CN108360322A - A kind of Gypsisol embankment fill material and construction method - Google Patents

A kind of Gypsisol embankment fill material and construction method Download PDF

Info

Publication number
CN108360322A
CN108360322A CN201810109909.9A CN201810109909A CN108360322A CN 108360322 A CN108360322 A CN 108360322A CN 201810109909 A CN201810109909 A CN 201810109909A CN 108360322 A CN108360322 A CN 108360322A
Authority
CN
China
Prior art keywords
embankment
gypsisol
fill material
construction method
embankment fill
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810109909.9A
Other languages
Chinese (zh)
Inventor
杨成永
王镇
李文茂
程霖
王锦
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Lin Ce Railway LLC
Beijing Jiaotong University
Original Assignee
Lin Ce Railway LLC
Beijing Jiaotong University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Lin Ce Railway LLC, Beijing Jiaotong University filed Critical Lin Ce Railway LLC
Priority to CN201810109909.9A priority Critical patent/CN108360322A/en
Publication of CN108360322A publication Critical patent/CN108360322A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C3/00Foundations for pavings
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/02Improving by compacting
    • E02D3/046Improving by compacting by tamping or vibrating, e.g. with auxiliary watering of the soil

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • Soil Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Agronomy & Crop Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Road Paving Structures (AREA)
  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
  • Devices Affording Protection Of Roads Or Walls For Sound Insulation (AREA)

Abstract

The invention discloses a kind of Gypsisol embankment fill material and construction methods.The Gypsisol embankment fill material includes:Embankment fill material under bedding is Gypsisol original soil;Embankment of roadbed bottom filler makes a sudden snatch 1 for Gypsisol original soil and mountain:1 mixture;And surface layer of subgrade bed embankment fill material, make a sudden snatch 1 for Gypsisol original soil and mountain:1 blends the mixture that every cube of earth material addition 100kg flyash is formed again.Gypsisol embankment fill material provided by the invention and construction method, reduce the quantity for abandoning the earthwork, save engineering cost, reduce the influence to environment.

