CN108259858A - The monitoring method and device of substation's scene and equipment - Google Patents

The monitoring method and device of substation's scene and equipment Download PDF

Info

Publication number
CN108259858A
CN108259858A CN201810315632.5A CN201810315632A CN108259858A CN 108259858 A CN108259858 A CN 108259858A CN 201810315632 A CN201810315632 A CN 201810315632A CN 108259858 A CN108259858 A CN 108259858A
Authority
CN
China
Prior art keywords
substation
image
data
scene
equipment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810315632.5A
Other languages
Chinese (zh)
Other versions
CN108259858B (en
Inventor
胡娟
吴莉娟
冯宇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sichuan Whayer Information Industry Co Ltd
Original Assignee
Sichuan Whayer Information Industry Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sichuan Whayer Information Industry Co Ltd filed Critical Sichuan Whayer Information Industry Co Ltd
Priority to CN201810315632.5A priority Critical patent/CN108259858B/en
Publication of CN108259858A publication Critical patent/CN108259858A/en
Application granted granted Critical
Publication of CN108259858B publication Critical patent/CN108259858B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04NPICTORIAL COMMUNICATION, e.g. TELEVISION
    • H04N7/00Television systems
    • H04N7/18Closed-circuit television [CCTV] systems, i.e. systems in which the video signal is not broadcast
    • H04N7/181Closed-circuit television [CCTV] systems, i.e. systems in which the video signal is not broadcast for receiving images from a plurality of remote sources
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06TIMAGE DATA PROCESSING OR GENERATION, IN GENERAL
    • G06T17/00Three dimensional [3D] modelling, e.g. data description of 3D objects
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06TIMAGE DATA PROCESSING OR GENERATION, IN GENERAL
    • G06T7/00Image analysis
    • G06T7/50Depth or shape recovery
    • G06T7/55Depth or shape recovery from multiple images
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06TIMAGE DATA PROCESSING OR GENERATION, IN GENERAL
    • G06T2207/00Indexing scheme for image analysis or image enhancement
    • G06T2207/10Image acquisition modality
    • G06T2207/10004Still image; Photographic image
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06TIMAGE DATA PROCESSING OR GENERATION, IN GENERAL
    • G06T2207/00Indexing scheme for image analysis or image enhancement
    • G06T2207/10Image acquisition modality
    • G06T2207/10016Video; Image sequence
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06TIMAGE DATA PROCESSING OR GENERATION, IN GENERAL
    • G06T2207/00Indexing scheme for image analysis or image enhancement
    • G06T2207/30Subject of image; Context of image processing
    • G06T2207/30108Industrial image inspection

Landscapes

  • Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Multimedia (AREA)
  • Signal Processing (AREA)
  • Computer Graphics (AREA)
  • Geometry (AREA)
  • Software Systems (AREA)
  • Computer Vision & Pattern Recognition (AREA)
  • Image Processing (AREA)
  • Image Analysis (AREA)

Abstract

The embodiment of the present invention provides the monitoring method and device of a kind of substation's scene and equipment.The monitoring method of substation's scene and equipment includes:Obtain the first image sequence data of substation's scene of collecting device acquisition;Analog reconstruction is carried out to substation's scene according to described first image sequence data and obtains the simulation scene photo of substation's scene;The second image data of the substation equipment of the collecting device acquisition is obtained, textures update is carried out to the simulation scene photo according to second image data, obtains the real-time status simulation drawing of the substation equipment.Substation fortune inspection personnel can grasp the substation field situation in real time.

