CN108444790A - A kind of impervious sample production method of the soil cement of practicality - Google Patents

A kind of impervious sample production method of the soil cement of practicality Download PDF

Info

Publication number
CN108444790A
CN108444790A CN201810484839.5A CN201810484839A CN108444790A CN 108444790 A CN108444790 A CN 108444790A CN 201810484839 A CN201810484839 A CN 201810484839A CN 108444790 A CN108444790 A CN 108444790A
Authority
CN
China
Prior art keywords
sample
sample preparation
cylinder
preparation cylinder
soil
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810484839.5A
Other languages
Chinese (zh)
Other versions
CN108444790B (en
Inventor
魏建东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhengzhou University
Original Assignee
Zhengzhou University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhengzhou University filed Critical Zhengzhou University
Priority to CN201810484839.5A priority Critical patent/CN108444790B/en
Publication of CN108444790A publication Critical patent/CN108444790A/en
Application granted granted Critical
Publication of CN108444790B publication Critical patent/CN108444790B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01NINVESTIGATING OR ANALYSING MATERIALS BY DETERMINING THEIR CHEMICAL OR PHYSICAL PROPERTIES
    • G01N1/00Sampling; Preparing specimens for investigation
    • G01N1/28Preparing specimens for investigation including physical details of (bio-)chemical methods covered elsewhere, e.g. G01N33/50, C12Q
    • G01N1/286Preparing specimens for investigation including physical details of (bio-)chemical methods covered elsewhere, e.g. G01N33/50, C12Q involving mechanical work, e.g. chopping, disintegrating, compacting, homogenising

Landscapes

  • Physics & Mathematics (AREA)
  • Health & Medical Sciences (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Chemical & Material Sciences (AREA)
  • Analytical Chemistry (AREA)
  • Biochemistry (AREA)
  • General Health & Medical Sciences (AREA)
  • General Physics & Mathematics (AREA)
  • Immunology (AREA)
  • Pathology (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
  • Sampling And Sample Adjustment (AREA)

Abstract

The invention discloses a kind of impervious sample production methods of the soil cement of practicality, belong to soil test technique field.The device that this production method uses includes mainly sample preparation cylinder, pressure-like plug, experimental desk and magnet base.Sample preparation cylinder is half-and-half type cylinder, is fitted together two cylinder pieces by bolt.Experimental desk lower surface is fixed with magnet base, is fixed sample preparation cylinder on the table by magnetic force.Flexible liner plate in sample preparation cylinder.The sample compactness obtained using this production method is uniform, cracked during avoidable late maintaining, and this production method is easy to operate, efficient.

