CN108343066B - Subway transfer station tie line pit in pit supporting structure and excavation method - Google Patents

Subway transfer station tie line pit in pit supporting structure and excavation method Download PDF

Info

Publication number
CN108343066B
CN108343066B CN201810371737.2A CN201810371737A CN108343066B CN 108343066 B CN108343066 B CN 108343066B CN 201810371737 A CN201810371737 A CN 201810371737A CN 108343066 B CN108343066 B CN 108343066B
Authority
CN
China
Prior art keywords
bottom plate
foundation pit
reinforced concrete
pit
main body
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201810371737.2A
Other languages
Chinese (zh)
Other versions
CN108343066A (en
Inventor
梁旋
谢仁良
王国炜
李德明
邹何
罗振铭
熊杰
李刚银
舒鹏为
徐小迪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway No2 Bureau Engineering Co ltd
China Railway Erju 1st Engineering Co Ltd
Original Assignee
China Railway No2 Bureau Engineering Co ltd
China Railway Erju 1st Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway No2 Bureau Engineering Co ltd, China Railway Erju 1st Engineering Co Ltd filed Critical China Railway No2 Bureau Engineering Co ltd
Priority to CN201810371737.2A priority Critical patent/CN108343066B/en
Publication of CN108343066A publication Critical patent/CN108343066A/en
Application granted granted Critical
Publication of CN108343066B publication Critical patent/CN108343066B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/04Making large underground spaces, e.g. for underground plants, e.g. stations of underground railways; Construction or layout thereof

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Sustainable Development (AREA)
  • Environmental & Geological Engineering (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

The invention provides a pit-in-pit supporting structure of a tie line of a subway transfer station and an excavation method, wherein the supporting structure comprises supporting rods, reinforced concrete brackets and a main structure bottom plate, the main structure bottom plate comprises a poured structure bottom plate and a post-poured structure bottom plate, the reinforced concrete brackets are poured above the end part of the poured main structure bottom plate at intervals along the direction of the tie line, one end of each supporting rod is supported on a foundation pit enclosure structure, and the other end of each supporting rod is supported on the reinforced concrete bracket, so that the problems that the deformation of the pit wall exceeds standard at present, temporary reinforcement measures are adopted before excavation of the tie line foundation pit, the construction requirement is high, the cost investment is large, the environment protection is not facilitated and the like are solved. Belongs to the field of subway construction.

Description

Subway transfer station tie line pit in pit supporting structure and excavation method
Technical Field
The invention relates to a subway transfer station tie line pit-in-pit supporting structure and an excavation method, and belongs to the field of subway construction.
Background
The construction of the connecting lines is generally carried out after the construction of the main body structure of the station is completed, and the construction is organized according to the sequence, so that the construction safety risks of the main body foundation pit and the connecting line foundation pit of the station are reduced to a certain extent, but the construction of the connecting lines is carried out by additionally maintaining the structure, the construction cost is greatly increased, and the construction period is longer. The Hangzhou subway SG5-9 standard Shen Banlu station is designed into 3, 5 wire transfer stations, the stations are arranged in an inverted T shape, the 3 wire stations are arranged in the north-south direction along the half-way of the ground, the 5 wire stations are arranged in the east-west direction across Shen Banlu and are of an underground two-layer structure. 3. A tie line is arranged between stations of the No. 5 wire, the height difference of the tie line is 4.91m (-13.050 m to-17.960 m), and the longitudinal slope is 38.272 per mill. The station foundation pit excavation is constructed in a mode of excavating a main foundation pit and a tie line foundation pit simultaneously. The station tie line is designed to be a concave curve trend, and the side pressure of the earth on the pit wall is very large in the pit wall excavation construction of the tie line through design checking calculation, so that the deformation of the pit wall exceeds the standard, temporary reinforcement measures are needed before the tie line pit excavation, and the safety of the pit excavation is ensured. Usually, the pit-in-pit support adopts the modes of drilling and grouting row piles, cement soil stirring piles, high-pressure jet grouting piles, gravity retaining walls and the like, but the mode has high construction requirements, large cost investment and is not beneficial to environmental protection.
Disclosure of Invention
The invention aims at: the utility model provides a subway transfer station tie line pit in pit bearing structure and excavation method to solve at present and surpass standard in pit wall deflection, the interim reinforcement measure that takes before the tie line foundation ditch excavation, construction requirement is high, and the cost is invested in greatly, is unfavorable for environmental protection scheduling problem.
In order to solve the problems, the method for excavating the pits in the tie-line pits of the subway transfer station is to be adopted, and comprises the following specific steps:
step one: excavating to the bottom of a main body foundation pit, completing pouring of a main body structure bottom plate in the main body foundation pit range, reserving a section of width as a post-pouring strip on the side line of a distance connecting line structure during pouring, reserving a steel bar joint at the end part, and reserving the post-pouring strip width as follows: the excavation depth of the foundation pit of the connecting line is +1.5m;
step two: pouring reinforced concrete brackets at intervals along the direction of the connecting lines on the top of the end part of the bottom plate of the poured main body structure, wherein the distance between the brackets is the same as the distance between temporary support rods, and the foundation pit excavation can be ensured to be smoothly carried out by the mechanical energy in the later stage;
step three: after the strength of the structural bottom plate and the reinforced concrete bracket reaches 85% of the design strength, installing a support rod piece, wherein one end of the support rod piece is supported on the foundation pit enclosure structure, the other end of the support rod piece is supported on the reinforced concrete bracket, and the support rod piece, the reinforced concrete bracket and the poured structural bottom plate are connected into a whole to be used as a horizontal support structure for bearing the soil pressure at two sides of the foundation pit;
step four: excavating a tie line foundation pit, wherein the foundation pit slope is formed by the following steps of 1:1, slope laying and excavating, wherein a platform with the distance of more than or equal to 1.5m is reserved between poured bottom plates on the excavation edge;
step five: applying a main structure of the connecting line, and filling the main structure of the connecting line between slopes by adopting C20 plain concrete until the bottom elevation of a main foundation pit is filled after the main structure of the connecting line reaches 85% of the design strength;
step six: applying a post-cast strip of the bottom plate of the main body structure, and curing, wherein the post-cast strip steel bars are effectively connected with reserved steel bars according to the design specification;
step seven: and after the concrete strength reaches 85% of the design requirement, dismantling the tie line foundation pit support and the reinforced concrete bracket, and then carrying out subsequent main body structural engineering construction.
In the second step, the reinforced concrete brackets are alternately arranged according to the intervals of 2m and 4m, and connecting steel bars are reserved at the reinforced concrete brackets when the main body structure bottom plate is manufactured, so that the reinforced concrete brackets and the structure bottom plate form a whole, and the stress stability is ensured;
and step four, excavating the foundation pit in layers, hanging 6.5@250×250 reinforcing steel meshes on the slope every time when one layer is excavated, and spraying 10cm thick C15 plain spray concrete as slope protection.
The invention also provides a subway transfer station tie line pit in pit supporting structure which comprises a supporting rod piece, reinforced concrete brackets and a main body structure bottom plate, wherein the main body structure bottom plate comprises a poured structure bottom plate and a rear pouring structure bottom plate, the reinforced concrete brackets are poured above the end part of the poured main body structure bottom plate at intervals along the tie line direction, one end of the supporting rod piece is supported on a foundation pit enclosure structure, and the other end of the supporting rod piece is supported on the reinforced concrete brackets.
In the supporting structure, the reinforced concrete brackets are alternately arranged along the direction of the connecting line at intervals of 2m and 4 m;
the end face of the support rod piece is vertical to the side wall of the support bracket and tightly clung to the side wall of the support bracket, so that the support rod piece is ensured to be uniformly stressed; the reinforced concrete bracket is arranged on the top surface of the end part of the bottom plate of the main body structure, and the reinforced concrete bracket and the bracket are effectively connected into a whole through the reserved reinforcing steel bars of the bottom plate during construction; the support rod piece is generally a steel pipe and can also be a reinforced concrete support rod piece; the reinforced concrete bracket is generally of a cuboid structure, and the length, width and height are 1m, 1.2m; when the tie line foundation pit is excavated, the horizontal support stress system formed by the support rod pieces, the reinforced concrete brackets and the main structure bottom plate is utilized to bear the soil pressure at two sides of the pit wall, so that the safety of the foundation pit excavation is ensured.
Compared with the prior art, the invention has the following advantages:
1. the supporting structure of the pit in the tie line pit is formed by the supporting rod pieces, the reinforced concrete bracket and the main structure bottom plate, the supporting structure is definite in stress, simple in structure, low in construction requirement and low in cost investment, and is beneficial to environmental protection;
2. the horizontal supporting structure fully utilizes the poured structural bottom plate to offset the pressure of the two side walls, so that the investment of materials is reduced, and the cost is reduced;
3. compared with the conventional supporting mode, the supporting structure is small in construction difficulty and easy to control in construction quality.
Drawings
FIG. 1 is a schematic top view of a station Shen Banlu to SG5-9 in Hangzhou subway according to an embodiment of the present invention;
FIG. 2 is a partial enlarged view at B in FIG. 1
FIG. 3 is a cross-sectional view at A-A in FIG. 2;
the concrete filling machine comprises a reference numeral 1-support rod piece, 2-reinforced concrete bracket, 3-main structure bottom plate, 31-poured structure bottom plate, 32-post-poured structure bottom plate, 4-foundation pit enclosure structure (underground continuous wall), 5-connecting line structure, 6-10cm thick C15 plain concrete, 6.5@250X250 reinforcing steel mesh and 7-plain concrete filling. 8-station main body structure, 9-station No. 5 wire underground two-layer structure, 10-station No. 3 wire underground three-layer structure, 11-tie line structure side line and 12-tie line center line.
Detailed Description
For the purpose of promoting an understanding of the principles of the invention, reference will now be made in detail to the embodiments described herein, including examples, illustrated in the accompanying drawings.
Examples
As shown in fig. 1, taking a station Shen Banlu of a hangzhou subway SG5-9 as an example, the station is designed into a transfer station with 3 and 5 lines, the 5 line of the station is of an underground two-layer structure, the 3 line of the station is of an underground three-layer structure, connecting lines are connected with the 3 line along the 5 line of the station in a transitional manner, the height difference of the connecting lines is 4.91m (-13.050 m to-17.960 m), and the longitudinal slope is 38.272 permillage.
As shown in fig. 2 and 3, the present embodiment provides a pit-in-pit supporting structure in a tie line pit of a subway transfer station, which is a combined structure including a supporting rod 1, a reinforced concrete bracket 2 and a main structure bottom plate 3, the main structure bottom plate 3 including a poured structure bottom plate 31 and a post-poured structure bottom plate 32. One end of a support rod piece 1 is supported on the side wall of the underground diaphragm wall of the foundation pit, the other end of the support rod piece is supported on the side wall of a reinforced concrete bracket 2, and the end face of the support rod piece 1 is mixed with reinforcing steel barsThe side wall of the concrete bracket 2 is in a vertical state and is tightly connected and tightly compacted, so that the uniform stress of the support rod piece 1 is ensured; the reinforced concrete bracket 2 is arranged on the top surface of the end part of the poured structure bottom plate 31, and steel bars are reserved on the top surface of the poured structure bottom plate 31 during construction so as to be effectively connected with the reinforced concrete bracket 2; the support rod 1 isA steel pipe; the reinforced concrete bracket 2 is of a cuboid structure, and the length, width and height are 1m, 1.2m; when the tie line foundation pit is excavated, a horizontal supporting stress system is formed by the supporting rod pieces 1, the reinforced concrete brackets 2 and the poured structural bottom plate 31 to bear the pressure on two sides of the pit wall, so that the safety of the foundation pit excavation is ensured.
The construction method comprises the following steps:
step 1: excavating to the bottom elevation of the main body foundation pit, rapidly completing pouring of a main body structure bottom plate in the main body foundation pit range, reserving a width as a post-pouring strip on the edge line of the distance connecting line structure during pouring, and reserving reinforcing steel bars at the positions of reinforced concrete brackets at the ends of the poured structure bottom plate. The width of the reserved post-pouring band is as follows: the excavation depth of the connecting line foundation pit is +1.5m.
Step 2: as shown in fig. 1, reinforced concrete brackets are arranged on the top surface of the end part of the bottom plate of the poured main body structure at intervals along the direction of the connecting line. The length, width and height of the reinforced concrete bracket are respectively 1m multiplied by 1.2m, the distance between each bracket is the same as the distance between temporary supporting rods, and the later mechanical energy is ensured to be smoothly excavated. Alternately arranged at intervals of 2m and 4 m. When the cast structure bottom plate is manufactured, the steel bars are reserved at the arrangement positions of the reinforced concrete brackets, so that the reinforced concrete bracket steel bars and the cast structure bottom plate steel bars are effectively connected to form a whole, and the stress stability is ensured.
Step 3: after the strength of the poured structural bottom plate and the reinforced concrete bracket reaches 85% of the design strength, installing a support rod piece, wherein the support rod piece isOne end of the supporting rod piece is supported on the side wall of the foundation pit underground diaphragm wallThe other end is supported on the side wall of the reinforced concrete bracket, and the support rod piece, the reinforced concrete bracket and the poured structure bottom plate are connected into a whole to be used as a horizontal support structure for bearing the pressure on two sides of the foundation pit.
Step 4: excavating a tie line foundation pit, wherein the foundation pit slope is formed by the following steps of 1:1, slope laying and excavating, wherein a platform with the excavation edge distance of not less than 1.5m is reserved between the bottom plates of the poured structure. The foundation pit is excavated in layers, each layer is excavated, 6.5@250X250 reinforcing steel meshes are hung on the slope, and 10cm thick C15 plain concrete is sprayed to serve as temporary protection of the slope.
Step 5: and (3) constructing a connecting line structure, and filling a triangular area between the connecting line structure and the side slope by adopting C20 plain concrete after the strength of the connecting line structure reaches 85% of the design strength, and filling the triangular area to the elevation of the bottom plate of the post-pouring structure.
Step six: and after the construction, pouring the structural bottom plate, maintaining, and effectively connecting the reinforcing steel bars of the structural bottom plate with the reserved reinforcing steel bars at the end parts of the poured structural bottom plate according to the design specification.
Step seven: and after the strength of the concrete reaches 85% of the design requirement, dismantling the tie line foundation pit support and the reinforced concrete bracket. And then carrying out subsequent main body structure engineering construction.
The foregoing description of the preferred embodiments of the invention is not intended to be limiting, but rather is intended to cover all modifications, equivalents, and alternatives falling within the spirit and principles of the invention.

Claims (3)

1. The method for excavating the middle pit of the tie line pit of the subway transfer station is characterized by comprising the following steps of:
step one: excavating to the bottom of a main body foundation pit, completing pouring of a main body structure bottom plate in the main body foundation pit range, reserving a section of width as a post-pouring strip on the side line of a distance connecting line structure during pouring, reserving a steel bar joint at the end part, and reserving the post-pouring strip width as follows: the excavation depth of the foundation pit of the connecting line is +1.5m;
step two: pouring reinforced concrete brackets at intervals along the direction of the connecting lines on the top of the end part of the bottom plate of the poured main body structure, wherein the distance between the brackets is the same as the distance between temporary support rods, and the foundation pit excavation can be ensured to be smoothly carried out by the mechanical energy in the later stage;
step three: after the strength of the structural bottom plate and the reinforced concrete bracket reaches 85% of the design strength, installing a support rod piece, wherein one end of the support rod piece is supported on the foundation pit enclosure structure, the other end of the support rod piece is supported on the reinforced concrete bracket, and the support rod piece, the reinforced concrete bracket and the poured structural bottom plate are connected into a whole to be used as a horizontal support structure for bearing the soil pressure at two sides of the foundation pit;
step four: excavating a tie line foundation pit, wherein the foundation pit slope is formed by the following steps of 1:1, slope laying and excavating, wherein a platform with the distance of more than or equal to 1.5m is reserved between poured bottom plates on the excavation edge;
step five: applying a main structure of the connecting line, and filling the main structure of the connecting line between slopes by adopting C20 plain concrete until the bottom elevation of a main foundation pit is filled after the main structure of the connecting line reaches 85% of the design strength;
step six: applying a post-cast strip of the bottom plate of the main body structure, and curing, wherein the post-cast strip steel bars are effectively connected with reserved steel bars according to the design specification;
step seven: and after the concrete strength reaches 85% of the design requirement, dismantling the tie line foundation pit support and the reinforced concrete bracket, and then carrying out subsequent main body structural engineering construction.
2. The method according to claim 1, wherein: in the second step, the reinforced concrete brackets are alternately arranged according to the intervals of 2m and 4m, and connecting steel bars are reserved at the reinforced concrete brackets when the main body structure bottom plate is manufactured, so that the reinforced concrete brackets and the structure bottom plate form a whole.
3. The method according to claim 1, wherein: and step four, excavating the foundation pit in layers, hanging 6.5@250×250 reinforcing steel meshes on the slope every time when one layer is excavated, and spraying 10cm thick C15 plain spray concrete as slope protection.
CN201810371737.2A 2018-04-24 2018-04-24 Subway transfer station tie line pit in pit supporting structure and excavation method Active CN108343066B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810371737.2A CN108343066B (en) 2018-04-24 2018-04-24 Subway transfer station tie line pit in pit supporting structure and excavation method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810371737.2A CN108343066B (en) 2018-04-24 2018-04-24 Subway transfer station tie line pit in pit supporting structure and excavation method

Publications (2)

Publication Number Publication Date
CN108343066A CN108343066A (en) 2018-07-31
CN108343066B true CN108343066B (en) 2023-11-17

Family

ID=62955398

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810371737.2A Active CN108343066B (en) 2018-04-24 2018-04-24 Subway transfer station tie line pit in pit supporting structure and excavation method

Country Status (1)

Country Link
CN (1) CN108343066B (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103410153A (en) * 2013-08-30 2013-11-27 南通八建集团有限公司 Adjacent deep foundation trench and shallow foundation trench synchronous construction method
CN103628503A (en) * 2013-11-27 2014-03-12 中铁第四勘察设计院集团有限公司 Construction method for using underground second-layer station enclosure to make underground third-layer transfer joint
CN104947677A (en) * 2014-03-28 2015-09-30 中国二十冶集团有限公司 Rapid cofferdam filling construction method for pit in pit
CN209412830U (en) * 2018-04-24 2019-09-20 中铁二局第一工程有限公司 A kind of subway transfer station interconnection cheats support construction in hole

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103410153A (en) * 2013-08-30 2013-11-27 南通八建集团有限公司 Adjacent deep foundation trench and shallow foundation trench synchronous construction method
CN103628503A (en) * 2013-11-27 2014-03-12 中铁第四勘察设计院集团有限公司 Construction method for using underground second-layer station enclosure to make underground third-layer transfer joint
CN104947677A (en) * 2014-03-28 2015-09-30 中国二十冶集团有限公司 Rapid cofferdam filling construction method for pit in pit
CN209412830U (en) * 2018-04-24 2019-09-20 中铁二局第一工程有限公司 A kind of subway transfer station interconnection cheats support construction in hole

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
地铁车站换乘节点处深浅基坑支护方案研究;李胜强;;建材与装饰(第02期);全文 *
带联络线及大三角区的换乘车站围护结构设计要点研究;徐乃芳等;《浙江建筑》;第34卷(第4期);第20-24页 *
李胜强 ; .地铁车站换乘节点处深浅基坑支护方案研究.建材与装饰.2016,(第02期),全文. *

Also Published As

Publication number Publication date
CN108343066A (en) 2018-07-31

Similar Documents

Publication Publication Date Title
CN203498799U (en) Prefabricated hollow pipe pile water-facing envelop enclosure
CN105756091B (en) A kind of Metro station excavation construction method of control adjacent building composition deformation
CN207017275U (en) Recyclable system of deep foundation pit support can be assembled
CN103938634B (en) A kind of deep foundation pit supporting structure and construction method
CN210288410U (en) Ultra-large deep foundation pit support-replacing backfill structure
CN210066671U (en) Novel rectangular gallery structure
CN210262549U (en) Combined pile-slab wall structure for improving existing line roadbed slope width
CN112983467B (en) Treatment method for tunnel gate closing type large collapse
CN106759471A (en) Arched retaining wall structure formed by waste tires and construction method thereof
CN210768793U (en) Two-lining construction system at intersection of main tunnel and double-layer construction transverse channel
CN211646413U (en) Modular lattice steel frame shotcrete anchor supporting construction
CN103015432A (en) Construction method for changing steel pipe supports of ramp foundation pit
CN108343066B (en) Subway transfer station tie line pit in pit supporting structure and excavation method
CN112176879A (en) Bridge pier foundation underpinning structure and construction method
CN208023601U (en) A kind of prefabricated pile foundation support table side form of mutual buckle type
CN110685287A (en) Double-row pile foundation pit supporting system with drainage ditch and retaining wall and construction method
CN213508572U (en) Piping lane supporting construction
CN209412830U (en) A kind of subway transfer station interconnection cheats support construction in hole
CN110616714B (en) Novel enclosure construction method for existing underground structure deepening
CN211873014U (en) System for bailey truss protects cable
CN211266407U (en) System for protecting cable
CN211690389U (en) Inter-pile retaining plate structure for adjacent anti-slide piles
CN109537599B (en) Construction method of support replacing structure of deep foundation pit support system
CN202925551U (en) Foundation pit brace replacing and construction structure at irregular place of ramp
CN109555130B (en) Middle plate of subway main body structure and temporary supporting structure and construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant