CN108381746A - The construction method of sliding caisson platform precasting box beam - Google Patents

The construction method of sliding caisson platform precasting box beam Download PDF

Info

Publication number
CN108381746A
CN108381746A CN201810128504.XA CN201810128504A CN108381746A CN 108381746 A CN108381746 A CN 108381746A CN 201810128504 A CN201810128504 A CN 201810128504A CN 108381746 A CN108381746 A CN 108381746A
Authority
CN
China
Prior art keywords
area
sliding rail
box beam
sliding
reinforcing bar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810128504.XA
Other languages
Chinese (zh)
Other versions
CN108381746B (en
Inventor
邹少祥
陈荣刚
莫智彪
易重庆
闫红江
刘洋
李金亮
岳大勇
兰廷波
刘顺利
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
FUJIAN EXPRESSWAY ZHIXIN CONSTRUCTION MANAGEMENT Co.,Ltd.
China Railway Tunnel Group Construction Co Ltd
Original Assignee
China Railway Tunnel Group Sichu Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Tunnel Group Sichu Co Ltd filed Critical China Railway Tunnel Group Sichu Co Ltd
Publication of CN108381746A publication Critical patent/CN108381746A/en
Application granted granted Critical
Publication of CN108381746B publication Critical patent/CN108381746B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B15/00General arrangement or layout of plant ; Industrial outlines or plant installations
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B11/00Apparatus or processes for treating or working the shaped or preshaped articles
    • B28B11/24Apparatus or processes for treating or working the shaped or preshaped articles for curing, setting or hardening
    • B28B11/245Curing concrete articles
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B23/00Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects
    • B28B23/02Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects wherein the elements are reinforcing members
    • B28B23/04Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects wherein the elements are reinforcing members the elements being stressed
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B23/00Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects
    • B28B23/02Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects wherein the elements are reinforcing members
    • B28B23/04Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects wherein the elements are reinforcing members the elements being stressed
    • B28B23/046Post treatment to obtain pre-stressed articles

Landscapes

  • Engineering & Computer Science (AREA)
  • Chemical & Material Sciences (AREA)
  • Ceramic Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Manufacturing & Machinery (AREA)
  • Structural Engineering (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention discloses the construction methods of sliding caisson platform precasting box beam, include the following steps:Establish construction site, construction site includes two sliding rails, along sliding rail slidably and with the separable traveling platform of sliding rail and along the construction area that every sliding rail is arranged, construction area is divided into bonding pad, reinforcing bar binding area, concreting area, high temperature steam curing area, common maintenance area and prestressed stretch-draw area according to working procedure successively along glide direction of the traveling platform on every sliding rail, two sliding rails are parallel and are set up in parallel along sliding rail width direction, and on two sliding rails traveling platform glide direction it is opposite;At least provided with 4 traveling platforms on each sliding rail, work continuously for realizing each working procedure on each sliding rail, to realizing the cycle construction of multiple prefabricated case beams on two sliding rails.The present invention can effectively improve prefabricated box -beam speed, improve construction efficiency.

Description

The construction method of sliding caisson platform precasting box beam
Technical field
The present invention relates to bridge construction technical fields.It is more particularly related to which a kind of sliding pedestal is pre- The construction method of box beam processed.
Background technology
Currently, prefabricated case beam with bridge substructure synchronous construction, short time limit due to that can be factory produced and precast box Beam is easy to control compared with cast-in-situ box girder quality, is more and more widely used in bridge construction.
Currently, prefabricated case beam is mainly completed by precast beam field.First in Liang Chang concreting fixed bases, wait for solid Determine after pedestal intensity reaches design requirement, then bed die is installed on fixed base, binding baseplate reinforcing bar, web reinforcement, installation side Mould and inner membrance, backform, bind roof steel bar, casting concrete, maintenance, tensioned prestressing bar, complete that beam piece is prefabricated, and lifting is to depositing Carried out after Liang Qu next it is beam prefabricated.This method is construction flow process, and later process can only wait until that preceding working procedure completes simultaneously matter After amount is met the requirements, later process could carry out, and the method seriously constrains the prefabricated speed of box beam.
Invention content
There are one purposes to be to provide a kind of construction method of sliding caisson platform precasting box beam by the present invention, and this method utilizes movement Pedestal loopy moving on two sliding rails realizes that multi-disc box beam is prefabricated simultaneously on a construction site, is formed continuous parallel Work pattern, and prefabricated box -beam speed is effectively improved in the case where meeting quality requirement, improve construction efficiency.
In order to realize these purposes and other advantages according to the present invention, a kind of sliding caisson platform precasting box beam is provided Construction method includes the following steps:
One, establish construction site, construction site includes two sliding rails, along sliding rail slidably and and sliding rail Separable traveling platform and along every sliding rail setting construction area, construction area is along traveling platform in every sliding rail On glide direction successively according to working procedure be divided into bonding pad, reinforcing bar binding area, concreting area, high temperature steam curing Area, common maintenance area and prestressed stretch-draw area, two sliding rails are parallel and are set up in parallel along sliding rail width direction, And on two sliding rails traveling platform glide direction on the contrary, making the prestressed stretch-draw area of a sliding rail and another cunning The bonding pad in dynamic rail road is arranged close to;
Two, the construction procedure of a prefabricated case beam is followed successively by each sliding rail:
A, box beam reinforcing bar is bound in reinforcing bar binding area, and box beam core model is installed, obtain steel bar framework of box beam;
B, a traveling platform is slid onto into concreting area from the bonding pad of sliding rail by reinforcing bar binding area, and Steel bar framework of box beam is hung on the traveling platform in concreting area, installation box beam external mold and casting concrete wait for concrete Box beam core model is removed after initial set and box beam external mold obtains precast beam piece;
C, traveling platform is slid onto to high temperature steam curing area and common maintenance area successively carry out the steaming of precast beam piece respectively Vapour conserves and watering maintenance;
D, traveling platform is slid onto into pre- answer from common maintenance area after precast beam piece intensity in step C reaches design strength Power stretched zone tensioned prestressing bar and mud jacking, complete the prefabricated of box beam, by prefabricated box girder hoisting to depositing Liang Chang, and by traveling platform It is hung to the bonding pad of another sliding rail;
Wherein, at least provided with 4 traveling platforms on each sliding rail, for realizing coagulation on each sliding rail Each working procedure is worked continuously in native pouring area, high temperature steam curing area, common maintenance area and prestressed stretch-draw area, from And realize the cycle construction of multiple prefabricated case beams on two sliding rails.
Preferably, the reinforcing bar of the construction method of the sliding caisson platform precasting box beam, every sliding rail binds area It is equipped with working workbench with concreting area both sides, reinforcing bar binds area and the top in concreting area and is equipped with factory Canopy.
Preferably, the construction method of the sliding caisson platform precasting box beam, two sliding rail dislocation are set up in parallel, So that the reinforcing bar binding area and concreting area on two sliding rails are disposed in parallel in factory's canopy.
Preferably, the construction method of the sliding caisson platform precasting box beam, reinforcing bar bind area by rack and reinforcing bar tire Film forms, and across sliding rail and is set on workbench on the rack, and the reinforcing bar fetal membrane is placed on rack, rack and The longitudinal centre line of reinforcing bar fetal membrane is parallel with sliding rail;
Step A the specific steps are:Box beam baseplate reinforcing bar and side plate reinforcing bar are first bound on reinforcing bar fetal membrane, then box beam is installed Core film finally binds box beam roof steel bar.
Preferably, the construction method of the sliding caisson platform precasting box beam, the box beam core removed after concrete initial set Mould and box beam external mold are positioned on the workbench of concreting area both sides, and box beam core model is hung to reinforcing bar and binds area both sides Workbench on.
Preferably, the construction method of the sliding caisson platform precasting box beam, further includes first be set in factory's canopy The second gantry crane outside gantry crane and factory's canopy, wherein in step B, steel bar framework of box beam is hung to concrete by reinforcing bar binding area and pours Build area and box beam core model to be hung to the workbench of reinforcing bar binding area both sides realized by the first gantry crane, moved in step D Dynamic pedestal is real by the second gantry crane from the bonding pad of prestressed stretch-draw area to another sliding rail of a sliding rail It is existing.
Preferably, the construction method of the sliding caisson platform precasting box beam, concreting area are supported with high-temperature steam Shield area is additionally provided with concrete initial set area, and traveling platform, which is slid onto concrete initial set area, after casting concrete in step B waits for it Box beam core model and box beam external mold are removed after initial set.
The present invention includes at least following advantageous effect:
1) present invention substitutes tradition using the construction site pre-established using along the slidable traveling platform of sliding rail Fixed base carry out prefabricated box -beam so that prefabricated box -beam each working procedure formed a pipelining pattern, To realize the different process synchronous constructions of multiple prefabricated case beams, the parallel operations pattern of multiple prefabricated case beams is formed, to carry The efficiency of high prefabricated box -beam;
2) two sliding rail parallel side-by-sides setting, and traveling platform glide direction is opposite, it is possible to reduce traveling platform from One sliding rail is hung to the displacement distance on another sliding rail, to reduce working strength;
3) two sliding rail dislocation are arranged side by side, its reinforcing bar is bound area and concreting area is disposed in parallel in factory's canopy It is interior, workbench can be made full use of and reduce floor space, reduce the working strength for establishing construction site;
4) since concrete initial set needs the regular hour, concreting area and high temperature steam curing area it Between a concrete initial set area is specially set, the construction efficiency of working procedure early period can be improved.
Part is illustrated to embody by further advantage, target and the feature of the present invention by following, and part will also be by this The research and practice of invention and be understood by the person skilled in the art.
Description of the drawings
Fig. 1 is the top view layout of the construction site of one embodiment of the invention;
Fig. 2 is the left view layout drawing of the construction site of one embodiment of the invention.
Specific implementation mode
Present invention will be described in further detail below with reference to the accompanying drawings, to enable those skilled in the art with reference to specification text Word can be implemented according to this.
It should be noted that experimental method described in following embodiments is unless otherwise specified conventional method, institute Reagent and material are stated, unless otherwise specified, is commercially obtained;In the description of the present invention, term " transverse direction ", " vertical To ", "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", the instructions such as "outside" side Position or position relationship are to be based on the orientation or positional relationship shown in the drawings, and are merely for convenience of description of the present invention and simplification of the description, It is not instruction or implies that signified device or element must have a particular orientation, with specific azimuth configuration and operation, because This is not considered as limiting the invention.
As shown in Figure 1, the present invention provides a kind of construction method of sliding caisson platform precasting box beam, include the following steps:
One, construction site is established, construction site includes two sliding rails (i.e. by track pedestal 10 and 9 groups of track of walking At), slide along sliding rail slidably and with the separable traveling platform of sliding rail (being not shown in Fig. 1-2) and along every The construction area of track setting, construction area are divided according to working procedure successively along glide direction of the traveling platform on every sliding rail Area 1, concreting area 2, high temperature steam curing area 3, common maintenance area 4 and prestressed stretch-draw area are bound for bonding pad 6, reinforcing bar 5, two sliding rails are parallel and are set up in parallel along sliding rail width direction as shown in Figure 1, and on two sliding rails The glide direction of traveling platform is on the contrary, make the prestressed stretch-draw area 5 of a sliding rail and the bonding pad 6 of another sliding rail It is arranged close to, completes to bear as the traveling platform on another sliding rail wherein the bonding pad 6 of an interactive track is equivalent to Carry the post-job temporary storage area of box beam;It should be noted that two sliding rails be side by side be not edge on the width side by side On sliding rail length direction side by side, i.e. two sliding rails are not on one wire;
Two, the construction procedure of a prefabricated case beam is followed successively by each sliding rail:
A, box beam reinforcing bar is bound in reinforcing bar binding area 1, and box beam core model is installed, obtain steel bar framework of box beam;
B, a traveling platform is slid onto into concreting area 2 from the bonding pad of sliding rail 6 by reinforcing bar binding area, And be hung to steel bar framework of box beam on the traveling platform in concreting area 2, installation box beam external mold and casting concrete wait for coagulation Box beam core model is removed after native initial set and box beam external mold obtains precast beam piece;It should be noted that traveling platform passes through lifting in advance It is placed in bonding pad;In addition, since reinforcing bar binding area utilizes the rack 12 and reinforcing bar fetal membrane 11 above workbench and sliding rail Reinforcing bar binding is carried out, is limited by place height and construction and is not easy to the steel bar framework of box beam of completion being lifted into reinforcing bar binding area Traveling platform on, therefore, reinforcing bar pedestal directly slides onto concreting area 2 from bonding pad by reinforcing bar binding area, then will Steel bar framework of box beam is hung on the traveling platform in concreting area, and construction is more convenient;It is next pre- in progress that reinforcing bar binds area 1 The steel flxer sequence of box beam processed;
C, traveling platform is slid onto to high temperature steam curing area 3 and common maintenance area 4 successively carry out precast beam piece respectively Steam curing and watering conserve;It is realized to precast beam piece by establishing first high temperature steam curing case in high temperature steam curing area 3 High temperature steam curing, so high temperature steam curing area 3 indicates that it is entity structure, and bonding pad with realizing to draw in Fig. 1 6, reinforcing bar binding area 1, concreting area 2, common maintenance area 4 and prestressed stretch-draw area 5 are not entity structure, belong to sliding For the subregion of Construction of Precast Box Beam process setting on track, therefore distinguished using dotted line;Reinforcing bar pouring area 2 continues From the concreting of next steel bar framework of box beam;After traveling platform moves to common maintenance area 4 from high temperature steam curing area 3, High temperature steam curing area carries out the high temperature steam curing process of next precast beam piece (coming from reinforcing bar pouring area) again;
D, traveling platform is slid onto from common maintenance area 4 after precast beam piece intensity in step C reaches design strength pre- 5 tensioned prestressing bar of stress tension area and mud jacking, complete the prefabricated of box beam, by prefabricated box girder hoisting to depositing Liang Chang, and will move Pedestal is hung to the bonding pad 6 of another sliding rail;When traveling platform slides onto prestressed stretch-draw area 5, it is common conserve area 4 continue into The watering maintenance of a piece of precast beam piece (coming from high temperature steam curing area) under row;When traveling platform slides onto bonding pad 6, answer in advance The prestressed stretch-draw process of a piece of prefabricated case beam (from common maintenance area 4) under continuing of power stretched zone 5;
Wherein, at least provided with 4 traveling platforms on each sliding rail, for realizing coagulation on each sliding rail The continuous work of each working procedure in native pouring area 2, high temperature steam curing area 3, common maintenance area 4 and prestressed stretch-draw area 5 Industry, to realize the cycle construction of multiple prefabricated case beams on two sliding rails.If on each sliding rail only have 1 or 2 traveling platforms of person, then illustrate that construction area has subregion that can not construct, therefore result in waste of resources.Only construction area Each region constructing, can just make full use of resource.I.e. after the completion of 3 operation of high-temperature steam area, traveling platform loads box beam Into common maintenance area 4, and high temperature is entered by traveling platform below from the box beam after the completion of 2 operation of concreting area Steam dome 3 carries out high temperature steam curing operation, and the process in other regions of construction area is not always the case what cycle carried out, each The process construction of a box beam is completed, then enters the construction area of next process, and that process for being available is corresponding applies Work area is then used for next box beam and enters after the completion of the construction of a upper process.
In the technical scheme, traditional fixed base is replaced using traveling platform, by traveling platform in sliding rail Upper movement makes the different processes of prefabricated case beam be completed in different regions, different to synchronize progress in different zones It constructs while box beam;Since each sliding rail is very long, when traveling platform slides onto prestressing force from concreting area When drawing area, if be continuing on same track, it certainly will need traveling platform being hung to coagulation by lifting appliance Native pouring area, however using two sliding rails that are parallel and being set up in parallel along width, it is slided at two using traveling platform It is prefabricated to box beam progress in opposite direction on track, it, can be from a cunning when traveling platform, which loads, completes Construction of Precast Box Beam The prestressed stretch-draw area in dynamic rail road is hung to the bonding pad of another sliding rail by lifting appliance, can reduce lifting away from From reduction workload improves working efficiency.
Construction site is provided that two sliding rails, can also be 2n items connection track in fact, it is important that every cunning All it is so that the different processes of prefabricated case beam is completed in different regions using traveling platform sliding on dynamic rail road, for example, n items connect It integrates with a wherein sliding rail point-blank, in addition n items connection track and another sliding rail are straight at one On line, by the repeated arrangement along its length of two sliding rails in Fig. 1;Or 2n items connection track and two sliding rails are put down Row is set up in parallel, by two sliding rails in Fig. 1 along its width direction repeated arrangement.
In another technical solution, as shown in Fig. 2, the construction method of the sliding caisson platform precasting box beam, every The reinforcing bar binding area 1 of sliding rail and 2 both sides of concreting area are equipped with working workbench 7, and reinforcing bar binds 1 He of area The top in concreting area 2 is equipped with factory's canopy 8.Need placement material more since reinforcing bar binds area 1 and concreting area 2, Manual operation is more, therefore workbench 7 is arranged and is convenient for work.
In another technical solution, as shown in Figs. 1-2, the construction method of the sliding caisson platform precasting box beam, two The dislocation of sliding rail is set up in parallel, so that the reinforcing bar binding area 1 and concreting area 2 on two sliding rails are set up in parallel In factory's canopy 8.Since the construction area direction of two sliding rails is on the contrary, and reinforcing bar binding area and concreting area all need Workbench and factory's canopy are set, carry out shifting to install two sliding rails, the demand can be met, saves space, drop The low construction intensity for establishing construction site.
In another technical solution, as shown in Fig. 2, the construction method of the sliding caisson platform precasting box beam, reinforcing bar Binding area 1 is made of rack 12 and reinforcing bar fetal membrane 11, across sliding rail and is set on workbench 7 on the rack 12, The reinforcing bar fetal membrane 11 is placed on rack 12, and the longitudinal centre line of rack 12 and reinforcing bar fetal membrane 11 is parallel with sliding rail;
Step A the specific steps are:Box beam baseplate reinforcing bar and side plate reinforcing bar, then installs case are first bound on reinforcing bar fetal membrane 11 Beam core film finally binds box beam roof steel bar.
In the technical scheme, this be the binding of the technical program prefabricated case beam reinforcing bar early period method, same using moving Under conditions of dynamic pedestal carries out pipelining, other can also be used not influence the construction method of prefabricated case beam quality.
In another technical solution, the construction method of the sliding caisson platform precasting box beam is torn open after concrete initial set The box beam core model and box beam external mold removed is positioned on the workbench 7 of 2 both sides of concreting area, and box beam core model is hung to steel Muscle is bound on the workbench of 1 both sides of area.It is convenient for the construction of next prefabricated case beam in this way.The box beam external mold is located at sliding rail On workbench at left and right sides of road, positioned in concreting area Fast Installation convenient for box beam external mold.
In another technical solution, as shown in Figs. 1-2, the construction method of the sliding caisson platform precasting box beam, also Including the second gantry crane outside the first gantry crane being set in factory's canopy 8 and factory's canopy, wherein in step B, steel bar framework of box beam by Reinforcing bar binding area 1 is hung to concreting area 2 and box beam core model to be hung to the workbench 7 of reinforcing bar binding 1 both sides of area be to pass through What the first gantry crane was realized, traveling platform is from the prestressed stretch-draw area 5 of a sliding rail to another sliding rail in step D Bonding pad 6 be by the second gantry crane realize.First gantry crane is not shown in the accompanying drawings in the second gantry crane.
In another technical solution, the construction method of the sliding caisson platform precasting box beam, concreting area 2 with High temperature steam curing area 3 is additionally provided with concrete initial set area (not shown in figures), and casting concrete will move later in step B Pedestal slides onto concrete initial set area and removes box beam core model and box beam external mold after its initial set.Since concrete initial set needs centainly Time therefore a concrete initial set area can be specially set between concreting area and high temperature steam curing area, with Improve the construction efficiency of working procedure early period.In this case, the quantity of traveling platform can be more than 4 on every sliding rail A, the time spent to avoid concrete initial set wastes in other processes, to improve working efficiency.
Although the embodiments of the present invention have been disclosed as above, but its is not only in the description and the implementation listed With it can be fully applied to various fields suitable for the present invention, for those skilled in the art, can be easily Realize other modification, therefore without departing from the general concept defined in the claims and the equivalent scope, the present invention is simultaneously unlimited In specific details and legend shown and described herein.

Claims (7)

1. the construction method of sliding caisson platform precasting box beam, which is characterized in that include the following steps:
One, construction site is established, construction site includes two sliding rails, can slidably and with sliding rail divide along sliding rail From traveling platform and along every sliding rail setting construction area, construction area is along traveling platform on every sliding rail Glide direction is divided into bonding pad, reinforcing bar binding area, concreting area, high temperature steam curing area, general according to working procedure successively Logical maintenance area and prestressed stretch-draw area, two sliding rails are parallel and are set up in parallel along sliding rail width direction, and two On sliding rail traveling platform glide direction on the contrary, make a sliding rail prestressed stretch-draw area and another sliding rail The bonding pad in road is arranged close to;
Two, the construction procedure of a prefabricated case beam is followed successively by each sliding rail:
A, box beam reinforcing bar is bound in reinforcing bar binding area, and box beam core model is installed, obtain steel bar framework of box beam;
B, a traveling platform is slid onto into concreting area from the bonding pad of sliding rail by reinforcing bar binding area, and by case Beam reinforcement cages are hung on the traveling platform in concreting area, and installation box beam external mold and casting concrete wait for concrete initial set It removes box beam core model afterwards and box beam external mold obtains precast beam piece;
C, traveling platform is slid onto to the steam that high temperature steam curing area and common maintenance area carry out precast beam piece respectively successively support Shield and watering maintenance;
D, traveling platform is slid onto into prestressing force from common maintenance area after precast beam piece intensity in step C reaches design strength Area's tensioned prestressing bar and mud jacking are drawn, the prefabricated of box beam is completed, by prefabricated box girder hoisting to depositing Liang Chang, and traveling platform is hung to The bonding pad of another sliding rail;
Wherein, it is poured for realizing concrete on each sliding rail at least provided with 4 traveling platforms on each sliding rail Build that area, high temperature steam curing area, each working procedure is worked continuously in common maintenance area and prestressed stretch-draw area, to real The cycle construction of multiple prefabricated case beams on existing two sliding rails.
2. the construction method of sliding caisson platform precasting box beam as described in claim 1, which is characterized in that every sliding rail Reinforcing bar binds area and concreting area both sides and is equipped with working workbench, and reinforcing bar binds area and concreting area Top is equipped with factory's canopy.
3. the construction method of sliding caisson platform precasting box beam as claimed in claim 2, which is characterized in that two sliding rail mistakes Position is set up in parallel, so that the reinforcing bar binding area and concreting area on two sliding rails are disposed in parallel in factory's canopy.
4. the construction method of sliding caisson platform precasting box beam as claimed in claim 3, which is characterized in that reinforcing bar binds Qu Youtai Frame and reinforcing bar fetal membrane composition across sliding rail and are set on workbench on the rack, and the reinforcing bar fetal membrane is placed in platform On frame, the longitudinal centre line of rack and reinforcing bar fetal membrane is parallel with sliding rail;
Step A the specific steps are:Box beam baseplate reinforcing bar and side plate reinforcing bar are first bound on reinforcing bar fetal membrane, then box beam core is installed Film finally binds box beam roof steel bar.
5. the construction method of sliding caisson platform precasting box beam as claimed in claim 4, which is characterized in that torn open after concrete initial set The box beam core model and box beam external mold removed is positioned on the workbench of concreting area both sides, and box beam core model is hung to reinforcing bar On the workbench for binding area both sides.
6. the construction method of sliding caisson platform precasting box beam as claimed in claim 5, which is characterized in that further include being set to factory The second gantry crane outside the first gantry crane and factory's canopy in canopy, wherein in step B, steel bar framework of box beam is hung by reinforcing bar binding area Being hung to reinforcing bar to bind the workbench of area both sides to concreting area and box beam core model is realized by the first gantry crane , in step D traveling platform from the bonding pad of prestressed stretch-draw area to another sliding rail of a sliding rail be to pass through Second gantry crane is realized.
7. the construction method of sliding caisson platform precasting box beam as described in claim 1, which is characterized in that concreting area with High temperature steam curing area is additionally provided with concrete initial set area, and traveling platform is slid onto concrete by casting concrete later in step B First coagulation zone removes box beam core model and box beam external mold after its initial set.
CN201810128504.XA 2017-12-19 2018-02-08 Construction method of sliding type pedestal prefabricated box girder Active CN108381746B (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN201711379196X 2017-12-19
CN201711379196 2017-12-19

Publications (2)

Publication Number Publication Date
CN108381746A true CN108381746A (en) 2018-08-10
CN108381746B CN108381746B (en) 2020-06-19

Family

ID=63074598

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810128504.XA Active CN108381746B (en) 2017-12-19 2018-02-08 Construction method of sliding type pedestal prefabricated box girder

Country Status (1)

Country Link
CN (1) CN108381746B (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112132423A (en) * 2020-09-04 2020-12-25 中铁大桥局集团有限公司 Production management method and system for rail-movable beam-making pedestal
CN112265134A (en) * 2020-11-02 2021-01-26 中交路桥华南工程有限公司 Beam-making area of beam body precast yard
CN112873487A (en) * 2021-01-20 2021-06-01 广东预立预制构件有限公司 Production method of T-shaped beam, small box beam and segment piece heavy prefabricated part
CN112976288A (en) * 2021-04-14 2021-06-18 展鹏(福建)工贸有限公司 Production method of automatic brick production line
CN113442279A (en) * 2021-07-09 2021-09-28 四川东泉机械设备制造有限公司 Continuous circulating pouring method for concrete member
CN113771204A (en) * 2021-10-28 2021-12-10 山东交通学院 Circulation production method of prefabricated box girder and box girder template device
CN113997402A (en) * 2021-11-17 2022-02-01 中铁一局集团有限公司 Annular production line of prefabricated T roof beam
CN114932610A (en) * 2022-04-22 2022-08-23 嘉兴路虹机械有限公司 Automatic production system based on stair mould

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3958320A (en) * 1972-09-19 1976-05-25 Lely Cornelis V D Methods for the manufacture of prefabricated building sections or room units and factories for the implementation of such methods
CN101125441A (en) * 2007-08-31 2008-02-20 中铁二局股份有限公司 Post-tensioned method prestressed concrete box beam whole opening prefabricated construction method
CN201143725Y (en) * 2007-12-27 2008-11-05 中铁四局集团有限公司 Rapid prefabricating production line for box girder of passenger special line
CN202021677U (en) * 2011-02-23 2011-11-02 浙江天晟梁板有限公司 Recycling production system of precast beam plate
CN102528927A (en) * 2012-01-30 2012-07-04 中铁四局集团第五工程有限公司 Production line precast beam construction method
CN105345926A (en) * 2015-09-25 2016-02-24 安徽水利开发股份有限公司 Prefabricated construction method for prestressed concrete box girder

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3958320A (en) * 1972-09-19 1976-05-25 Lely Cornelis V D Methods for the manufacture of prefabricated building sections or room units and factories for the implementation of such methods
CN101125441A (en) * 2007-08-31 2008-02-20 中铁二局股份有限公司 Post-tensioned method prestressed concrete box beam whole opening prefabricated construction method
CN201143725Y (en) * 2007-12-27 2008-11-05 中铁四局集团有限公司 Rapid prefabricating production line for box girder of passenger special line
CN202021677U (en) * 2011-02-23 2011-11-02 浙江天晟梁板有限公司 Recycling production system of precast beam plate
CN102528927A (en) * 2012-01-30 2012-07-04 中铁四局集团第五工程有限公司 Production line precast beam construction method
CN105345926A (en) * 2015-09-25 2016-02-24 安徽水利开发股份有限公司 Prefabricated construction method for prestressed concrete box girder

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112132423A (en) * 2020-09-04 2020-12-25 中铁大桥局集团有限公司 Production management method and system for rail-movable beam-making pedestal
CN112132423B (en) * 2020-09-04 2023-12-29 中铁大桥局集团有限公司 Production management method and system for track movable beam making pedestal
CN112265134A (en) * 2020-11-02 2021-01-26 中交路桥华南工程有限公司 Beam-making area of beam body precast yard
CN112873487A (en) * 2021-01-20 2021-06-01 广东预立预制构件有限公司 Production method of T-shaped beam, small box beam and segment piece heavy prefabricated part
CN112976288A (en) * 2021-04-14 2021-06-18 展鹏(福建)工贸有限公司 Production method of automatic brick production line
CN112976288B (en) * 2021-04-14 2022-06-07 展鹏(福建)工贸有限公司 Production method of automatic brick production line
CN113442279A (en) * 2021-07-09 2021-09-28 四川东泉机械设备制造有限公司 Continuous circulating pouring method for concrete member
CN113771204A (en) * 2021-10-28 2021-12-10 山东交通学院 Circulation production method of prefabricated box girder and box girder template device
CN113997402A (en) * 2021-11-17 2022-02-01 中铁一局集团有限公司 Annular production line of prefabricated T roof beam
CN114932610A (en) * 2022-04-22 2022-08-23 嘉兴路虹机械有限公司 Automatic production system based on stair mould

Also Published As

Publication number Publication date
CN108381746B (en) 2020-06-19

Similar Documents

Publication Publication Date Title
CN108381746A (en) The construction method of sliding caisson platform precasting box beam
CN106677049B (en) Assembled steel-concrete combined structure bridge and construction method
CN107584650A (en) Using the bridge prefabrication devices and methods therefor of self-propelled continuous productive process
CN102392536B (en) Construction method for long-span hanging vestibule type template support system
CN108638324A (en) A kind of construction method of prefabricated case beam
CN114770706B (en) Light T-beam prefabrication equipment and prefabrication installation construction method
CN102251667B (en) Construction method for reinforced concrete arched roof of grain store
CN110700105B (en) Synchronous construction method for high pier column and tie beam and template used in same
CN105908902A (en) Positioning frame for prefabricated pier column reinforcing bar cages and construction method of pier column reinforcing bar cages
CN110158474A (en) Cast-in-place box girder bottom web reinforcing steel bar segmental prefabrication binding mould and binding method
CN108818919A (en) Precast T-Beam reinforcing bar is bound in advance and the construction method of integral installation
CN106638947A (en) Prefabricated frame structure and cascaded prefabrication construction method thereof
CN107460889A (en) Integral movable support formwork in underground comprehensive pipe gallery construction and construction method thereof
CN106337361A (en) Separated fiber reinforced plastic (FRP)-concrete-steel composite girder bridge structure and construction method thereof
CN105484403A (en) Assembly type concrete bidirectional ribbed floor and construction method therefor
CN110145341A (en) A kind of gang form system for circular tunnel concreting
CN208502068U (en) A kind of partial precast assembly prestress girder with rolled steel section en cased in concrete
CN208052253U (en) A kind of positioning moulding bed prefabricated for T beam web reinforced frames
CN104647587B (en) Combined sleeve driving type steel structure girder fabricating table seat and prefabricated box girder combined sleeve driving method
CN106285721B (en) A kind of railway culvert method of construction based on sliding mode system
CN210288124U (en) Prefabricated ligature mould of cast-in-place box girder bottom web reinforcing bar segmentation
CN104797762B (en) Building and construction method thereof
CN204278213U (en) A kind of tinuous production manufacturing prestressed concrete railway board used for high-speed railway
CN107042575A (en) A kind of umbrella skeleton support assembled core and prefabricated component manufacture method
CN103015704A (en) Slab column-shear wall structure building based on precast reinforced concrete hollow formworks and construction method thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: No. 29 Park Avenue XiXiangTang District, Nanning city 530007 the Guangxi Zhuang Autonomous Region

Patentee after: China Railway Tunnel Bureau Group Construction Co.,Ltd.

Address before: No. 29 Park Avenue XiXiangTang District, Nanning city 530007 the Guangxi Zhuang Autonomous Region

Patentee before: SICHU CO., LTD. OF CHINA RAILWAY TUNNEL Group

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20200731

Address after: No. 29 Park Avenue XiXiangTang District, Nanning city 530007 the Guangxi Zhuang Autonomous Region

Co-patentee after: FUJIAN EXPRESSWAY ZHIXIN CONSTRUCTION MANAGEMENT Co.,Ltd.

Patentee after: China Railway Tunnel Bureau Group Construction Co.,Ltd.

Address before: No. 29 Park Avenue XiXiangTang District, Nanning city 530007 the Guangxi Zhuang Autonomous Region

Patentee before: China Railway Tunnel Bureau Group Construction Co.,Ltd.