CN108425632A - A kind of building drilling equipment that drilling efficiency is high - Google Patents
A kind of building drilling equipment that drilling efficiency is high Download PDFInfo
- Publication number
- CN108425632A CN108425632A CN201810177533.5A CN201810177533A CN108425632A CN 108425632 A CN108425632 A CN 108425632A CN 201810177533 A CN201810177533 A CN 201810177533A CN 108425632 A CN108425632 A CN 108425632A
- Authority
- CN
- China
- Prior art keywords
- spacing part
- shaft
- cone tooth
- drilling
- rotating shaft
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000005553 drilling Methods 0.000 title claims abstract description 46
- NJPPVKZQTLUDBO-UHFFFAOYSA-N novaluron Chemical compound C1=C(Cl)C(OC(F)(F)C(OC(F)(F)F)F)=CC=C1NC(=O)NC(=O)C1=C(F)C=CC=C1F NJPPVKZQTLUDBO-UHFFFAOYSA-N 0.000 claims abstract description 12
- 238000009434 installation Methods 0.000 claims description 8
- 238000010276 construction Methods 0.000 description 10
- 238000010586 diagram Methods 0.000 description 2
- 238000005516 engineering process Methods 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 230000005611 electricity Effects 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 238000000034 method Methods 0.000 description 1
- 238000002360 preparation method Methods 0.000 description 1
- 230000006641 stabilisation Effects 0.000 description 1
- 238000011105 stabilization Methods 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21B—EARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B15/00—Supports for the drilling machine, e.g. derricks or masts
- E21B15/003—Supports for the drilling machine, e.g. derricks or masts adapted to be moved on their substructure, e.g. with skidding means; adapted to drill a plurality of wells
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- Geology (AREA)
- Mining & Mineral Resources (AREA)
- Mechanical Engineering (AREA)
- Physics & Mathematics (AREA)
- Environmental & Geological Engineering (AREA)
- Fluid Mechanics (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Drilling And Boring (AREA)
- Processing Of Stones Or Stones Resemblance Materials (AREA)
Abstract
The invention discloses a kind of building drilling equipments that drilling efficiency is high,Including pedestal,The chassis interior is provided with first rotating shaft,The first rotating shaft is rotatably arranged on pedestal both sides by bearing,The first cone tooth is provided in the first rotating shaft,The first cone tooth and the second cone tooth engagement,The second cone tooth is fixed in the second shaft,Second shaft bottom is rotatably arranged on base bottom by bearing,The first rotating shaft left end is provided with handwheel,Second shaft upper end is provided with support element,The support element upper end is provided with mounting bracket,The mounting bracket bottom is provided with connector,The connector bottom is provided with mounting plate,It is provided with electric drill on the mounting plate,It is provided with boring work platform below the electric drill,It is provided with longitudinal spacing part and cross spacing part on the boring work platform,The configuration of the present invention is simple,It is easy to use,Labor intensity is low,Borehole stability is high.
Description
Technical field
The present invention relates to construction equipment field, the high building drilling equipment of specifically a kind of drilling efficiency.
Background technology
Construction refers to the production activity of engineering construction implementation phase, is the building course of all kinds of buildings, can also
It says it is various lines on design drawing, in specified place, becomes process in kind.It includes basic engineering construction, master
Body structure construction, roof construction, decorative engineering construction etc..The place of construction operation is known as " construction site " or cries
" construction site ", is also named building site.Architectural engineering is applying man-hour requirement to specific position progress drilling machine pore-forming, and existing drilling machine is
Hand-held easily causes to deviate during use to the orientation of drilling, and shakes the stabilization of larger impact drilling machine work, and labour is strong
Degree is big, for this purpose, it is proposed that a kind of more practical architectural engineering drilling machine hole-forming device.
Invention content
The purpose of the present invention is to provide a kind of building drilling equipments that drilling efficiency is high, to solve in above-mentioned background technology
The problem of proposition.
To achieve the above object, the present invention provides the following technical solutions:
A kind of building drilling equipment that drilling efficiency is high, including pedestal, the chassis interior are provided with first rotating shaft, and described first
Shaft is rotatably arranged on pedestal both sides by bearing, the first cone tooth is provided in the first rotating shaft, the first cone tooth is two
A, the first cone tooth and the second cone tooth engagement, the second cone tooth are fixed in the second shaft, second rotating shaft bottom
Portion is rotatably arranged on base bottom by bearing, and second shaft upper end is provided with external screw thread, and the first rotating shaft left end is set
It is equipped with handwheel, second shaft upper end is provided with support element, and the support element is internally provided with internal thread, on the support element
End is provided with mounting bracket, and the mounting bracket bottom is provided with connector, and the connector bottom is provided with mounting plate, the installation
It is provided with electric drill on plate, is provided with boring work platform below the electric drill, longitudinal spacing part is provided on the boring work platform
With cross spacing part, the longitudinal spacing part and cross spacing part are slidably arranged in by sliding slot on boring work platform, described vertical
Threaded hole is respectively provided on locating part and cross spacing part, the longitudinal spacing part and cross spacing part bottom are provided with installation
Part, the installation part both sides are provided with pulley, and scale is arranged on the boring work platform, and the scale is two, the scale
It is parallel to be arranged with sliding slot, it is provided with pointer on the longitudinal spacing part and cross spacing part.
As a further solution of the present invention:External screw thread cooperation on internal thread and the second shaft on the support element.
As further scheme of the invention:On the electric drill assembly setting mounting plate.
As further scheme of the invention:The longitudinal spacing part and cross spacing part are both provided with by threaded hole
Clamping screw.
As further scheme of the invention:The pulley is arranged in sliding slot.
As further scheme of the invention:It is provided with scale on the scale.
As further scheme of the invention:It is arranged close to scale on the pointer.
Compared with prior art, the beneficial effects of the invention are as follows:The present invention is passed through by fixing on a mounting board electric drill
It moves up and down device and drives mounting plate movement, prevent electric drill when drilling from shaking, improve the accuracy of drilling when drilling, set simultaneously
Vertical and horizontal limiting device has been set, the movement of drilling part is limited, the stability of drilling has been further improved, reduces simultaneously
Labor intensity, the configuration of the present invention is simple is easy to use, and labor intensity is low, and borehole stability is high.
Description of the drawings
Fig. 1 is the structural schematic diagram of the high building drilling equipment of drilling efficiency.
Fig. 2 is A-A direction views in Fig. 1.
Fig. 3 is the structural schematic diagram of cross spacing part in the high building drilling equipment of drilling efficiency.
Fig. 4 is enlarged drawing at B in Fig. 3.
In figure:1- pedestals, 2- first rotating shafts, the second shafts of 3-, 4- handwheels, 5- first bore tooth, 6- second bores tooth, 7- supports
Part, 8- mounting brackets, 9- connectors, 10- mounting plates, 11- electric drills, 12- boring works platform, 13- clamping screws, 14- longitudinal spacings
Part, 15- cross spacings part, 16- sliding slots, 17- scales, 18- pointers, 19- installation parts, 20- pulleys.
Specific implementation mode
In the description of the present invention, it is to be understood that, term "center", " longitudinal direction ", " transverse direction ", "upper", "lower",
The orientation or positional relationship of the instructions such as "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outside" is
It is based on the orientation or positional relationship shown in the drawings, is merely for convenience of description of the present invention and simplification of the description, rather than instruction or dark
Show that signified device or element must have a particular orientation, with specific azimuth configuration and operation, therefore should not be understood as pair
The limitation of the present invention.In addition, term " first ", " second " etc. are used for description purposes only, it is not understood to indicate or imply phase
To importance or implicitly indicate the quantity of indicated technical characteristic.The feature for defining " first ", " second " etc. as a result, can
To express or implicitly include one or more this feature.In the description of the present invention, unless otherwise indicated, " multiple "
It is meant that two or more.