Description

A kind of impervious sample production method of the soil cement of practicality
Technical field
The present invention relates to a kind of impervious sample production methods of the soil cement of practicality, belong to soil test technique field.
Background technology
In Excavation Process, water-head is generally had inside and outside foundation pit.Under the action of water-head, the water outside foundation pit can ooze Quicksand can occur in people's foundation pit, when serious or dash forward to gush, foundation pit is damaged.Water-stop curtain can be effectively prevented this kind of broken Bad, the underground water penetrated into foundation pit will be reduced significantly, it is easier to be discharged.In deep excavation project, underground water buried depth Can be that water-stop curtain is arranged in material around foundation pit with soil cement when shallower and soil layer infiltration coefficient is larger.Soil cement is just It is the mixture of soil and cement, generally uses Construction of High Pressure Jet Grouting Pile machinery in engineering, cement grout is mixed into shape in the soil body At.Therefore, it is necessary to understand the impervious characteristic of soil cement, to determine the best additive ratio of cement in soil cement, this just need into The impermeability test of row soil cement.
The preparation of the impervious sample of soil cement is a very the key link, and the quality of sample directly influences test result Accuracy.Currently, there are two types of the shapes of the impervious sample made in laboratory:Cylindrical and conical butt.In view of scene The cement soil sample of core boring sampling is cylindric, for the ease of the comparison of test results of the sample obtained with scene, indoor making Soil cement impervious sample should preferentially use it is cylindric.It is previous that such columned sample is generally made using cutting ring.
During making cylindric sample using cutting ring, it is real that soil cement is that layering is hit, and be easy to cause the compacting of sample Spend uneven, Coating combination, which is in subsequent maintenance, is susceptible to crackle.These factors can all have an impact test result, Urgently develop the impervious sample production method of soil cement of more rational practicality.
Invention content
It is an object of the invention to solve the problems, such as the deficiencies in the prior art and, it is anti-to provide a kind of soil cement of practicality Ooze sample production method.
The present invention provides a kind of impervious sample production method of the soil cement of practicality, the producing device of use includes mainly system Sample cylinder, pressure-like plug, experimental desk, magnet base and liner plate;Experimental desk lower surface is fixed with magnet base, and magnet base is by magnetic force by sample preparation Cylinder is fixed on desktop upper surface;Sample preparation cylinder is half-and-half type, is fitted together by bolt assembly by two cylinder pieces;Cylinder piece it is lateral There is flange, is useful for connecting the bolt hole of another piece on the flange;Liner plate is close to sample preparation cylinder inner wall, in lateral head and the tail phase It connects, is vertically higher by 10mm than sample preparation cylinder.
The process for making the impervious sample of soil cement includes mainly following steps:
Step 1:Two cylinder pieces are taken, it is opposite to be stitched together, the two is connected with, sample preparation cylinder is formed;
Step 2:Sample preparation cylinder is placed on smooth experimental desk, is fixed sample preparation cylinder by magnetic force;
Step 3:Liner plate is put into sample preparation cylinder, laterally keeps liner plate end to end, at this point, liner plate is close to sample preparation cylinder inner wall, liner plate Inner wall brushing mineral oil, as releasing agent;
Step 4:The cement soil sample soil stirred evenly is weighed, slowly pours into sample preparation cylinder, flattens;
Step 5:Pressure sample plug is put into sample preparation cylinder, by slowly applying pressure so that the upper surface of pressure-like plug and sample preparation cylinder Upper surface is concordant, and in the pressurized state, is kept for 5 minutes;
Step 6:Removal bolt assembly, to release magnetic force, cylinder piece removes pressure-like plug, has obtained cement rotation turn switch Soil sample;
Step 7:A cutting ring is taken, horizontal is on duroplasts backing plate, during the cement soil sample that step 5 obtains is put into cutting ring Between position, adjustment position makes the gap uniformity of cement soil sample and cutting ring inner wall, the stone that injection heating is crossed into gap with needle tubing Wax liquor body, it is ensured that sealing after 1 hour, has just obtained the impervious sample of soil cement.
Sample preparation cylinder uses half-and-half type, is for the ease of taking out the sample made, avoiding directly from cylinder(Such as cutting ring)It is interior When release, sample is damaged and is damaged.The soil cement for making needed for a sample is disposably packed into sample preparation cylinder, can avoid The problems such as compactness caused by reality is hit in layering is uneven and subsequent sample is also easy to produce crackle.The operation of sample preparation cylinder is fixed using magnet base Get up very convenient, quick, and keeps experiment table surface clean and tidy.It is in order in the internal diameter and standard for keeping sample preparation cylinder using liner plate In the case that cutting ring internal diameter is equal, the cement soil sample produced is put into when sealing with wax in cutting ring, cement soil sample in cutting ring There is a preset gap between wall, to ensure wax-layer thickness.
The internal diameter of the sample preparation cylinder is equal with standard cutting ring, is 61.8mm, outer diameter 70mm, is highly 80mm, cylinder There is flange in piece lower end.The internal diameter of sample preparation cylinder is equal with standard cutting ring internal diameter, convenient for being used for sample preparation cylinder to make conventional soil mechanics Sample increases the use scope of sample preparation cylinder.The flange of cylinder piece lower end is the preferably fixed sample preparation cylinder in order to increase magnetic force.