Description

The monitoring method and device of substation's scene and equipment
Technical field
The present invention relates to field of computer technology, in particular to a kind of substation's scene and the monitoring method of equipment And device.
Background technology
In unattended operation transformer station, based on safety and to the requirement that accident timely responds to, necessity is needed to configure Real-time automatically-monitored means, grasp the variable condition of substation equipment and transformer equipment operation conditions, improve substation's fortune The efficiency of work is examined, reduces the invalid and inefficient amount of labour.
Invention content
The method for real-time monitoring and device that are designed to provide a kind of substation's scene and equipment of the embodiment of the present invention.
The monitoring method of a kind of substation's scene and equipment of the present invention includes:
Obtain the first image sequence data of substation's scene of collecting device acquisition;
Substation's scene is simulated according to described first image sequence data to obtain substation's scene Simulate scene photo;
The second image data of the substation equipment state that the collecting device acquires in real time is obtained, according to described Two image datas obtain the real-time status mould of the substation equipment to the simulation scene photo part area data textures update Intend figure.
The embodiment of the present invention also provides the monitoring device of a kind of substation's scene and equipment, the supervisory control of substation device packet It includes:
First acquisition module, for obtaining the first image sequence data of substation's scene of collecting device acquisition;
Reconstructed module obtains for carrying out analog reconstruction to substation's scene according to described first image sequence data The simulation scene photo of substation's scene;
Second acquisition module, for obtaining the second figure of the substation equipment state that the collecting device acquires in real time As data;
Update module, for simulating scene photo part area data textures more to described according to second image data Newly, the real-time status simulation drawing of the substation equipment is obtained.
Compared with prior art, the monitoring method and device of substation's scene of the embodiment of the present invention and equipment, with reference to regarding Frequency evidence and substation's region scene data carry out analog reconstruction to obtain by image data to substation's region scene first The simulation scene photo of substation's region scene;Secondly, it is contemplated that substation's fortune inspection safety and efficiently, based on substation's cloth Point video camera, gives full play to monitoring and the fine picture of collecting device data, and collecting device status data information is existing to the simulation Field figure part area data updates to obtain the real-time status simulation drawing of the substation equipment;Finally, substation's fortune inspection personnel can The substation field situation is grasped by the equipment real-time status simulation drawing in real time;It facts have proved the method to substation O&M is with practical value.
For the above objects, features and advantages of the present invention is enable to be clearer and more comprehensible, preferred embodiment cited below particularly, and coordinate Appended attached drawing, is described in detail below.
Description of the drawings
It in order to illustrate the technical solution of the embodiments of the present invention more clearly, below will be to needed in the embodiment attached Figure is briefly described.It is to be appreciated that the following drawings illustrates only certain embodiments of the present invention, therefore it is not construed as pair The restriction of range, for those of ordinary skill in the art, without creative efforts, can also be according to this A little attached drawings obtain other relevant attached drawings.
Fig. 1 is the flow chart of the monitoring method of substation's scene that present pre-ferred embodiments provide and equipment.
Fig. 2 is the detailed of the step S104 of the monitoring method of substation's scene that present pre-ferred embodiments provide and equipment Flow chart.
Fig. 3 is the detailed of the step S1042 of the monitoring method of substation's scene that present pre-ferred embodiments provide and equipment Thin flow chart.
Fig. 4 is the block diagram of electric terminal that present pre-ferred embodiments provide.
Fig. 5 is that the function module of the monitoring device of substation's scene that present pre-ferred embodiments provide and equipment is illustrated Figure.
Specific embodiment
Below in conjunction with attached drawing in the embodiment of the present invention, the technical solution in the embodiment of the present invention is carried out clear, complete Ground describes, it is clear that described embodiment is only part of the embodiment of the present invention, instead of all the embodiments.Usually exist The component of the embodiment of the present invention described and illustrated in attached drawing can be configured to arrange and design with a variety of different herein.Cause This, the detailed description of the embodiment of the present invention to providing in the accompanying drawings is not intended to limit claimed invention below Range, but it is merely representative of the selected embodiment of the present invention.Based on the embodiment of the present invention, those skilled in the art are not doing Go out all other embodiments obtained under the premise of creative work, shall fall within the protection scope of the present invention.
It should be noted that:Similar label and letter represents similar terms in following attached drawing, therefore, once a certain Xiang Yi It is defined in a attached drawing, does not then need to that it is further defined and explained in subsequent attached drawing.Meanwhile the present invention's In description, term " first ", " second " etc. are only used for distinguishing description, and it is not intended that instruction or hint relative importance.
Three-dimensional reconstruction is based on one group of orderly or unordered picture or image for having certain degree of overlapping, using calculating Machine vision and multiple view solid geometry principle, construct the three-dimensional scenic close with the scene of multi-angle picture presentation, supply User grasps the situation of change of monitored scene more fully hereinafter.
Due to the raising of laser scanner scans precision, upsurge of the people to Three Dimensional Reconfiguration is excited, target is logical Cross the precision that cheap cost reaches scanner;With the development of artificial intelligence technology and to some NP (Non- Deterministic Polynomial Problems, there are the indecisive problems that multinomial algorithm can solve) problem It solves, more and more intelligent visuals are applied by familiar and understanding, are caused in archaeology of cultural relic, design field and manufacturing industry Power in by Three Dimensional Reconfiguration come model restore or automatic modeling, preferably preserve or displaying model;Our product simultaneously It also is intended to combine relevant application, realizes the virtual visualization intelligent real-time monitoring of equipment.
In a scene of unattended operation transformer station, based on safety and unexpected high efficiency consideration, Wo Menjie occurs Video data and substation's scene image are closed, using high-definition camera acquisition substation regional area scene image combination video prison Target device video data (security consideration, certain clearer images of equipment can not shooting at close range) is controlled, with target object Geometry integrality and visual effect be target, realize target object reconstruct virtual visualization equipment displaying;Automatic collection is supervised The video data of equipment state variation is controlled, image is based on using increment reconstruct and the newer mode of textures and video is combined realization The real-time update of virtual scene equipment state;It facts have proved that the method is with practical value to the O&M of substation, effectively improves and patrols It examines working efficiency, reduce labor intensity.It is described in detail below by several embodiments.
Embodiment 1
Referring to Fig. 1, it is the stream for the supervisory control of substation method applied to electric terminal that present pre-ferred embodiments provide Cheng Tu.Idiographic flow shown in FIG. 1 will be described in detail below.
Step S101 obtains the first image sequence data of substation's scene of collecting device acquisition.
In the present embodiment, the collecting device can be video camera, and using band, there are one the video cameras of central projection distortion Projection model;I.e.:
Wherein, f represents focal length;S represents distortion factor;cx,cyRepresent camera center coordinate.
Represent the spin matrix of video camera;Represent the translation of video camera;
I.e.
Image characteristic pointSpatial point corresponding with the simulation scene photoBetween geometrical relationship.
