CN108316285A - Operating platform and construction method suitable for the construction of deep hole large diameter hole pile cages - Google Patents

Operating platform and construction method suitable for the construction of deep hole large diameter hole pile cages Download PDF

Info

Publication number
CN108316285A
CN108316285A CN201810264133.8A CN201810264133A CN108316285A CN 108316285 A CN108316285 A CN 108316285A CN 201810264133 A CN201810264133 A CN 201810264133A CN 108316285 A CN108316285 A CN 108316285A
Authority
CN
China
Prior art keywords
steel
construction
hole
operating platform
large diameter
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810264133.8A
Other languages
Chinese (zh)
Inventor
郑勇
曾伯川
胡建
鄢自刚
李连方
王强
邓红军
艾江临
兰勇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Third Engineering Co Ltd of China Railway No 8 Engineering Group Co Ltd
Original Assignee
Third Engineering Co Ltd of China Railway No 8 Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Third Engineering Co Ltd of China Railway No 8 Engineering Group Co Ltd filed Critical Third Engineering Co Ltd of China Railway No 8 Engineering Group Co Ltd
Priority to CN201810264133.8A priority Critical patent/CN108316285A/en
Publication of CN108316285A publication Critical patent/CN108316285A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The invention discloses a kind of operating platforms and construction method suitable for the construction of deep hole large diameter hole pile cages, operating platform includes the steel pile casting of fabrication hole and the round card slot type operating platform that the fan-shaped platform by being arranged in the piecemeal of steel pile casting surrounding forms, the sector platform is that two blocks of angle steel weld the skeleton to be formed by junction steel plate, is completely spread with crude steel silk screen between the skeleton;Card slot is formed between two blocks of angle steel, the card slot is stuck on steel pile casting.Compared with prior art, the positive effect of the present invention is:Present invention mainly solves steel reinforcement cage aperture jointing quantity is more, it is long to expend the time, the problems such as bottom hole sediment thickness is difficult to control, and the construction of steel reinforcement cage can be started while drilling, shorten the time of each cycle, construction speed is largely accelerated, duration tighter project is very suitable for.

