CN108330745A - The implementation of soft clay area tramcar assembled sub-rail foundation - Google Patents

The implementation of soft clay area tramcar assembled sub-rail foundation Download PDF

Info

Publication number
CN108330745A
CN108330745A CN201810132450.4A CN201810132450A CN108330745A CN 108330745 A CN108330745 A CN 108330745A CN 201810132450 A CN201810132450 A CN 201810132450A CN 108330745 A CN108330745 A CN 108330745A
Authority
CN
China
Prior art keywords
prefabricated
crossbeam
reinforced concrete
slab
shear pin
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810132450.4A
Other languages
Chinese (zh)
Other versions
CN108330745B (en
Inventor
黄爱军
张向霞
王春凯
秦晓光
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Urban Construction Design Research Institute Group Co Ltd
Original Assignee
Shanghai Urban Construction Design Research Institute Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Urban Construction Design Research Institute Group Co Ltd filed Critical Shanghai Urban Construction Design Research Institute Group Co Ltd
Priority to CN201810132450.4A priority Critical patent/CN108330745B/en
Publication of CN108330745A publication Critical patent/CN108330745A/en
Application granted granted Critical
Publication of CN108330745B publication Critical patent/CN108330745B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B2/00General structure of permanent way
    • E01B2/006Deep foundation of tracks
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/12Pile foundations
    • E02D27/14Pile framings, i.e. piles assembled to form the substructure
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes

Landscapes

  • Engineering & Computer Science (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Foundations (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The invention discloses the implementation of soft clay area tramcar assembled sub-rail foundation, prefabrication PHC pile foundations, prefabricated reinforced concrete crossbeam and precast rc slab structure three parts components;Prefabricated roadbed beam corresponds to pile foundation position reserved steel bar, wait under beam reinforcing bar and its tail portion steel plate be put into prefabricated pile it is hollow after, shear pin rim of the mouth is reserved on prefabricated reinforced concrete crossbeam, precast rc slab structure shear pin mother mouth is formed into common beam slab force transferring structure together with the socket joint of corresponding prefabricated reinforced concrete beam structure shear pin rim of the mouth when assembly;The different plates of precast rc slab overlap on crossbeam.Beneficial effects of the present invention:The present invention uses prefabricated components, it makes precision height and quality is guaranteed, simultaneously improve in-site installation efficiency and installation accuracy, can save field workforce, shorten construction period, improve road structure globality, can it is quick, safe and environment-friendly, efficiently complete tramcar sub-rail foundation structure.