The material of the liner plate is spring steel, and plate thickness 3.0mm, no restrained condition is a tablet.Then carry out impervious examination It when testing preparation, needs that cement soil sample is put into cutting ring and is sealed with wax, to obtain impervious sample.The internal diameter of cutting ring is 61.8mm, a height of 40mm.After cement soil sample obtained is put into cutting ring, the gap of 3.0mm can meet the paraffin after heating The flowing of liquid ensures that sample is tightly wrapped up.The material of liner plate uses spring steel, it can be ensured that liner plate has enough elasticity, just In bending, and during taking out cement-stabilized soil sample, elasticity can make liner plate automatically disengage cement soil sample, and will not be to soil cement Sample generates damage or destroys.
A diameter of 55.0mm of the pressure-like plug is highly 40mm.The height of sample is 40mm, and the height of pressure-like plug is 40mm, the high 80mm of sample preparation cylinder.When sample preparation, the sample soil weighed is poured into sample preparation cylinder, after leveling, is put into pressure-like plug, by squeezing Pressure-like plug is pressed, the either flush of the upper surface and sample preparation cylinder of pressure-like plug is made, the soil cement that height is 40mm has then just been obtained and has tried Sample.There is the gap of average 0.4mm between pressure-like plug and liner plate, can avoid pressure-like plug pressure-like plug and touch sample preparation cylinder inner wall.
The sample preparation cylinder, pressure-like plug, experimental desk and bolt assembly material be stainless steel.This is to ensure gained Sample is not polluted by iron rust, also for the service life for increasing the device.
Compared with existing sample production method, the present invention can make sample one-pass molding, avoid in the manufacturing process of sample Sample later stage problem of Cracking caused by carrying out multilayer compacting;Sample uniform force during being compacted soil cement ensures closely knit Degree is uniform;The present apparatus makes simply, at low cost, easy to operate, and it is simple, efficient, quick to make sample flow channel.
Description of the drawings
Fig. 1 the structural representation of present invention.
Fig. 2 cylinder piece front schematic views.
The A-A sectional views of Fig. 3 cylinder pieces.
Fig. 4 cylinder piece schematic rear views.
Side schematic view after two cylinder piece assemblings of Fig. 5.
B-B sectional views after two cylinder piece assemblings of Fig. 6.
It is marked in figure:1- pieces;2- side flange bolts hole;3- pressure-like plugs;4- side flange bolts;5- sample soil;6- side flanges Nut;7- side flanges;8- bottom flanges;9- desktops;10- supporting legs;11- magnet bases;12- rotary switches;13- liner plates.
Specific implementation mode
The following is specific embodiments of the present invention, and technical scheme of the present invention is described in conjunction with attached drawing.
Embodiment
The practical impervious sample production method of soil cement in the embodiment, used device include mainly sample preparation cylinder, pressure-like Plug 3, experimental desk and magnet base 11, referring specifically to Fig. 1-Fig. 6.Experimental desk is made of desktop 9 and 4 supporting legs 10,9 following table of desktop Face is fixed with magnet base 11, and magnet base 11 carries the rotary switch 12. of adjustable magnetic force size.Sample preparation cylinder is by two 1 group of cylinder pieces At having side flange bolt hole 2 on the side flange 7 of cylinder piece 1.Two cylinder pieces 1 are assembled in by side flange bolt 4 and side flange nut 6 Together.There is bottom flange 8 in the lower end of cylinder piece 1.The internal diameter of sample preparation cylinder is 61.8mm, outer diameter 70mm, is highly 80mm.Pressure-like plug 3 A diameter of 55.0mm, be highly 40mm.Clip 2 is made of two clip pieces 7, passes through diametrically opposite two bolt assemblies It links together, bolt assembly includes bolt 4 and nut 6.Liner plate 13 is close to sample preparation cylinder inner wall, end to end in transverse direction, vertically It is higher by 10mm than sample preparation cylinder.The material of liner plate 13 is spring steel, and plate thickness 3.0mm, no restrained condition is a tablet.Sample preparation cylinder, pressure Sample plug 3, experimental desk, all bolts and nuts material be stainless steel.
When making the impervious sample of soil cement, using following steps:
Step 1:Two cylinder pieces 1 are taken, it is opposite to be stitched together, side flange bolt 4 and side flange nut 6 are taken, side flange bolt 4 is made to wear Side flange bolt hole 2 is crossed, side flange nut 6 is tightened, forms sample preparation cylinder;
Step 2:Sample preparation cylinder is placed on to the upper surface of the desktop 9 of smooth experimental desk, adjustment position makes sample preparation cylinder be located at mark Position, lower face with the upper surface of desktop 9 is seamless contacts, rotation turn switch 12 is fixed sample preparation cylinder by magnetic force;
Step 3:Liner plate 13 is put into sample preparation cylinder, laterally keeps liner plate 13 end to end, at this point, liner plate 13 is close in sample preparation cylinder Wall.13 inner wall brushing mineral oil of liner plate, as releasing agent;
Step 4:The cement soil sample soil 5 stirred evenly is weighed, is slowly poured into sample preparation cylinder, is flattened;
Step 5:Pressure sample plug 3 is put into sample preparation cylinder, by slowly applying pressure so that the upper surface of pressure-like plug 3 and sample preparation cylinder Upper surface it is concordant, and in the pressurized state, kept for 5 minutes, this be in order to avoid molding cement soil sample occur it is larger Resilience;
Step 6:Unscrew side flange nut 6, removal bolt assembly, rotation turn switch 12 releases magnetic force, cylinder piece 1, removal Pressure-like plug 3 obtains cement soil sample at this point, liner plate 13 automatically strips;
Step 7:A cutting ring is taken, horizontal is on duroplasts backing plate, during the cement soil sample that step 5 obtains is put into cutting ring Between position, adjustment position makes the gap uniformity of cement soil sample and cutting ring inner wall, the stone that injection heating is crossed into gap with needle tubing Wax liquor body, it is ensured that sealing after 1 hour, has just obtained the impervious sample of soil cement.
The description of above-mentioned specific implementation mode is merely to illustrate the present invention, rather than the rights protection model of the limitation present invention It encloses.

Claims (5)

1. a kind of impervious sample production method of the soil cement of practicality, it is characterised in that:The producing device of use includes mainly sample preparation Cylinder, pressure-like plug, experimental desk, magnet base and liner plate;Experimental desk lower surface is fixed with magnet base, and magnet base is by magnetic force by sample preparation cylinder It is fixed on desktop upper surface;Sample preparation cylinder is half-and-half type, is fitted together by bolt assembly by two cylinder pieces;The lateral of cylinder piece has Flange is useful for connecting the bolt hole of another piece on the flange;Liner plate is close to sample preparation cylinder inner wall, end to end in transverse direction, Vertically 10mm is higher by than sample preparation cylinder;The process for making the impervious sample of soil cement includes mainly following steps:
Step 1:Two cylinder pieces are taken, it is opposite to be stitched together, the two is connected with, sample preparation cylinder is formed;
Step 2:Sample preparation cylinder is placed on smooth experimental desk, is fixed sample preparation cylinder by magnetic force;
Step 3:Liner plate is put into sample preparation cylinder, laterally keeps liner plate end to end, at this point, liner plate is close to sample preparation cylinder inner wall, liner plate Inner wall brushing mineral oil, as releasing agent;
Step 4:The cement soil sample soil stirred evenly is weighed, slowly pours into sample preparation cylinder, flattens;
Step 5:Pressure sample plug is put into sample preparation cylinder, by slowly applying pressure so that the upper surface of pressure-like plug and sample preparation cylinder Upper surface is concordant, and in the pressurized state, is kept for 5 minutes;
Step 6:Removal bolt assembly, to release magnetic force, cylinder piece removes pressure-like plug, has obtained cement rotation turn switch Soil sample;
Step 7:A cutting ring is taken, horizontal is on duroplasts backing plate, during the cement soil sample that step 5 obtains is put into cutting ring Between position, adjustment position makes the gap uniformity of cement soil sample and cutting ring inner wall, the stone that injection heating is crossed into gap with needle tubing Wax liquor body, it is ensured that sealing after 1 hour, has just obtained the impervious sample of soil cement.
2. the impervious sample production method of soil cement according to claim 1, it is characterised in that:The internal diameter of the sample preparation cylinder It is equal with standard cutting ring, it is 61.8mm, outer diameter 70mm, is highly 80mm, there is flange in cylinder piece lower end.
3. the impervious sample production method of soil cement according to claim 1, it is characterised in that:The material of liner plate is spring Steel, plate thickness 3.0mm, no restrained condition are a tablet.
4. the impervious sample production method of soil cement according to claim 1, it is characterised in that:Pressure-like plug it is a diameter of 55.0mm is highly 40mm.
5. the impervious sample production method of soil cement according to claim 1, it is characterised in that:Sample preparation cylinder, pressure-like plug, experiment The material of table and bolt assembly is stainless steel.
CN201810484839.5A 2018-05-20 2018-05-20 Practical cement soil impervious sample manufacturing method Active CN108444790B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810484839.5A CN108444790B (en) 2018-05-20 2018-05-20 Practical cement soil impervious sample manufacturing method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810484839.5A CN108444790B (en) 2018-05-20 2018-05-20 Practical cement soil impervious sample manufacturing method

Publications (2)

Publication Number Publication Date
CN108444790A true CN108444790A (en) 2018-08-24
CN108444790B CN108444790B (en) 2024-02-27

Family

ID=63204062

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810484839.5A Active CN108444790B (en) 2018-05-20 2018-05-20 Practical cement soil impervious sample manufacturing method

Country Status (1)

Country Link
CN (1) CN108444790B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110006715A (en) * 2019-01-25 2019-07-12 同创工程设计有限公司 A kind of modified native method for making sample without lateral confinement sample of stream modeling
CN110296928A (en) * 2019-07-19 2019-10-01 三峡大学 The device and method of visualization fracture seepage is simulated using magnetic fluid
CN111879580A (en) * 2020-06-22 2020-11-03 北京建筑大学 Sample preparation device and sample preparation method for geotechnical large triaxial test

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06174614A (en) * 1992-10-05 1994-06-24 Nifco Inc Mold for mock-up for testing concrete strength
US20130196160A1 (en) * 2011-05-18 2013-08-01 Riken Method for forming protein crystal
CN204241292U (en) * 2014-12-05 2015-04-01 南京市建筑安装工程质量检测中心 A kind of soil cement flexible wall permeameter cement stock mould
CN105067411A (en) * 2015-09-14 2015-11-18 河海大学 Sampling device for laboratory test of sludge solidification treatment and sampling method thereof
CN205130096U (en) * 2015-11-06 2016-04-06 中建商品混凝土西安有限公司 A examination mould brush for applying paint glue sand examination mould release agent
CN105716924A (en) * 2016-04-25 2016-06-29 苏州市建设工程质量检测中心有限公司 Concrete anti-permeability test model
CN205607724U (en) * 2016-04-25 2016-09-28 苏州市建设工程质量检测中心有限公司 Impervious test mould of concrete
CN105973782A (en) * 2016-05-25 2016-09-28 长安大学 Determination instrument and determination method for osmotic coefficients of drilling and coring test part
CN207300679U (en) * 2017-09-20 2018-05-01 山东山推胜方工程机械有限公司 A kind of concrete impervious test mould
CN208155689U (en) * 2018-05-20 2018-11-27 郑州大学 A kind of impervious sample producing device of practical soil cement