Description

Operating platform and construction method suitable for the construction of deep hole large diameter hole pile cages
Technical field
The invention mainly relates to the constructions of deep hole large diameter bored pile steel reinforcement cage, and especially geological condition is bad, easily collapses Hole area.
Background technology
Existing borehole filling pile cage of reinforcement construction is usually section by section in aperture welding or sleeve connection, this construction method For the long shorter cast-in-situ bored pile of stake, there is very high practicability, because steel reinforcement cage is shorter, need to weld in aperture Connector is fewer, and time consumption is fewer, is easy to control the quality of stake;But works as and encounter the brill that stake is long, diameter is bigger When hole pouring pile, just there is prodigious drawback in the construction technology of aperture connection section by section, because the length increase of steel reinforcement cage leads to steel The piece-ups of muscle cage aperture connection increase, and the aperture connection required time is also significantly increased, and the connection of Large-size rebar cage Mode is sleeve connection, and precision and difficulty the ratio welding of sleeve connection are high, time-consuming also relatively long, in both the above situation Under, the soil being suspended in mud and sand sedimentation are may result in bottom hole, and bottom hole sediment thickness is caused to severely exceed, it is secondary Borehole cleaning can take a substantial amount of time and expense or even secondary pile hole cleaning cannot be satisfied the requirement of design sediment, need to propose steel reinforcement cage Again borehole cleaning causes to do over again, and causes larger duration loss and economic loss.
Area especially poor in geological conditions, if the overlong time of steel reinforcement cage decentralization, also likely causes collapse hole, Bury the serious problems such as steel reinforcement cage.
Invention content
In order to overcome the disadvantages mentioned above of the prior art, the present invention provides one kind being suitable for deep hole large diameter hole pile cages The operating platform and construction method of construction, it is intended to improve original drilled pile reinforcing cage and connect the construction work of decentralization section by section in aperture Skill makes steel reinforcement cage in advance, drilling while steel reinforcement cage can the parallel splicing in fabrication hole, through the invention can be real It is existing:First, steel reinforcement cage assembly no longer needs to splice after drilling terminates borehole cleaning, can accelerate with drilling parallel operations Construction speed, ensure that the duration;Two are the reduction of the connector quantity of aperture connection after pore-forming, shorten the construction time, greatly The risk for reducing collapse hole of degree, overcomes the sediment thickness of bottom hole because of steel reinforcement cage construction time long and exceeded problem, It ensure that pile quality.
The technical solution adopted by the present invention to solve the technical problems is:One kind being suitable for deep hole large diameter hole pile cages The operating platform of construction, including circle that the steel pile casting of fabrication hole and the fan-shaped platform by being arranged in the piecemeal of steel pile casting surrounding form Shape card slot type operating platform, the sector platform are that two blocks of angle steel weld the skeleton to be formed by junction steel plate, the skeleton it Between completely spread with crude steel silk screen;Card slot is formed between two blocks of angle steel, the card slot is stuck on steel pile casting.
The present invention also provides a kind of construction methods suitable for deep hole large diameter hole pile cages operating platform, including such as Lower step:The closer position other than the region that drills, inserting piling steel pile casting, drilling form the aperture technique consistent with stake diameter is designed Hole;Piecemeal makes fan-shaped platform in advance, and after fabrication hole is formed, the card slot of the fan-shaped platform of piecemeal is stuck in the steel of fabrication hole On casing, tightens bolt and card slot is reinforced;It is completely spread with crude steel silk screen between the skeleton of fan-shaped platform, by the anti-encirclement of steel pipe Column is inserted on the reserved fence installation reinforcing bar of fan-shaped platform and forms hands-off operation platform, and hangs up properly nameplate.
Compared with prior art, the positive effect of the present invention is:The time required to steel reinforcement cage decentralization has been greatly shortened, and Good condition is created for next step secondary pile hole cleaning, accelerates integrated engineering construction speed, labor is saved for subsequent process The input of the costs such as power, machinery, material.
Traditional construction technology is to be welded section by section in aperture, but the characteristics of deep hole large diameter drill hole pile is that steel reinforcement cage is long Degree length, the quantity of merogenesis is more, and bar diameter is big to be needed to use sleeve connection, and installation difficulty is big, cannot can be made with multiplexing as welding Surface construction, sleeve connection must obtain incremental, each sleeve can only be bit by bit tight inward, take it is especially more, at this Being suspended in the boring mud among mud in the process can slowly precipitate, and the time is longer, and the boring mud of precipitation is more, and the difficulty of secondary pile hole cleaning is just It is bigger, and the risk that steel reinforcement cage is buried is higher.
Present invention mainly solves steel reinforcement cage aperture jointing quantity is more, expend that the time is long, and bottom hole sediment thickness is difficult to The problems such as control, and the construction of steel reinforcement cage can be started while drilling, the time of each cycle is shortened, largely On accelerate construction speed, be very suitable for duration tighter project.
Description of the drawings
Examples of the present invention will be described by way of reference to the accompanying drawings, wherein:
Fig. 1 is totally-enclosed fence operating platform plan view;
Fig. 2 is fan-shaped platform cross-sectional view.
Specific implementation mode
A kind of card slot type operating platform suitable for the construction of deep hole large diameter hole pile cages, as depicted in figs. 1 and 2, packet Include the steel pile casting 1 of fabrication hole, the fan-shaped platform 2 of piecemeal, bolt 3, card slot 4, fence installation reinforcing bar 5, card slot angle steel 6, card slot angle Steel 7, junction steel plate 8 etc..
The closer position other than the region that drills, inserting piling steel pile casting 1, drilling form the aperture technique consistent with stake diameter is designed (depth can determines according to actual conditions, at least over the length of the quasi- steel reinforcement cage of two feast-brand marks in hole;Quantity also can be according to the number of drilling machine Amount, duration progress requirement and determine).
The round card slot type operating platform of fabrication hole surrounding setting, card slot type operating platform is by several pieces of fan-shaped platforms The main skeleton of 2 compositions, fan-shaped platform 2 is angle steel 6 and angle steel 7 (50 × 50 × 6mm of angle steel model), and top is welded with 230 × 40 × 5 junction steel plate 8 makes angle steel 6 and angle steel 7 be connected, and forming card slot 4, (width of card slot protects when can be according to construction The wall thickness of cylinder determines that slightly wider than casing wall thickness 1~2 millimeter is best), trepanning on angle steel 6, size and the bolt 3 in hole match, just In 3 fixed card slot of bolt, fence installation 5 main purpose of reinforcing bar is easy for the protective fence installed the operating platform below.It is round The main operational principle of card slot type operating platform be angle steel 6, angle steel 7, junction steel plate 8 form card slot 4 be stuck on steel pile casting 1, Bolt 3 reinforces the stability of card slot, and multiple round operating platforms of card slot skeleton composition install steel pipe on fence installation reinforcing bar 5 Protective fence forms " locked in " operation platform.
Piecemeal makes fan-shaped platform 2 in advance, and after fabrication hole is formed, the card slot 4 of the fan-shaped platform 2 of piecemeal is stuck in steel shield On cylinder 1, the fixation of bolt 3 is tightened, ensures the stability of totally enclosed type operating platform, is completely spread with crude steel silk screen between main skeleton, The steel pipe fence of 120cm is inserted on the fence installation reinforcing bar 5 reserved, and hangs up properly nameplate, convenient for construction personnel in technique Splice bar cage in hole also ensures the safety of construction personnel.The fence installation reinforcing bar 5 uses a diameter of 25 millimeters of reinforcing bar It is welded on operating platform 2;The thickness of the operating platform 2 is 50 millimeters, and the height of the fence installation reinforcing bar 5 is 80 millis The leg pillar height degree of rice, the operating platform 2 is 250 millimeters, is welded using 50 × 50 × 6 angle steel.
The poor area of geology is contemplated that the steel pile casting of fabrication hole all with proceeding to bottom hole, avoid fabrication hole exposure for a long time and Collapse hole, casing can be extracted after the completion of construction, recycling.It can prevent collapse hole from influencing the use of fabrication hole in this way, it can also The multiple borehole cleaning in work progress is avoided, construction efficiency is influenced.
The fabrication hole is also required to mud off, periodically uses rotary drilling rig cleaning technology hole, ensure fabrication hole has Imitate depth.

Claims (10)

1. a kind of operating platform suitable for the construction of deep hole large diameter hole pile cages, it is characterised in that:Steel including fabrication hole The round card slot type operating platform that casing and the fan-shaped platform by being arranged in the piecemeal of steel pile casting surrounding form, the sector platform The skeleton to be formed is welded by junction steel plate for two blocks of angle steel, is completely spread with crude steel silk screen between the skeleton;Between two blocks of angle steel Card slot is formed, the card slot is stuck on steel pile casting.
2. the operating platform according to claim 1 suitable for the construction of deep hole large diameter hole pile cages, it is characterised in that: It is provided with bolt hole on angle steel, coordinates with bolt, card slot is reinforced.
3. the operating platform according to claim 1 suitable for the construction of deep hole large diameter hole pile cages, it is characterised in that: The width of the card slot is 1~2 millimeter wider than the wall thickness of steel pile casting.
4. the operating platform according to claim 1 suitable for the construction of deep hole large diameter hole pile cages, it is characterised in that: Fence installation reinforcing bar is provided on the outside of fan-shaped platform, installation steel pipe protective fence forms " locked in " operation on fence installation reinforcing bar Platform.
5. the operating platform according to claim 4 suitable for the construction of deep hole large diameter hole pile cages, it is characterised in that: The steel pipe protective fence height is 120cm.
6. the operating platform according to claim 1 suitable for the construction of deep hole large diameter hole pile cages, it is characterised in that: The specification of the junction steel plate is 230 × 40 × 5mm.
7. the operating platform according to claim 1 suitable for the construction of deep hole large diameter hole pile cages, it is characterised in that: 50 × 50 × 6mm of the angle steel model.
8. a kind of construction method suitable for deep hole large diameter hole pile cages operating platform, it is characterised in that:Including walking as follows Suddenly:The closer position other than the region that drills, inserting piling steel pile casting, drilling form the aperture fabrication hole consistent with stake diameter is designed;It carries Preceding piecemeal makes fan-shaped platform, and after fabrication hole is formed, the card slot of the fan-shaped platform of piecemeal is stuck in the steel pile casting of fabrication hole On, it tightens bolt and card slot is reinforced;It is completely spread with crude steel silk screen between the skeleton of fan-shaped platform, steel pipe protective fence is inserted Hands-off operation platform is formed on the fence installation reinforcing bar that fan-shaped platform is reserved, and hangs up properly nameplate.
9. the construction method according to claim 8 suitable for deep hole large diameter hole pile cages operating platform, feature It is:For the area that geology is poor, the steel pile casting of the fabrication hole is all with proceeding to bottom hole.
10. the construction method according to claim 8 suitable for deep hole large diameter hole pile cages operating platform, feature It is:After the completion of construction, extracts the steel pile casting and reused.
CN201810264133.8A 2018-03-28 2018-03-28 Operating platform and construction method suitable for the construction of deep hole large diameter hole pile cages Pending CN108316285A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810264133.8A CN108316285A (en) 2018-03-28 2018-03-28 Operating platform and construction method suitable for the construction of deep hole large diameter hole pile cages

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810264133.8A CN108316285A (en) 2018-03-28 2018-03-28 Operating platform and construction method suitable for the construction of deep hole large diameter hole pile cages

Publications (1)

Publication Number Publication Date
CN108316285A true CN108316285A (en) 2018-07-24

Family

ID=62900357

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810264133.8A Pending CN108316285A (en) 2018-03-28 2018-03-28 Operating platform and construction method suitable for the construction of deep hole large diameter hole pile cages

Country Status (1)

Country Link
CN (1) CN108316285A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112177555A (en) * 2020-10-22 2021-01-05 中国能源建设集团陕西省电力设计院有限公司 Detachable wellhead reinforcing and protecting device

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08226121A (en) * 1995-02-21 1996-09-03 Kajima Corp Reinforcement cage erecting device for cast-in-place pile
JP2008111256A (en) * 2006-10-30 2008-05-15 Shimizu Corp Joint structure and construction method for pile head part
CN101338561A (en) * 2008-08-13 2009-01-07 中铁大桥局集团第四工程有限公司 Reinforcement cage quick-assembling positioning system
CN103556626A (en) * 2013-10-31 2014-02-05 中铁港航局集团有限公司 Hanging structure for hoisting large-diameter hole drilling filling pile steel bar cage
CN208328900U (en) * 2018-03-28 2019-01-04 中铁八局集团第三工程有限公司 Operating platform suitable for the construction of deep hole large diameter hole pile cages

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08226121A (en) * 1995-02-21 1996-09-03 Kajima Corp Reinforcement cage erecting device for cast-in-place pile
JP2008111256A (en) * 2006-10-30 2008-05-15 Shimizu Corp Joint structure and construction method for pile head part
CN101338561A (en) * 2008-08-13 2009-01-07 中铁大桥局集团第四工程有限公司 Reinforcement cage quick-assembling positioning system
CN103556626A (en) * 2013-10-31 2014-02-05 中铁港航局集团有限公司 Hanging structure for hoisting large-diameter hole drilling filling pile steel bar cage
CN208328900U (en) * 2018-03-28 2019-01-04 中铁八局集团第三工程有限公司 Operating platform suitable for the construction of deep hole large diameter hole pile cages

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112177555A (en) * 2020-10-22 2021-01-05 中国能源建设集团陕西省电力设计院有限公司 Detachable wellhead reinforcing and protecting device
CN112177555B (en) * 2020-10-22 2024-06-11 中国能源建设集团陕西省电力设计院有限公司 Detachable wellhead reinforcing and protecting device

Similar Documents

Publication Publication Date Title
CN105735251B (en) Cutting type full-casing follow-up pile-forming construction method and system of bridge pile foundation rotary drilling rig
CN110439571B (en) Transverse channel construction method for leading flat pilot tunnel to main tunnel and transverse channel
CN107288357A (en) In reverse construction steel pipe column plumbing device and utilize the device carry out pile integrated construction technique
CN103469817B (en) Existing subway station main structure broadening construction method
AU2021106928A4 (en) Construction method for excavation of deep pit with triaxial mixing pile waterstop curtains and rotary bored cast-in-place pile supports
CN101696578A (en) Construction method for pouring foundations of main pylon piers of bridge on deep water inclined runway
CN108708284B (en) A kind of steel trestle construction method for resisting flood discharge bed scour
CN112761076A (en) Lock catch steel pipe pile cofferdam applied to water level change condition and construction method
CN106065628B (en) Based on the major diameter running water pipe security protection construction method faced forever with reference to theory
CN107653878A (en) Cast-in-situ bored pile is reusable to be longitudinally separated formula steel pile casting construction
CN104131566B (en) A kind of basement is without the construction method of horizontal support foundation ditch
CN110273413A (en) A kind of efficient construction method of prefabricated pile
CN208328900U (en) Operating platform suitable for the construction of deep hole large diameter hole pile cages
US6485234B2 (en) Apparatus and method for making cylindrical columns
CN108316285A (en) Operating platform and construction method suitable for the construction of deep hole large diameter hole pile cages
CN106245668A (en) A kind of truss-like pile foundation and construction method thereof
ITTO20110913A1 (en) PROCEDURE FOR THE CONSTRUCTION OF LARGE DIAMETER POLES AND EXCAVATION TOOL
CN215669558U (en) Front-mounted inclined pile of foundation pit supporting system
KR102325623B1 (en) Construction method of retaining wall
CN106759377A (en) The construction method of recyclable building enclosure
CN106761849A (en) Supporting construction is served as a contrast at the beginning of a kind of high density formation tunnel based on lock foot pad plate
CN202280053U (en) Construction equipment of energy-saving pressure distributive cemented soil anti-floating pile
JP4645091B2 (en) Expanded pile and construction method of the expanded pile
CN109235453A (en) Deep basal pit PRC tubular pole assembled method for protecting support
CN113373915B (en) Method for reinforcing steel column pile structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20180724