CN108390372A - A kind of power grid accident fast power restoration method under baseline risk - Google Patents
A kind of power grid accident fast power restoration method under baseline risk Download PDFInfo
- Publication number
- CN108390372A CN108390372A CN201810162559.2A CN201810162559A CN108390372A CN 108390372 A CN108390372 A CN 108390372A CN 201810162559 A CN201810162559 A CN 201810162559A CN 108390372 A CN108390372 A CN 108390372A
- Authority
- CN
- China
- Prior art keywords
- telegram
- reply
- power grid
- module
- value
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J3/00—Circuit arrangements for ac mains or ac distribution networks
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J2203/00—Indexing scheme relating to details of circuit arrangements for AC mains or AC distribution networks
- H02J2203/20—Simulating, e g planning, reliability check, modelling or computer assisted design [CAD]
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J3/00—Circuit arrangements for ac mains or ac distribution networks
- H02J3/001—Methods to deal with contingencies, e.g. abnormalities, faults or failures
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y04—INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
- Y04S—SYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
- Y04S10/00—Systems supporting electrical power generation, transmission or distribution
- Y04S10/50—Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications
- Y04S10/52—Outage or fault management, e.g. fault detection or location
Landscapes
- Engineering & Computer Science (AREA)
- Power Engineering (AREA)
- Supply And Distribution Of Alternating Current (AREA)
Abstract
The present invention relates to the technical fields of electric power system dispatching operation, more particularly, to a kind of power grid accident fast power restoration method under baseline risk.A kind of power grid accident fast power restoration method under baseline risk, wherein the telegram in reply module being connect including decision-making module, with decision-making module, the computing module being connect with telegram in reply module;The telegram in reply model under electric network wiring scheme and the various baseline risk accidents of storage is established by each Substation parameters of EMS system, circuit model and connection relation.Stress model triggers accident event, and inverting accident process selects optimal telegram in reply path events, and Brief News are generated by tidal current chart Dynamic Display telegram in reply process with switch motion, equipment coloring mode.Whole process does not influence the normal operation of SCADA system.
Description
Technical field
The present invention relates to the technical fields of electric power system dispatching operation, more particularly, to power grid under a kind of baseline risk
Accident fast power restoration method.
Background technology
When power grid occurrence of large-area power outage, dispatcher is generally dynamic according to trouble-signal, decompression website and circuit, protection
Make situation, failure judgement position compares the roadmap of accident prediction, determines processing method and telegram in reply path, or by tune
Degree person handles the empirically determined telegram in reply path of power grid accident, this process often consumes the long time, is unfavorable for quickly locating
Director's event;In addition, electric network accident management method differs, it is understood that there may be a variety of telegram in reply paths need to discuss when dispatcher is handled true
Fixed a certain telegram in reply path.
Invention content
The present invention is at least one defect overcome described in the above-mentioned prior art, provides power grid accident under a kind of baseline risk
Fast power restoration method, the support platform of application schedules automated system establish telegram in reply path optimal under all kinds of power grid accidents
Scheme base, when power grid accident occurs, can quickly simulated accident is sent a telegram in reply path in dispatch automated system, and will be optimal
Telegram in reply path is shown by dynamically leading the form of figure, and substitution is in the past refering to the roadmap of accident prediction or by scheduling
Member experience come determine telegram in reply path method.
The technical scheme is that:A kind of power grid accident fast power restoration method under baseline risk, wherein including decision model
Block, the telegram in reply module being connect with decision-making module, the computing module being connect with telegram in reply module;
The decision-making module has selected required scheme system load section and has executed event, and data standard is carried out for telegram in reply process
It is standby;
The telegram in reply module includes central monitoring position, device unit and control centre;
Central monitoring position mainly monitors the variation of power grid and is sent to control centre, and center provides data in order to control;Device unit needle
To relay protection, automatic device models and equipment, and center provides parameter and action logic in order to control;Control centre is telegram in reply module
Core, after receiving the data of central monitoring position, the parameter information of coupling apparatus unit determines startup scheme, and according to device
Action logic action in unit;
The computing module includes:Topology calculating, Load flow calculation and short circuit calculation;Service is provided during telegram in reply, when opening
Off status by coloring, the modes such as out-of-limit provides intuitive displaying after changing for dispatcher.Since telegram in reply shows the time
Limitation, frequent movement switch brings frequent topological Load flow calculation, has higher requirement to calculating speed.