Description

A kind of Gypsisol embankment fill material and construction method
Technical field
The present invention relates to railway engineering technology fields, and in particular to a kind of Gypsisol embankment fill material and construction method.
Background technology
Gypsisol (gypseous gravelly soil, gravelly sand soil) distribution of strata area is wide, thickness is big.Gypsum in Gypsisol belongs to Middle dissolved salt (gypsum dissolution degree is 2 ‰ or so at the standard conditions), can be dissolved in water and take away, cause Gypsisol have the swollen property of pine, Dilatancy and shrinkage.People are inexperienced as embankment fill material to Gypsisol at present, cause Gypsisol to be not yet written related Geotechnical investigation specification cannot act as substrate or filler for building.In previous railway construction, to the stone of exposure in field of fetching earth Cream soil needs are purged, and change filling out to the Gypsisol that embankment underlies.
Gypsisol is purged or is changed and is filled out, builder's road length certainly will be increased, increases side's amount of spoir, increases spoil ground Scale.Therefore, influence degree of the engineering construction to environment can be obviously increased, and increases project cost.
Invention content
In order to solve the above technical problems, a kind of Gypsisol embankment fill material of present invention offer and construction method.The present invention passes through Indoor and field test proposes that Gypsisol is used as the ameliorative measure of embankment fill material and the construction technology of embankment.
To achieve the above object, the present invention uses following technical scheme:
One aspect of the present invention provides a kind of Gypsisol embankment fill material, including:
Embankment fill material under bedding is Gypsisol original soil;
Embankment of roadbed bottom filler makes a sudden snatch 1 for Gypsisol original soil and mountain:1 mixture;And
Surface layer of subgrade bed embankment fill material makes a sudden snatch 1 for Gypsisol original soil and mountain:1, which blends every cube of earth material again, adds 100kg fine coal The mixture that ash is formed.
Another aspect of the present invention also provides the construction method of above-mentioned Gypsisol embankment fill material, includes the following steps:
1) embankment fill material is prepared;
2) railway embankment;
Embankment fill material under the bedding of bedding lower part loose laying depth 45cm, the bottom layer of subgrade of bottom layer of subgrade loose laying depth 40cm Embankment fill material, the surface layer of subgrade bed embankment fill material of surface layer of subgrade bed loose laying depth 35cm;One layer has often been spread once to be compacted;
3) embankment slope surface is handled.
Preferably, the technique of the compacting is:Weak shake+1 time of the static pressure+2 times of 22T vibrated rollers 1 time is shaken by force.
In an advantageous embodiment, step 3) processing embankment slope surface is specially to use gravelly soil Bao Po.
It is highly preferred that the thickness of the gravelly soil Bao Po is 0.2m.
In another preferred embodiment, it is specially that embankment both sides are widened that step 3), which handles embankment slope surface,.
It is highly preferred that 0.5m is respectively widened in embankment both sides.
Beneficial effects of the present invention
Gypsisol embankment fill material provided by the invention and construction method, reduce the quantity for abandoning the earthwork, save engineering Expense reduces the influence to environment.
Description of the drawings
Fig. 1 changes for Gypsisol leaching deformation coefficient.
Fig. 2 is the sectional schematic diagram of common railway embankment.
Specific implementation mode
The present invention is specifically described below by embodiment, it is necessary to which indicated herein is that the present embodiment is served only for pair The present invention is further described, and should not be understood as limiting the scope of the invention, and the person skilled in the art in the field can To make some nonessential modifications and adaptations according to the content invented above.In the absence of conflict, the reality in the present invention The feature applied in example and embodiment can be combined with each other.
The technical issues of to solve to make embankment fill material using Gypsisol, following scientific research is carried out:
1, Gypsisol physical and mechanical parameter is tested
(1) salt content of Gypsisol
Its chemical composition and content analyzed to level land Gypsisol soil sample and mountainous region Gypsisol soil sample, measure soluble salt content and Middle dissolved salt content, the results are shown in Table 1.
The salt content of 1 Gypsisol of table
(2) swelling rate test of Gypsisol
Totally 18 samples, i.e.,:Level land Gypsisol soil sample 3, mountainous region Gypsisol soil sample 3, level land Gypsisol make a sudden snatch again with mountain Measure ratio 2:1 aggregate sample 3, level land Gypsisol and mountain make a sudden snatch weight ratio 1:2 aggregate samples 3, every cube of level land Gypsisol incorporation 50 Kilogram II grades of flyash aggregate samples 3, every cube of level land Gypsisol mix 100 kilograms of II grades of flyash aggregate samples 3.It carries out swollen Swollen rate experiment, is divided into no-load swelling rate test and linear swelling ratio tests two parts, the results are shown in Table 2;Each soil sample number According to the average value for taking respective 3 parallel tests.
The expansion rate of 2 Gypsisol of table
2, Leaching test (having load) in Gypsisol room
3 groups of totally 6 groups of soil samples, respectively 3 groups of level land Gypsisol and mountainous region Gypsisol.Soil sample is numbered:Level land 1-1 (the 1st sample of the 1st group of level land Gypsisol), level land 1-2 (the 2nd sample of the 1st group of level land Gypsisol), and so on, it prepares altogether 18 soil samples, soil sample height 20mm.Measure lixiviation deformation coefficient under loads at different levels of level land Gypsisol and mountainous region Gypsisol and Stabilization time.It the results are shown in Table 3;Each soil sample data takes the average value of respective 3 groups of parallel tests.
Sample collapsible settement amount and stabilization time average value under 3 load at different levels of table
3, pour to strain to test (no-load) in Gypsisol room
Totally 18 samples, i.e.,:Level land Gypsisol soil sample 3, mountainous region Gypsisol soil sample 3, level land Gypsisol make a sudden snatch again with mountain Measure ratio 2:1 aggregate sample 3, level land Gypsisol and mountain make a sudden snatch weight ratio 1:2 aggregate samples 3, every cube of level land Gypsisol incorporation 50 Kilogram II grades of flyash aggregate samples 3, every cube of level land Gypsisol mix 100 kilograms of II grades of flyash aggregate samples 3.Simulation 30 Under the conditions of annual rainfall, the breathing variable quantity of soil sample.It the results are shown in Table 4, Fig. 1;Each soil sample data takes the flat of respective 3 parallel tests Mean value.
4 pour to strain to test soil sample average deformation coefficient of table
4, live embankment test section fills
Fill length 40m, bottom layer width 16m, ratio of slope 1:1.5 embankment test section.
1) former gypsum earth material is filled out successively from the bottom up, every cube of former Gypsisol mixes 50 kilograms of II grades of coal ash mixed materials, Every cube of former Gypsisol mixes 100 kilograms of II grades of coal ash mixed materials, former gypsum earth material, and former Gypsisol splits weight ratio 2 with mountain:1 Mixture, former Gypsisol split weight ratio 1 with mountain:2 mixtures, the good gravel earth material of grading.
2) every layer of loose laying depth 40cm is pressed using 22T vibrated rollers by+2 times weak+1 time strong shake of shaking of 1 time static pressure It is real.
3) it after the completion of every layer of spreading, measures the compactness banketed and layer top mark is high.
5 live embankment test section consolidation effect inspections
After the completion of every layer is banketed and rolls, K is used30To check that consolidation effect, measurement result are shown in Table 5.
The coefficient of subgrade reaction that every layer of table 5 bankets
The compactibility of survey region filler is preferable, and original soil and aggregate sample can reach railway road by common compaction process The compaction requirement of dike surface layer of subgrade bed.I grades of railroad embankment gravel class soil coefficient of subgrade reaction K30, 1.0 are required under bedding, bottom layer of subgrade 1.2, surface layer of subgrade bed 1.5.
6, live embankment test section observation
Under local condition of raining, observation and measurement test section embankment Infiltration, banket ingredient leaching and Embankment Subsidence Situation.
According to the test data of indoor and outdoor, to Gypsisol just like drawing a conclusion:
1) salt content is higher, can reach 20%~30%.
2) there is dilatancy, linear swelling ratio is 1% or so after absorbing water;There is molten sunken property, lixiviation under the conditions of leaching The effect of deflection no-load is lower up to 2%~3%, has under load action up to 5%~10%.
3) compactibility is preferable, is that can reach the compaction requirement of railroad embankment surface layer of subgrade bed using common compaction process.
4) incorporation that mountain makes a sudden snatch reduces the content of salinity in Gypsisol, thus can reduce Gypsisol dilatancy and it is molten fall into Property.The incorporation that mountain makes a sudden snatch increases Gypsisol coarse grain component, therefore improves the permeability and compactibility of Gypsisol.
5) flyash has improving effect to Gypsisol.Incorporation flyash can obviously reduce the permeability of Gypsisol, dilatancy With molten sunken property.
According to above-mentioned conclusion, with reference to figure 2, it is as follows that present invention proposition uses Gypsisol to carry out the step of railroad embankment fills:
1) embankment fill material is prepared.Embankment fill material under bedding:Directly use Gypsisol original soil;Embankment of roadbed bottom filler:Stone Cream soil original soil and mountain make a sudden snatch 1:1 mixture;Surface layer of subgrade bed embankment fill material:Original soil and mountain make a sudden snatch 1:1, which blends again every cube of earth material, adds The mixture for adding 100kg flyash to be formed.
2) railway embankment.Embankment fill material under the bedding of bedding lower part loose laying depth 45cm, bottom layer of subgrade loose laying depth The embankment of roadbed bottom filler of 40cm, the surface layer of subgrade bed embankment fill material of surface layer of subgrade bed loose laying depth 35cm;One layer of progress is often spread Primary compacting;It is that can reach the compaction requirement of railroad embankment surface layer of subgrade bed using common compaction process.Preferably, it is compacted work Skill is that weak shake+1 time of the static pressure+2 times of 22T vibrated rollers 1 time is shaken by force.
3) embankment slope surface is handled:Widened using gravelly soil Bao Po or embankment both sides.
When using gravelly soil packet slope, the thickness of the gravelly soil Bao Po is preferably 0.2m.
When being widened using embankment both sides, it is preferable that 0.5m is respectively widened in embankment both sides.
Obviously, described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.Based on this Embodiment in invention, every other reality obtained by those of ordinary skill in the art without making creative efforts Example is applied, the scope of the present invention is belonged to.

Claims (7)

1. a kind of Gypsisol embankment fill material, which is characterized in that the Gypsisol embankment fill material includes:
Embankment fill material under bedding is Gypsisol original soil;
Embankment of roadbed bottom filler makes a sudden snatch 1 for Gypsisol original soil and mountain:1 mixture;And
Surface layer of subgrade bed embankment fill material makes a sudden snatch 1 for Gypsisol original soil and mountain:1, which blends every cube of earth material again, adds 100kg flyash shapes At mixture.
2. the construction method of Gypsisol embankment fill material described in a kind of claim 1, which is characterized in that include the following steps:
1) embankment fill material is prepared;
2) railway embankment;
Embankment fill material under the bedding of bedding lower part loose laying depth 45cm, the embankment of roadbed bottom of bottom layer of subgrade loose laying depth 40cm Filler, the surface layer of subgrade bed embankment fill material of surface layer of subgrade bed loose laying depth 35cm;One layer has often been spread once to be compacted;
3) embankment slope surface is handled.
3. construction method according to claim 2, which is characterized in that the technique of the compacting is:22T vibrated rollers 1 It shakes by force all over+2 times weak shake+1 time of static pressure.
4. construction method according to claim 2, which is characterized in that it is specially to use rubble that step 3), which handles embankment slope surface, Native Bao Po.
5. construction method according to claim 4, which is characterized in that the thickness of the gravelly soil Bao Po is 0.2m.
6. construction method according to claim 2, which is characterized in that it is specially embankment both sides that step 3), which handles embankment slope surface, Widen.
7. construction method according to claim 6, which is characterized in that 0.5m is respectively widened in embankment both sides.
CN201810109909.9A 2018-02-05 2018-02-05 A kind of Gypsisol embankment fill material and construction method Pending CN108360322A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810109909.9A CN108360322A (en) 2018-02-05 2018-02-05 A kind of Gypsisol embankment fill material and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810109909.9A CN108360322A (en) 2018-02-05 2018-02-05 A kind of Gypsisol embankment fill material and construction method

Publications (1)

Publication Number Publication Date
CN108360322A true CN108360322A (en) 2018-08-03

Family

ID=63004837

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810109909.9A Pending CN108360322A (en) 2018-02-05 2018-02-05 A kind of Gypsisol embankment fill material and construction method

Country Status (1)

Country Link
CN (1) CN108360322A (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4397899A (en) * 1980-10-03 1983-08-09 True Temper Corporation Variable thickness mat for use at the stress transition zone juncture of a bridge-roadway or the juncture of a railroad crossing-roadway
CN1683719A (en) * 2004-09-07 2005-10-19 陈永烽 Expansion soil ecological modifying agent and construction method
CN101974877A (en) * 2010-10-18 2011-02-16 中铁第四勘察设计院集团有限公司 Rapid transit railway soft rock-improved soil roadbed structure
CN205348198U (en) * 2015-12-30 2016-06-29 中铁第四勘察设计院集团有限公司 Native karst cutting reinforced structure expands

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4397899A (en) * 1980-10-03 1983-08-09 True Temper Corporation Variable thickness mat for use at the stress transition zone juncture of a bridge-roadway or the juncture of a railroad crossing-roadway
CN1683719A (en) * 2004-09-07 2005-10-19 陈永烽 Expansion soil ecological modifying agent and construction method
CN101974877A (en) * 2010-10-18 2011-02-16 中铁第四勘察设计院集团有限公司 Rapid transit railway soft rock-improved soil roadbed structure
CN205348198U (en) * 2015-12-30 2016-06-29 中铁第四勘察设计院集团有限公司 Native karst cutting reinforced structure expands

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
于强哉: "铁路沿线含石膏土的工程性质及处理措施研究", 《建筑施工》 *

Similar Documents

Publication Publication Date Title
Özcan et al. Geo-engineering characterization and an approach to estimate the in-situ long-term settlement of a peat deposit at an industrial district
CN105862535B (en) A kind of construction method of barged-in fill curing stake roadbed
Celik et al. An investigation of the effect of sand content on geotechnical properties of fibrous peat
Cantré et al. Installation of fine-grained organic dredged materials in combination with geosynthetics in the German DredgDikes research dike facility
Ademila Geotechnical properties and effects of palm kernel shell ash and cement on residual soils in pavement construction along Owo-Ikare Road, Southwestern Nigeria
CN108360322A (en) A kind of Gypsisol embankment fill material and construction method
Juradin et al. Influence of binder, aggregate and compaction techniques on the properties of single-sized pervious concrete
KR20000053728A (en) Solidified composition to strengthen weak stratum and constructing method using the same
Kumbhare et al. Experimental studies on alternate foundations for load transfer in deep clay deposits
Islam et al. Behaviour of stabilised peat: A field study
Ugwuanyi et al. Suitability of Olokoro and Amaoba lateritic soil as pavement construction materials
Oke Deltaic lateritic soil in 1: 5: 11 mix design for producing controlled low-strength material (CLSM) for pavement backfill
Al-Waily Effect of mixing granular materials on soft soil properties
CN114293421B (en) Carbonaceous shale embankment and filling construction method thereof
Bush Understanding stabilized earth construction
CN107831092A (en) A kind of levee body filler relative compaction detection method of clear beach material fill technology
Ismael et al. Influence of relative compaction on the shear strength of compacted surface sands
Kumar et al. Effect of cement content on unconfined Compressive strength of Jamshoro soil
GUDI COMPARISON OF THE GEOTECHNICAL CHARACTERISTICS OF THE PREDOMINATE SOIL TYPE IN THE OLD SITE TO THE NEW SITE IN NIGER
Prajudi et al. Analysis of Soft Soil Shear Strength on Slopes Stabilized Using Volcanic Ash and Phosphoric Acid
Ramesh GROUND IMPROVEMENT TECHNIQUES TO ENHANCE THE BEARING CAPACITY OF WEAK SOIL USING BENTONITE
NZEKWABAM STRENGTH PROPERTIES OF LATERITE STABILIZED WITH CEMENT AND SAND
Toukan Static and impact compaction of a lateritic soil
Gana et al. STABILIZATION OF LATERITIC SOIL USING ASPHALTIC STABILIZATION OF LATERITIC SOIL USING ASPHALTIC EMULSION AND BAGASSE ASH AS BINDER EMULSION AND BAGASSE ASH AS BINDER
Duncan et al. Soil Compaction

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20180803