistance to capsizing, anti-bending strength, extraction-resistant behavior, lifting construction quality and the construction efficiency for effectively improving bridge, are conducive to shorten the construction period, construction cost is reduced, the influence of construction period is reduced.

Description

Assembling type girder bridge and construction method
Technical field
The present invention relates to packaged type bridges field of engineering technology, more particularly to a kind of assembling type girder bridge and construction method.
Background technology
In bridge structure, bridge pier is always the focal point of Bridge Design and construction as main supporting member, at present city City's elevated bridge is to reduce bridge construction especially influence of the bent cap cast-in-place construction to traffic above-ground, further shortens the construction period, carries High efficiency, adapt to modernization, intensive manufacture development model needs, frequently with prefabricated assembled structure type and engineering method, Coherent traffic noise is small, construction quality is high, short construction period, noise is low, working security is high, and advantage is very notable.
It, in the prior art will frequently with forms such as welding, overlap joint, grout sleeves in terms of assembled is applied to substructure Precast pier and the reinforcing bar on basis are linked together, but pier shaft is not effectively formed stress channel with being connected for basis, thus are made It is poor at junction anti-seismic performance, anti-bending strength, extraction-resistant behavior, and backfill concrete reach intensity before, pier shaft need to be adopted It is consolidated with crane or using holder, additionally increases engineering expense, meanwhile, larger operation side is needed, therefore, for field There are certain restrictions for the smaller construction site in ground, and larger to Coherent traffic noise, and influence time is longer.
Invention content
Poor, peace that there are stress performances it is an object of the invention to overcoming pier shaft prefabricated in the prior art and basic junction This higher, low construction efficiency is dressed up, larger to Coherent traffic noise, the above-mentioned deficiency such as influence time is longer provides a kind of assembled beam Bridge and construction method.
To achieve the goals above, the present invention provides following technical schemes:
A kind of assembling type girder bridge, including upper component, lower member, support system and basis, the lower member includes prefabricated Pier shaft and prefabricated bent cap, the basis include cushion cap, the top of the pier shaft connects the bent cap, the bottom of the pier shaft The cushion cap is connected with ground anchor bolt by steel plate, the steel plate connects the reinforcing bar in the pier shaft, the ground anchor bolt connection Reinforcing bar in the cushion cap, ground anchor bolt described in the Kong Weiyu on the steel plate are adapted to one by one.
Using assembling type girder bridge of the present invention, including upper component, lower member, support system and basis, pre- When pier shaft processed, steel plate is connected into the reinforcing bar in the pier shaft, in construction bearing platform, ground anchor bolt is connected into the steel in the cushion cap Then muscle lifts the pier shaft, be adapted to connection one by one with each hole position on steel plate by each ground anchor bolt, then pass through spiral shell Mother's locking, to by the pier shaft and cushion cap stable connection, protect bridge pier without crane protection or holder after connection, save Cost, can enhance the stability of bridge pier using this structure, and form effective stress channel, and superstructure load passes through pier Body reinforcing bar arrives ground anchor bolt to steel plate and finally arrives cushion cap again, and cushion cap diffusion load reaches ground, pier shaft and basis it is whole jointly by Power, and bolted mode enhances resistance of the pier bottom to shear action, effectively improves anti-seismic performance, the antidumping of bridge Ability, anti-bending strength, extraction-resistant behavior, lifting construction quality and construction efficiency, are conducive to shorten the construction period, and reduce construction cost, subtract The influence of few construction period, is widely used in middle earthquake intensity earthquake areas.
Preferably, the cushion cap top surface is equipped with groove, and the steel plate is set in the groove.
It is further preferred that being equipped with concrete component in the groove, the concrete component covers the steel plate and ground Anchor bolt.
It is further preferred that the concrete component is cast-in-place concrete structure.
It is further preferred that the top surface of the concrete component is flushed with cushion cap top surface.
Using above-mentioned set-up mode so that pier shaft is linked together with basis, further increases bonding strength, enhances pier bottom pair The resistance of shear action promotes anti-seismic performance.
Preferably, the cushion cap is cast-in-place concrete structure.
Preferably, the steel plate is welded to connect the reinforcing bar in the pier shaft, and the ground anchor bolt is welded to connect the cushion cap Interior reinforcing bar.
Preferably, the junction of the pier shaft and bent cap is tongue-and-groove structure, and the tongue-and-groove structure is equipped with waterproof layer.