In the present invention, when accident occurs for power grid, the unpromising dispatcher of EMS system does decision and provides the complementary of service
Software, dispatcher can only be by checking SCADA alarm signals, according to protection act information analysis abort situation, in conjunction with current
The method of operation, system loading determine processing method and restoration path etc..Often consuming the long period in this process influences
Telegram in reply efficiency, and dispatcher is needed to have abundant experiences of power accidents disposal.Thus propose that power grid accident is quick under baseline risk
Telegram in reply leads diagram technology, quickly determines that processing scheme selectes optimal telegram in reply path in accident to auxiliary dispatching personnel, when
When baseline risk power grid accident occurs for riverhead power grid, according to prestoring, model Dynamic Display in a manner of switch changed position, topology coloring is multiple
Electric process.By using EMS system data, generates dynamic telegram in reply at DTS system interface and lead figure, topology, which calculates, realizes Dynamic Display
The optimal telegram in reply path when baseline risk power grid accident occurs.This system can be stored in a manner of section, load data and model,
And refresh newest gathered data, various risk cases are triggered by leading figure interface simulation, inverting accident process is not influencing
In the case of SCADA system normal operation, the process that simulated accident is sent a telegram in reply when handling can simultaneously serve as dispatcher's skills training
With the platform of promotion.
Specifically, the decision-making module includes establishing scheme base, establishes scheme base and include accident event, send a telegram in reply to switch and hold
Act part and corresponding trend section;
Start after executing telegram in reply, first carries out event of failure combination relay protection and automatic device model reappears phenomenon of the failure, later
Execute on off sequence one by one, including Fault Isolation, telegram in reply and the completion of falling load telegram in reply process.
The central monitoring position includes measuring monitor,
It measures monitor and mainly monitors measuring value, short circuit calculation value, equipment live state and switch division state;When detection limit is sent out
The data after variation are sent to control centre after changing;Wherein electriferous state and switch division state, state value only has two
A need to judge it is different;And measuring value, short circuit calculation value need to consider variation reference value, different types of monitoring variable
Detected value is different;Judgment mode is:
WhereinTo change reference value,For last computation value,For the value of this calculating.
The control centre is algorithm core, and all devices have been loaded when creating, and is monitored when receiving
After the signal at center, the device involved by signal is filtered out, whether is started by decision logic determining device and manner of execution;Control
Center processed is also responsible for the traffic control of whole process, including the time counts and call as needed auxiliary calculating, telegram in reply process letter
Breath statistics etc..
Compared with prior art, advantageous effect is:Pass through each Substation parameters of EMS system, circuit model and connection relation
Establish the telegram in reply model under riverhead electric network wiring scheme and the various baseline risk accidents of storage.Stress model triggers accident event,
Inverting accident process selects optimal telegram in reply path events, multiple by tidal current chart Dynamic Display with switch motion, equipment coloring mode
Electric process, and generate Brief News.Whole process does not influence the normal operation of SCADA system.
Description of the drawings
Fig. 1 is general frame flow diagram of the present invention.
Specific implementation mode
The attached figures are only used for illustrative purposes and cannot be understood as limitating the patent;It is attached in order to more preferably illustrate the present embodiment
Scheme certain components to have omission, zoom in or out, does not represent the size of actual product;To those skilled in the art,
The omitting of some known structures and their instructions in the attached drawings are understandable.Being given for example only property of position relationship described in attached drawing
Illustrate, should not be understood as the limitation to this patent.
