CN108376953A - A kind of pipe gallery communication crane span structure grating type line device and its installation method - Google Patents
A kind of pipe gallery communication crane span structure grating type line device and its installation method Download PDFInfo
- Publication number
- CN108376953A CN108376953A CN201810256764.5A CN201810256764A CN108376953A CN 108376953 A CN108376953 A CN 108376953A CN 201810256764 A CN201810256764 A CN 201810256764A CN 108376953 A CN108376953 A CN 108376953A
- Authority
- CN
- China
- Prior art keywords
- span structure
- crane span
- grid
- communication
- vertical
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02G—INSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
- H02G3/00—Installations of electric cables or lines or protective tubing therefor in or on buildings, equivalent structures or vehicles
- H02G3/02—Details
- H02G3/04—Protective tubing or conduits, e.g. cable ladders or cable troughs
- H02G3/0456—Ladders or other supports
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02G—INSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
- H02G1/00—Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines
- H02G1/06—Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for laying cables, e.g. laying apparatus on vehicle
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02G—INSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
- H02G3/00—Installations of electric cables or lines or protective tubing therefor in or on buildings, equivalent structures or vehicles
- H02G3/02—Details
- H02G3/04—Protective tubing or conduits, e.g. cable ladders or cable troughs
- H02G3/0406—Details thereof
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Laying Of Electric Cables Or Lines Outside (AREA)
Abstract
A kind of pipe gallery communication crane span structure grating type line device, including communication crane span structure, communicate and are arranged at intervals with multiple grille frames inside crane span structure, which includes vertical grid and lateral grid;The both ends of lateral grid are fixedly connected with the two side of communication crane span structure, and are formed with multiple pods on lateral grid;Vertically grid is provided with multiple, is formed in the middle part of the vertical grid and is coordinated the translot being fixedly mounted with pod, and vertical grating base is formed with the collet being fixedly connected with communication crane span structure.The grating type line device of this programme effectively overcomes the problems, such as that Cabling clutter, later period maintenance are difficult in pipe gallery communication crane span structure, and pipe gallery of making rational planning for communicates the use space of crane span structure, and specification cable laying quality effectively reduces later stage operation maintenance difficulty.
Description
Technical field
The present invention relates to underground pipe networks to build technical field more particularly to a kind of pipe gallery communication crane span structure grating type point
Line apparatus and its installation method.
Background technology
Currently, being usually laid in pipe gallery engineering communication cable in reserved communication crane span structure, crane span structure is generally slot type
Crane span structure.After piping lane examination passes through, all kinds of pipelines such as China Mobile, China Unicom, China Telecom, cable television concentrate the bridge that is laid in
In frame, in order to distinguish the ownership unit of communication cable, often through the form tied up, the independent bunchy laying of constituent parts communication cable
In in crane span structure.
Find that communicating various communication cables in crane span structure in the prior art mixes by engineering practice, identification is laborious, in the later stage
Pipe gallery operation maintenance during cable repair it is difficult, when the later stage increases pipeline with repair pipeline, pipeline extraction is not easy reality
It is existing.
It is retrieved by publication, finds following related patents:
Piping lane module and its splicing construction (CN206693267U) disclose a kind of piping lane module, including arranged in parallel
Front side board and back side panel, several for connecting the cross-arm beam of front side board and back side panel, the bottom surface of cross-arm beam offers several recessed
The top surface respective slot of slot, cross-arm beam is equipped with the boss that height is less than depth of groove, and boss is chimeric with groove to make adjacent piping lane mould
The upper surface of the alignment of block, front side board and back side panel be towards the inclined surface tilted down between the two, inclined surface with it is adjacent
The front side board of piping lane module and the lower surface of back side panel form opening towards the angle between front side board and back side panel.It is convenient
Be conducive to increase integrally-built security and stability after module is spliced while construction.
By comparative analysis, applicant thinks that this programme overcomes pipe gallery communication crane span structure center line compared with prior art
The problem of cable laying is chaotic, later period maintenance is difficult and line device installation complexity is not easy to replace, and simple in structure, installation side
Just, the novelty of provable this programme.
Invention content
It is an object of the invention in place of overcome the deficiencies in the prior art, provide a kind of pipe gallery communication crane span structure grid
Formula line device and its installation method overcome the problems, such as that Cabling clutter, later period maintenance are difficult in pipe gallery communication crane span structure,
Pipe gallery of making rational planning for communicates the use space of crane span structure, and specification cable laying quality effectively reduces later stage operation maintenance difficulty.
The purpose of the present invention is what is be achieved through the following technical solutions:
A kind of pipe gallery communication crane span structure grating type line device, including communication crane span structure, communication crane span structure inside interval are set
Multiple grille frames are equipped with, which includes vertical grid and lateral grid;The both ends of lateral grid and communication crane span structure
Two side is fixedly connected, and is formed with multiple pods on lateral grid;Vertically grid is provided with multiple, is made in the middle part of the vertical grid
Have and coordinate the translot being fixedly mounted with pod, and vertical grating base is formed with the collet being fixedly connected with communication crane span structure.
A kind of pipe gallery communication crane span structure installation method of grating type line device, includes the following steps:
Step 1, communication crane span structure is made, and the vertical grid of one row is installed every the positions 8~10m on communication crane span structure, vertically
The collet of grid is welded and fixed with communication crane span structure, and the translot of vertical grid is towards the threading direction of communication cable;
Step 2, it is laid with first layer communication cable between multiple vertical grids on communication crane span structure;
Step 3, lateral grid is installed, multiple pods on lateral grid is made to be fitted to the cross on multiple vertical grids
In slot, then by the both ends of lateral grid and communicate crane span structure two side be welded and fixed;
Step 4, second layer communication cable is laid between multiple vertical grids of lateral grids top.
Advantages of the present invention and economic effect are:
The present invention is uniformly arranged compartment in pipe gallery communication cable crane span structure, and crane span structure is divided into multiple spaces, is each family
Communication cable ownership unit individually divides space, is numbered on Hatch Opening, corresponding communication cable ownership unit, and standardized management is reserved
Space.
By be arranged compartment can also the communication cables of effective protection constituent parts be independent of each other, convenient for conduction, isolation and protection.
Description of the drawings
Fig. 1 is the stereogram (not installing communication cable) of the present invention;
Fig. 2 is the front view of the present invention;
Fig. 3 is the lateral grid of the present invention and vertical grid connection diagram;
Fig. 4 is present invention communication crane span structure schematic view of the mounting position.
In figure:1- communicates crane span structure;The vertical grids of 2-;3- transverse direction grids;4- first layer communication cables;5- second layer connections
Cable;6- pods;7- translots;8- collets.
Specific implementation mode
For that can further appreciate that present disclosure, feature and effect, the following examples are hereby given, and coordinates attached drawing detailed
It is described as follows.It should be noted that the present embodiment is descriptive, it is not restrictive, cannot thus limits the guarantor of the present invention
Protect range.
A kind of pipe gallery communication grating type line device of crane span structure 1, including communication crane span structure, communication crane span structure inside interval are set
Multiple grille frames are equipped with, which includes vertical grid 2 and lateral grid 3;The both ends of lateral grid and communication crane span structure
Two side be fixedly connected, and be formed with multiple pods 6 on lateral grid;Vertical grid is provided with multiple, vertical grid middle part
It is formed with and coordinates the translot 7 being fixedly mounted with pod, and vertical grating base is formed with the collet being fixedly connected with communication crane span structure.
A kind of pipe gallery communication crane span structure installation method of grating type line device, includes the following steps:
Step 1, communication crane span structure is made, and the vertical grid of one row is installed every the positions 8~10m on communication crane span structure, vertically
The collet of grid is welded and fixed with communication crane span structure, and the translot of vertical grid is towards the threading direction of communication cable;
Step 2, it is laid with first layer communication cable 4 between multiple vertical grids on communication crane span structure;
Step 3, lateral grid is installed, multiple pods on lateral grid is made to be fitted to the cross on multiple vertical grids
In slot, then by the both ends of lateral grid and communicate crane span structure two side be welded and fixed;
Step 4, second layer communication cable 5 is laid between multiple vertical grids of lateral grids top.
The construction procedure of this programme is as follows:
As shown in Figure 1, it includes communication crane span structure, vertical grid and transverse direction that pipe gallery, which communicates crane span structure grating type line device,
Grid communicates on crane span structure, each 8~10m, and one group of vertical grid and lateral grid is arranged, and vertical grid can be in communication crane span structure
It being directly connected to fix in manufacturing process, or installation connection can be carried out at the scene by bolt, vertical grating base is formed with collet,
And clamped and connected by translot and pod with lateral grid, the vertical grid after connecting is inserted into inside lateral grid, and is protected
It holds vertical grid to be mutually perpendicular to lateral grid, is then welded and fixed lateral grid and vertical grid, in addition vertical grid
Translot opening direction should thread direction against communication cable.Specific implementation is as follows:
Communication cable is divided into two layers of arrangement in communicating crane span structure, needs to be threaded from low to high in principle.
First layer communication cable installs lateral lattice after the completion of communicating laying in one section of vertical grid in crane span structure, in the section
Grid;Lateral grid is directly connect by the tongue and groove of translot and pod with vertical grid, and takes fixation.
Finally, second layer communication cable is laid.
It should be understood that for those of ordinary skills, it can be modified or changed according to the above description,
And all these modifications and variations should all belong to the protection domain of appended claims of the present invention.
Claims (2)
1. a kind of pipe gallery communicates crane span structure grating type line device, including communication crane span structure, it is characterised in that:The communication bridge
Multiple grille frames are arranged at intervals with inside frame, which includes vertical grid and lateral grid;The transverse direction grid
Both ends are fixedly connected with the two side of communication crane span structure, and are formed with multiple pods on lateral grid;The vertical grid is provided with more
It is a, it is formed in the middle part of the vertical grid and coordinates the translot being fixedly mounted with pod, and vertical grating base is formed with and is fixed with communication crane span structure
The collet of connection.
2. a kind of pipe gallery as described in claim 1 communicates the crane span structure installation method of grating type line device, feature
It is:Include the following steps:
Step 1, communication crane span structure is made, and the vertical grid of one row, vertical grid are installed every the positions 8~10m on communication crane span structure
Collet be welded and fixed with communication crane span structure, and the translot of vertical grid is towards the threading direction of communication cable;
Step 2, it is laid with first layer communication cable between multiple vertical grids on communication crane span structure;
Step 3, lateral grid is installed, multiple pods on lateral grid is made to be fitted to the translot on multiple vertical grids
It is interior, then the both ends of lateral grid and the two side of communication crane span structure are welded and fixed;
Step 4, second layer communication cable is laid between multiple vertical grids of lateral grids top.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810256764.5A CN108376953A (en) | 2018-03-27 | 2018-03-27 | A kind of pipe gallery communication crane span structure grating type line device and its installation method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810256764.5A CN108376953A (en) | 2018-03-27 | 2018-03-27 | A kind of pipe gallery communication crane span structure grating type line device and its installation method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108376953A true CN108376953A (en) | 2018-08-07 |
Family
ID=63019366
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810256764.5A Pending CN108376953A (en) | 2018-03-27 | 2018-03-27 | A kind of pipe gallery communication crane span structure grating type line device and its installation method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108376953A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114629064A (en) * | 2022-02-14 | 2022-06-14 | 北京百度网讯科技有限公司 | Cable bridge system and data center |
CN117039779A (en) * | 2023-10-10 | 2023-11-10 | 国网山东省电力公司安丘市供电公司 | Power supply installation assembly |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2830843Y (en) * | 2005-08-29 | 2006-10-25 | 孙启玉 | Fixer of high voltage cable in cable duct |
CN202914894U (en) * | 2012-10-24 | 2013-05-01 | 福建省电力有限公司 | Cable collating device |
CN103775100A (en) * | 2014-02-26 | 2014-05-07 | 华瀚管道***科技有限公司 | Prefabricated assembled urban comprehensive pipe gallery |
CN205544026U (en) * | 2016-04-29 | 2016-08-31 | 王泽宸 | Simply manage line ware |
CN106594387A (en) * | 2016-12-27 | 2017-04-26 | 二十二冶集团天津建设有限公司 | Pipe gallery group pipe transportation device |
CN107579491A (en) * | 2017-10-29 | 2018-01-12 | 江苏鼎荣电气集团有限公司 | A kind of composite fireproof layer type cable crane span structure |
-
2018
- 2018-03-27 CN CN201810256764.5A patent/CN108376953A/en active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2830843Y (en) * | 2005-08-29 | 2006-10-25 | 孙启玉 | Fixer of high voltage cable in cable duct |
CN202914894U (en) * | 2012-10-24 | 2013-05-01 | 福建省电力有限公司 | Cable collating device |
CN103775100A (en) * | 2014-02-26 | 2014-05-07 | 华瀚管道***科技有限公司 | Prefabricated assembled urban comprehensive pipe gallery |
CN205544026U (en) * | 2016-04-29 | 2016-08-31 | 王泽宸 | Simply manage line ware |
CN106594387A (en) * | 2016-12-27 | 2017-04-26 | 二十二冶集团天津建设有限公司 | Pipe gallery group pipe transportation device |
CN107579491A (en) * | 2017-10-29 | 2018-01-12 | 江苏鼎荣电气集团有限公司 | A kind of composite fireproof layer type cable crane span structure |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114629064A (en) * | 2022-02-14 | 2022-06-14 | 北京百度网讯科技有限公司 | Cable bridge system and data center |
CN114629064B (en) * | 2022-02-14 | 2024-02-23 | 北京百度网讯科技有限公司 | Cable bridge system and data center |
CN117039779A (en) * | 2023-10-10 | 2023-11-10 | 国网山东省电力公司安丘市供电公司 | Power supply installation assembly |
CN117039779B (en) * | 2023-10-10 | 2024-04-09 | 国网山东省电力公司安丘市供电公司 | Power supply installation assembly |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108376953A (en) | A kind of pipe gallery communication crane span structure grating type line device and its installation method | |
CN102767646B (en) | A kind of long cable section of ingoing line seal arrangement and there is the distribution box of sealing device | |
CN107683062A (en) | A kind of rack and wiring mechanism | |
CN203967713U (en) | For the terminal clamping device of crane cable | |
CN105762728A (en) | Method for pre-burying of strong and weak electricity box and electrical tubing | |
CN203932871U (en) | A kind of Novel cable fixture | |
CN103015737B (en) | A kind of mounting method of steel containment cofferdam of nuclear power plant | |
CN204267889U (en) | The multi-thread cable clamp that a kind of single bolt can be locked | |
CN212991859U (en) | Cross cable bridge connecting piece | |
CN201467115U (en) | Antenna subsystem | |
CN213633938U (en) | Butterfly-shaped leading-in optical cable for pipeline | |
CN107278077A (en) | The whole coil holder of communication cabinet | |
CN211266372U (en) | Cable laying equipment | |
CN210469617U (en) | Distribution frame for information technology engineering | |
CN204422835U (en) | A kind of aviation plug distributing box | |
CN207582994U (en) | A kind of big near coal-mine safety device | |
CN205188798U (en) | Bridge is with interval optical communication post of simple and easy installation formula | |
CN206421089U (en) | FTTH integrated informations corridor accesses fiber-dividing box | |
CN211981466U (en) | Cable intermediate head well | |
CN204992454U (en) | Six types of line solidus wares in IDC computer lab | |
CN209233351U (en) | A kind of pipe gallery communication gantry harness separating device | |
CN213276053U (en) | Wire clamp for 5G communication optical cable | |
CN204681026U (en) | The cable fixture of cable shaft and junction, cable tunnel | |
CN217642637U (en) | Communication engineering cable laying protection device | |
CN210713332U (en) | Joint connection structure of assembly type building outer wall |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20180807 |
|
RJ01 | Rejection of invention patent application after publication |