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete
Site preparation describes, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on
Embodiment in the present invention, it is obtained by those of ordinary skill in the art without making creative efforts every other
Embodiment shall fall within the protection scope of the present invention.
Please refer to Fig.1~4, in the embodiment of the present invention, a kind of building drilling equipment that drilling efficiency is high, including pedestal 1, institute
It states pedestal 1 and is internally provided with first rotating shaft 2, the first rotating shaft 2 is rotatably arranged on 1 both sides of pedestal by bearing, and described first
The first cone tooth 5 is provided in shaft 2, the first cone tooth 5 is two, and the first cone tooth 5 is engaged with the second cone tooth 6, described
Second cone tooth 6 is fixed in the second shaft 3, and 3 bottom of the second shaft is rotatably arranged on 1 bottom of pedestal by bearing,
Second shaft, 3 upper end is provided with external screw thread, and 2 left end of the first rotating shaft is provided with handwheel 4,3 upper end of the second shaft
It is provided with support element 7, the support element 7 is internally provided with internal thread, on the internal thread and the second shaft 3 on the support element 7
External screw thread cooperation, 7 upper end of the support element is provided with mounting bracket 8, and 8 bottom of the mounting bracket is provided with connector 9, the company
9 bottom of fitting is provided with mounting plate 10, and electric drill 11, the assembly setting mounting plate 10 of the electric drill 11 are provided on the mounting plate 10
On, 11 lower section of the electric drill is provided with boring work platform 12, and longitudinal spacing part 14 and cross are provided on the boring work platform 12
To locating part 15, the longitudinal spacing part 14 and cross spacing part 15 are slidably arranged in by sliding slot 16 on boring work platform 12,
Threaded hole, institute's longitudinal spacing part 14 and cross spacing part 15 are respectively provided on the longitudinal spacing part 14 and cross spacing part 15
It is both provided with clamping screw 13 by threaded hole, the longitudinal spacing part 14 and 15 bottom of cross spacing part are provided with installation part
19,19 both sides of the installation part are provided with pulley 20, and the pulley 20 is arranged in sliding slot 16, is set on the boring work platform 12
Scale 17 to be set, scale is provided on the scale 17, the scale 17 is two, and the scale 17 is parallel to be arranged with sliding slot 16,
It is provided with pointer 18 on the longitudinal spacing part 14 and cross spacing part 15, is arranged close to scale 17 on the pointer 18.
The present invention operation principle be:The position adjustment cross spacing part 15 and longitudinal spacing part 14 of drilling part as needed
Position, when longitudinal spacing part 14 and cross spacing part 15 are adjusted to suitable position, rotation clamping screw 13 moves downward will be vertical
It is fixed on boring work platform 12 to locating part 14 and cross spacing part 15, drilling part is placed on boring work platform 12, led to
It crosses longitudinal spacing part 14 and cross spacing part 15 carries out horizontal and vertical restriction, electric drill 11 is powered, and rotation hand wheel 4 passes through the first cone
Tooth 5, second bores tooth 6, support element 7, mounting bracket 8, connector 9 and the drive electric drill 11 of mounting plate 10 and moves downward and drill, and bores
The cone of tooth 5, second tooth 6, support element 7, mounting bracket 8, connector 9 and mounting plate 10 are bored by handwheel 4, first after the completion of hole and drive electricity
It bores 11 and exits drilling part, complete drilling.
It is obvious to a person skilled in the art that invention is not limited to the details of the above exemplary embodiments, Er Qie
In the case of without departing substantially from spirit or essential attributes of the invention, the present invention can be realized in other specific forms.Therefore, no matter
From the point of view of which point, the present embodiments are to be considered as illustrative and not restrictive, and the scope of the present invention is by appended power
Profit requires rather than above description limits, it is intended that all by what is fallen within the meaning and scope of the equivalent requirements of the claims
Variation is included within the present invention.Any reference signs in the claims should not be construed as limiting the involved claims.
In addition, it should be understood that although this specification is described in terms of embodiments, but not each embodiment is only wrapped
Containing an independent technical solution, this description of the specification is merely for the sake of clarity, and those skilled in the art should
It considers the specification as a whole, the technical solutions in the various embodiments may also be suitably combined, forms those skilled in the art
The other embodiment being appreciated that.
Claims (7)
1. a kind of building drilling equipment that drilling efficiency is high, which is characterized in that including pedestal(1), the pedestal(1)Inside setting
There is first rotating shaft(2), the first rotating shaft(2)It is rotatably arranged on pedestal by bearing(1)Both sides, the first rotating shaft(2)On
It is provided with the first cone tooth(5), the first cone tooth(5)It is two, the first cone tooth(5)With the second cone tooth(6)Engagement, it is described
Second cone tooth(6)It is fixed at the second shaft(3)On, second shaft(3)Bottom is rotatably arranged on pedestal by bearing
(1)Bottom, second shaft(3)Upper end is provided with external screw thread, the first rotating shaft(2)Left end is provided with handwheel(4), described
Second shaft(3)Upper end is provided with support element(7), the support element(7)It is internally provided with internal thread, the support element(7)On
End is provided with mounting bracket(8), the mounting bracket(8)Bottom is provided with connector(9), the connector(9)Bottom is provided with peace
Loading board(10), the mounting plate(10)On be provided with electric drill(11), the electric drill(11)Lower section is provided with boring work platform(12),
The boring work platform(12)On be provided with longitudinal spacing part(14)With cross spacing part(15), the longitudinal spacing part(14)With
Cross spacing part(15)Pass through sliding slot(16)It is slidably arranged in boring work platform(12)On, the longitudinal spacing part(14)And transverse direction
Locating part(15)On be respectively provided with threaded hole, the longitudinal spacing part(14)With cross spacing part(15)Bottom is provided with installation part
(19), the installation part(19)Both sides are provided with pulley(20), the boring work platform(12)Upper setting scale(17), the mark
Ruler(17)It is two, the scale(17)Parallel and sliding slot(16)Setting, the longitudinal spacing part(14)With cross spacing part
(15)On be provided with pointer(18).
2. the high building drilling equipment of drilling efficiency according to claim 1, which is characterized in that the support element(7)On
Internal thread and the second shaft(3)On external screw thread cooperation.
3. the high building drilling equipment of drilling efficiency according to claim 1, which is characterized in that the electric drill(11)Assembly
Mounting plate is set(10)On.
4. the high building drilling equipment of drilling efficiency according to claim 1, which is characterized in that the longitudinal spacing part
(14)With cross spacing part(15)It is both provided with clamping screw by threaded hole(13).
5. the high building drilling equipment of drilling efficiency according to claim 1, which is characterized in that the pulley(20)Setting
In sliding slot(16)It is interior.
6. the high building drilling equipment of drilling efficiency according to claim 1, which is characterized in that the scale(17)On set
It is equipped with scale.