As shown in Figure 1, a kind of power grid accident fast power restoration method under baseline risk, wherein including decision-making module and decision
The telegram in reply module of module connection, the computing module being connect with telegram in reply module;
The decision-making module has selected required scheme system load section and has executed event, and data standard is carried out for telegram in reply process
It is standby;
The telegram in reply module includes central monitoring position, device unit and control centre;
Central monitoring position mainly monitors the variation of power grid and is sent to control centre, and center provides data in order to control;Device unit needle
To relay protection, automatic device models and equipment, and center provides parameter and action logic in order to control;Control centre is telegram in reply module
Core, after receiving the data of central monitoring position, the parameter information of coupling apparatus unit determines startup scheme, and according to device
Action logic action in unit;
The computing module includes:Topology calculating, Load flow calculation and short circuit calculation;Service is provided during telegram in reply, when opening
Off status by coloring, the modes such as out-of-limit provides intuitive displaying after changing for dispatcher.Since telegram in reply shows the time
Limitation, frequent movement switch brings frequent topological Load flow calculation, has higher requirement to calculating speed.
In the present invention, when accident occurs for power grid, the unpromising dispatcher of EMS system does decision and provides the complementary of service
Software, dispatcher can only be by checking SCADA alarm signals, according to protection act information analysis abort situation, in conjunction with current
The method of operation, system loading determine processing method and restoration path etc..Often consuming the long period in this process influences
Telegram in reply efficiency, and dispatcher is needed to have abundant experiences of power accidents disposal.Thus propose that power grid accident is quick under baseline risk
Telegram in reply leads diagram technology, quickly determines that processing scheme selectes optimal telegram in reply path in accident to auxiliary dispatching personnel, when
When baseline risk power grid accident occurs for riverhead power grid, according to prestoring, model Dynamic Display in a manner of switch changed position, topology coloring is multiple
Electric process.By using EMS system data, generates dynamic telegram in reply at DTS system interface and lead figure, topology, which calculates, realizes Dynamic Display
The optimal telegram in reply path when baseline risk power grid accident occurs.This system can be stored in a manner of section, load data and model,
And refresh newest gathered data, various risk cases are triggered by leading figure interface simulation, inverting accident process is not influencing
In the case of SCADA system normal operation, the process that simulated accident is sent a telegram in reply when handling can simultaneously serve as dispatcher's skills training
With the platform of promotion.
Specifically, the decision-making module includes establishing scheme base, establishes scheme base and include accident event, send a telegram in reply to switch and hold
Act part and corresponding trend section;
Start after executing telegram in reply, first carries out event of failure combination relay protection and automatic device model reappears phenomenon of the failure, later
Execute on off sequence one by one, including Fault Isolation, telegram in reply and the completion of falling load telegram in reply process.
The central monitoring position includes measuring monitor,
It measures monitor and mainly monitors measuring value, short circuit calculation value, equipment live state and switch division state;When detection limit is sent out
The data after variation are sent to control centre after changing;Wherein electriferous state and switch division state, state value only has two
A need to judge it is different;And measuring value, short circuit calculation value need to consider variation reference value, different types of monitoring variable
Detected value is different;Judgment mode is:
WhereinTo change reference value,For last computation value,For the value of this calculating.
The control centre is algorithm core, and all devices have been loaded when creating, and is monitored when receiving
After the signal at center, the device involved by signal is filtered out, whether is started by decision logic determining device and manner of execution;Control
Center processed is also responsible for the traffic control of whole process, including the time counts and call as needed auxiliary calculating, telegram in reply process letter
Breath statistics etc..
Obviously, the above embodiment of the present invention be only to clearly illustrate example of the present invention, and not be pair
The restriction of embodiments of the present invention.For those of ordinary skill in the art, may be used also on the basis of the above description
To make other variations or changes in different ways.There is no necessity and possibility to exhaust all the enbodiments.It is all this
All any modification, equivalent and improvement etc., should be included in the claims in the present invention made by within the spirit and principle of invention
Protection domain within.
Claims (4)
1. a kind of power grid accident fast power restoration method under baseline risk, which is characterized in that connect including decision-making module, with decision-making module
The telegram in reply module connect, the computing module being connect with telegram in reply module;
The decision-making module has selected required scheme system load section and has executed event, and data standard is carried out for telegram in reply process
It is standby;
The telegram in reply module includes central monitoring position, device unit and control centre;
Central monitoring position mainly monitors the variation of power grid and is sent to control centre, and center provides data in order to control;Device unit needle
To relay protection, automatic device models and equipment, and center provides parameter and action logic in order to control;Control centre is telegram in reply module
Core, after receiving the data of central monitoring position, the parameter information of coupling apparatus unit determines startup scheme, and according to device
Action logic action in unit;
The computing module includes:Topology calculating, Load flow calculation and short circuit calculation;Service is provided during telegram in reply, when opening
Off status by coloring, the modes such as out-of-limit provides intuitive displaying after changing for dispatcher.
2. power grid accident fast power restoration method under a kind of baseline risk according to claim 1, it is characterised in that:Described
Decision-making module includes establishing scheme base, and it includes accident event, telegram in reply switch execution event and corresponding trend to establish scheme base
Section;
Start after executing telegram in reply, first carries out event of failure combination relay protection and automatic device model reappears phenomenon of the failure, later
Execute on off sequence one by one, including Fault Isolation, telegram in reply and the completion of falling load telegram in reply process.
3. power grid accident fast power restoration method under a kind of baseline risk according to claim 1, it is characterised in that:Described
Central monitoring position includes measuring monitor,
It measures monitor and mainly monitors measuring value, short circuit calculation value, equipment live state and switch division state;When detection limit is sent out
The data after variation are sent to control centre after changing;Wherein electriferous state and switch division state, state value only has two
A need to judge it is different;And measuring value, short circuit calculation value need to consider variation reference value, different types of monitoring variable
Detected value is different;Judgment mode is:
WhereinTo change reference value,For last computation value,For the value of this calculating.
4. power grid accident fast power restoration method under a kind of baseline risk according to claim 1, it is characterised in that:Described
Control centre is algorithm core, and all devices have been loaded when creating, after receiving the signal of central monitoring position, sieve
Whether the device involved by select-out signal, started and manner of execution by decision logic determining device;Control centre is also responsible for whole
The traffic control of a process, including time count and call as needed auxiliary calculating, telegram in reply procedural information statistics etc..
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810162559.2A CN108390372A (en) | 2018-02-27 | 2018-02-27 | A kind of power grid accident fast power restoration method under baseline risk |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810162559.2A CN108390372A (en) | 2018-02-27 | 2018-02-27 | A kind of power grid accident fast power restoration method under baseline risk |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108390372A true CN108390372A (en) | 2018-08-10 |
Family
ID=63069918
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810162559.2A Pending CN108390372A (en) | 2018-02-27 | 2018-02-27 | A kind of power grid accident fast power restoration method under baseline risk |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108390372A (en) |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101236575A (en) * | 2008-01-30 | 2008-08-06 | 山东大学 | Black start assistant decision making support/training system and its method |
CN101958536A (en) * | 2010-09-20 | 2011-01-26 | 中国电力科学研究院 | Distribution network failure isolation and quick power service restoration decision support system |
CN103296677A (en) * | 2013-05-09 | 2013-09-11 | 国家电网公司 | On-line large power grid recovery assistant decision-making system |