Description

The implementation of soft clay area tramcar assembled sub-rail foundation
Technical field
The present invention relates under tramcar Construction Technology field more particularly to soft clay area tramcar assembled rail The implementation on basis.
Background technology
The reinforced concrete structure of soft clay area tramcar sub-rail foundation generally use sheet pile form, according to construction party Method can be divided into three kinds of cast-in-place structural, fabricated construction and assembled overall structure.Tramcar roadbed sheet-pile structure is most at present The form of setting, prefabricated pile reserved joint bar, later stage roadbed contignation integration are combined with cast-in-place roadbed beam slab using prefabricated pile Cast-in-place to be linked to be entirety with prefabricated pile, this construction method needs to set up template, binding steel at the scene due to the structure of cast-in-place part Muscle and casting concrete, therefore field labor is big, long in time limit, structural mechanical property is influenced by site operation quality.And by It is installed and is formed by connecting at the scene by prefabricated components in prefabricated construction, save field workforce, short construction period, be convenient for work Industry and mechanization production, with the raising that tramcar civil engineering requires duration and construction quality, precast assembly one Change sub-rail foundation and becomes the key technology constructed for tramcar.But the globality and rigidity due to fabricated construction are poor, In rail electricity sub-rail foundation structure, in order to improve globality and antidetonation between prefabricated pile, roadbed beam slab, rail bed board three Performance, at the same improve installation effectiveness and installation accuracy need a kind of prefabricated pile, roadbed beam slab and rail bed board connecting node and Corresponding construction reaches simple, connects the requirements such as reliable, easy for construction.
The present situation of this field the relevant technologies:
Existing tramcar sub-rail foundation construction and defect:Tramcar sub-rail foundation structure mostly uses greatly at present Prefabricated pile is combined the form of setting with cast-in-place roadbed beam slab, and prefabricated pile reserved joint bar, later stage roadbed contignation integration is cast-in-place Be linked to be entirety with prefabricated pile, this construction method due to the structure of cast-in-place part need to set up at the scene template, assembling reinforcement and Casting concrete, therefore field labor is big, long in time limit, structural mechanical property is influenced by site operation quality.
Those skilled in the art are dedicated to solving above-mentioned technological deficiency.
Invention content
In view of the drawbacks described above of the prior art, technical purpose of the invention is to improve prefabricated pile, roadbed beam slab, track Globality between road bed board three and anti-seismic performance, while installation effectiveness and installation accuracy are improved, and providing soft clay area has The implementation of rail electric car assembled sub-rail foundation
To realize the above-mentioned technical purpose, the present invention provides the embodiment party of soft clay area tramcar assembled sub-rail foundation Method, including:
Step 1:Prefabrication PHC pile foundations, prefabricated reinforced concrete crossbeam and precast rc slab structure three parts Component;
Step 2:Prefabricated roadbed beam corresponds to pile foundation position reserved steel bar, and reinforcing bar length is more than 1m;
Step 3:When on-site consolidation, steel plate is welded in reinforcing bar bottom under prefabricated roadbed beam, and steel plate welding position needs The relative positioning deviation for measuring prefabricated prefabricated reinforced concrete crossbeam and prefabricated PHC pile foundations in advance adjusts steel according to specific positioning Plate welding position, steel plate size and location are to be put into prefabricated tubular pile central hollow position to be advisable;
Step 4:Wait under beam reinforcing bar and its tail portion steel plate be put into prefabricated pile it is hollow after, the concrete reserved from beam pours Hole is smash toward prefabricated pile and beam connecting node casting concrete, prefabricated roadbed beam is reliably connected with prefabricated pile, complete pile foundation with Prefabricated reinforced concrete beam structure assembles;
Step 5:Shear pin rim of the mouth is reserved on prefabricated reinforced concrete crossbeam, in corresponding positions under precast rc slab Shear pin mother's mouth that headroom in reserved is more than rim of the mouth 2mm is set, by precast rc slab structure shear pin mother's mouth when assembly Together with the socket joint of corresponding prefabricated reinforced concrete beam structure shear pin rim of the mouth, common beam slab force transferring structure is formed;
Step 6:The different plates of precast rc slab overlap on crossbeam, and horizontal direction spigot-and-socket is used when assembly Assembly method using wedge-shaped interface form, and is packed into hydro-expansive rubber elastic sealing gasket and carries out water-proofing treatment;
Step 7:Prefabricated PHC pile foundations, prefabricated reinforced concrete crossbeam, precast rc slab Standard are integral.
Preferably, wherein prefabricated reinforced concrete crossbeam is mounted on the upper end of prefabricated PHC pile foundations, precast rc slab Mounted on the upper end of prefabricated reinforced concrete crossbeam.
Preferably, the upper end of wherein prefabricated reinforced concrete crossbeam is provided with several shear pin rims of the mouth, wherein pre-manufactured steel The lower end of reinforced concrete plate is provided with several shear pin mother's mouths being connect with shear pin rim of the mouth corresponding matching, wherein shearing pin Inserted with shear pin between mouth and shear pin mother's mouth.
Preferably, it is provided with bed course when the lower end construction of wherein prefabricated reinforced concrete crossbeam.
Preferably, position corresponding with prefabricated PHC pile foundations center is provided on beam wherein in prefabricated reinforced concrete crossbeam Casting and compacting of concrete hole is reserved, the circumferential part that casting and compacting of concrete hole is reserved on beam is provided with reserved steel bar under beam.
Preferably, crossbeam main reinforcement, concrete slab distributing reinforcement, crossbeam waist muscle are provided in the prefabricated reinforced concrete crossbeam With crossbeam lacing wire and stirrup, the top of reserved steel bar is connect with crossbeam main reinforcement under the beam.
Preferably, the lower part of reserved steel bar is provided with steel plate in prefabricated PHC pile foundations under the beam, the steel plate Thickness is 20mm.
Preferably, the shape of the steel plate is circle.
Beneficial effects of the present invention:
The present invention uses prefabricated components, makes precision height and quality is guaranteed, while improving in-site installation efficiency and peace Precision is filled, the globality that can be saved field workforce, shorten construction period, improve road structure can be quick, safe and environment-friendly, high Complete tramcar sub-rail foundation structure in effect ground.
Description of the drawings
Fig. 1 is the roadbed plan view of the present invention;
Fig. 2 is the A-A drawings in side sectional elevation of the present invention;
Fig. 3 is the prefabricated pile foundation and roadbed beam connecting node reservation conditions figure of the present invention;
Fig. 4 is the prefabricated pile foundation of the present invention and roadbed beam connecting node figure;
Fig. 5 is the steel plate plane detail drawing of the present invention;
Fig. 6 is the steel plate sectional detail drawing of the present invention;
Fig. 7 is the roadbed beam of the present invention, plate arrangement of reinforcement;
Fig. 8 is the B-B section prefabricated reinforced concrete simply supported slabs lap-joint way detail drawing of the present invention.
Specific implementation mode
The technique effect of the design of the present invention, concrete structure and generation is described further below with reference to attached drawing, with It is fully understood from the purpose of the present invention, feature and effect.
As shown in Figures 1 to 8, the implementation of soft clay area tramcar assembled sub-rail foundation, implementation are:
Step 1:Prefabrication PHC pile foundations, prefabricated reinforced concrete crossbeam and precast rc slab structure three parts Component;
Step 2:Prefabricated roadbed beam corresponds to pile foundation position reserved steel bar, and reinforcing bar length is more than 1m;
Step 3:When on-site consolidation, steel plate is welded in reinforcing bar bottom under prefabricated roadbed beam, and steel plate welding position needs The relative positioning deviation for measuring prefabricated reinforced concrete crossbeam and prefabricated PHC pile foundations in advance adjusts steel plate weldering according to specific positioning Position is connect, steel plate size and location are to be put into prefabricated tubular pile central hollow position to be advisable;
Step 4:Wait under beam reinforcing bar and its tail portion steel plate be put into prefabricated pile it is hollow after, the concrete reserved from beam pours Hole is smash toward prefabricated pile and beam connecting node casting concrete, prefabricated roadbed beam is reliably connected with prefabricated pile, complete pile foundation with Prefabricated reinforced concrete beam structure assembles;
Step 5:Shear pin rim of the mouth is reserved on prefabricated reinforced concrete crossbeam, in corresponding positions under precast rc slab Shear pin mother's mouth that headroom in reserved is more than rim of the mouth 2mm is set, by precast rc slab structure shear pin mother's mouth when assembly Together with the socket joint of corresponding prefabricated reinforced concrete beam structure shear pin rim of the mouth, common beam slab force transferring structure is formed;
Step 6:The different plates of precast rc slab overlap on crossbeam, and horizontal direction spigot-and-socket is used when assembly Assembly method using wedge-shaped interface form, and is packed into hydro-expansive rubber elastic sealing gasket and carries out water-proofing treatment;
Step 7:Prefabricated PHC pile foundations, prefabricated reinforced concrete crossbeam, precast rc slab Standard are integral.
Wherein prefabricated reinforced concrete crossbeam 2 is mounted on the upper end of prefabricated PHC pile foundations 1, and precast rc slab 3 is installed In the upper end of prefabricated reinforced concrete crossbeam 2.
The upper end of wherein prefabricated reinforced concrete crossbeam 2 is provided with several shear pin rims of the mouth 4, wherein precast reinforced coagulation The lower end of native plate 3 is provided with several shear pin mother mouths 5 being connect with 4 corresponding matching of shear pin rim of the mouth, wherein shear pin rim of the mouth 4 Inserted with shear pin 6 between shear pin mother mouth 5.
It is provided with bed course 7 when wherein the lower end of prefabricated reinforced concrete crossbeam 2 is constructed.
Position corresponding with prefabricated 1 center of PHC pile foundations is provided with to reserve on beam and mix wherein in prefabricated reinforced concrete crossbeam 2 Solidifying soil, which pours, smashes hole 8, and the circumferential part that casting and compacting of concrete hole 8 is reserved on beam is provided with reserved steel bar 9 under beam.
Further, be provided in the prefabricated reinforced concrete crossbeam 2 crossbeam main reinforcement 11, concrete slab distributing reinforcement 14, Crossbeam waist muscle 13 and crossbeam lacing wire and stirrup 12, the top of reserved steel bar 9 is connect with crossbeam main reinforcement 11 under the beam, under the beam The lower part of reserved steel bar 9 is provided with steel plate 10 in prefabricated PHC pile foundations 1, and the thickness of the steel plate 10 is 20mm, the thickness The shape of steel plate 10 is circle.
The present invention uses prefabricated components, makes precision height and quality is guaranteed, while improving in-site installation efficiency and peace Precision is filled, the globality that can be saved field workforce, shorten construction period, improve road structure can be quick, safe and environment-friendly, high Complete tramcar sub-rail foundation structure in effect ground.
In the construction of tramcar sub-rail foundation, to save field workforce, shortening construction period, installation effectiveness and peace are improved Precision is filled, while to improve the globality of road structure, adoptable practical and moderate structure type is as follows:Form base under rail The three parts component of plinth structure includes prefabricated pile, roadbed beam, roadbed harden structure, is prefabrication reinforced concrete member, In prefabricated roadbed beam correspond to pile foundation position reserved steel bar, component is pre- according to being put into after welding steel under live spacer bar when assembling The hollow range of stake processed, reserving hole can be in pile crown position disturbing concrete on beam, and thus prefabricated pile, beam can be reliably connected, together There are shear pins on Shi Luji beams, and reserving shear pin with base board lower surface forms spigot-and-socket mounting structure, and three parts component is adopted It is assembled into tramcar sub-rail foundation overall structure to upper type, prefabricated pile, beam are single component, and prefabricated board can be according to scene Situation is flexibly determined across number.
The preferred embodiment of the present invention has been described in detail above.It should be appreciated that those skilled in the art without It needs creative work according to the present invention can conceive and makes many modifications and variations.Therefore, all technologies in the art Personnel are available by logical analysis, reasoning, or a limited experiment on the basis of existing technology under this invention's idea Technical solution, all should be in the protection domain being defined in the patent claims.

Claims (8)

1. the implementation of soft clay area tramcar assembled sub-rail foundation, including:
Step 1:Prefabrication PHC pile foundations, prefabricated reinforced concrete crossbeam and precast rc slab structure three parts structure Part;
Step 2:Prefabricated roadbed beam corresponds to pile foundation position reserved steel bar, and reinforcing bar length is more than 1m;
Step 3:When on-site consolidation, steel plate is welded in reinforcing bar bottom under prefabricated roadbed beam, and steel plate welding position needs prior The relative positioning deviation for measuring prefabricated prefabricated reinforced concrete crossbeam and prefabricated PHC pile foundations adjusts steel plate weldering according to specific positioning Position is connect, steel plate size and location are to be put into prefabricated tubular pile central hollow position to be advisable;
Step 4:Wait under beam reinforcing bar and its tail portion steel plate be put into prefabricated pile it is hollow after, the casting and compacting of concrete hole reserved from beam Toward prefabricated pile and beam connecting node casting concrete, prefabricated roadbed beam is reliably connected with prefabricated pile, completion pile foundation with it is prefabricated Reinforced concrete beams Standard;
Step 5:Shear pin rim of the mouth is reserved on prefabricated reinforced concrete crossbeam, it is pre- in corresponding position under precast rc slab Liu Neinei headroom is more than shear pin mother's mouth of rim of the mouth 2mm, by precast rc slab structure shear pin mother mouth and phase when assembly It answers prefabricated reinforced concrete beam structure shear pin rim of the mouth socket joint together, forms common beam slab force transferring structure;
Step 6:The different plates of precast rc slab overlap on crossbeam, are assembled using horizontal direction spigot-and-socket when assembly Mode using wedge-shaped interface form, and is packed into hydro-expansive rubber elastic sealing gasket and carries out water-proofing treatment;
Step 7:Prefabricated PHC pile foundations, prefabricated reinforced concrete crossbeam, precast rc slab Standard are integral.
2. the implementation of tramcar assembled sub-rail foundation in soft clay area as described in claim 1, it is characterised in that:Its Middle prefabricated reinforced concrete crossbeam is mounted on the upper end of prefabricated PHC pile foundations, and precast rc slab is mounted on precast reinforced mixed The upper end of solidifying soil crossbeam.
3. the implementation of tramcar assembled sub-rail foundation in soft clay area as described in claim 1, it is characterised in that:Its The upper end of middle prefabricated reinforced concrete crossbeam is provided with several shear pin rims of the mouth, and the lower end of wherein precast rc slab is set Several shear pin mother's mouths being connect with shear pin rim of the mouth corresponding matching are equipped with, wherein between shear pin rim of the mouth and shear pin mother's mouth Inserted with shear pin.
4. the implementation of tramcar assembled sub-rail foundation in soft clay area as described in claim 1, it is characterised in that:Its It is provided with bed course when the lower end construction of middle prefabricated reinforced concrete crossbeam.
5. the implementation of tramcar assembled sub-rail foundation in soft clay area as described in claim 1, it is characterised in that:Its Position corresponding with prefabricated PHC pile foundations center, which is provided on beam, in middle prefabricated reinforced concrete crossbeam reserves casting and compacting of concrete hole, The circumferential part that casting and compacting of concrete hole is reserved on beam is provided with reserved steel bar under beam.
6. the implementation of tramcar assembled sub-rail foundation in soft clay area as described in claim 1, it is characterised in that:Institute It states and is provided with crossbeam main reinforcement, concrete slab distributing reinforcement, crossbeam waist muscle and crossbeam lacing wire and stirrup in prefabricated reinforced concrete crossbeam, The top of reserved steel bar is connect with crossbeam main reinforcement under the beam.
7. the implementation of tramcar assembled sub-rail foundation in soft clay area as described in claim 1, it is characterised in that:Institute The lower part for stating reserved steel bar under beam is provided with steel plate in prefabricated PHC pile foundations, and the thickness of the steel plate is 20mm.
8. the implementation of tramcar assembled sub-rail foundation in soft clay area as described in claim 1, it is characterised in that:Institute The shape for stating steel plate is circle.
CN201810132450.4A 2018-02-09 2018-02-09 Implementation method of tramcar assembled under-rail foundation in soft soil area Active CN108330745B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810132450.4A CN108330745B (en) 2018-02-09 2018-02-09 Implementation method of tramcar assembled under-rail foundation in soft soil area

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810132450.4A CN108330745B (en) 2018-02-09 2018-02-09 Implementation method of tramcar assembled under-rail foundation in soft soil area

Publications (2)

Publication Number Publication Date
CN108330745A true CN108330745A (en) 2018-07-27
CN108330745B CN108330745B (en) 2020-06-09

Family

ID=62927334

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810132450.4A Active CN108330745B (en) 2018-02-09 2018-02-09 Implementation method of tramcar assembled under-rail foundation in soft soil area

Country Status (1)

Country Link
CN (1) CN108330745B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111395059A (en) * 2020-03-23 2020-07-10 中铁二院工程集团有限责任公司 Light roadbed structure crossing karez, design and construction method
CN112095370A (en) * 2020-09-10 2020-12-18 上海市城市建设设计研究总院(集团)有限公司 Prefabricated tramcar roadbed and track integrated structure and construction method

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002047649A (en) * 2000-08-04 2002-02-15 Geotop Corp Pile head treating method in preboring construction method
CN202787247U (en) * 2012-09-18 2013-03-13 天津港建设公司 PHC (prestressed high-strength concrete) pile and steel pipe pile composited pile for long piled wharfs
CN204455724U (en) * 2015-01-04 2015-07-08 上海市城市建设设计研究总院 For the integral structure of Deep Thick Soft Ground Area roadbed track
CN205063961U (en) * 2015-10-20 2016-03-02 上海市城市建设设计研究总院 Push pipe tube coupling structure
CN105586967A (en) * 2016-02-25 2016-05-18 福建省建筑设计研究院 Prefabricated pile cap for composite foundation
CN106677073A (en) * 2017-02-14 2017-05-17 上海市城市建设设计研究总院(集团)有限公司 Construction method for semi-integral jointless bridge structure adaptive to soft soil foundation

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002047649A (en) * 2000-08-04 2002-02-15 Geotop Corp Pile head treating method in preboring construction method
CN202787247U (en) * 2012-09-18 2013-03-13 天津港建设公司 PHC (prestressed high-strength concrete) pile and steel pipe pile composited pile for long piled wharfs
CN204455724U (en) * 2015-01-04 2015-07-08 上海市城市建设设计研究总院 For the integral structure of Deep Thick Soft Ground Area roadbed track
CN205063961U (en) * 2015-10-20 2016-03-02 上海市城市建设设计研究总院 Push pipe tube coupling structure
CN105586967A (en) * 2016-02-25 2016-05-18 福建省建筑设计研究院 Prefabricated pile cap for composite foundation
CN106677073A (en) * 2017-02-14 2017-05-17 上海市城市建设设计研究总院(集团)有限公司 Construction method for semi-integral jointless bridge structure adaptive to soft soil foundation

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111395059A (en) * 2020-03-23 2020-07-10 中铁二院工程集团有限责任公司 Light roadbed structure crossing karez, design and construction method
CN112095370A (en) * 2020-09-10 2020-12-18 上海市城市建设设计研究总院(集团)有限公司 Prefabricated tramcar roadbed and track integrated structure and construction method

Also Published As

Publication number Publication date
CN108330745B (en) 2020-06-09

Similar Documents

Publication Publication Date Title
CN108951870B (en) Construction method of low-rise fully-assembled concrete shear wall structure system
CN108301317A (en) A kind of assembled bridge pier structure and its construction method
CN106245670B (en) Exposed steel column base construction method
CN113481931B (en) Modular assembly type high-pile wharf structure and construction method thereof
CN108221504A (en) The construction method of soft clay area tramcar assembled roadbed track plank bed
CN108005401A (en) A kind of support and change method of the column of existing frame structure base isolation reinforcement
CN109339087B (en) Infrastructure system of low-rise building
CN108330745A (en) The implementation of soft clay area tramcar assembled sub-rail foundation
CN113005926A (en) Construction method of mountain area abrupt slope pier reinforcing device
CN106835879A (en) Highway is laterally without support type peg board formula without earth roadbed and its construction method
CN108396630A (en) The big box-beam structure of precast concrete with the connection of wet seam direction across bridge
KR20120029625A (en) Construction method of steel composite girder bridge applying precast deck
CN111827095A (en) Prefabricated assembled hollow pier with built-in rib plates and construction method
CN103233537A (en) Heavy-load superimposed overhead terrace and construction method
CN114045940A (en) Profile steel connecting node of precast concrete tubular pile column and hollow floor or flat slab
CN206529778U (en) Customized type prestress anchorage cable reaction beam mounting structure
CN108277750A (en) The porous cast-in-place box culvert construct method of high roadbed deep soft foundation pile formula big cross section
CN101666069A (en) Construction technology for stretching notch by cast-in-situ prestress box beam
CN110374012A (en) A kind of prefabricated engineering method of T beam original position Support Method
CN110185056A (en) Precast block assembles suspended deck structure and assembling method
CN207109593U (en) A kind of T-shaped high pier Cast-in-place Bent Cap formwork erecting structure
CN106677073B (en) Adapt to the semi-monolithic formula seamless bridge construction method of soft soil foundation
CN216860140U (en) Length-adjustable steel pedestal for precast beam construction
CN205742249U (en) A kind of prestressed concrete back cover cushion cap template
CN106120690A (en) A kind of inverter box flattens platform and preparation method thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant