CN108360384A - Underway push construction method - Google Patents

Underway push construction method Download PDF

Info

Publication number
CN108360384A
CN108360384A CN201810169838.1A CN201810169838A CN108360384A CN 108360384 A CN108360384 A CN 108360384A CN 201810169838 A CN201810169838 A CN 201810169838A CN 108360384 A CN108360384 A CN 108360384A
Authority
CN
China
Prior art keywords
tube coupling
pushing tow
underway
riverbed
arc
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810169838.1A
Other languages
Chinese (zh)
Other versions
CN108360384B (en
Inventor
王昌将
吴德兴
李长俊
郭霄
马芹纲
王成树
段亚军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Shuzhijiaoyuan Technology Co Ltd
Original Assignee
Zhejiang Provincial Institute of Communications Planning Design and Research Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Provincial Institute of Communications Planning Design and Research Co Ltd filed Critical Zhejiang Provincial Institute of Communications Planning Design and Research Co Ltd
Priority to CN201810169838.1A priority Critical patent/CN108360384B/en
Publication of CN108360384A publication Critical patent/CN108360384A/en
Application granted granted Critical
Publication of CN108360384B publication Critical patent/CN108360384B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Foundations (AREA)

Abstract

The present invention provides a kind of underway push construction method, are related to underway technical field of construction, the step of when shallower for riverbed:Design arc-shaped channel traces line;Excavate foundation trench and pushing tow working pit;Support stake is set in foundation trench;Setting incremental launching device and the pre- control equipment of tube coupling in working pit;Head section tube couplings are prefabricated and attachment is installed;Preparation before head section tube coupling pushing tows;Head section tube coupling pushing tows;Second section tube coupling is prefabricated and attachment is installed;Preparation before second section tube coupling pushing tow;Second section tube coupling pushing tow;…;Head section tube couplings reach precalculated position, terminate pushing tow;Foundation trench backfills, and equipment is removed to be backfilled with working pit, and construction is completed.And the step of when larger for riverbed undulating and above-mentioned steps are essentially identical, difference is the directly transition in the form of underwater bridge of the deep section in riverbed, and excavates and backfill without foundation trench.The method overcomes the problem for needing special dry-docking place, sinking complex process, construction cost high in existing immersed tunnelling method underway construction.

Description

Underway push construction method
Technical field
The present invention relates to underway technical field of construction, in particular to a kind of underway push construction method.
Background technology
With greatly developing for Urban Underground Space Excavation in recent years, submerged tunnel engineering increasingly increases in urban construction It is more.Immersed tunnelling method is to build one of important method of submerged tunnel, advantage when having strong good waterproof performance, ground adaptability, big cross section The advantages that apparent.But immersed tunnelling method needs the large-scale place for building dry-docking, large-scale transportation by driving ship, the accurate sinking positioning of tube coupling and precisely Docking system etc., construction technology is more complex, and large dry dock place is limited by urban land, and immersed tube cube transportation can influence shipping; Submerged tunnel is built compared to shield method, Mining Method, immersed tunnelling method builds submerged tunnel cost higher at home at present.Current Problem is, if the advantages of having a kind of new construction method, can playing immersed tunnelling method and overcomes the sinking technique of immersed tunnelling method multiple Disadvantage miscellaneous, of high cost.
Bridge pushing construction method has been obtained for widely applying in the construction of continuous bridge and cable-stayed bridge, this method gram The defect of Large-scale Bridge Erector, complicated construction technique need to be arranged by having taken traditional Summarized Account of Bridge Erection Construction, had and saved construction land tenure, plant Simply, be not necessarily to simple large-scale lifting appliance, construction technology, short time limit, it is at low cost the advantages that.
In view of the plurality of advantages of immersed tunnelling method complex process and disadvantage of high cost and bridge pushing construction method, by immersed tube Both method and incremental launching method combine, and form new underway push construction method, are a kind of complete with engineering application value New approaches.
Invention content
The purpose of the present invention is to provide a kind of underway push construction method, to overcome underway in the prior art The high problem of the immersed tunnelling method sinking complex process of construction use, construction cost.
The present invention provides a kind of underway push construction method, in turn includes the following steps:
S1:Underway longitudinal direction path line is designed, when riverbed undulating is larger and section deep at least one section of riverbed, is indulged It is located at the top of riverbed bottom surface at the deep section in riverbed to path line;
S2:According to longitudinal path line, pushing tow working pit is excavated on bank, excavates foundation trench under water, when there is the deep section in riverbed When, the region is without excavating;
S3:It constructs a pair of of support stake at interval of certain distance in foundation trench, an end bearing is installed on pile top, when there is riverbed deep When segment, support stake is suitably encrypted in the region;
S4:Parados, jack group, top iron, arc tube coupling prefab-form, template thousand after being set gradually in pushing tow working pit Jin topmast seat, tube coupling jacking bracket, arc-shaped guide rail;
S5:The prefabricated first segment tube coupling of shuttering in working pit assembles water ballast after waiting for tube coupling maintenance in tube coupling Case simultaneously connects hydraulic pipeline, is sealed in tube coupling front end installation steel closure door, and the steel nose girder of arc is installed after steel closure door;
S6:The tube coupling and steel nose girder that pushing tow is waited for the support of tube coupling jacking bracket, withdraw arc tube coupling prefab-form, in pipe Section bottom surface is symmetrically installed two groups of guide and limit steel bars;
S7:Start jack group, the distance for the tube coupling that advances along arc-shaped guide rail pushing tow first segment tube coupling;
S8:Jack group is retracted, the prefabricated second section tube coupling of shuttering, continuous knot is formed with first segment tube coupling in working pit Structure after waiting for tube coupling maintenance, ballast tank is assembled in tube coupling and connects hydraulic pipeline;
S9:The tube coupling and steel nose girder that pushing tow is waited for the support of tube coupling jacking bracket, withdraw tube coupling prefab-form, in the second section Tube coupling bottom surface is symmetrically installed two groups of guide and limit steel bars;
S10:Start jack group, the distance of tube coupling one tube coupling of advance is saved along arc-shaped guide rail pushing tow second;
S11:The incremental launching construction that step S8-S10 completes follow-up tube coupling is repeated, each section tube coupling will during pushing tow Before entering water, design water injection rate is disposably filled to ballast tank in the tube coupling to prevent from floating, so sequentially pushing tow and to each The water tank with water of oral siphon section, until first segment tube coupling smoothly reaches opposite bank precalculated position and terminates pushing tow;
S12:Foundation trench is backfilled, to the deep section in riverbed without backfill, removes incremental launching device in tube coupling affiliated facility and working pit, Backfilling working is cheated, and entire underway incremental launching construction is completed.
Further;The longitudinal direction path line is arc-shaped, and arc-shaped track is matched with riverbed bottom profile, and arc-shaped Horizontal distance and the ratio between vertical height be typically no less than 50.
Further;The cross-sectional outling line of the foundation trench exceeds underway outer contour, and the foundation trench bottom surface ratio is set The low at least 30cm in tube coupling bottom surface is counted, the foundation trench both sides also set up the slope for preventing from back-silting.
Further;The stake diameter of the support stake is at least 80cm, and stake top is higher at least 10cm than the foundation trench bottom, described Stake end bearing include guide pad equipped with guide groove, stainless steel plate and can be tangent with tube coupling bottom arc track face cunning Block, the guide groove of the guide pad and the guide and limit steel bar of the tube coupling lower part match.
Further;The tube coupling is arc-shaped tube coupling, the size shape all same of all tube couplings, the adjacent pipe It pours to form continuous structure by wet seam between section, the steel nose girder length is span between the longitudinally adjacent support stake 0.6-0.7 times.
Further;When there is the deep section in riverbed, the region is with underwater type of bridge transition, the tube coupling top in the region Face is provided with the anti-protective layer that casts anchor, and the tube coupling in the region is internally provided with the ballast structure to neutral buoyancy.
Compared with the existing technology, underway push construction method provided by the invention has the beneficial effect that:
(1) it is not necessarily to the special prefabricated place of large dry dock, only need to excavate the top of appropriate size on bank according to actual conditions Push away working pit;
(2) due to there is support stake to position the support of tube coupling, excavating precision and foundation trench flatness requirement to foundation trench reduces, base Slot construction is simplified;
(3) it is not necessarily to cube transportation ship and underwater tube coupling precise positioning docking system, after need to being only arranged in the working pit of bank Parados, jack group, top iron, arc tube coupling prefab-form, template jacking bracket, tube coupling jacking bracket, arc-shaped guide rail etc. Simple device, construction equipment and construction technology are relatively simple;
(4) due to without special dry-docking place, and construction equipment and technique are simplified, cost can be effectively reduced;
(5) entire pushing tow underway is continuous structure, and without GINA waterstops, water resistance is more preferable, normally In the case of can accomplish it is watertight.
Description of the drawings
It, below will be to specific in order to illustrate more clearly of the specific embodiment of the invention or technical solution in the prior art Embodiment or attached drawing needed to be used in the description of the prior art are briefly described, it should be apparent that, in being described below Attached drawing is some embodiments of the present invention, for those of ordinary skill in the art, before not making the creative labor It puts, other drawings may also be obtained based on these drawings.
Fig. 1 is underway incremental launching construction process schematic representation when riverbed is shallower;
Each component meaning is as follows in Fig. 1:(a) underway longitudinal direction trajectory design;(b) foundation trench excavates;(c) Construction Support Stake;(d) working pit equipment is installed;(e) first section tube coupling is prefabricated and attachment is installed;(f) prepare before first section tube coupling pushing tow;(g) first section Tube coupling pushing tow;(h) the second section tube coupling is prefabricated and attachment is installed;(i) prepare before the second section tube coupling pushing tow;(j) the second section tube coupling top It pushes away;……;(k) first section tube coupling reaches opposite bank precalculated position;(l) it backfills foundation trench, remove equipment and backfilling working hole;
Fig. 2 is underway incremental launching construction process schematic representation when riverbed undulating is larger;
Each component meaning is as follows in Fig. 2:(a) underway longitudinal direction trajectory design;(b) foundation trench excavates;(c) Construction Support Stake;(d) working pit equipment is in place;(e) first section tube coupling reaches opposite bank precalculated position;(f) it backfills foundation trench, remove equipment and backfiller It cheats;
Fig. 3 is that foundation trench excavates cross-sectional view;
Fig. 4 is support pile constructing process schematic diagram;
Each component meaning is as follows in Fig. 4:(a) inserting piling steel pile casting;(b) it draws water;(c) construction drill bored concrete pile;(d) stake is installed Hold bearing;(e) top steel pile casting is cut off;
Fig. 5 is the detail structure chart of tube coupling used in underway incremental launching construction and support stake bearing;
Each component meaning is as follows in Fig. 5:(a) tube coupling and stake end bearing elevation;(b) tube coupling and stake end bearing cross sectional view I-I;(c) stake end bearing and tube coupling bottom surface transverse direction contact relation drawing J;(d) stake end bearing longitudinally contacts pass with tube coupling bottom surface It is sectional view K-K;(e) tube coupling and guide and limit steel bar graphics.
Icon:10- stream stages;The original bed-configuration lines of 20-;The original riverbed bottom surfaces 30-;The longitudinal directions 40- path line; 50- working pits;60- foundation trenches;70- foundation trench cross-sectional outling lines;80- supports stake;Parados after 90-;100- jack groups; 110- pushes up iron;120- arc tube coupling prefab-forms;130- template jacking brackets;140- tube coupling jacking brackets;150- Arc-shaped guide rail;160- steel is sealed up a door;170- steel nose girders;180- tube couplings;190- foundation trenches backfill material;200- working pits backfill material; 210- end bearings;220- ballast tanks;The deep section in the riverbeds 230-;The gentle section in the riverbeds 240-;250- steel pile castings;260- Cast-in-situ bored pile;1801- guide and limit steel bars;2101- guide pads;2102- stainless steel plates;2103- polytetrafluoroethylene (PTFE) is slided Block.
Specific implementation mode
Technical scheme of the present invention is clearly and completely described below in conjunction with attached drawing, it is clear that described implementation Example is a part of the embodiment of the present invention, instead of all the embodiments.Based on the embodiments of the present invention, ordinary skill The every other embodiment that personnel are obtained without making creative work, shall fall within the protection scope of the present invention.
In the description of the present invention, it should be noted that term "center", "upper", "lower", "left", "right", "vertical", The orientation or positional relationship of the instructions such as "horizontal", "inner", "outside" be based on the orientation or positional relationship shown in the drawings, merely to Convenient for the description present invention and simplify description, do not indicate or imply the indicated device or element must have a particular orientation, With specific azimuth configuration and operation, therefore it is not considered as limiting the invention.In addition, term " first ", " second " are only For descriptive purposes, it is not understood to indicate or imply relative importance.
In the description of the present invention, it should be noted that unless otherwise clearly defined and limited, term " installation ", " phase Even ", " connection " shall be understood in a broad sense, for example, it may be being fixedly connected, may be a detachable connection, or be integrally connected;It can Can also be electrical connection to be mechanical connection;It can be directly connected, can also indirectly connected through an intermediary, Ke Yishi Connection inside two elements.For the ordinary skill in the art, above-mentioned term can be understood at this with concrete condition Concrete meaning in invention.
The embodiment of the present invention is that the advantages of immersed tunnelling method and incremental launching method is combined, and retains immersed tunnelling method and excavates foundation trench 60, places pipe Section 180, the Basic practice for backfilling foundation trench 60 are abandoned each section tube coupling 180 traditional method that sinking is docked successively under water, are used instead straight The method for entering underwater foundation trench 60 from continuous 180 structure of tube coupling of bank pushing tow is connect, can give full play to that incremental launching method is simple for process, cost Low advantage, while overcoming immersed tube tunnel sinking complex process, defect of high cost, ultimately form a kind of completely new underway Push construction method.
In the present embodiment, Fig. 1 and Fig. 2 introduce respectively riverbed it is shallower when underway push construction method and riverbed rise Underway push construction method when lying prostrate larger, horizontal direction engineer's scale is bigger than vertical engineer's scale in figure, real work hole 50 The ratio of slope sheet gradient shown in figure is small.
Specifically, as shown in Figure 1, when riverbed is shallower, underway push construction method provided in this embodiment has Body process is as follows:
S1:According to riverbank riverbed landform, riverbed engineering geological condition and surrounding enviroment, stream stage 10 and original river are being verified In the case of bed contour line 20, design underway longitudinal direction path line 40, longitudinal path line 40 should be arc-shaped, and arc track is answered It is matched as possible with gentle 240 bottom profile of section in riverbed, the ratio between horizontal distance and vertical height of circular arc are typically no less than 50.Wherein Longitudinal path line 40 is necessary for circular arc line, if broken line or other non-circular arc lines, necessarily will appear tube coupling 180 during pushing tow Bottom surface is detached from support stake 80, and pushing tow can not be normally carried out.
S2:According to practical riverbed situation, selectivity is filled out using specialized dredger, dredger, sand compaction pile ship, jackstone rammer Ship, broken stone leveling ship etc. are dredged along design longitudinal direction path line 40 and dig foundation trench 60 and progress basement process, foundation trench cross section under water Contour line 70 should exceed underway outer contour, 60 bottom surface longitudinal direction track of foundation trench should substantially with the arc-shaped bottom surface phase in channel Match, 60 bottom surface of foundation trench should be lower at least 30cm than 180 bottom surface of design tube coupling, and rational slope should be arranged to prevent non-return in 60 both sides of foundation trench It becomes silted up, extending appropriate location ashore in longitudinal path line 40 excavates pushing tow working pit 50, and the length of working pit 50 should be according to list 180 length of section tube coupling, the pre- control equipment of tube coupling and incremental launching device, live site condition etc. determine after being checked.
S3:Using cast-in-situ bored pile method at interval of a pair of of support stake 80 of certain distance construction, longitudinal two-phase in foundation trench 60 The maximum outreach of neighbour's support stake 80 should determine that support 80 diameters of stake are typically no less than 80cm, and stake is long after structure stress checks It should be determined according to 180 load of top tube coupling and lower part Checking Ground Bearing Capacity, stake top is at least higher 10cm than excavating 60 bottom of foundation trench. As shown in figure 5, support stake 80 top setting stake end bearing 210, stake end bearing 210 is by guide pad 2101, stainless steel plate 2102, poly- Tetrafluoroethene sliding block 2103 forms, and polytetrafluoroethylene (PTFE) sliding block 2103 should be tangent with the 180 bottom arc track face of tube coupling of design, sliding Block is vertically installed positioning accuracy and is preferably controlled within 1cm, and the guide groove of guide pad 2101 should be with the guide and limit of 180 lower part of tube coupling Steel bar 1801 matches, and level is played by the mutual Horizontal limiting between guide and limit steel bar 1801 and stake top guide pad 2101 Guiding role.
S4:Parados 90, jack group 100, top iron 110, arc tube coupling prefab-form after being arranged in pushing tow working pit 50 120, the maximum top power of template jacking bracket 130, tube coupling jacking bracket 140, arc-shaped guide rail 150, jack group 100 answers root Calculate and determine according to design, if it is insufficient to occur top power during later stage pushing tow, it is contemplated that using more large-tonnage jack group 100 or Cable is connected in 170 front end of steel nose girder to pull from opposite bank.
S5:The prefabricated first segment tube coupling 180 of shuttering in working pit 50,180 length of single-unit tube coupling should consider work It is determined after cheating the factors such as the limitation of 50 lands used and construction period.After waiting for that tube coupling 180 conserves, water ballast is assembled in tube coupling 180 Case 220 simultaneously connects hydraulic pipeline, is sealed in 180 front end of tube coupling installation steel closure door 160, and install arc after steel closure door 160 The steel nose girder 170 of shape, 170 length of steel nose girder are generally 0.6-0.7 times of 80 span of adjacent supports stake.
S6:The tube coupling 180 and steel nose girder 170 for waiting for pushing tow are supported with tube coupling jacking bracket 140, and it is prefabricated to withdraw arc tube coupling Template 120 is symmetrically installed two groups of guide and limit steel bars 1801 in 180 bottom surface of tube coupling.
S7:First section 180 pushing tow anti-overturning of tube coupling checking computations are carried out, start jack group 100 after checking computations are qualified, along arc The distance of 150 pushing tow first segment tube coupling 180 of guide rail, one tube coupling of advance can pass through if the stroke length of jack group 100 is inadequate The length for increasing top iron 110 solves.
S8:Pushing tow jack is retracted, the prefabricated second section tube coupling 180 of shuttering in working pit 50, with first segment tube coupling 180 Continuous structure is formed, after waiting for that tube coupling 180 conserves, ballast tank 220 is assembled in tube coupling 180 and connects hydraulic pipeline, is pressed The size of cabin water tank 220 should be determined according to antifloating computation, ensure the section tube coupling system gross weight when water of water tank injection certain volume Power is more than suffered buoyancy in water.
S9:The tube coupling 180 and steel nose girder 170 for waiting for pushing tow are supported with tube coupling jacking bracket 140, and it is prefabricated to withdraw arc tube coupling Template 120 is symmetrically installed two groups of guide and limit steel bars 1801 in the second 180 bottom surface of section tube coupling.
S10:Start jack group 100, along 150 pushing tow second of arc-shaped guide rail section tube coupling 180 advance tube coupling away from From.
S11:Carry out follow-up each section 180 pushing tow of tube coupling successively with reference to above-mentioned S8-S10 processes.If being found during pushing tow Foundation trench 60 back-silts when influencing normal pushing tow, should suspend pushing tow, the pushing tow again after 60 dredging of foundation trench.If steel nose girder during pushing tow 170 arrival stake end bearings, 210 top and do not fall on an end bearing 210 that (or steel nose girder 170 is too low collision stake end bearing 210 Risk), it can be by being allowed to suitably fall (on or in the 220 additional water filling (or drawing water) of ballast tank of a few section tube couplings 180 in front end It is floating) it is adjusted, also it can carry out auxiliary guiding control by the way that olecranon is arranged in 170 front end of steel nose girder.
Left and right linkage by jack group 100 during pushing tow is adjusted, 50 inner arc guide rail 150 of working pit is oriented to, The methods of mutual Horizontal limiting between 180 bottom guide and limit steel bar 1801 of tube coupling and stake top guide pad 2101 carries out level side It is adjusted to being oriented to, once 180 horizontal trajectory of tube coupling deviates from planned course, pushing tow should be suspended, should taken the necessary measures and correct water Put down behind track pushing tow again.Before a certain section tube coupling 180 will enter water during pushing tow, to ballast tank 220 in the tube coupling 180 Disposable to be filled to design water injection rate, design water injection rate should ensure that the section tube coupling system total force is suffered slightly larger than in water at this time Buoyancy, so sequentially pushing tow and the water tank with water to each oral siphon section 180, until smoothly to reach opposite bank pre- for first segment tube coupling 180 End pushing tow is set in positioning.
S12:Using 190 backfill foundation trench 60 of foundation trench backfill material, removes the closure door of the steel on first segment tube coupling 180 160 and steel is led Beam 170 removes ballast tank 220 and hydraulic pipeline in each tube coupling 180, removes rear parados 90 in working pit 50, jack group 100, iron 110, arc tube coupling prefab-form 120, template jacking bracket 130, tube coupling jacking bracket 140, arc-shaped guide rail are pushed up 150, working pit backfill 200 backfilling workings of material hole 50 is finally used, entire underway incremental launching construction is completed.
As shown in Fig. 2, when riverbed undulating is larger, the specific process of underway push construction method provided in this embodiment It is as follows:
S1:According to riverbank riverbed landform, riverbed engineering geological condition and surrounding enviroment, design underway longitudinal direction path line 40, longitudinal path line 40 should be circular arc, and arc track should be matched with gentle 240 bottom profile of section in riverbed as possible, to reduce foundation trench 60 excavate workload, and for the deep section 230 in riverbed with underwater type of bridge transition, the ratio between horizontal distance and vertical height of circular arc are general Not less than 50.Wherein longitudinal direction path line 40 is necessary for circular arc line, inevitable during pushing tow if broken line or other non-circular arc lines It will appear 180 bottom surface of tube coupling and be detached from support stake 80, pushing tow can not be normally carried out.
S2:According to practical riverbed situation, selectivity is filled out using specialized dredger, dredger, sand compaction pile ship, jackstone rammer Ship, broken stone leveling ship etc. are dredged along planned course line and dig foundation trench 60 and progress basement process, foundation trench cross-sectional outling line under water 70 should be suitably larger than channel outer contour, and 60 bottom surface longitudinal direction track of foundation trench should substantially match with the arc-shaped bottom surface in channel, foundation trench 60 bottom surfaces should be lower at least 30cm than 180 bottom surface of design tube coupling, and 60 both sides of foundation trench should be arranged rational slope and become silted up to prevent non-return, to river Groove depth segment 230 is without excavating.Extend appropriate location ashore in longitudinal path line 40 and excavates pushing tow working pit 50, working pit After 50 length should be checked according to 180 length of single-unit tube coupling, the pre- control equipment of tube coupling and incremental launching device, live site condition etc. It determines.
S3:Using cast-in-situ bored pile method at interval of a pair of of support stake 80 of certain distance construction, longitudinal two-phase in foundation trench 60 The maximum outreach of neighbour's support stake 80 should determine after structure stress checks, and support stake should be suitably encrypted to the deep section in riverbed 230 80.Support 80 diameters of stake are typically no less than 80cm, and stake is long should be true according to 180 load of top tube coupling and lower part Checking Ground Bearing Capacity Fixed, stake top is at least higher 10cm than excavating 60 bottom of foundation trench.As shown in figure 5,80 top of support stake setting stake end bearing 210, stake end Bearing 210 is made of guide pad 2101, stainless steel plate 2102, polytetrafluoroethylene (PTFE) sliding block 2103, and polytetrafluoroethylene (PTFE) sliding block 2103 is answered Tangent with the 180 bottom arc track face of tube coupling of design, sliding block is vertically installed positioning accuracy and is preferably controlled within 1cm, guide pad 2101 guide groove should match with the guide and limit steel bar 1801 of 180 lower part of tube coupling, pass through guide and limit steel bar 1801 and stake Mutual Horizontal limiting between the guide pad 2101 of top plays the role of horizontally-guided.
S4:Parados 90, jack group 100, top iron 110, arc tube coupling prefab-form after being arranged in pushing tow working pit 50 120, the maximum top power of template jacking bracket 130, tube coupling jacking bracket 140, arc-shaped guide rail 150, jack group 100 answers root Calculate and determine according to design, if it is insufficient to occur top power during later stage pushing tow, it is contemplated that using more large-tonnage jack group 100 or Cable is connected in 170 front end of steel nose girder to pull from opposite bank.
S5:The prefabricated first segment tube coupling 180 of shuttering in working pit 50,180 length of single-unit tube coupling should consider work It is determined after cheating the factors such as the limitation of 50 lands used and construction period.After waiting for that tube coupling 180 conserves, water ballast is assembled in tube coupling 180 Case 220 simultaneously connects hydraulic pipeline, is sealed in 180 front end of tube coupling installation steel closure door 160, and install arc after steel closure door 160 Shape steel nose girder 170,170 length of steel nose girder are generally 0.6-0.7 times of 80 span of adjacent supports stake.
S6:The tube coupling 180 and steel nose girder 170 for waiting for pushing tow are supported with tube coupling jacking bracket 140, and it is prefabricated to withdraw arc tube coupling Template 120 is symmetrically installed two groups of guide and limit steel bars 1801 in 180 bottom surface of tube coupling.
S7:First section 180 pushing tow anti-overturning of tube coupling checking computations are carried out, start jack group 100 after checking computations are qualified, along arc The distance of 150 pushing tow first segment tube coupling 180 of guide rail, one tube coupling 180 of advance can if the stroke length of jack group 100 is inadequate The length that iron 110 is pushed up by increase solves.
S8:Pushing tow jack is retracted, the prefabricated second section tube coupling 180 of shuttering in working pit 50, with first segment tube coupling 180 Continuous structure is formed, after waiting for that tube coupling 180 conserves, ballast tank 220 is assembled in tube coupling 180 and connects hydraulic pipeline, is pressed The size of cabin water tank 220 should be determined according to antifloating computation, ensure the section tube coupling system gross weight when water of water tank injection certain volume Power is more than suffered buoyancy in water.
S9:The tube coupling 180 and steel nose girder 170 for waiting for pushing tow are supported with tube coupling jacking bracket 140, and it is prefabricated to withdraw arc tube coupling Template 120 is symmetrically installed two groups of guide and limit steel bars 1801 in the second 180 bottom surface of section tube coupling.
S10:Start jack group 100, along 150 pushing tow second of arc-shaped guide rail section one tube coupling 180 of advance of tube coupling 180 Distance.
S11:Carry out follow-up each section 180 pushing tow of tube coupling successively with reference to above-mentioned S8-S10 processes.If being found during pushing tow Foundation trench 60 back-silts when influencing normal pushing tow, should suspend pushing tow, the pushing tow again after 60 dredging of foundation trench.If steel nose girder during pushing tow 170 arrival stake end bearings, 210 top and do not fall on an end bearing 210 that (or steel nose girder 170 is too low collision stake end bearing 210 Risk), it can be by being allowed to suitably fall (on or in the 220 additional water filling (or drawing water) of ballast tank of a few section tube couplings 180 in front end It is floating) it is adjusted, also it can carry out auxiliary guiding control by the way that olecranon is arranged in 170 front end of steel nose girder.
Left and right linkage by jack group 100 during pushing tow is adjusted, 50 inner arc guide rail 150 of working pit is oriented to, The methods of mutual Horizontal limiting between 180 bottom guide and limit steel bar 1801 of tube coupling and stake top guide pad 2101 carries out horizontal direction It is oriented to and adjusts, once 180 horizontal trajectory of tube coupling deviates from planned course, pushing tow should be suspended, should take the necessary measures amendment level Pushing tow again after to track.Before a certain section tube coupling 180 will enter water during pushing tow, to ballast tank 220 1 in the tube coupling 180 Secondary property is filled to design water injection rate, and design water injection rate should ensure that the 180 system total force of tube coupling is suffered slightly larger than in water at this time Buoyancy, so sequentially pushing tow and the water tank with water to each oral siphon section 180, until smoothly to reach opposite bank pre- for first segment tube coupling 180 End pushing tow is set in positioning.
S12:Using 190 backfill foundation trenches 60 of foundation trench backfill material, to the deep section in riverbed 230 without backfill, the deep section in riverbed 230 The anti-protective layer that casts anchor of adequate thickness should be arranged in 180 top surface of tube coupling, should be arranged inside deep 230 tube coupling 180 of section in riverbed necessary Ballast structure is with neutral buoyancy.Steel closure door 160 and the steel nose girder 170 on first segment tube coupling 180 are removed, is removed in each tube coupling 180 Ballast tank 220 and hydraulic pipeline, rear parados 90, jack group 100, top iron 110, the arc tube coupling removed in working pit 50 are pre- Pallet 120, template jacking bracket 130, tube coupling jacking bracket 140, arc-shaped guide rail 150, are finally backfilled using working pit Expect 200 backfilling workings hole 50, completes entire underway incremental launching construction.
The present embodiment can generate following advantageous effect by above two underway push construction method:
(1) it is not necessarily to the special prefabricated place of large dry dock, only need to excavate the top of appropriate size on bank according to actual conditions Push away working pit 50;
(2) due to there is the support positioning of support 80 pairs of tube couplings 180 of stake, precision is excavated to foundation trench 60 and 60 flatness of foundation trench is wanted Reduction, the construction of foundation trench 60 is asked to be simplified;
(3) it is not necessarily to 180 precise positioning docking system of 180 transportation by driving ship of tube coupling and underwater tube coupling, it only need to be in bank working pit 50 Parados 90, jack group 100, top iron 110, arc tube coupling prefab-form 120, template jacking bracket 130, tube coupling after interior setting The simple devices such as jacking bracket 140, arc-shaped guide rail 150, construction equipment and construction technology are relatively simple;
(4) due to without special dry-docking place, and construction equipment and technique are simplified, cost can be effectively reduced;
(5) entire pushing tow underway is continuous structure, and without GINA waterstops, water resistance is more preferable, normally In the case of can accomplish it is watertight.
Specifically, the present embodiment also certain steps in underway push construction method are done it is described in detail below.
First, foundation trench excavates cross section as shown in figure 3, excavating foundation trench 60 below original riverbed bottom surface 30 in step s 2 And install support stake 80,60 bottom surface of foundation trench should at least 30cm lower than the bottom surface of tube coupling 180, support stake 80 stake end bearing 210 answer At least than 70 high 10cm of foundation trench cross-sectional outling line, 60 both sides of foundation trench should be arranged rational slope and become silted up to prevent non-return.
Again as shown in figure 4, the cast-in-situ bored pile method of installation support stake 80 in step s3 is as follows:
The first inserting piling steel pile casting 250 in foundation trench 60, after the completion of 250 inserting piling of steel pile casting, top needs to be higher by stream stage 10. Then, the water in steel pile casting 250 is drained, after draining, the concrete perfusion in steel pile casting 250 forms cast-in-situ bored pile 260, At this time, it may be necessary to ensure that the top of cast-in-situ bored pile 260 is higher than 60 bottom surface of foundation trench about 10cm.Finally, by 260 top of cast-in-situ bored pile Steel pile casting 250 cut off, ultimately form the support stake 80 of needs.
Finally, in step S3-S11, tube coupling 180 is with 210 thin portion structure of stake end bearing as shown in figure 5, tube coupling 180 is Arc tube coupling, tube coupling 180 is interior to be arranged ballast tank 220, and 180 bottom surface of tube coupling is symmetrical arranged two groups of guide and limit steel bars 1801. 80 top setting stake end bearing 210 of stake is supported, stake end bearing 210 is by guide pad 2101, stainless steel plate 2102 and polytetrafluoroethylene (PTFE) Sliding block 2103 forms.One group of guide and limit steel bar 1801 matches with a pair of of stake top guide pad 2101 plays horizontal direction guide and limit Effect.Polytetrafluoroethylene (PTFE) sliding block 2103 is in tangent relation with 180 bottom surface of tube coupling, and the transfer rolling of polytetrafluoroethylene (PTFE) sliding block 2103 can Effectively reduce frictional resistance when the two is opposite to be slided.
Finally it should be noted that:The above embodiments are only used to illustrate the technical solution of the present invention., rather than its limitations;To the greatest extent Present invention has been described in detail with reference to the aforementioned embodiments for pipe, it will be understood by those of ordinary skill in the art that:Its according to So can with technical scheme described in the above embodiments is modified, either to which part or all technical features into Row equivalent replacement;And these modifications or replacements, various embodiments of the present invention technology that it does not separate the essence of the corresponding technical solution The range of scheme.

Claims (6)

1. a kind of underway push construction method, which is characterized in that in turn include the following steps:
S1:Underway longitudinal direction path line is designed, when riverbed undulating is larger and section deep at least one section of riverbed, longitudinal rail Trace is located at the top of riverbed bottom surface at the deep section in riverbed;
S2:According to longitudinal path line, pushing tow working pit is excavated on bank, excavates foundation trench under water, it, should when there is the deep section in riverbed Region is without excavating;
S3:It constructs a pair of of support stake at interval of certain distance in foundation trench, an end bearing is installed on pile top, when there is the deep section in riverbed When, suitably encrypt support stake in the region;
S4:Parados, jack group, top iron, arc tube coupling prefab-form, template jack after being set gradually in pushing tow working pit Bearing, tube coupling jacking bracket, arc-shaped guide rail;
S5:The prefabricated first segment tube coupling of shuttering in working pit assembles ballast tank simultaneously after waiting for tube coupling maintenance in tube coupling Hydraulic pipeline is connected, is sealed in tube coupling front end installation steel closure door, and the steel nose girder of arc is installed after steel closure door;
S6:The tube coupling and steel nose girder that pushing tow is waited for the support of tube coupling jacking bracket, withdraw arc tube coupling prefab-form, at tube coupling bottom Face is symmetrically installed two groups of guide and limit steel bars;
S7:Start jack group, the distance for the tube coupling that advances along arc-shaped guide rail pushing tow first segment tube coupling;
S8:Jack group is retracted, the prefabricated second section tube coupling of shuttering, continuous structure is formed with first segment tube coupling in working pit, After waiting for tube coupling maintenance, ballast tank is assembled in tube coupling and connects hydraulic pipeline;
S9:The tube coupling and steel nose girder that pushing tow is waited for the support of tube coupling jacking bracket, withdraw tube coupling prefab-form, and tube coupling is saved second Bottom surface is symmetrically installed two groups of guide and limit steel bars;
S10:Start jack group, the distance of tube coupling one tube coupling of advance is saved along arc-shaped guide rail pushing tow second;
S11:The incremental launching construction that step S8-S10 completes follow-up tube coupling is repeated, each section tube coupling will enter water during pushing tow Before, design water injection rate is disposably filled to ballast tank in the tube coupling to prevent from floating, so sequentially pushing tow and to respectively entering water The water tank with water of tube coupling, until first segment tube coupling smoothly reaches opposite bank precalculated position and terminates pushing tow;
S12:Foundation trench is backfilled, to the deep section in riverbed without backfill, removes incremental launching device in tube coupling affiliated facility and working pit, is backfilled Working pit completes entire underway incremental launching construction.
2. underway push construction method according to claim 1, which is characterized in that the longitudinal direction path line is circular arc Shape, arc-shaped track are matched with riverbed bottom profile, and the ratio between arc-shaped horizontal distance and vertical height is typically no less than 50.
3. underway push construction method according to claim 1, which is characterized in that the cross-sectional outling of the foundation trench Line exceeds underway outer contour, and the foundation trench bottom surface is lower at least 30cm than design tube coupling bottom surface, and the foundation trench both sides are also set Set the slope for preventing from back-silting.
4. underway push construction method according to claim 1, which is characterized in that the stake diameter of the support stake is at least For 80cm, stake top is higher at least 10cm than the foundation trench bottom, and stake end bearing includes guide pad, stainless steel equipped with guide groove Plate and sliding block that can be tangent with tube coupling bottom arc track face, the institute of the guide groove of the guide pad and the tube coupling lower part Guide and limit steel bar is stated to match.
5. underway push construction method according to claim 1, which is characterized in that the tube coupling is arc-shaped pipe It saves, the size shape all same of all tube couplings, pours to form continuous structure by wet seam between the adjacent tube coupling, institute State 0.6-0.7 times that steel nose girder length is span between the longitudinally adjacent support stake.
6. underway push construction method according to claim 1, which is characterized in that, should when there is the deep section in riverbed Region is with underwater type of bridge transition, and the tube coupling top surface in the region is provided with the anti-protective layer that casts anchor, and the region is described Tube coupling is internally provided with the ballast structure to neutral buoyancy.
CN201810169838.1A 2018-02-28 2018-02-28 Underway push construction method Active CN108360384B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810169838.1A CN108360384B (en) 2018-02-28 2018-02-28 Underway push construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810169838.1A CN108360384B (en) 2018-02-28 2018-02-28 Underway push construction method

Publications (2)

Publication Number Publication Date
CN108360384A true CN108360384A (en) 2018-08-03
CN108360384B CN108360384B (en) 2019-11-22

Family

ID=63002890

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810169838.1A Active CN108360384B (en) 2018-02-28 2018-02-28 Underway push construction method

Country Status (1)

Country Link
CN (1) CN108360384B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109944605A (en) * 2019-04-04 2019-06-28 上海市城市建设设计研究总院(集团)有限公司 Jacking pipe joints prefabricated components and pipe jacking construction method with grooved hole
CN111254981A (en) * 2020-01-20 2020-06-09 中交第三航务工程局有限公司 Draw formula suspension tunnel structure to one side under water

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0275412B1 (en) * 1987-01-22 1993-01-20 Strabag Bau - Ag Method of producing an elongate structure
JP2000120095A (en) * 1998-10-12 2000-04-25 Taisei Corp Method for constructing underwater tunnel
KR20090107333A (en) * 2008-04-08 2009-10-13 정병영 Immersed Bridge System of Complex Type and The Construction Method Thereof
KR20090129001A (en) * 2008-06-12 2009-12-16 삼성중공업 주식회사 A bridge structure of floating type
CN202865755U (en) * 2012-08-31 2013-04-10 中交第二航务工程局有限公司 Immersed tunnel pipe joint axis positioning system
CN103147462A (en) * 2013-03-22 2013-06-12 王余富 Slotting incremental launching construction method
CN103711986A (en) * 2013-11-29 2014-04-09 中交第四航务工程局有限公司 Pushing system and method for factory method segment prefabrication construction
CN104532876A (en) * 2014-12-17 2015-04-22 北京工业大学 Deep see immersed type tunnel based on rigidity carrier
CN107700543A (en) * 2017-09-01 2018-02-16 中交第航务工程局有限公司 Longitudinally adjusted system and method after immersed tube tunnel final joint implantation
CN107700544A (en) * 2017-09-01 2018-02-16 中交第航务工程局有限公司 Off-lying sea immersed tube installation method

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0275412B1 (en) * 1987-01-22 1993-01-20 Strabag Bau - Ag Method of producing an elongate structure
JP2000120095A (en) * 1998-10-12 2000-04-25 Taisei Corp Method for constructing underwater tunnel
KR20090107333A (en) * 2008-04-08 2009-10-13 정병영 Immersed Bridge System of Complex Type and The Construction Method Thereof
KR20090129001A (en) * 2008-06-12 2009-12-16 삼성중공업 주식회사 A bridge structure of floating type
CN202865755U (en) * 2012-08-31 2013-04-10 中交第二航务工程局有限公司 Immersed tunnel pipe joint axis positioning system
CN103147462A (en) * 2013-03-22 2013-06-12 王余富 Slotting incremental launching construction method
CN103711986A (en) * 2013-11-29 2014-04-09 中交第四航务工程局有限公司 Pushing system and method for factory method segment prefabrication construction
CN104532876A (en) * 2014-12-17 2015-04-22 北京工业大学 Deep see immersed type tunnel based on rigidity carrier
CN107700543A (en) * 2017-09-01 2018-02-16 中交第航务工程局有限公司 Longitudinally adjusted system and method after immersed tube tunnel final joint implantation
CN107700544A (en) * 2017-09-01 2018-02-16 中交第航务工程局有限公司 Off-lying sea immersed tube installation method

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109944605A (en) * 2019-04-04 2019-06-28 上海市城市建设设计研究总院(集团)有限公司 Jacking pipe joints prefabricated components and pipe jacking construction method with grooved hole
CN109944605B (en) * 2019-04-04 2024-03-12 上海市城市建设设计研究总院(集团)有限公司 Pipe-jacking pipe joint prefabricated part with slotted holes and pipe-jacking construction method
CN111254981A (en) * 2020-01-20 2020-06-09 中交第三航务工程局有限公司 Draw formula suspension tunnel structure to one side under water
CN111254981B (en) * 2020-01-20 2021-04-13 中交第三航务工程局有限公司 Draw formula suspension tunnel structure to one side under water

Also Published As

Publication number Publication date
CN108360384B (en) 2019-11-22

Similar Documents

Publication Publication Date Title
CN105386408B (en) Deep-water bridge pile foundation construction method
CN104196034B (en) A kind of utilize steel sheet pile as the foundation ditch construction method in supporting cofferdam
CN102094425B (en) Foundation pit construction method adopting shallow buried depth Larsen steel plate pile as protective cofferdam
CN104612162B (en) A kind of Deep Foundation Pit of Metro Stations excavation construction method
CN102691294B (en) Construction method of underground continuous wall
CN107313431B (en) Close on not contour foundation pit method for synchronously constructing
CN100497841C (en) Supporting leg type underground continuous wall construction method
CN106930321B (en) The construction method of underground structure is built in a kind of stake of pipe-jacking with large diameter combination hole
CN102720140B (en) Large-span prestress concrete continuous beam deepwater pier construction process
CN110017144B (en) Loess tunnel three-step construction method considering substrate reinforcement treatment
CN105756091B (en) A kind of Metro station excavation construction method of control adjacent building composition deformation
CN108842819A (en) A kind of urban track traffic cable run method for tunnel construction
CN110043264A (en) A kind of construction method of jacking prefabricated rectangle shaft structure pattern
CN104164881A (en) Piling wall overlapping cantilever foundation pit support construction method and structure
CN108360384B (en) Underway push construction method
CN109707002B (en) Device and method for accurately positioning, sinking and installing large water intake head
CN110055973B (en) Foundation pit enclosure structure under high-speed railway bridge with limited construction space and water stopping method
CN106930278A (en) A kind of method that compromise joint pipe is used for support pile occlusion
CN106758759A (en) A kind of trestle pile foundation and its anchoring process for deep water drift net riverbed
CN110374109B (en) Application method of construction method pile enclosure in comprehensive pipe gallery foundation pit
CN210141142U (en) Underground structure is built in same direction as digging in hole stake secret
CN110777827A (en) Structure capable of carrying out deep water area hollowing repair in rapid stream state
CN218969976U (en) Pushing structure suitable for pushing method construction continuous wall
CN211285658U (en) Structure capable of carrying out deep water area hollowing repair in rapid stream state
CN110130399A (en) Tilt trapezoidal piping lane system and its construction method of the supporting in conjunction with main structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: No. 928, yuhangtang Road, Xihu District, Hangzhou City, Zhejiang Province 310011

Patentee after: Zhejiang shuzhijiaoyuan Technology Co.,Ltd.

Address before: No. 928, yuhangtang Road, Xihu District, Hangzhou City, Zhejiang Province 310011

Patentee before: ZHEJIANG PROVINCIAL INSTITUTE OF COMMUNICATIONS PLANNING DESIGN & RESEARCH Co.,Ltd.

CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: No. 928, yuhangtang Road, Xihu District, Hangzhou City, Zhejiang Province 310011

Patentee after: ZHEJIANG PROVINCIAL INSTITUTE OF COMMUNICATIONS PLANNING DESIGN & RESEARCH Co.,Ltd.

Address before: No. 89 round City West Road, Xihu District, Hangzhou, Zhejiang

Patentee before: ZHEJIANG PROVINCIAL INSTITUTE OF COMMUNICATIONS PLANNING, DESIGN & RESEARCH