US20160139212A1 (en) * | 2014-11-13 | 2016-05-19 | Eleon Energy, Inc. | Methods and systems for power restoration planning employing simulation and transient test analysis |
CN107171312A (en) * | 2017-05-15 | 2017-09-15 | 国家电网公司 | A kind of fast quick-recovery optimal path choosing method of power distribution network large-area power-cuts |
CN107180569A (en) * | 2017-06-26 | 2017-09-19 | 广东电网有限责任公司惠州供电局 | A kind of intelligent simulation training system and method towards major network power system |
CN107730093A (en) * | 2017-09-27 | 2018-02-23 | 广东电网有限责任公司佛山供电局 | A kind of System and method in power grid accident telegram in reply path |
-
2018
- 2018-02-27 CN CN201810162559.2A patent/CN108390372A/en active Pending
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101236575A (en) * | 2008-01-30 | 2008-08-06 | 山东大学 | Black start assistant decision making support/training system and its method |
CN101958536A (en) * | 2010-09-20 | 2011-01-26 | 中国电力科学研究院 | Distribution network failure isolation and quick power service restoration decision support system |
CN103296677A (en) * | 2013-05-09 | 2013-09-11 | 国家电网公司 | On-line large power grid recovery assistant decision-making system |
US20160139212A1 (en) * | 2014-11-13 | 2016-05-19 | Eleon Energy, Inc. | Methods and systems for power restoration planning employing simulation and transient test analysis |
CN107171312A (en) * | 2017-05-15 | 2017-09-15 | 国家电网公司 | A kind of fast quick-recovery optimal path choosing method of power distribution network large-area power-cuts |
CN107180569A (en) * | 2017-06-26 | 2017-09-19 | 广东电网有限责任公司惠州供电局 | A kind of intelligent simulation training system and method towards major network power system |
CN107730093A (en) * | 2017-09-27 | 2018-02-23 | 广东电网有限责任公司佛山供电局 | A kind of System and method in power grid accident telegram in reply path |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103220173B (en) | A kind of alarm monitoring method and supervisory control system | |
CN111579923B (en) | Power distribution network fault diagnosis system and method | |
CN104598369B (en) | The software supervision method and apparatus realized in a mobile device | |
JPH08307524A (en) | Method and equipment for discriminating risk in abnormal conditions of constitutional element of communication network | |
CN103533084B (en) | Real-time DMS (device management system) of B/S (browser/server) framework and method thereof | |
CN103227662B (en) | A kind of electric power communication device safety detection method based on mode control and system | |
CN102158364A (en) | Time slice scheduling-based device polling method and device | |
CN110347694B (en) | Equipment monitoring method, device and system based on Internet of things | |
CN107872339A (en) | O&M implementation method and device, Virtual Networking System in a kind of virtualization network | |
CN103532738A (en) | Port connection relationship determination method and device | |
CN111017756A (en) | Distributed tower crane electric control system, equipment and storage medium for fault online diagnosis | |
CN109783311A (en) | Monitor processing method, device, equipment and the readable storage medium storing program for executing of breakpoint behavior | |
CN111130867B (en) | Intelligent household equipment alarm method and device based on Internet of things | |
CN102932170B (en) | Network element load inequality detection processing method, device and system thereof | |
CN109193947A (en) | Power distribution room monitoring method, device, server and computer readable storage medium | |
CN110224872B (en) | Communication method, device and storage medium | |
CN108390372A (en) | A kind of power grid accident fast power restoration method under baseline risk | |
CN108234162A (en) | TDCS/CTC system early warning methods based on port data flow monitoring | |
CN105527909A (en) | Data monitoring device, data monitoring method and monitoring system | |
CN106027297A (en) | Method and sever for implementing alarming | |
CN115167297A (en) | Intelligent manufacturing industry Internet of things based on thread control and control method | |
CN107977774A (en) | A kind of method of electrical network weak link automatic identification after failure | |
CN116260747A (en) | Monitoring method and device of terminal test equipment and electronic equipment | |
CN112711517A (en) | Server performance monitoring method and device, storage medium and terminal | |
KR101155867B1 (en) | Outage-management system and its method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20180810 |
|
RJ01 | Rejection of invention patent application after publication |