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06174614A (en) * 1992-10-05 1994-06-24 Nifco Inc Mold for mock-up for testing concrete strength
US20130196160A1 (en) * 2011-05-18 2013-08-01 Riken Method for forming protein crystal
CN204241292U (en) * 2014-12-05 2015-04-01 南京市建筑安装工程质量检测中心 A kind of soil cement flexible wall permeameter cement stock mould
CN105067411A (en) * 2015-09-14 2015-11-18 河海大学 Sampling device for laboratory test of sludge solidification treatment and sampling method thereof
CN205130096U (en) * 2015-11-06 2016-04-06 中建商品混凝土西安有限公司 A examination mould brush for applying paint glue sand examination mould release agent
CN105716924A (en) * 2016-04-25 2016-06-29 苏州市建设工程质量检测中心有限公司 Concrete anti-permeability test model
CN205607724U (en) * 2016-04-25 2016-09-28 苏州市建设工程质量检测中心有限公司 Impervious test mould of concrete
CN105973782A (en) * 2016-05-25 2016-09-28 长安大学 Determination instrument and determination method for osmotic coefficients of drilling and coring test part
CN207300679U (en) * 2017-09-20 2018-05-01 山东山推胜方工程机械有限公司 A kind of concrete impervious test mould
CN208155689U (en) * 2018-05-20 2018-11-27 郑州大学 A kind of impervious sample producing device of practical soil cement

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110006715A (en) * 2019-01-25 2019-07-12 同创工程设计有限公司 A kind of modified native method for making sample without lateral confinement sample of stream modeling
CN110296928A (en) * 2019-07-19 2019-10-01 三峡大学 The device and method of visualization fracture seepage is simulated using magnetic fluid
CN110296928B (en) * 2019-07-19 2022-04-08 三峡大学 Device and method for simulating visual fracture seepage by using magnetofluid
CN111879580A (en) * 2020-06-22 2020-11-03 北京建筑大学 Sample preparation device and sample preparation method for geotechnical large triaxial test

Also Published As

Publication number Publication date
CN108444790B (en) 2024-02-27

Similar Documents

Publication Publication Date Title
CN108444790A (en) A kind of impervious sample production method of the soil cement of practicality
CN103389249B (en) A kind of clay core wall Hydraulic fracturing test device and test method
CN108444789A (en) A kind of preparation method of the impervious sample of soil cement
CN208140451U (en) A kind of preparation facilities of the impervious sample of soil cement
CN208155689U (en) A kind of impervious sample producing device of practical soil cement
CN208155690U (en) A kind of impervious sample producing device of soil cement
CN107421811B (en) Proppant pressure experiment machine and method for fracturing
CN108444892A (en) A kind of impervious sample production method of the soil cement of simplicity
CN208155802U (en) A kind of impervious sample producing device of the soil cement of simplicity
CN110629622B (en) Grouting reinforcement device for roadbed construction and use method thereof
CN108398307A (en) A kind of impervious sample production method of soil cement
CN108396793A (en) A kind of impervious sample production method of easy soil cement
CN208201957U (en) A kind of impervious sample producing device of easy soil cement
CN214616582U (en) Jacking construction reinforced concrete pipe grouting non-return device
KR100469525B1 (en) The replacement type pillar-shaped hardening structure formation equipment and the formation method of leading mortar jet
CN217580080U (en) Drilling and grouting drilling tool for compaction grouting dry construction
CN114718046A (en) Sleeve valve pipe grouting structure for deep soil filling layer and construction method thereof
CN107817151A (en) A kind of saturation remodeling cohesive soil preparation of soil sample device and its application method
CN114411700A (en) Steel pile body for steel pipe grouting pile construction while sinking pipe and grouting
CN112144516A (en) Construction method of concrete pile
CN111779201A (en) Inverted roof water seepage and leakage stoppage construction method
CN215332702U (en) Slip casting drill device
CN113551968B (en) Preparation method of pipe jacking structure and surrounding rock soil body model forming device
CN110158386A (en) A kind of grouting method reinforced for road rehabilitation
CN110645023A (en) Tunnel secondary lining arch anti-void longitudinal withdrawal pipe type belt mold grouting equipment

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant