CN108386198A - A kind of novel tunnel inverted arch basement weak country rock processing method - Google Patents

A kind of novel tunnel inverted arch basement weak country rock processing method Download PDF

Info

Publication number
CN108386198A
CN108386198A CN201810101090.1A CN201810101090A CN108386198A CN 108386198 A CN108386198 A CN 108386198A CN 201810101090 A CN201810101090 A CN 201810101090A CN 108386198 A CN108386198 A CN 108386198A
Authority
CN
China
Prior art keywords
inverted arch
slip casting
steel
construction
tunnel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810101090.1A
Other languages
Chinese (zh)
Inventor
周刚
梁志强
崔成涛
邹智波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sinohydro Bureau 14 Co Ltd
Original Assignee
Sinohydro Bureau 14 Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sinohydro Bureau 14 Co Ltd filed Critical Sinohydro Bureau 14 Co Ltd
Priority to CN201810101090.1A priority Critical patent/CN108386198A/en
Publication of CN108386198A publication Critical patent/CN108386198A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/001Improving soil or rock, e.g. by freezing; Injections
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/107Reinforcing elements therefor; Holders for the reinforcing elements
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/18Arch members ; Network made of arch members ; Ring elements; Polygon elements; Polygon elements inside arches
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/18Arch members ; Network made of arch members ; Ring elements; Polygon elements; Polygon elements inside arches
    • E21D11/20Special cross- sections, e.g. corrugated

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Civil Engineering (AREA)
  • Soil Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The present invention relates to a kind of novel tunnel inverted arch basement weak country rock processing methods, belong to construction engineering technical field, the specific steps are:1)The excavation of tunnel inverted arch and leveling:Tunnel inverted arch according to design drawing size excavate simultaneously artificial smooth;2)Inverted arch preliminary bracing;3)Drilling:It is vertically drilled using hand air drill on inverted arch preliminary bracing face, and installs Φ 50mm steel pipes, spacing 1m, quincunx laying bores injected hole in the tube wall four of steel pipe, laying that injected hole is quincunx;4)Slip casting:Steel pipe using cement mortar carries out slip casting after the completion of setting, and when inverted arch substrate underground water is larger, using cement-silicate slurries slip casting, when construction, when every hole grouting pressure reaches design grouting pressure, terminates slip casting;5)After the completion of the construction of steel pipe cement mortar, normal construction inverted arch and inverted arch is required to fill according to design drawing.The present invention reduces the influence of weak surrounding rock foundation settlement as far as possible, it is ensured that tunnel agent structure, construction quality and tunnel operation security.

Description

A kind of novel tunnel inverted arch basement weak country rock processing method
Technical field
The invention belongs to construction engineering technical fields, specifically, being related to a kind of novel tunnel inverted arch basement weak country rock Processing method.
Background technology
Currently, Weak Surrounding Rock Construction only payes attention to the selection of tunnel excavation engineering method and tunnel main body supporting parameter in tunnel, face upward The weak surrounding rock processing of skewback bottom does not attract great attention, and weak surrounding rock is under outer load action, and sedimentation is big, and the duration It is long.Tunnel Engineering is built on weak surrounding rock, potential settlement after construction can cause communications and transportation and tunnel agent structure very big Harm, therefore soft foundation should take reasonable effective Reinforcement Measures.The mode of Soft Ground has very much, respectively There are advantage and disadvantage and limitation, rational foundation treatment mode how to be selected to be directly related to construction quality, project progress and engineering Investment.
Invention content
In order to solve the problems, such as background technology, the present invention provides a kind of novel tunnel inverted arch basement weak country rocks Processing method, to realize the influence for reducing weak surrounding rock foundation settlement, it is ensured that tunnel agent structure, construction quality and tunnel operation Safety.
To achieve the above object, the present invention is achieved through the following technical solutions:
A kind of novel tunnel inverted arch basement weak country rock processing method, the specific steps are:
1)The excavation of tunnel inverted arch and leveling
Tunnel inverted arch according to design drawing size excavate simultaneously artificial smooth;
2)Inverted arch preliminary bracing
After using concrete to spray 4cm to inverted arch substrate element first, I22 I-steel is installed in the inverted arch substrate of gunite concrete, Spacing is 0.6m between two neighboring I22 I-steel, and distributing reinforcement, Φ are laid using 25 spirals of Φ and the welding of I22 I-steel Spacing between 25 spirals is 1m, and steel arch-shelf is connected as entirety, finally sprays C25 concrete again to design thickness;
3)Drilling
It is vertically drilled using hand air drill on inverted arch preliminary bracing face, and installs Φ 50mm steel pipes, Φ 50mm steel pipe plum blossoms Shape is laid, and the tube wall surrounding of spacing 1m, Φ 50mm steel pipes bores injected hole, laying that injected hole is quincunx, pitch of holes 15cm;
4)Slip casting
Φ 50mm steel pipes using cement mortar carry out slip casting after the completion of setting, when construction, when every hole grouting pressure reaches design slip casting When pressure, grouting pressure 0.5-1.0MPa terminates slip casting;
5)After the completion of the construction of steel pipe cement mortar, normal construction inverted arch and inverted arch is required to fill according to design drawing.
Preferably, step 3)In, Φ 50mm length of steel pipe is 4.5m, wall thickness 3.5mm, is enclosed for ease of conduit insertion Rock, front end set a length of 10cm pointed cones head, and the tail portion 1m of steel pipe does not set injected hole.
Preferably, step 4)In, the weight ratio of water and cement is 1 in cement grout:1, cement grade 425;Using When cement-water-clay system slip casting, cement mortar is 1 with waterglass volume ratio:0.5, waterglass Baume degrees is 30, modulus 2.4, Grouting pressure 0.5-1.0MPa.
Beneficial effects of the present invention:
After inverted arch closing cyclization, drill on inverted arch preliminary bracing face, and the steel that injected hole is drilled on its tube wall is installed in hole Pipe, then reinforces weak surrounding rock to inverted arch substrate slip casting by steel pipe, reduces weak surrounding rock foundation settlement as far as possible It influences, it is ensured that tunnel agent structure, construction quality and tunnel operation security;Meanwhile this method directly utilizes constructing tunnel existing The reinforcing of inverted arch basement weak country rock can be realized in equipment, less using equipment, material, safe operation, simple, conveniently, not shadow Tunnel normal construction is rung, speed is fast.
Description of the drawings
Fig. 1 is that inverted arch basement weak country rock handles cross-sectional view;
Fig. 2 is that inverted arch basement weak country rock handles skiagraph;
Fig. 3 is 50 steel-tube construction schematic diagrames of Φ.
In figure, 50 steel pipes of 1- Φ, 2- soft bases, 3- weak surrounding rocks paragraph, the normal country rock paragraphs of 4-.
Specific implementation mode
Below in conjunction with the embodiment of the present invention and attached drawing, technical solution in the embodiment of the present invention carries out clear, complete Ground describes, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.Based on this Embodiment in invention, every other reality obtained by those of ordinary skill in the art without making creative efforts Example is applied, shall fall within the protection scope of the present invention.
Embodiment
A kind of novel tunnel inverted arch basement weak country rock processing method, the specific steps are:
1)The excavation of tunnel inverted arch and leveling
Tunnel inverted arch according to design drawing size excavate simultaneously artificial smooth;
2)Inverted arch preliminary bracing
After spraying 4cm to inverted arch substrate element using the concrete marked as C25 first, installed in the inverted arch substrate of gunite concrete I22 I-steel, spacing is 0.6m between two neighboring I22 I-steel, is laid using 25 spirals of Φ and the welding of I22 I-steel Distributing reinforcement, the spacing between 25 spirals of Φ is 1m, and steel arch-shelf is connected as entirety, finally again spray C25 concrete to designing thickness Degree;
3)Drilling
It is vertically drilled using hand air drill on inverted arch preliminary bracing face, and installs Φ 50mm steel pipes 1,1 plum of Φ 50mm steel pipes Flower-shape is laid, and the tube wall surrounding of spacing 1m, Φ 50mm steel pipes 1 bores injected hole, laying that injected hole is quincunx, and pitch of holes is 15cm;The length of Φ 50mm steel pipes 1 is 4.5m, wall thickness 3.5mm, is inserted into country rock for ease of conduit, front end sets a length of 10cm points The tail portion 1m of conehead, steel pipe does not set injected hole;As shown in Figure 3;
4)Slip casting
Φ 50mm steel pipes using cement mortar carry out slip casting after the completion of setting, when construction, when every hole grouting pressure reaches design slip casting When pressure, grouting pressure 0.5-1.0MPa terminates slip casting;The weight ratio of water and cement is 1 in cement grout:1, cement grade is 425;When using cement-water-clay system slip casting, cement mortar is 1 with waterglass volume ratio:0.5, waterglass Baume degrees is 30, mould Number is 2.4, grouting pressure 0.5-1.0MPa;
5)After the completion of the construction of steel pipe cement mortar, normal construction inverted arch and inverted arch is required to fill according to design drawing.
The present invention is that the novel inverted arch basement weak country rock processing method for the treatment of of soft foundation is carried out after inverted arch closing cyclization, can Constructing tunnel existing equipment is directly utilized, it is less using equipment, material, it is safe operation, simple, conveniently, it is normal that tunnel is not influenced Construction, speed are fast.The application of the present invention for reducing the influence of weak surrounding rock foundation settlement as far as possible, it is ensured that tunnel main body knot Structure, construction quality and tunnel operation security are of great significance.
Finally illustrating, preferred embodiment above and attached drawing are merely illustrative of the technical solution of the present invention and unrestricted, Although the present invention has been described in detail by above preferred embodiment, however, those skilled in the art should understand that, Various changes can be made to it in the form and details, without departing from model defined by claims of the present invention It encloses.

Claims (3)

1. a kind of novel tunnel inverted arch basement weak country rock processing method, it is characterised in that:The specific steps are:
1)The excavation of tunnel inverted arch and leveling
Tunnel inverted arch according to design drawing size excavate simultaneously artificial smooth;
2)Inverted arch preliminary bracing
After using concrete to spray 4cm to inverted arch substrate element first, I22 I-steel is installed in the inverted arch substrate of gunite concrete, Spacing is 0.6m between two neighboring I22 I-steel, and distributing reinforcement, Φ are laid using 25 spirals of Φ and the welding of I22 I-steel Spacing between 25 spirals is 1m, and steel arch-shelf is connected as entirety, finally sprays C25 concrete again to design thickness;
3)Drilling
It is vertically drilled using hand air drill on inverted arch preliminary bracing face, and installs Φ 50mm steel pipes, Φ 50mm steel pipe plum blossoms Shape is laid, and the tube wall surrounding of spacing 1m, Φ 50mm steel pipes bores injected hole, laying that injected hole is quincunx, pitch of holes 15cm;
4)Slip casting
Φ 50mm steel pipes using cement mortar carry out slip casting after the completion of setting, when construction, when every hole grouting pressure reaches design slip casting When pressure, grouting pressure 0.5-1.0MPa terminates slip casting;
5)After the completion of the construction of steel pipe cement mortar, normal construction inverted arch and inverted arch is required to fill according to design drawing.
2. a kind of novel tunnel inverted arch basement weak country rock processing method according to claim 1, it is characterised in that:Step 3)In, Φ 50mm length of steel pipe is 4.5m, wall thickness 3.5mm, is inserted into country rock for ease of conduit, front end sets a length of 10cm pointed cones The tail portion 1m of head, steel pipe does not set injected hole.
3. a kind of novel tunnel inverted arch basement weak country rock processing method according to claim 1, it is characterised in that:Step 4)In, the weight ratio of water and cement is 1 in cement grout:1, cement grade 425;When using cement-water-clay system slip casting, Cement mortar is 1 with waterglass volume ratio:0.5, waterglass Baume degrees is 30, modulus 2.4, grouting pressure 0.5-1.0MPa.
CN201810101090.1A 2018-02-01 2018-02-01 A kind of novel tunnel inverted arch basement weak country rock processing method Pending CN108386198A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810101090.1A CN108386198A (en) 2018-02-01 2018-02-01 A kind of novel tunnel inverted arch basement weak country rock processing method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810101090.1A CN108386198A (en) 2018-02-01 2018-02-01 A kind of novel tunnel inverted arch basement weak country rock processing method

Publications (1)

Publication Number Publication Date
CN108386198A true CN108386198A (en) 2018-08-10

Family

ID=63074834

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810101090.1A Pending CN108386198A (en) 2018-02-01 2018-02-01 A kind of novel tunnel inverted arch basement weak country rock processing method

Country Status (1)

Country Link
CN (1) CN108386198A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111379571A (en) * 2018-12-30 2020-07-07 中铁十四局集团有限公司 Pipeline, pipe shed structure and pipe shed construction method with same
CN111810185A (en) * 2020-06-30 2020-10-23 中铁二院工程集团有限责任公司 Tunnel bottom pre-reinforcement construction method
CN112127900A (en) * 2020-09-07 2020-12-25 中国水利水电第十四工程局有限公司 Construction method for hidden half-wall and half-arch protection structure of exposed arch of shallow-buried bias tunnel penetrating through accumulation body
JP2021110188A (en) * 2020-01-14 2021-08-02 株式会社カテックス Natural ground reinforcement method
CN116427451A (en) * 2023-03-13 2023-07-14 中铁九局集团第三建设有限公司 Micro pile reinforcement construction method for tunnel foundation under poor geological conditions

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103089275A (en) * 2013-01-16 2013-05-08 山东大学 Control method of surrounding rocks in water-rich very-broken surrounding rock tunnel collapse sections
CN103821536A (en) * 2014-03-20 2014-05-28 中铁七局集团第三工程有限公司 Construction method for tunnel on landslide section
CN104963696A (en) * 2015-07-28 2015-10-07 中国电建集团成都勘测设计研究院有限公司 Construction method for arching tunnel bottom
CN105781571A (en) * 2016-03-11 2016-07-20 中交第二公路工程局有限公司 Construction method for soft rock deformation tunnel lining support dismantling-replacing arch
CN106351671A (en) * 2016-10-17 2017-01-25 中铁五局集团第五工程有限责任公司 Excavation and supporting structure for weak surrounding rock super-large cross-section tunnel and construction method thereof
CN107152282A (en) * 2017-06-09 2017-09-12 中国铁建大桥工程局集团有限公司 Steel pipe pile reinforced tunnel inverted arch soft soil foundation construction engineering method

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103089275A (en) * 2013-01-16 2013-05-08 山东大学 Control method of surrounding rocks in water-rich very-broken surrounding rock tunnel collapse sections
CN103821536A (en) * 2014-03-20 2014-05-28 中铁七局集团第三工程有限公司 Construction method for tunnel on landslide section
CN104963696A (en) * 2015-07-28 2015-10-07 中国电建集团成都勘测设计研究院有限公司 Construction method for arching tunnel bottom
CN105781571A (en) * 2016-03-11 2016-07-20 中交第二公路工程局有限公司 Construction method for soft rock deformation tunnel lining support dismantling-replacing arch
CN106351671A (en) * 2016-10-17 2017-01-25 中铁五局集团第五工程有限责任公司 Excavation and supporting structure for weak surrounding rock super-large cross-section tunnel and construction method thereof
CN107152282A (en) * 2017-06-09 2017-09-12 中国铁建大桥工程局集团有限公司 Steel pipe pile reinforced tunnel inverted arch soft soil foundation construction engineering method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
李新荣: ""钢管桩加固隧道仰拱软弱地基施工技术"", 《建筑•建材•装饰》 *

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111379571A (en) * 2018-12-30 2020-07-07 中铁十四局集团有限公司 Pipeline, pipe shed structure and pipe shed construction method with same
JP2021110188A (en) * 2020-01-14 2021-08-02 株式会社カテックス Natural ground reinforcement method
JP7010312B2 (en) 2020-01-14 2022-01-26 株式会社カテックス Ground reinforcement method
CN111810185A (en) * 2020-06-30 2020-10-23 中铁二院工程集团有限责任公司 Tunnel bottom pre-reinforcement construction method
CN111810185B (en) * 2020-06-30 2022-04-05 中铁二院工程集团有限责任公司 Tunnel bottom pre-reinforcement construction method
CN112127900A (en) * 2020-09-07 2020-12-25 中国水利水电第十四工程局有限公司 Construction method for hidden half-wall and half-arch protection structure of exposed arch of shallow-buried bias tunnel penetrating through accumulation body
CN112127900B (en) * 2020-09-07 2022-07-05 中国水利水电第十四工程局有限公司 Construction method for hidden half-wall and half-arch protection structure of exposed arch of shallow-buried bias tunnel penetrating through accumulation body
CN116427451A (en) * 2023-03-13 2023-07-14 中铁九局集团第三建设有限公司 Micro pile reinforcement construction method for tunnel foundation under poor geological conditions

Similar Documents

Publication Publication Date Title
CN108386198A (en) A kind of novel tunnel inverted arch basement weak country rock processing method
CN111411993A (en) Large-section tunnel supporting system penetrating through huge karst cave hall and construction method
CN107642360A (en) Tunneling boring front pre-grouting construction method
CN110878696B (en) Method for reinforcing surrounding rock of tunnel section at junction of upper soft and lower hard stratum shield method and mine method
CN106703814A (en) Mined metro station hole pile construction method
CN108457656A (en) A kind of unearthed method for tunnel construction
CN110195604B (en) Construction method for tunnel main tunnel TBM (tunnel boring machine) tunneling section
CN102606168B (en) Construction method for preventing settlement and deformation of shallow-buried-excavation tunnel in excavation
CN103758123A (en) Method for constructing protecting wall lining of cast-in-place manual hole digging pile
CN107965325B (en) A kind of small interval shallow tunnel just branch arch replacement construction method
CN109209389A (en) Hazy tunnel construction method
CN113153308A (en) Construction method for double arch tunnel collapse section
CN110528523A (en) A kind of highly permeable stratum building foundation pit horizontal grouting back cover construction method
CN115539048A (en) Construction method for shallow-buried bias tunnel portal
CN109209443A (en) A kind of construction method of breaking surrounding rock tunnel structure
CN216342131U (en) Shield tunnel invades limit stake and handles reinforced structure
CN104153783B (en) A kind of rich in subsoil water and loose sand sand cobble diversion tunnel construction technology
CN109184742B (en) Advanced pre-grouting method for high-pressure water-rich soft surrounding rock mountain tunnel
CN117489367A (en) Tunnel collapse treatment reinforcing structure and method under bad geological conditions of hydropower station
CN112855225B (en) Soft rock tunnel supporting construction method with high safety
CN101358529A (en) Short tube and short tube sand consolidation agent strengthening construction process
CN113266417A (en) Construction method of karst cave pile foundation
CN109695453B (en) Auxiliary excavation construction method for vertical shaft main tunnel three-dimensional intersection
CN208330417U (en) Shield tunnel shearing resistance formula whirl spraying is freezed to block iterative structure
CN110159276A (en) Tunnel excavation technique in a kind of disintegration in water ultimate soft rock stratum

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20180810