In one embodiment, the collecting device can be communicated to connect with the electric terminal, the collecting device After collecting described first image sequence data, described first image sequence data is transferred to by the electronics end by network End.In another embodiment, after the collected described first image sequence data of the collecting device, by first figure As sequence data is imported by data line in the electric terminal.In another embodiment, it is stored in the electric terminal Described first image sequence data obtains described first image sequence data from memory when needing to use.
Further, to ensure that result integrality and visual quality, the collecting device can be high-definition cameras.It uses High-definition camera shoots the image data of substation's scene, and overlaying graphics degree is preferably more than 60%.Specifically, the height Clear video camera is shot at visual angle for 5~15 degree of ranges, the target object number of iterations at least three in substation's scene.
Step S102 carries out substation's scene according to described first image sequence data described in analog reconstruction obtains The simulation scene photo of substation's scene.
In the present embodiment, the simulation scene photo can be graphics.
In the present embodiment, the reconstruct of point cloud, surface reconstruction, surface optimization and surface can be included by building the simulation scene photo Several steps such as textures, the Three Dimensional Reconfiguration of view-based access control model projection realize sparse cloud reconstruct, together using increment SFM algorithms When obtain accurate camera parameters information and matching characteristic point data;Approximate adjacent domains searching algorithm based on patch sampling is real Existing dense reconstruct;Based on CGAL (Computational Geometry Algorithms Library, computational geometry algorithms library) Generate surface triangle gridding;Algorithm is cut based on minimal graph and carries out surface optimization;Based on model surface segmentation, Surface Parameterization and line The method that reason is packaged realizes surface textures.
Step S103 obtains the second image data of the substation equipment state of the collecting device acquisition.
In the present embodiment, the substation equipment periphery is equipped with collecting device, for example, it may be monitor camera, institute State the image data that collecting device acquires the substation equipment state according to default presetting bit.
In the present embodiment, second image data can include:1) device status data of single image, for example, regarding Frequency sectional drawing, form JPG;2) video stream data of monitoring objective object collecting device;3) in the case of multiple monitor cameras, Take the image or video stream data of monitor camera overlapping region.The video stream data of the acquisition is converted to picture number by frame per second According to for example, form JPG can be converted to.
Step S104 according to second image data to the simulation scene photo part area data textures update, is obtained To the real-time status simulation drawing of the substation equipment.
In the present embodiment, the real-time status simulation drawing can be the reality presented with the update of second image data When three-dimensional picture.
The step S104 includes increment reconstruct and the newer process of textures.In detail, as shown in Fig. 2, being described as two Step.
Step S1041, the second image data of acquisition are added in a manner of increment in described first image sequence data, It is added in grouping image according to visible features point number, based on triangulation location, bundle adjustment and filter false matching characteristic point Alternative manner calculates the collecting device parameter and matching characteristic point.
Step S1041 provides guarantee for textures update.
Step S1042 is raw according to the plane projection between the characteristic point and the simulation scene photo and back projection's relationship Into conformal figure;Cascade connection extraction texture between image based on visibility constraints and conformal figure and second image data Data update texture atlas, to be updated by part area data textures.
Specifically.The textures update can be a kind of texture replacement method of the Surface Parameterization of characteristic point, it is contemplated that Instrument and switch are that the texture of plane is replaced, projection and back projection generation conformal of the characteristic point based on plane of single image data Figure extracts data texturing based on the cascade connection between visibility constraints and conformal figure and image data, updates texture atlas, real Existing textures update;Based on multiple image datas, optimal view, the patch based on individual view are selected according to characteristic point visibility constraints Figure update method realizes that texture is replaced.
Increment reconstruct according to the different step S1041 of the type of second image data uses different processing sides Method is described in detail below, in one embodiment, when the device status data that second image data is single image When, based on increment reconfiguration principle, calculate monitor camera parameter information and matching characteristic point correspondence;It is updated based on textures former Reason realizes equipment state update.
In another embodiment, when second image data is video stream data, the video streaming data packet It includes:Unchanged video flowing and the video flowing of PTZ controls;When the video stream data is unchanged video flowing, reconstructed using increment Method calculates the parameter of collecting device and matching characteristic point;It is described when the video flowing that the video stream data is controlled for PTZ Video stream data is the image data converted by frame per second, when image number is more than or equal to three, using increment SFM algorithms, is calculated Camera parameters and matching characteristic point;When image number is less than three, using increment reconfiguration principle, the parameter of collecting device is calculated With matching characteristic point.
When second image data is video stream data, it is divided by situation as unchanged video flowing and PTZ (Pan/ Tilt/Zoom) the video flowing of control;The first situation can be converted at the device status data situation of the single image Reason.The second situation, the video stream data are the image datas (JPG) converted by frame per second, are more than or equal to three in image data When, using increment SFM algorithms, calculate camera parameters information and matching characteristic point;Image number uses increment weight when being less than three Structure principle calculates the parameter of collecting device and matching characteristic point;Based on the second situation in textures more new principle, equipment shape is realized State updates.
In another embodiment, when multiple monitor cameras being installed in the range of substation's restriction, monitoring is taken to take the photograph The image or video stream data of camera overlapping region, video flowing are converted to the image data (lattice of the image data of conversion by frame per second Formula is JPG).It is interpreted as, according to the characteristic point of overlapping region, calculates characteristic point and simulate the relationship between scene photo, such feelings The method that condition determines to reconstruct using increment SFM or increment according to image number;In addition, if the data of collecting device acquisition are without weight Folded or degree of overlapping is less, and the probability that leads to the failure is larger, and such situation in scene is fewer at present, therefore omits.
In the present embodiment, the equipment being monitored in substation's scene is broadly divided into three types:A, instrument;B, it switchs (character type or character type switch);C, disconnecting switch and disconnecting link (state change).Instrument and the result of on off state variation use The newer technology of textures;According to current method, the feelings such as the existing gap during textures are newer is effectively solved, blocks Condition;There are larger differences for collecting device acquisition data resolution and the first image sequence data resolution ratio, and visual effect is bad, adopts It is solved with fusion super resolution technologies.
The image considered in the second image data is blocked or is pasted from circumstance of occlusion, image and video monitoring image Figure has the gap, illumination etc., situation, to improve visual effect, in the present embodiment, as shown in Figure 3.The step S1042 can also be wrapped It includes:Step S10421 and step S10422.
Step S10421, the calculating geometry simulated between scene photo and target view in the second image data is corresponding to close System, determines the camera parameters information of optimal view image and matching characteristic point, and edge feature point is verified based on plane equation.
In the present embodiment, the target view can be the opposite better view of matching in second image data.
In the present embodiment, the instrument and switch are Planar Mappings, i.e., using plane equation:
F(xi,yi,zi):Axi+Byi+Czi+ D=0; (3)
3 points can determine a plane;
Wherein, (Xr,Xl)、(Yr,Yl)、(Zr,Zl) the corresponding simulation scene photo of image boundary characteristic point is represented respectively Target scene formed spatial point X, Y, Z value.Based on the model space point corresponding to plane equation authentication image characteristic point Whether in approximately the same plane, if error is too small, can optimize;Error is excessive, illustrates two kinds of situations:1st, camera parameters need excellent Change or matching characteristic point has exterior point, using triangulation location and the alternative manner of light-stream adjustment, verify matching characteristic point and optimization Camera parameters;2nd, image data acquiring fails, and can directly terminate.
Further, to x, y, z difference derivation, you can obtain normal line vector:
That is,Arbitrary straight line its normal vector connected in plane is the same;Needle To normal vector unanimous circumstances, unified approach processing may be used in boundary, effectively improves computational efficiency, while improves vision effect Fruit.
Step S10422, based on it is described simulation scene photo and the second image data characteristic point between geometrical correspondence, Projection and image of the scene photo to image are simulated to the reversed of model scene photo using the Surface Parameterization method of feature based point The plane bidirectional projection relationship of projection generates conformal figure;Feature based visibility of a point constrains and tri patch region extension principle Conformal figure and the cascade connection of image data are established, generates data texturing, updates conformal atlas, by data texturing update to model Surface realizes that texture is replaced, and then obtains the real-time status simulation drawing of the substation equipment.
Specifically,
π surfaces forward projection, β represent back projection;
Based on the correspondence (formula 2) between the simulation scene photo and the second image data characteristic point, feature based Point correspondence Surface Parameterization method (simulation scene photo to image projection and image to model scene photo reversed throwing Shadow) two-way plane projection relationship, generate conformal figure;Feature based visibility of a point constrains (formula 4) and tri patch extension principle Conformal figure and the image cascade connection of the second image data are established, generates data texturing, updates conformal atlas, by data texturing more Newly to model surface, realize that texture is replaced, obtain the real-time status simulation drawing of the substation equipment.It is to result impact factor Distortion and illumination for being generated when the accuracy of matching characteristic point and camera parameters, shooting photo etc..
A kind of substation's scene of the embodiment of the present invention and the monitoring method of equipment, with reference to video data and substation region Contextual data carries out analog reconstruction to substation's region scene by the first image sequence data first and obtains the area of substation The simulation scene photo of domain scene;Secondly, acquisition substation equipment status data updates to obtain the change to the simulation scene photo The real-time status simulation drawing of power station equipment;The method of base in this present embodiment, on the basis of gathered data is effective, reconstructs geometry Substation's scenario simulation figure of integrality and high visual quality, substation fortune inspection personnel can grasp the substation field feelings in real time Condition;It facts have proved that the method is with practical value to the O&M of substation.
Embodiment 2
As shown in figure 4, it is the block diagram of an electric terminal 100.The electric terminal 100 is filled including supervisory control of substation Put 110, memory 111, storage control 112, processor 113, Peripheral Interface 114, input-output unit 115, display unit 116.It will appreciated by the skilled person that structure shown in Fig. 4 is only to illustrate, not to the knot of electric terminal 100 It is configured to limit.For example, electric terminal 100 may also include more either less components than shown in Fig. 4 or have and figure Different configuration shown in 4.Electric terminal 100 described in the present embodiment can be personal computer, image processing server or Mobile electronic device etc. has the computing device of image-capable.
The memory 111, storage control 112, processor 113, Peripheral Interface 114, input-output unit 115 and aobvious Show that 116 each element of unit is directly or indirectly electrically connected between each other, to realize the transmission of data or interaction.For example, these Element can be realized by one or more communication bus or signal wire be electrically connected between each other.The supervisory control of substation device 110 can be stored in the memory 111 or be solidificated in institute including at least one in the form of software or firmware (Firmware) State the software function module in the operating system (Operating System, OS) of electric terminal 100.The processor 113 is used In performing the executable module that is stored in memory, for example, the software function module that includes of the supervisory control of substation device 110 or Computer program.
Wherein, the memory 111 may be, but not limited to, random access memory (Random Access Memory, RAM), read-only memory (Read Only Memory, ROM), programmable read only memory (Programmable Read-Only Memory, PROM), erasable read-only memory (Erasable Programmable Read-Only Memory, EPROM), electricallyerasable ROM (EEROM) (Electric Erasable Programmable Read-Only Memory, EEPROM) etc..Wherein, memory 111 is for storing program, the processor 113 after execute instruction is received, Described program is performed, the method performed by electric terminal 100 that the process that any embodiment of the embodiment of the present invention discloses defines can To be applied to realize in processor 113 or by processor 113.
The processor 113 may be a kind of IC chip, have the processing capacity of signal.Above-mentioned processor 113 can be general processor, including central processing unit (Central Processing Unit, abbreviation CPU), network processes Device (Network Processor, abbreviation NP) etc.;It can also be digital signal processor (DSP), application-specific integrated circuit (ASIC), field programmable gate array (FPGA) either other programmable logic device, discrete gate or transistor logic, Discrete hardware components.It can realize or perform disclosed each method, step and the logic diagram in the embodiment of the present invention.It is general Processor can be microprocessor or the processor can also be any conventional processor etc..
Various input/output devices are coupled to processor 113 and memory 111 by the Peripheral Interface 114.At some In embodiment, Peripheral Interface 114, processor 113 and storage control 112 can be realized in one single chip.Other one In a little examples, they can be realized by independent chip respectively.
The input-output unit 115 is used to be supplied to user input data.The input-output unit 115 can be, But it is not limited to, mouse and keyboard etc..
The display unit 116 provided between the electric terminal 100 and user an interactive interface (such as user behaviour Make interface) or for display image data give user reference.In the present embodiment, the display unit can be liquid crystal display Or touch control display.Can be the capacitance type touch control screen or resistance for supporting single-point and multi-point touch operation if touch control display Formula touch screen etc..Single-point and multi-point touch operation is supported to refer to that touch control display can sense on the touch control display one Or the touch control operation generated simultaneously at multiple positions, and processor is transferred to be calculated and located the touch control operation that this is sensed Reason.
Specifically, operating system is stored in the memory 111, in an example, the operating system can be Windows 764bit, naturally it is also possible to be the operating system of higher configuration.The memory of the electric terminal can be 16gb RAM, 128gb SSD for the OS, 1TB HDD for main (programs and data were run from the HDD).The video card of the electric terminal 100 can be nVidia GTX 970GPU, and certainly, the video card can also be configured more High video card.The processor 113 can be with Intel Core i7-4790K CPU (4cores/8threads, up to 4.4Ghz), certainly, the processor 113 can preferably be located by the processor or processing capacity of processing capacity Manage device.Specifically, those skilled in the art can select the configuration of each accessory of the electric terminal 100 according to demand.
Referring to Fig. 5, it is the function mould of the supervisory control of substation device 110 described in Fig. 4 of present pre-ferred embodiments offer Block schematic diagram.Modules in supervisory control of substation device 110 and unit in the embodiment of the present invention are for performing the above method Each step in embodiment.The supervisory control of substation device 110 includes:First acquisition module 1101, reconstructed module 1102, Two acquisition modules 1103 and update module 1104.
First acquisition module 1101, for obtaining the first image sequence number of substation's scene of collecting device acquisition According to.
The reconstructed module 1102, for being simulated according to described first image sequence data to substation's scene Reconstruct obtains the simulation scene photo of substation's scene.
Second acquisition module 1103, for obtaining the substation equipment state that the collecting device acquires in real time The second image data.
The update module 1104, for simulating scene photo part area data to described according to second image data Textures update, and obtain the real-time status simulation drawing of the substation equipment.
In the present embodiment, the update module 1104 may include:Characteristic point acquiring unit and textures unit.
The characteristic point acquiring unit reconstructs for increment, increment reconstruct include the second image data of acquisition with The mode of increment is added in described first image sequence data, is added in grouping image, is based on according to visible features point number The alternative manner of triangulation location, bundle adjustment and filter false matching characteristic point is calculated the collecting device parameter and obtains Take matching characteristic point.
The textures unit updates for textures, and the textures update includes existing according to the characteristic point and the simulation Plane projection and back projection's relationship between the figure of field, generate conformal figure;Based on visibility constraints and conformal figure and second figure As data image between cascade connection extract data texturing, update texture atlas, and pass through part area data textures more Newly.
In the present embodiment, it is single image equipment shape that the characteristic point acquiring unit, which is additionally operable to when second image data, During state data, based on increment reconstructing method, the parameter of collecting device and matching characteristic point are calculated;When second image data is During video stream data, the video stream data includes:Unchanged video flowing and the video flowing of PTZ controls;The video stream data During for unchanged video flowing, based on increment reconstructing method, the parameter of collecting device and matching characteristic point are calculated;When the video flowing During the video flowing that data are controlled for PTZ, the video stream data is pressed to the image data of frame per second conversion, when image data number is big When equal to three, using increment SFM algorithms, camera parameters and matching characteristic point are calculated;When image data number 3, use Increment reconfiguration principle calculates the parameter of collecting device and matching characteristic point.
The textures unit is additionally operable to calculate the geometry pair in the simulation scene photo and the second image between optimal view It should be related to, determine the camera parameters of target view and matching characteristic point, characteristic point is verified based on plane equation;Based on the mould Intend the geometrical correspondence between scene photo and the second image data characteristic point, simulated using the Surface Parameterization method of characteristic point Projection and image of the scene photo to image generate conformal figure to the plane bidirectional projection relationship of the back projection of model scene photo; Feature based visibility of a point constrains and tri patch region extension principle establishes conformal figure and the cascade connection of image data, generates Data texturing updates conformal atlas, by data texturing update to model surface, realizes that texture is replaced, to obtain the substation The real-time status simulation drawing of equipment.
In the present embodiment, first acquisition module 1101 is additionally operable to obtain the visual angle of the collecting device at 5~15 degree, And the image of the target object in substation repeats the first image sequence data that the image of number at least three is formed.
Other details about the present embodiment can further refer to the description in above method embodiment, herein no longer It repeats.
The supervisory control of substation device of the embodiment of the present invention is reconstructed to obtain substation by using image data The simulation scene photo of substation is stated, then the simulation scene photo is updated to obtain institute by collected second image data Real-time status simulation drawing is stated, related personnel can be enable to check the substation field feelings by the real-time status simulation drawing Condition.In addition, making monitored picture vivider by simulation drawing, related personnel can more clearly understand the field condition of substation.
In several embodiments provided herein, it should be understood that disclosed device and method can also pass through Other modes are realized.The apparatus embodiments described above are merely exemplary, for example, flow chart and block diagram in attached drawing Show the device of multiple embodiments according to the present invention, the architectural framework in the cards of method and computer program product, Function and operation.In this regard, each box in flow chart or block diagram can represent the one of a module, program segment or code Part, a part for the module, program segment or code include one or more and are used to implement holding for defined logic function Row instruction.It should also be noted that at some as in the realization method replaced, the function that is marked in box can also be to be different from The sequence marked in attached drawing occurs.For example, two continuous boxes can essentially perform substantially in parallel, they are sometimes It can perform in the opposite order, this is depended on the functions involved.It is it is also noted that every in block diagram and/or flow chart The combination of a box and the box in block diagram and/or flow chart can use function or the dedicated base of action as defined in performing It realizes or can be realized with the combination of specialized hardware and computer instruction in the system of hardware.
In addition, each function module in each embodiment of the present invention can integrate to form an independent portion Point or modules individualism, can also two or more modules be integrated to form an independent part.
If the function is realized in the form of software function module and is independent product sale or in use, can be with It is stored in a computer read/write memory medium.Based on such understanding, technical scheme of the present invention is substantially in other words The part contribute to the prior art or the part of the technical solution can be embodied in the form of software product, the meter Calculation machine software product is stored in a storage medium, is used including some instructions so that a computer equipment (can be People's computer, server or network equipment etc.) perform all or part of the steps of the method according to each embodiment of the present invention. And aforementioned storage medium includes:USB flash disk, mobile hard disk, read-only memory (ROM, Read-Only Memory), arbitrary access are deposited The various media that can store program code such as reservoir (RAM, Random Access Memory), magnetic disc or CD.It needs Illustrate, herein, relational terms such as first and second and the like be used merely to by an entity or operation with Another entity or operation distinguish, and without necessarily requiring or implying between these entities or operation, there are any this realities The relationship or sequence on border.Moreover, term " comprising ", "comprising" or its any other variant are intended to the packet of nonexcludability Contain so that process, method, article or equipment including a series of elements not only include those elements, but also including It other elements that are not explicitly listed or further includes as elements inherent to such a process, method, article, or device. In the absence of more restrictions, the element limited by sentence "including a ...", it is not excluded that including the element Process, method, also there are other identical elements in article or equipment.
The foregoing is only a preferred embodiment of the present invention, is not intended to restrict the invention, for the skill of this field For art personnel, the invention may be variously modified and varied.All within the spirits and principles of the present invention, that is made any repaiies Change, equivalent replacement, improvement etc., should all be included in the protection scope of the present invention.It should be noted that:Similar label and letter exists Similar terms are represented in following attached drawing, therefore, once being defined in a certain Xiang Yi attached drawing, are then not required in subsequent attached drawing It is further defined and is explained.
The above description is merely a specific embodiment, but protection scope of the present invention is not limited thereto, any Those familiar with the art in the technical scope disclosed by the present invention, can readily occur in change or replacement, should all contain Lid is within protection scope of the present invention.Therefore, protection scope of the present invention should be subject to the protection scope in claims.

Claims (10)

  1. A kind of 1. monitoring method of substation's scene and equipment, which is characterized in that the monitoring side of substation's scene and equipment Method includes:
    Obtain the first image sequence data of substation's scene of collecting device acquisition;
    Substation's scene is simulated according to described first image sequence data, obtains the simulation of substation's scene Scene photo;
    Obtain the second image data of the substation equipment state of the collecting device acquisition;
    According to second image data to the simulation scene photo part area data textures update, obtain the substation and set Standby real-time status simulation drawing.
  2. 2. the monitoring method of substation's scene as described in claim 1 and equipment, which is characterized in that described according to described second Image data obtains the real-time status simulation of the substation equipment to the simulation scene photo part area data textures update Figure, step:
    Increment reconstructs, and the second image data that the increment reconstruct includes obtaining is added to described first image in a manner of increment In sequence data, added in grouping image according to visible features point number, based on triangulation location, bundle adjustment and filter false Alternative manner with characteristic point calculates the collecting device parameter and matching characteristic point;
    Textures update, and the textures update is including according to the plane projection between the characteristic point and the simulation scene photo and instead Projection relation generates conformal figure;Cascade between image based on visibility constraints and conformal figure and second image data Relationship extracts data texturing, updates texture atlas, and pass through part area data textures and update.
  3. 3. the monitoring method of substation's scene as claimed in claim 2 and equipment, which is characterized in that the increment reconstruct packet It includes:
    When second image data is the device status data of single image, based on increment reconstructing method, calculates acquisition and set Standby parameter and matching characteristic point;
    When second image data is video stream data, the video stream data includes:Unchanged video flowing and there are PTZ controls The video flowing of system;When the video stream data is unchanged video flowing, based on increment reconstructing method, the parameter of collecting device is calculated With matching characteristic point;When the video flowing that the video stream data is controlled for PTZ, the video stream data is converted to by frame per second When image data number is more than or equal to three, camera parameters and matching characteristic are calculated using increment SFM algorithms for image data Point;When image data number is less than three, the parameter of collecting device and matching characteristic point are calculated using increment reconfiguration principle.
  4. 4. the monitoring method of substation's scene as claimed in claim 2 and equipment, which is characterized in that the newer step of textures Suddenly include:
    A) geometrical correspondence between optimal view in the simulation scene photo and the second image is calculated, determines that target view is taken the photograph Camera parameter and matching characteristic point verify characteristic point based on plane equation;
    B) based on the geometrical correspondence between the simulation scene photo and the second image data characteristic point, using feature based point Surface Parameterization method simulation scene photo it is two-way to the projection of image and the plane of image to the back projection of model scene photo Projection relation generates conformal figure;Feature based visibility of a point constrains and tri patch region extension principle establishes conformal figure and second The cascade connection generation data texturing of the image of image data, updates conformal atlas, real by data texturing update to model surface Existing texture is replaced, and then obtain the real-time status simulation drawing of the substation equipment.
  5. 5. the monitoring method of substation's scene as described in claim 1 and equipment, which is characterized in that the acquisition collecting device The step of first image sequence data of the substation of acquisition, includes:
    The image for obtaining target object of the collecting device acquisition visual angle between 5~15 degree, in substation repeats number extremely The first image sequence data that image three few is formed.
  6. A kind of 6. monitoring device of substation's scene and equipment, which is characterized in that the monitoring dress of substation's scene and equipment Put including:
    First acquisition module, for obtaining the first image sequence data of substation's scene of collecting device acquisition;
    Reconstructed module, for being reconstructed to obtain the change to substation's scenario simulation according to described first image sequence data The simulation scene photo of power station scene;
    Second acquisition module, for obtaining the second picture number of the substation equipment state that the collecting device acquires in real time According to;
    Update module, for updating to obtain to the simulation scene photo part area data textures according to second image data The real-time status simulation drawing of the substation equipment.
  7. 7. the monitoring device of substation's scene as claimed in claim 6 and equipment, which is characterized in that the update module packet It includes:
    Characteristic point acquiring unit reconstructs for increment, and the second image data that the increment reconstruct includes obtaining is with the side of increment Formula is added in described first image sequence data, according to visible features point number add in grouping image in, based on triangulation location, The alternative manner of bundle adjustment and filter false matching characteristic point calculates the collecting device parameter and matching characteristic point;
    Textures unit updates for textures, and the textures update is included according between the characteristic point and the simulation scene photo Plane projection and back projection's relationship, generate conformal figure;Based on visibility constraints and conformal figure and second image data Cascade connection extraction data texturing between image, updates texture atlas, and pass through part area data textures and update.
  8. 8. the monitoring device of substation's scene as claimed in claim 7 and equipment, which is characterized in that the characteristic point obtains single Member is used for:
    When second image data is the device status data of single image, based on increment reconstructing method, calculates acquisition and set Standby parameter and matching characteristic point;
    When second image data is video stream data, the video stream data includes:Unchanged video flowing and PTZ controls Video flowing;When the video stream data is unchanged video flowing, using increment reconstructing method, calculate collecting device parameter and Matching characteristic point;When the video flowing that the video stream data is controlled for PTZ, the video stream data is the figure converted by frame per second As data, when image data number is more than or equal to three, camera parameters and matching characteristic point are calculated using increment SFM algorithms; When image data number is less than three, the parameter of collecting device and matching characteristic point are calculated using increment reconfiguration principle.
  9. 9. the monitoring device of substation's scene as claimed in claim 7 and equipment, which is characterized in that the textures unit is also used In:
    The geometrical correspondence between optimal view in the simulation scene photo and the second image is calculated, determines taking the photograph for target view Camera parameter and matching characteristic point, and characteristic point is verified based on plane equation;
    Based on the geometrical correspondence between the simulation scene photo and the second image data characteristic point, using feature based point Surface Parameterization method simulates plane two-way throwing of the scene photo to the projection and image to the back projection of model scene photo of image Shadow relationship generates conformal figure;Feature based visibility of a point constrains and tri patch region extension principle establishes conformal figure and picture number According to cascade connection generate data texturing, update conformal atlas, by data texturing update to model surface, realize that texture is replaced, And then obtain the real-time status simulation drawing of the substation equipment.
  10. 10. the monitoring device of substation's scene as claimed in claim 6 and equipment, which is characterized in that described first obtains mould Block is additionally operable to, and obtaining the collecting device acquisition visual angle, the image of target object repeats number between 5~15 degree, in substation The image of at least three forms the first image sequence data.
CN201810315632.5A 2018-04-10 2018-04-10 Method and device for monitoring scene and equipment of transformer substation Active CN108259858B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810315632.5A CN108259858B (en) 2018-04-10 2018-04-10 Method and device for monitoring scene and equipment of transformer substation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810315632.5A CN108259858B (en) 2018-04-10 2018-04-10 Method and device for monitoring scene and equipment of transformer substation

Publications (2)

Publication Number Publication Date
CN108259858A true CN108259858A (en) 2018-07-06
CN108259858B CN108259858B (en) 2020-10-30

Family

ID=62748038

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810315632.5A Active CN108259858B (en) 2018-04-10 2018-04-10 Method and device for monitoring scene and equipment of transformer substation

Country Status (1)

Country Link
CN (1) CN108259858B (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110838163A (en) * 2018-08-15 2020-02-25 浙江宇视科技有限公司 Mapping processing method and device
CN111710032A (en) * 2020-06-05 2020-09-25 广东电网有限责任公司 Method, device, equipment and medium for constructing three-dimensional model of transformer substation
CN111860040A (en) * 2019-04-26 2020-10-30 广州赛姆科技资讯股份有限公司 Station signal equipment state acquisition method and device and computer equipment
CN112614059A (en) * 2020-11-30 2021-04-06 国网北京市电力公司 Transformer substation detection method and device, storage medium and processor
CN113256836A (en) * 2021-04-27 2021-08-13 交通运输部天津水运工程科学研究所 Immersive intelligent inspection method for port facilities

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20120081357A1 (en) * 2010-10-01 2012-04-05 Martin Habbecke System and method for interactive painting of 2d images for iterative 3d modeling
CN103021017A (en) * 2012-12-04 2013-04-03 上海交通大学 Three-dimensional scene rebuilding method based on GPU acceleration
CN103714420A (en) * 2013-12-11 2014-04-09 深圳先进技术研究院 Object three-dimensional reconstruction method and device
CN103914874A (en) * 2014-04-08 2014-07-09 中山大学 Compact SFM three-dimensional reconstruction method without feature extraction
CN104268939A (en) * 2014-09-28 2015-01-07 国家电网公司 Transformer substation virtual-reality management system based on three-dimensional panoramic view and implementation method of transformer substation virtual-reality management system based on three-dimensional panoramic view
US20150015574A1 (en) * 2013-07-09 2015-01-15 Nvidia Corporation System, method, and computer program product for optimizing a three-dimensional texture workflow
CN105825518A (en) * 2016-03-31 2016-08-03 西安电子科技大学 Sequence image rapid three-dimensional reconstruction method based on mobile platform shooting
CN105939481A (en) * 2016-05-12 2016-09-14 深圳市望尘科技有限公司 Interactive three-dimensional virtual reality video program recorded broadcast and live broadcast method

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20120081357A1 (en) * 2010-10-01 2012-04-05 Martin Habbecke System and method for interactive painting of 2d images for iterative 3d modeling
CN103021017A (en) * 2012-12-04 2013-04-03 上海交通大学 Three-dimensional scene rebuilding method based on GPU acceleration
US20150015574A1 (en) * 2013-07-09 2015-01-15 Nvidia Corporation System, method, and computer program product for optimizing a three-dimensional texture workflow
CN103714420A (en) * 2013-12-11 2014-04-09 深圳先进技术研究院 Object three-dimensional reconstruction method and device
CN103914874A (en) * 2014-04-08 2014-07-09 中山大学 Compact SFM three-dimensional reconstruction method without feature extraction
CN104268939A (en) * 2014-09-28 2015-01-07 国家电网公司 Transformer substation virtual-reality management system based on three-dimensional panoramic view and implementation method of transformer substation virtual-reality management system based on three-dimensional panoramic view
CN105825518A (en) * 2016-03-31 2016-08-03 西安电子科技大学 Sequence image rapid three-dimensional reconstruction method based on mobile platform shooting
CN105939481A (en) * 2016-05-12 2016-09-14 深圳市望尘科技有限公司 Interactive three-dimensional virtual reality video program recorded broadcast and live broadcast method

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110838163A (en) * 2018-08-15 2020-02-25 浙江宇视科技有限公司 Mapping processing method and device
CN110838163B (en) * 2018-08-15 2024-02-02 浙江宇视科技有限公司 Mapping processing method and device
CN111860040A (en) * 2019-04-26 2020-10-30 广州赛姆科技资讯股份有限公司 Station signal equipment state acquisition method and device and computer equipment
CN111860040B (en) * 2019-04-26 2024-05-10 广州赛姆科技资讯股份有限公司 Station signal equipment state acquisition method and device and computer equipment
CN111710032A (en) * 2020-06-05 2020-09-25 广东电网有限责任公司 Method, device, equipment and medium for constructing three-dimensional model of transformer substation
CN111710032B (en) * 2020-06-05 2023-09-26 广东电网有限责任公司 Method, device, equipment and medium for constructing three-dimensional model of transformer substation
CN112614059A (en) * 2020-11-30 2021-04-06 国网北京市电力公司 Transformer substation detection method and device, storage medium and processor
CN113256836A (en) * 2021-04-27 2021-08-13 交通运输部天津水运工程科学研究所 Immersive intelligent inspection method for port facilities

Also Published As

Publication number Publication date
CN108259858B (en) 2020-10-30

Similar Documents

Publication Publication Date Title
CN108259858A (en) The monitoring method and device of substation's scene and equipment
Wang et al. Pixel2Mesh: 3D mesh model generation via image guided deformation
CN111243093B (en) Three-dimensional face grid generation method, device, equipment and storage medium
US20180096537A1 (en) Using computed facial feature points to position a product model relative to a model of a face
CN109409335A (en) Image processing method, device, computer-readable medium and electronic equipment
CN105427385A (en) High-fidelity face three-dimensional reconstruction method based on multilevel deformation model
CN107077744A (en) Generated using the threedimensional model at edge
CN108961149A (en) Image processing method, device and system and storage medium
CN108961180A (en) infrared image enhancing method and system
CA2357962C (en) System and method for the coordinated simplification of surface and wire-frame descriptions of a geometric model
CN108154531A (en) A kind of method and apparatus for calculating body-surface rauma region area
US20210142511A1 (en) Method of generating 3-dimensional model data
CN109215131A (en) The driving method and device of conjecture face
Martin-Brualla et al. 3d time-lapse reconstruction from internet photos
Jancosek et al. Scalable multi-view stereo
CN103810748B (en) The building of 3D simulation system, management method and 3D simulator
Wang et al. Oblique photogrammetry supporting procedural tree modeling in urban areas
Hamdi et al. Ges: Generalized exponential splatting for efficient radiance field rendering
CN109785422A (en) The construction method and device of three-dimensional power grid scene
Xu et al. Towards globally optimal normal orientations for thin surfaces
Zeng et al. Multi-view self-supervised learning for 3D facial texture reconstruction from single image
RU2757563C1 (en) Method for visualizing a 3d portrait of a person with altered lighting and a computing device for it
CN109118413A (en) Urban activity demographics method and device thereof, computer-readable medium
CN107194980A (en) Faceform's construction method, device and electronic equipment
CN109002553B (en) Method and device for constructing hair model, electronic equipment and computer readable medium

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information

Address after: Two Lu Tian Hua high tech Zone of Chengdu City, Sichuan province 610000 No. 219 Tianfu Software Park C District 10 Building 16 layer

Applicant after: Huayan Intelligent Technology (Group) Co.,Ltd.

Address before: Two Lu Tian Hua high tech Zone of Chengdu City, Sichuan province 610000 No. 219 Tianfu Software Park C District 10 Building 16 layer

Applicant before: SICHUAN WHAYER INFORMATION INDUSTRY Co.,Ltd.

CB02 Change of applicant information
GR01 Patent grant
GR01 Patent grant
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of invention: Substation scene and equipment monitoring method and device

Effective date of registration: 20220811

Granted publication date: 20201030

Pledgee: Chengdu SME financing Company Limited by Guarantee

Pledgor: Huayan Intelligent Technology (Group) Co.,Ltd.

Registration number: Y2022980012288

PE01 Entry into force of the registration of the contract for pledge of patent right
PC01 Cancellation of the registration of the contract for pledge of patent right

Date of cancellation: 20230720

Granted publication date: 20201030

Pledgee: Chengdu SME financing Company Limited by Guarantee

Pledgor: Huayan Intelligent Technology (Group) Co.,Ltd.

Registration number: Y2022980012288

PC01 Cancellation of the registration of the contract for pledge of patent right
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of invention: Monitoring methods and devices for substation scenarios and equipment

Effective date of registration: 20230904

Granted publication date: 20201030

Pledgee: Chengdu SME financing Company Limited by Guarantee