Using above-mentioned set-up mode, edge joint position can be enhanced between the pier shaft and bent cap to the resistance energy of shear action Power is conducive to resist horizontal loading, effectively improves bonding strength and overall performance, further promotes the anti-seismic performance of bridge.
Preferably, spacer for bolt is equipped between the steel plate and ground anchor bolt.
Preferably, the size of the hole position on the steel plate is more than the size of the ground anchor bolt.
Be conducive to subtract convenient for being finely adjusted the vertical elevation of the pier shaft or plan-position using above-mentioned set-up mode Small installation error.
A kind of construction method of assembling type girder bridge is applied to the assembling type girder bridge as described in any of the above-described, construction method It comprises the steps of:
A, prefabricated pier shaft, wherein the reinforcing bar bottom junction steel plate in the pier shaft;
B, the reinforcing bar for binding cushion cap, ground anchor bolt is connected at the top of the reinforcing bar of the cushion cap;
C, the pier shaft is lifted, so that the steel plate is connect with ground anchor bolt, realizes that the pier shaft is connected with cushion cap;
D, bent cap is connected at the top of the pier shaft;
E, upper component and support system on the bent cap are installed, assembling type girder bridge is formed.
Using the construction method of assembling type girder bridge of the present invention, in prefabricated pier shaft, in the bottom of its embedded bar Welding steel connects ground anchor bolt in the reinforcing bar of pre-buried cushion cap at the top of its reinforcing bar, on the steel plate with the earth anchor spiral shell Perforating position on the position of bolt position adaptation, then lifts the pier shaft, so that the steel plate is connected with ground anchor bolt, then pass through The pier shaft can be realized after stable connection and stablize installation, supported without protective devices such as cranes, save for nut locking Less manpower machine cost, accelerates construction progress, and reduces the influence time to surrounding enviroment, then reconnects bent cap, finally install Upper component and support system complete the installation of assembling type girder bridge, can effectively reduce difficulty of construction using this method, saving is built This is caused, engineering construction quality and construction efficiency is promoted, is conducive to shorten the construction period, reduces shadow of the construction period to traffic and environment It rings, is particularly suitable for the limited engineering in construction site.
Preferably, between the step c and d, concrete structure is arranged in the junction for being also included in the pier shaft and cushion cap Part.
After the pier shaft is connect with cushion cap, in junction cast-in-situ concrete member, the stabilization of junction is further promoted Property, enhancing pier bottom promotes anti-seismic performance to the resistance of shear action.
In conclusion compared with prior art, the beneficial effects of the invention are as follows:
1, using assembling type girder bridge of the present invention, the stability of bridge pier can be enhanced, and form effective stress channel, Superstructure load arrives ground anchor bolt by pier shaft reinforcing bar to steel plate and finally arrives cushion cap again, and cushion cap diffusion load reaches ground, pier Body and the whole common stress in basis, and bolted mode enhances resistance of the pier bottom to shear action, effectively improves bridge The anti-seismic performance of beam, resistance to capsizing, anti-bending strength, extraction-resistant behavior, lifting construction quality and construction efficiency are conducive to shorten work Phase reduces construction cost, reduces the influence of construction period, be widely used in middle earthquake intensity earthquake areas.
2, using assembling type girder bridge of the present invention so that pier shaft is linked together with basis, and it is strong to further increase connection Degree, enhancing pier bottom promote anti-seismic performance to the resistance of shear action.
3, using assembling type girder bridge of the present invention, edge joint position between the pier shaft and bent cap can be enhanced, shearing is made Resistivity, is conducive to resist horizontal loading, effectively improves bonding strength and overall performance, further promotes the anti-of bridge Shock stability.
4, micro- convenient for being carried out to the vertical elevation of the pier shaft or plan-position using assembling type girder bridge of the present invention It adjusts, is conducive to reduce installation error.
5, using the construction method of assembling type girder bridge of the present invention, difficulty of construction can be effectively reduced, saves and builds Cost promotes engineering construction quality and construction efficiency, is conducive to shorten the construction period, and reduces shadow of the construction period to traffic and environment It rings, is particularly suitable for the limited engineering in construction site.
Description of the drawings:
Fig. 1 is the lateral partial structurtes sectional view of assembling type girder bridge of the present invention;
Fig. 2 is the structure top view of pier shaft of the present invention and cushion cap.
It is marked in figure:1- pier shafts, 2- cushion caps, 3- steel plates, 4- ground anchor bolts, 5- concrete components.
Specific implementation mode
Below in conjunction with the accompanying drawings and specific embodiment the present invention is described in further detail.But this should not be interpreted as to this The range for inventing above-mentioned theme is only limitted to embodiment below, all to belong to the present invention based on the technology that the content of present invention is realized Range.
Embodiment 1
As shown in Figs. 1-2, a kind of assembling type girder bridge of the present invention, including upper component, lower member, support system and base Plinth, the lower member include prefabricated pier shaft 1 and prefabricated bent cap, and the bent cap top is equipped with the upper component and bearing System, the basis include cast-in-place cushion cap 2, and the bottom of the pier shaft 1 connects the cushion cap 2, the top connection of the pier shaft 1 The junction of the bent cap, the pier shaft 1 and bent cap is tongue-and-groove structure, and 1 bottom of the pier shaft is connected with steel plate 3, the steel plate 3 The reinforcing bar being welded to connect in the pier shaft 1,2 top of the cushion cap are connected with ground anchor bolt 4, and the ground anchor bolt 4 is welded to connect Reinforcing bar in the cushion cap 2, all ground anchor bolts of Kong Weiyu on the steel plate 34 are adapted to one by one, the size of the hole position More than the size of the ground anchor bolt 4, the pier shaft 1 connects the cushion cap 2, the cushion cap 2 by steel plate 3 and ground anchor bolt 4 Top surface is equipped with groove, and the steel plate 3 is set in the groove, and cast-in-place concrete component 5 is filled in the groove, described mixed The top surface of solidifying soil component 5 is flushed with 2 top surface of cushion cap.
When the prefabricated pier shaft 1, the steel plate 3 is welded to connect to the embedded bar bottom of the pier shaft 1, is held described in binding When the reinforcing bar of platform 2, the ground anchor bolt is welded to connect at the top of the reinforcing bar of the cushion cap 2, then pours the cushion cap 2, then Lifting the pier shaft 1 makes steel plate 3 be put into the groove, so that the ground anchor bolt 4 is passed through the hole position of the steel plate 3, then root The plan-position that the pier shaft 1 is adjusted according to actual conditions adjusts the elevation of the pier shaft 1 by increasing and decreasing spacer for bolt, then passes through Nut locking, after installing, without the protection of the protective devices such as crane, bridge pier can voluntarily be stablized, then in the groove Casting concrete component 5, realization pier shaft 1 are integrally attached to cushion cap 2, finally install upper component and support system.
Embodiment 2
A kind of construction method of assembling type girder bridge of the present invention is applied using a kind of assembling type girder bridge as described in Example 1 Work method comprises the following steps:
A, prefabricated pier shaft, wherein the reinforcing bar bottom junction steel plate in the pier shaft;
B, the reinforcing bar for binding cushion cap, ground anchor bolt is connected at the top of the reinforcing bar of the cushion cap;
C, the pier shaft is lifted, so that the steel plate is connect with ground anchor bolt, realizes that the pier shaft is connected with cushion cap;
D, bent cap is connected at the top of the pier shaft;
Upper component and support system are installed on the bent cap, form assembling type girder bridge.
In prefabricated pier shaft 1, it is welded to connect steel plate 3 in the bottom of its embedded bar, in the reinforcing bar of pre-buried cushion cap 2, The top of its reinforcing bar connects ground anchor bolt 4, perforating on the position being adapted to 4 position of the ground anchor bolt on the steel plate 3 The size of position, the hole position is more than the size of the ground anchor bolt 4, is finely tuned when being easily installed, then lifting the pier shaft 1 makes steel Plate 3 is put into the groove of the cushion cap 2, and the steel plate 3 is made to be connected with ground anchor bolt 4, then corrects the installation of the pier shaft 1 Position adjusts plan-position and the absolute altitude of the pier shaft 1 by position and spacer for bolt between the ground anchor bolt 4 and hole position, By nut by after 4 stable connection of the steel plate 3 and ground anchor bolt, crane is withdrawn, casting concrete is formed in the groove Concrete component 5 so that pier shaft 1 is linked together with basis, you can that realizes the pier shaft 1 stablizes installation, then reconnects lid Beam finally installs upper component and support system, completes the installation of assembling type girder bridge, saves artificial mechanism cost, accelerates construction Progress is conducive to shorten the construction period, and reduces influence of the construction period to traffic and environment, is particularly suitable for the limited work in construction site Journey.
The foregoing is merely illustrative of the preferred embodiments of the present invention, is not intended to limit the invention, all essences in the present invention All any modification, equivalent and improvement etc., should all be included in the protection scope of the present invention made by within refreshing and principle.

Claims (10)

1. a kind of assembling type girder bridge, which is characterized in that include upper component, lower member, support system and basis, the lower part Component includes prefabricated pier shaft (1) and prefabricated bent cap, and the basis includes cushion cap (2), and the top of the pier shaft (1) connects institute Bent cap is stated, the bottom of the pier shaft (1) connects the cushion cap (2) by steel plate (3) and ground anchor bolt (4), and the steel plate (3) is even Connect the reinforcing bar in the pier shaft (1), the ground anchor bolt (4) connects the reinforcing bar in the cushion cap (2), on the steel plate (3) Ground anchor bolt described in Kong Weiyu (4) is adapted to one by one.
2. assembling type girder bridge according to claim 1, which is characterized in that cushion cap (2) top surface is equipped with groove, the steel Plate (3) is set in the groove.
3. assembling type girder bridge according to claim 2, which is characterized in that be equipped with concrete component (5), institute in the groove It states concrete component (5) and covers the steel plate (3) and ground anchor bolt (4).
4. assembling type girder bridge according to claim 3, which is characterized in that the concrete component (5) is cast-in-place concrete The top surface of structure, the concrete component (5) is flushed with cushion cap (2) top surface.
5. according to any assembling type girder bridges of claim 1-4, which is characterized in that the cushion cap (2) is cast-in-place concrete Structure.
6. according to any assembling type girder bridges of claim 1-4, which is characterized in that the steel plate (3) is welded to connect described Reinforcing bar in pier shaft (1), the ground anchor bolt (4) are welded to connect the reinforcing bar in the cushion cap (2).
7. according to any assembling type girder bridges of claim 1-4, which is characterized in that the steel plate (3) and ground anchor bolt (4) Between be equipped with spacer for bolt.
8. according to any assembling type girder bridges of claim 1-4, which is characterized in that the ruler of the hole position on the steel plate (3) The very little size more than the ground anchor bolt (4).
9. a kind of construction method of assembling type girder bridge, which is characterized in that be applied to the assembled as described in claim 1-8 is any Beam bridge, construction method comprise the steps of:
A, prefabricated pier shaft (1), wherein the reinforcing bar bottom junction steel plate (3) in the pier shaft (1);
B, the reinforcing bar of binding cushion cap (2), the connection ground anchor bolt (4) at the top of the reinforcing bar of the cushion cap (2);
C, the pier shaft (1) is lifted, so that the steel plate (3) is connect with ground anchor bolt (4), realizes the pier shaft (1) and cushion cap (2) It is connected;
D, bent cap is connected at the top of the pier shaft (1);
E, upper component and support system on the bent cap are installed, assembling type girder bridge is formed.
10. construction method according to claim 9, which is characterized in that between the step c and d, be also included in described The junction cast-in-situ concrete member (5) of pier shaft (1) and cushion cap (2).
CN201810297853.4A 2018-04-03 2018-04-03 Assembling type girder bridge and construction method Pending CN108457172A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810297853.4A CN108457172A (en) 2018-04-03 2018-04-03 Assembling type girder bridge and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810297853.4A CN108457172A (en) 2018-04-03 2018-04-03 Assembling type girder bridge and construction method

Publications (1)

Publication Number Publication Date
CN108457172A true CN108457172A (en) 2018-08-28

Family

ID=63235108

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810297853.4A Pending CN108457172A (en) 2018-04-03 2018-04-03 Assembling type girder bridge and construction method

Country Status (1)

Country Link
CN (1) CN108457172A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112030729A (en) * 2020-08-26 2020-12-04 绍兴文理学院 Prefabricated bridge pier and bearing platform connecting system for assembled beam bridge and construction method of prefabricated bridge pier and bearing platform connecting system
CN113668388A (en) * 2021-07-14 2021-11-19 武汉二航路桥特种工程有限责任公司 Pier-beam cooperative integral rapid installation and removal method based on vehicle-mounted equipment

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006207124A (en) * 2005-01-25 2006-08-10 Nippon Sharyo Seizo Kaisha Ltd Steel-made pier structural body and its construction method
CN104343080A (en) * 2014-09-29 2015-02-11 北京工业大学 Method for constructing segmental prefabricating and assembling swing foundation pier
CN107386098A (en) * 2017-06-26 2017-11-24 天津大学 Flexing suppress round end type concrete pier of steel tube and with cushion cap connection structure and method
CN107806109A (en) * 2017-09-28 2018-03-16 中交第公路勘察设计研究院有限公司 Precast assembly bridge pier attachment means and its construction method
CN208105023U (en) * 2018-04-03 2018-11-16 中国建筑第五工程局有限公司 Assembling type girder bridge

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006207124A (en) * 2005-01-25 2006-08-10 Nippon Sharyo Seizo Kaisha Ltd Steel-made pier structural body and its construction method
CN104343080A (en) * 2014-09-29 2015-02-11 北京工业大学 Method for constructing segmental prefabricating and assembling swing foundation pier
CN107386098A (en) * 2017-06-26 2017-11-24 天津大学 Flexing suppress round end type concrete pier of steel tube and with cushion cap connection structure and method
CN107806109A (en) * 2017-09-28 2018-03-16 中交第公路勘察设计研究院有限公司 Precast assembly bridge pier attachment means and its construction method
CN208105023U (en) * 2018-04-03 2018-11-16 中国建筑第五工程局有限公司 Assembling type girder bridge

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112030729A (en) * 2020-08-26 2020-12-04 绍兴文理学院 Prefabricated bridge pier and bearing platform connecting system for assembled beam bridge and construction method of prefabricated bridge pier and bearing platform connecting system
CN113668388A (en) * 2021-07-14 2021-11-19 武汉二航路桥特种工程有限责任公司 Pier-beam cooperative integral rapid installation and removal method based on vehicle-mounted equipment
CN113668388B (en) * 2021-07-14 2023-12-19 中交特种工程有限公司 Pier-beam collaborative integral rapid installation and removal method based on vehicle-mounted equipment

Similar Documents

Publication Publication Date Title
EP3153627B1 (en) Foundations system for towers and method for installing the foundations system for towers
CN100564700C (en) The job practices of lattice type steel column tower crane pedestal
EP2837554A1 (en) Partially floating marine platform for offshore wind-power, bridges and marine buildings, and construction method
CN105002834A (en) Deviation rectifying and strengthening method for piers
JP6834226B2 (en) Pile foundation and tower rebuilding method
LU102092B1 (en) Newly-built or expanded wind power foundation structure on soft ground and construction method thereof
CN108265618B (en) Underground reverse storey-adding construction method for viaduct pier foundation
CN208105023U (en) Assembling type girder bridge
CN105863042A (en) All-steel structure building and construction method thereof
CN102561384A (en) Steel hoop truss type elevated pile cap tower crane foundation construction method and structure
US8555599B2 (en) Method for the construction of a civil engineering structure and associated system
CN102720207A (en) Tower foundation and tower of wind-driven generator
CN103696429A (en) Concrete support and fish-belly sill combined supporting system of special-shaped foundation pit and construction method
US20110299937A1 (en) Pre-stressed concrete foundation for a marine building structure
CN202519697U (en) Steel hoop truss high pile-cap tower crane basic structure
CN108457172A (en) Assembling type girder bridge and construction method
CN104711931B (en) Temporary underwater pier manufacturing, assembling and disassembling method suitable for bridge erection
CN203654309U (en) Pile-caisson hydraulic structure
CN203855904U (en) Windproof net upright column structure
CN206828906U (en) A kind of temporary pavement bedding structure for Metro Deep Excavation
KR101282333B1 (en) Cross-type supporting structure and method for super-structure of bridge
JP4094416B2 (en) Construction method of multilevel intersection
EP2576918A2 (en) Pre-stressed concrete foundation for a marine building structure
CN106759089A (en) Simple mudflat wharf based on waste tires and construction method thereof
CN202298641U (en) Tower foundation structure of high pile cap

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20180828