7. the high building drilling equipment of drilling efficiency according to claim 1, which is characterized in that the pointer(18)Upper patch
Nearly scale(17)Setting.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810177533.5A CN108425632A (en) | 2018-03-05 | 2018-03-05 | A kind of building drilling equipment that drilling efficiency is high |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810177533.5A CN108425632A (en) | 2018-03-05 | 2018-03-05 | A kind of building drilling equipment that drilling efficiency is high |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108425632A true CN108425632A (en) | 2018-08-21 |
Family
ID=63157706
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810177533.5A Pending CN108425632A (en) | 2018-03-05 | 2018-03-05 | A kind of building drilling equipment that drilling efficiency is high |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108425632A (en) |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN85108188A (en) * | 1984-11-08 | 1986-04-10 | 林明鸾 | Boring and/or crane |
US20150218891A1 (en) * | 2013-02-13 | 2015-08-06 | Nabors Drilling Usa, Lp | Slingshot side saddle substructure |
CN204711278U (en) * | 2015-01-21 | 2015-10-21 | 湖北辉创重型工程有限公司 | A kind of hole drilling die |
CN105067511A (en) * | 2015-09-02 | 2015-11-18 | 浙江大学城市学院 | Transparent soil model pile experimental testing device and application method thereof |
CN205996452U (en) * | 2016-08-31 | 2017-03-08 | 山东世纪开元电子商务有限公司 | It is applied to the engraving locating template of laser engraving machine |
CN107309470A (en) * | 2017-08-18 | 2017-11-03 | 浙江湖州天强建筑材料有限公司 | A kind of construction material processing drilling machine |
CN107676045A (en) * | 2017-11-10 | 2018-02-09 | 赣州研顺飞科技有限公司 | A kind of high accuracy construction drilling platform |
-
2018
- 2018-03-05 CN CN201810177533.5A patent/CN108425632A/en active Pending
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN85108188A (en) * | 1984-11-08 | 1986-04-10 | 林明鸾 | Boring and/or crane |
US20150218891A1 (en) * | 2013-02-13 | 2015-08-06 | Nabors Drilling Usa, Lp | Slingshot side saddle substructure |
CN204711278U (en) * | 2015-01-21 | 2015-10-21 | 湖北辉创重型工程有限公司 | A kind of hole drilling die |
CN105067511A (en) * | 2015-09-02 | 2015-11-18 | 浙江大学城市学院 | Transparent soil model pile experimental testing device and application method thereof |
CN205996452U (en) * | 2016-08-31 | 2017-03-08 | 山东世纪开元电子商务有限公司 | It is applied to the engraving locating template of laser engraving machine |
CN107309470A (en) * | 2017-08-18 | 2017-11-03 | 浙江湖州天强建筑材料有限公司 | A kind of construction material processing drilling machine |
CN107676045A (en) * | 2017-11-10 | 2018-02-09 | 赣州研顺飞科技有限公司 | A kind of high accuracy construction drilling platform |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN208267752U (en) | It is a kind of to facilitate positioning and stable engineering the drilling device | |
CN206513311U (en) | Jumbolter | |
CN114277804B (en) | Stable foundation pit supporting beam and mounting method thereof | |
CN108425632A (en) | A kind of building drilling equipment that drilling efficiency is high | |
CN108543992A (en) | A method of suspended ceiling drilling is carried out to house, market | |
CN215339007U (en) | Multi-angle sampling device for building engineering material detection | |
CN108580950A (en) | A kind of building drilling device of practicability | |
CN104874827B (en) | Axial drilling machine | |
CN108543972A (en) | A kind of building drilling equipment easy to use | |
CN205685280U (en) | A kind of top plate drilling special stretchable lever machinery arm | |
CN108237243A (en) | For the suspended ceiling drilling equipment of building roof | |
CN109252684A (en) | A kind of reliable and stable equilibristat for building | |
CN213336865U (en) | Mining exploration equipment | |
CN108007715A (en) | The closed soil sampling apparatus of one kind drilling | |
CN212079190U (en) | Base for pneumatic jumbolter | |
CN207976215U (en) | A kind of gear position limiting formula Fast Installation mining drill carriage rock drill vibration-testing apparatus | |
CN208067378U (en) | A kind of architectural engineering drilling equipment | |
CN207495683U (en) | A kind of circle building blocks drilling equipment | |
CN221222185U (en) | Multifunctional engineering measuring device for building management | |
CN204920813U (en) | Boring tower and trepan | |
CN108414174A (en) | A kind of gear position limiting formula Fast Installation mining drill carriage rock drill vibration-testing apparatus | |
CN205765006U (en) | Insulating part inclined borehole workbench | |
CN221032447U (en) | Drilling device for engineering | |
JP2005271432A (en) | Core drill device | |
CN217841542U (en) | Anchor eye drilling equipment for civil engineering |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20180821 |
|
RJ01 | Rejection of invention patent application after publication |