CN108316366A - A kind of multi-functional foundation pit model assay systems equipment and its application method - Google Patents

A kind of multi-functional foundation pit model assay systems equipment and its application method Download PDF

Info

Publication number
CN108316366A
CN108316366A CN201810225173.1A CN201810225173A CN108316366A CN 108316366 A CN108316366 A CN 108316366A CN 201810225173 A CN201810225173 A CN 201810225173A CN 108316366 A CN108316366 A CN 108316366A
Authority
CN
China
Prior art keywords
main tank
handling
foundation pit
steel
assay systems
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810225173.1A
Other languages
Chinese (zh)
Inventor
张世民
何奇威
孙银锁
章丽莎
李煜
孙苗苗
黄英省
俞定
林***
张舒芸
徐嘉奕
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang University City College ZUCC
Original Assignee
Zhejiang University City College ZUCC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang University City College ZUCC filed Critical Zhejiang University City College ZUCC
Priority to CN201810225173.1A priority Critical patent/CN108316366A/en
Publication of CN108316366A publication Critical patent/CN108316366A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D33/00Testing foundations or foundation structures

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Investigating Strength Of Materials By Application Of Mechanical Stress (AREA)

Abstract

The present invention relates to multi-functional foundation pit model assay systems equipment, including model casing system and handling soil and loading system;The model casing system includes main tank, water tank and Double layer iron ladder;Main tank is made of steel plate, organic glass, angle steel and being bolted, main tank both sides assembly steel plate and ribbing, and junction sets sealing strip, and transparent organic glass whole plate, which is embedded in steel plate, is used as watch window;The handling soil and loading system include mound field, the native channel of handling, excavator, packaged type girder steel frame and pressue device;Mound field by steel plate, angle steel, be bolted and form, the native channel of mound field one end connection handling.The beneficial effects of the invention are as follows:The easy to operate, high degree of automation of the present invention, structure function diversification, can carry out the indoor model test of excavation of foundation pit effect on environment, can detect ess-strain, the pore water pressure of the soil body, can carry out dynamic load and static loading.

Description

A kind of multi-functional foundation pit model assay systems equipment and its application method
Technical field
The present invention relates to a kind of excavation models testing equipment field, more particularly to a kind of multi-functional foundation pit model assay systems Equipment and its application method.
Background technology
Model test is that according to certain principle of similitude specific engineering geological problems are carried out with a kind of method of reduced scale research, By in scale smaller or waiting than being tested accordingly on model, obtaining related data and checking design defect, it has also become work One of journey field research means the most main.China's economic strength is more and more richer, this be unable to do without the quick hair of urban construction Exhibition, high type, heavy type, large size buildings or structures be even more to emerge one after another, also increase the difficulty of construction technology, base pit engineering be for Ensure that ground excavates soil-baffling structure and ground needed for safety and stability of the underground space of formation during Underground Construction downwards The measures such as lower water management, environmental protection, importance are self-evident.However in urban construction domestic at present, foundation pit is opened Digging inevitably has an impact periphery subway tunnel, buildings or structures, pipeline etc..Existing data is mostly with case history Carry out influence of the excavation of foundation pit to periphery under a certain given area geological conditions of analytic explanation, and this respect at present temporarily almost without The development of corresponding indoor model test, so relevant research has great importance.
Invention content
The purpose of the present invention is overcoming deficiency in the prior art, a kind of multi-functional foundation pit model assay systems equipment is provided And its application method.
This multi-functional foundation pit model assay systems equipment, including model casing system and handling soil and loading system;
The model casing system includes main tank, water tank and Double layer iron ladder;Main tank is by steel plate, organic glass, angle steel and bolt Connection composition, main tank both sides assembly steel plate and ribbing, junction set sealing strip, and transparent organic glass whole plate, which is embedded in steel plate, to be made For watch window;Water tank setting main tank both sides and with partition panel and separate card slot separated with main tank, water tank by steel plate, angle steel and It is bolted composition;Double layer iron ladder is set on rear side of main tank;It is laid with concrete bed under entire babinet, concrete bed both sides are opened If draining water channel;Water-level observation hole is mounted equidistant in main tank and water tank both sides;Right side tank outer wall is equipped with display system;
The handling soil and loading system include mound field, the native channel of handling, excavator, packaged type girder steel frame and pressurization Device;Mound field by steel plate, angle steel, be bolted and form, the native channel of mound field one end connection handling;The native channel of handling is belt The native channel of formula handling loads and unloads native channel upper end and is arranged belt pulley, and plane, which also serves as, on belt pulley unloads native platform, loads and unloads native channel lower end Mound field eminence is mounted with concrete pier;Packaged type girder steel frame is by steel column, fixed I-steel girder and moveable I-steel Crossbeam forms, and I-shaped gooseneck slides side and the linear guide is housed;Excavator can move up dynamic in I-shaped gooseneck;Pressue device includes Hydraulic jack and load plate are equipped each with hydraulic jack on I-shaped gooseneck, and load plate is fixed in hydraulic jack lower end, Hydraulic jack can slide on I-shaped gooseneck.
As preferred:Pre-buried prefabricated tunnel model and laying monitoring element in the main tank.
As preferred:The Double layer iron ladder height is consistent with main tank.
As preferred:The steel column bottom is equipped with concrete pouring weight, and fixed part angle steel is bolted.
As preferred:Data operation system is equipped on rear side of the mound field, the data operation system includes that computer is shown Device, fiber grating monitoring system, water pressure data monitoring system and handling soil and Loading Control System.
As preferred:The excavator is small-sized excavator, is moved up in I-shaped gooseneck dynamic.
The application method of this multi-functional foundation pit model assay systems equipment, includes the following steps:
1) using the native channel of handling the soil body is filled to main tank quantification;
2) the pre-buried prefabricated test model in main tank lays monitoring element, opens both sides water tank sluice gate whenever necessary;
3) adjustment I-shaped gooseneck position is directed at pressing position;
4) start pressue device, proceed by simulation test, check display data;
5) experiment finishes, and stores data, site clearing.
The beneficial effects of the invention are as follows:
(1) easy to operate, high degree of automation of the invention, structure function diversification, can carry out excavation of foundation pit to environment shadow Loud indoor model test can detect ess-strain, the pore water pressure of the soil body, can carry out dynamic load and static loading, energy Under the conditions of excavation simulation, the stress strain response of detection periphery tunnel, house, underground utilities etc. can monitor tunnel, pipeline and room The parameters such as structural internal force, strain, sedimentation, horizontal displacement, ground settlement, soil horizontal displacement, the pore water pressure in room etc..
(2) present invention energy automatic data collection, system integration processing, reduces manual operation error, makes the data of acquisition It is more acurrate.
(3) model casing good airproof performance of the invention, strength and stiffness are big, will not deform, and can guarantee that stablizing for experiment carries out.
(4) transparent organic glass is used, can directly be observed filling soil body situation and follow-up test.
Description of the drawings
Fig. 1 is overall structure of the present invention;
Fig. 2 is partial structural diagram of the present invention.
Reference sign:1-main tank;2-water tanks;3-display systems;4-concrete beds;5-draining water channels; 6-water-level observation holes;7-watch windows;8-Double layer irons ladder;9-mound fields;The native channel of 10-handling;11-concrete piers; 12-excavators;13-steel columns;14-concrete pouring weights;15-I-steel girders;16-I-shaped goosenecks;17-load plates; 18-data operation systems;19-hydraulic jacks.
Specific implementation mode
The present invention is described further with reference to embodiment.The explanation of following embodiments is merely used to help understand this Invention.It should be pointed out that for those skilled in the art, without departing from the principle of the present invention, also Can be with several improvements and modifications are made to the present invention, these improvement and modification also fall into the protection domain of the claims in the present invention It is interior.
As shown in Figure 1, the multi-functional foundation pit model assay systems equipment, including three parts:Model casing system, handling Soil and loading system, data operation system 18.
The model casing system includes main tank 1, water tank 2 and Double layer iron ladder 8.Main tank 1 is by steel plate, organic glass, angle steel, spiral shell It tethers and connects composition;1 both sides assembly steel plate ribbing of main tank ensures that rigidity, junction sealing strip ensure leakproofness;Transparent organic glass Glass whole plate, which is embedded in steel plate, is used as watch window 7;Prison can be laid in main tank 1 according to the pre-buried prefabricated tunnel model of test requirements document Element is surveyed to acquire monitoring data etc. in Excavation Process.The setting of water tank 2 is in 1 both sides of main tank, with partition panel and partition card slot It is separated with main tank 1;Water tank 2 by steel plate, angle steel, be bolted and form, it acts as the height difference for changing 2 water level of both sides water tank, moulds Quasi- excavation of foundation pit precipitation etc., when not considering the influence of underground water can not water-filling, controlled by sluice gate.Double layer iron ladder 8 is placed in main tank 1 one Side can individually customize, and be highly consistent with main tank 1, facilitate related personnel or more.It is laid with concrete bed under entire babinet 4,4 both sides of concrete bed open up draining water channel 5, can efficiently be discharged and abandon water.Water level is mounted equidistant in main tank 1 and 2 both sides of water tank Peephole 6, can observatory control WATER LEVEL CHANGES at any time.Water tank 2 outer wall in side inlays liquid crystal real-time display system 3, and liquid crystal is real When display system 3 can show parameter, the state of current engineering of main test original paper test, be wirelessly connected and led to computer News.
The handling soil and loading system include mound field 9, the native channel 10 of handling, small-sized excavator 12, packaged type steel Roof beam structure and pressue device.Mound field 9 by steel plate, angle steel, be bolted and form, the native channel of one end connection handling 10.Handling soil is logical Road 10 is that belt-type loads and unloads native channel, and upper end is arranged belt pulley, and plane, which also serves as, on belt pulley unloads native platform, loads and unloads under native channel 10 End concrete pier 11 mounts 9 eminence of mound field, the mound of the soil body dug out out of main tank 1 using belt-conveying to place side Field 9, driving belt is controlled with motor.Can be cut the earth program by computer installation.Packaged type girder steel frame is by eight (front and back each four Root) steel column 13, the fixed I-steel girder 15 in two, top and two moveable compositions of I-shaped goosenecks 16, eight 13 bottoms of steel column Concrete pouring weight 14 is matched in portion, stablizes steel column 13, and fixed part angle steel is bolted, and moveable I-shaped gooseneck 16 slides Side fills the linear guide.Small-sized excavator 12 is that computer controls unmanned digging machine, can be moved freely on I-shaped gooseneck 16.Pressurization Device includes hydraulic jack 19, load plate 17, and two hydraulic jacks 19, oil jack are respectively equipped on I-shaped gooseneck 16 It pushes up 19 lower ends and fixes load plate 17, ensure uniform force when load, form a uniform face load, hydraulic jack 19 can be It is free to slide on I-shaped gooseneck 16.
The data operation system 18 includes other data prisons such as computer monitor, fiber grating monitoring system, water pressure Examining system and handling soil and Loading Control System etc..Monitoring acquisition control shows following function:1. all kinds of points can be obtained automatically The measurement data of cloth fibre strain temperature device can calibrate simultaneously transfer standard data format automatically;2. system uses database Mode stores, and has quick search, processing and analytic function;3. system data processing is with length correction, smoothing denoising, movement The operations such as average, convergent-divergent, translation, reversing, rotation, alignment, data edition and revocation return;4. SDA system data analysis curve With visualization, amplification is reduced, full figure roaming function;5. system has batch data processing function, can be by report and processing Graph is automatically generated and is exported;6. there is safety management function, can be to project data after authorized user's login system at Reason.
The application method of the multi-functional foundation pit model assay systems equipment, includes the following steps:
(1) soil body is filled into main tank 1 using the native channel 10 of handling, it is quantitative by test requirements document;
(2) the pre-buried prefabricated test model in main tank 1 lays monitoring element, opens 2 sluice gate of both sides water tank whenever necessary;
(3) 16 position of adjustment I-shaped gooseneck, is directed at pressing position;
(4) start pressue device, proceed by simulation test, check display data;
(5) experiment finishes, and stores data, site clearing.

Claims (7)

1. a kind of multi-functional foundation pit model assay systems equipment, it is characterised in that:Including model casing system and handling soil and load System;
The model casing system includes that main tank (1), water tank (2) and Double layer iron are terraced (8);Main tank (1) is by steel plate, organic glass, angle Steel sets sealing strip, transparent organic glass whole plate edge with composition, main tank (1) both sides assembly steel plate and ribbing, junction is bolted Watch window (7) is used as in steel plate;Water tank (2) setting in main tank (1) both sides and with partition panel and separates card slot and main tank (1) it separates, water tank (2) is made of steel plate, angle steel and being bolted;Double layer iron ladder (8) is set on rear side of main tank (1);Entire case Concrete bed (4) is laid under body, concrete bed (4) both sides open up draining water channel (5);In main tank (1) and water tank (2) both sides Water-level observation hole (6) is mounted equidistant;Right side water tank (2) outer wall is equipped with display system (3);
The handling soil and loading system include mound field (9), the native channel (10) of handling, excavator (12), packaged type girder steel Frame and pressue device;Mound field (9) by steel plate, angle steel, be bolted and form, the native channel of mound field (9) one end connection handling (10);The native channel (10) of handling is that belt-type loads and unloads native channel, loads and unloads native channel (10) upper end and belt pulley is arranged, put down on belt pulley Face, which also serves as, unloads native platform, loads and unloads native channel (10) lower end and mounts mound field (9) eminence with concrete pier (11);Packaged type girder steel Frame is made of steel column (13), fixed I-steel girder (15) and moveable I-shaped gooseneck (16), and I-shaped gooseneck (16) is sliding Dynamic side is equipped with the linear guide;Excavator (12) can move on I-shaped gooseneck (16);Pressue device includes hydraulic jack (19) and load plate (17) hydraulic jack (19), hydraulic jack (19) lower end, are equipped each on I-shaped gooseneck (16) Fixed load plate (17), hydraulic jack (19) can slide on I-shaped gooseneck (16).
2. multi-functional foundation pit model assay systems equipment according to claim 1, it is characterised in that:In the main tank (1) Pre-buried prefabricated tunnel model and laying monitoring element.
3. multi-functional foundation pit model assay systems equipment according to claim 1, it is characterised in that:The Double layer iron ladder (8) it is highly consistent with main tank (1).
4. multi-functional foundation pit model assay systems equipment according to claim 1, it is characterised in that:Steel column (13) bottom Portion is equipped with concrete pouring weight (14), and fixed part angle steel is bolted.
5. multi-functional foundation pit model assay systems equipment according to claim 1, it is characterised in that:The mound field (9) Rear side be equipped with data operation system (18), the data operation system (18) include computer monitor, fiber grating monitoring system, Water pressure data monitoring system and handling soil and Loading Control System.
6. multi-functional foundation pit model assay systems equipment according to claim 1, it is characterised in that:The excavator (12) For small-sized excavator, moved on I-shaped gooseneck (16).
7. a kind of application method of multi-functional foundation pit model assay systems equipment as described in claim 1, which is characterized in that packet Include following steps:
1) using the native channel (10) of handling the soil body is filled to main tank (1) quantification;
2) the pre-buried prefabricated test model in main tank (1) lays monitoring element, opens both sides water tank (2) sluice gate whenever necessary;
3) I-shaped gooseneck (16) position is adjusted, pressing position is directed at;
4) start pressue device, proceed by simulation test, check display data;
5) experiment finishes, and stores data, site clearing.
CN201810225173.1A 2018-03-19 2018-03-19 A kind of multi-functional foundation pit model assay systems equipment and its application method Pending CN108316366A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810225173.1A CN108316366A (en) 2018-03-19 2018-03-19 A kind of multi-functional foundation pit model assay systems equipment and its application method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810225173.1A CN108316366A (en) 2018-03-19 2018-03-19 A kind of multi-functional foundation pit model assay systems equipment and its application method

Publications (1)

Publication Number Publication Date
CN108316366A true CN108316366A (en) 2018-07-24

Family

ID=62899556

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810225173.1A Pending CN108316366A (en) 2018-03-19 2018-03-19 A kind of multi-functional foundation pit model assay systems equipment and its application method

Country Status (1)

Country Link
CN (1) CN108316366A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109342095A (en) * 2018-09-28 2019-02-15 沈阳工业大学 Under wear shallow earthing waters piping lane shield tunnel model test and leakage early warning system
CN110424475A (en) * 2019-07-09 2019-11-08 浙江工业大学 The simulator of long and narrow pit accident deformation under the conditions of a kind of bias and seepage flow
CN111042228A (en) * 2019-12-29 2020-04-21 北京中岩大地科技股份有限公司 Multifunctional stirring model test box and use method thereof
CN114193606A (en) * 2021-12-10 2022-03-18 上海公路桥梁(集团)有限公司 Assembly type cement concrete plate production equipment and installation and use method thereof

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001241289A (en) * 2000-02-29 2001-09-04 Shimizu Corp Method and faciliteis for testing tunnel stability
CN101086494A (en) * 2007-07-03 2007-12-12 浙江大学 Foundation and slope engineering model test platform
CN107012896A (en) * 2017-03-20 2017-08-04 山东大学 A kind of Multifunctional pile base model assay systems and its assembling and test method

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001241289A (en) * 2000-02-29 2001-09-04 Shimizu Corp Method and faciliteis for testing tunnel stability
CN101086494A (en) * 2007-07-03 2007-12-12 浙江大学 Foundation and slope engineering model test platform
CN107012896A (en) * 2017-03-20 2017-08-04 山东大学 A kind of Multifunctional pile base model assay systems and its assembling and test method

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109342095A (en) * 2018-09-28 2019-02-15 沈阳工业大学 Under wear shallow earthing waters piping lane shield tunnel model test and leakage early warning system
CN110424475A (en) * 2019-07-09 2019-11-08 浙江工业大学 The simulator of long and narrow pit accident deformation under the conditions of a kind of bias and seepage flow
CN110424475B (en) * 2019-07-09 2024-03-26 浙江工业大学 Simulator for bulging deformation of long and narrow foundation pit under bias and seepage conditions
CN111042228A (en) * 2019-12-29 2020-04-21 北京中岩大地科技股份有限公司 Multifunctional stirring model test box and use method thereof
CN111042228B (en) * 2019-12-29 2024-02-13 北京中岩大地科技股份有限公司 Multifunctional stirring model test box and application method thereof
CN114193606A (en) * 2021-12-10 2022-03-18 上海公路桥梁(集团)有限公司 Assembly type cement concrete plate production equipment and installation and use method thereof

Similar Documents

Publication Publication Date Title
CN108316366A (en) A kind of multi-functional foundation pit model assay systems equipment and its application method
CN107012896B (en) A kind of Multifunctional pile base model assay systems and its assembling and test method
Zhang et al. Influence of groundwater drawdown on excavation responses–A case history in Bukit Timah granitic residual soils
Hsiung et al. Three-dimensional effects of a deep excavation on wall deflections in loose to medium dense sands
CN202631519U (en) Universal model tank device for rainfall landslide tests
CN103884831B (en) A kind of roadbed side slope and underground works multifunction three-dimensional model test platform
Hsiung A case study on the behaviour of a deep excavation in sand
CN106226494B (en) A kind of orebody mining disturbance country rock leads to permeable similar physical analog test apparatus
CN103117020B (en) Experimental facility for simulating shield tunnel dynamically boring causing ground loss and surface subsidence
Lam Ground movements due to excavation in clay: physical and analytical models
CN105116101A (en) Simulation test system for prevention and control of mine disasters and application method thereof
CN110284530B (en) Multifunctional combined assembled model test box device combining foundation pit and tunnel and application
CN213875269U (en) Multifunctional tunnel model test device
CN211505504U (en) Test device for simulating tunnel crossing water-rich fault gushing water
CN204925064U (en) Mine calamity prevent and control analogue test system
Ou et al. A simplified estimation of excavation-induced ground movements for adjacent building damage potential assessment
CN103061774A (en) Shield tunnel construction environment simulation unit
Bovolenta et al. Effect of deep excavations and deformable retaining structures on neighboring buildings: A case study
CN106483012A (en) A kind of horizontal addload system and Geotechnical Engineering multifunction test system
Zhang et al. Ground subsidence characteristics caused by construction of shallow-buried tunnel in a sandy soil composite formation
Oztoprak et al. Impact of neighbouring deep excavation on high-rise sun plaza building and its surrounding
Anato et al. Numerical investigation of ground settlements induced by the construction of Nanjing WeiSanLu tunnel and parametric analysis
Ślusarek et al. Analysis of the influence of soil moisture on the stability of a building based on a slope
Miliziano et al. Prediction of tunnelling-induced effects on a historic building in Rome
CN211057878U (en) Multifunctional foundation pit model test system equipment

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination