Prior art keywords
data
server
project
flatness
shaft tower
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201611228511.4A
Other languages
Chinese (zh)
Inventor
颜涛
陇源杰
余斌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Construction Branch Of Yunnan Power Grid Co Ltd
Original Assignee
Construction Branch Of Yunnan Power Grid Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Construction Branch Of Yunnan Power Grid Co Ltd filed Critical Construction Branch Of Yunnan Power Grid Co Ltd
Priority to CN201611228511.4A priority Critical patent/CN108241963A/en
Publication of CN108241963A publication Critical patent/CN108241963A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply

Landscapes

  • Business, Economics & Management (AREA)
  • Engineering & Computer Science (AREA)
  • Human Resources & Organizations (AREA)
  • Strategic Management (AREA)
  • Economics (AREA)
  • Theoretical Computer Science (AREA)
  • Health & Medical Sciences (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Marketing (AREA)
  • General Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • Public Health (AREA)
  • Primary Health Care (AREA)
  • General Health & Medical Sciences (AREA)
  • Data Mining & Analysis (AREA)
  • Water Supply & Treatment (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses a kind of method, apparatus and managing and control system of project construction management and control, the data inputting instruction input by user of the method real-time reception, and data inputting instruction is sent to the server;Receive the whois lookup to the default template that matches of data inputting instruction;The default template is parsed, obtains corresponding data form;Operation of the user to the data form is received, obtains project data;The project data is sent to the server, the project data generates the foundation of real-time engineering progress for the server according to preset algorithm.It can be seen that, in the present invention, since user can be by mobile terminal according to required default template real time input data, server is allowd to generate real-time engineering progress, higher level's management and control department is allowd to understand current actual progress in real time, and due to not having to manually recorded data, the workload of typing personnel is alleviated, is improved work efficiency.

Description

A kind of method, apparatus and managing and control system of project construction management and control
Technical field
The present invention relates to technical field of data processing, more specifically, being to be related to a kind of method of project construction management and control, dress It puts and managing and control system.
Background technology
With the continuous development of national grid, various types of project constructions are also more and more.In numerous project constructions In, tower erection is one of essential project construction.
In the prior art, at the scene of tower erection, by the relevant data of the various projects of manual record, such as the letter at scene Breath is made a report on, and after returning to office from scene, by the data creating into forms such as job schedule reports, is sent to higher level's management and control The information such as project progress are checked by higher level's management and control department by department.
Under normal conditions, the scene of project construction such as tower erection is more remote, and office is typically specifically Point needs that the work of specific place progress data inputting could be arrived within such as one week in specific period so that higher level's management and control department The actual progress at scene can not be recognized in time, and the mode of this manual entry is relatively complicated, and the work of typing personnel It measures huge.
Invention content
In view of this, it the present invention provides a kind of method and system of project construction management and control, can solve in the prior art There are the problem of.
To achieve the above object, the present invention provides following technical solution:
The present invention provides a kind of method of project construction management and control, applied to the mobile end in project construction managing and control system End, the project construction managing and control system include at least one mobile terminal and server, the mobile terminal and the server It is connected using wireless mode, the method includes:
Real-time reception data inputting instruction input by user, and data inputting instruction is sent to the server;
Receive the whois lookup to the default template that matches of data inputting instruction;
The default template is parsed, obtains corresponding data form;
Operation of the user to the data form is received, obtains project data;
The project data is sent to the server, the project data is given birth to for the server according to preset algorithm Into the foundation of real-time engineering progress.
Preferably, it further includes:
Picture typing instruction input by user is received, the picture typing instruction includes the mark of project construction;
The picture that user is called to specify, server is sent to by the mark of the picture and the project construction, so that The server according to it is described mark determine with the corresponding file of the mark, and by the picture store to this document folder In.
Preferably, it further includes:
Shaft tower flatness computations input by user are received, the shaft tower flatness computations include shaft tower position Information;
The shaft tower flatness computations are sent to server, so that the server is according to the shaft tower flatness Computations transfer the flatness parameter to match with the shaft tower location information;Reception is returned described flat by the server Whole degree parameter;
It receives the flatness data that user inputs according to the flatness parameter and user is called to be joined according to the flatness The shaft tower picture that number is specified;
The shaft tower picture and the flatness data are sent in server, so that the server calls are preset Smooth algorithm be calculated according to the flatness data and the shaft tower picture and match with the shaft tower location information Flatness information;
Receive and show the flatness information that the server is sent.
Preferably, the operation for receiving user to the data form, obtains project data and includes:
The data form is shown in the display interface of the mobile terminal;
User is received to be operated according to the typing of item data each in the data form;
When the equal typing of each item data in the data form is completed, the data form that typing is completed is as engineering Data.
Preferably, the server includes the project data according to preset algorithm generation real-time engineering progress:
The server receives the project data;
Each item data in the project data is parsed as source data;
Using preset algorithm output result is obtained using the source data as input parameter;
The output result is converted into the form of progress bar or report as real-time engineering progress.
Preferably, it further includes:
Receive the realtime graphic at the project construction scene acquired using acquisition module;
The realtime graphic and acquisition module mark are sent to server so that the server is according to Realtime graphic and the generation of acquisition module mark identify corresponding real-time video with each acquisition module.
Another aspect of the present invention provides a kind of device of project construction management and control, including:
Data inputting command reception module, for the instruction of real-time reception data inputting input by user, and by the data Typing instruction is sent to the server;
Template receiving module, for receive the whois lookup to match with data inputting instruction it is default Template;
Parsing module for being parsed to the default template, obtains corresponding data form;
Project data generation module for receiving operation of the user to the data form, obtains project data;
Project data sending module, for the project data to be sent to the server, the project data is institute State foundation of the server according to preset algorithm generation real-time engineering progress.
Preferably, it further includes:
Computations receiving module, for receiving shaft tower flatness computations input by user, the shaft tower flatness Computations include shaft tower location information;
Parameter receiving module, for the shaft tower flatness computations to be sent to server, so that the server The flatness parameter to match with the shaft tower location information is transferred according to the shaft tower flatness computations;It receives by described The flatness parameter that server returns;
Parameter input module, for receiving flatness data that user inputs according to the flatness parameter and calling user The shaft tower picture specified according to the flatness parameter;
Parameter sending module, for the shaft tower picture and the flatness data to be sent in server, so that The preset smooth algorithm of server calls according to the flatness data and the shaft tower picture be calculated with it is described The flatness information that shaft tower location information matches;
Parameter display module, for receiving and showing the flatness information of the server transmission.
Preferably, the project data generation module includes:
Display unit, for the data form to be shown in the display interface of the mobile terminal;
Input receiving unit operates for receiving user according to the typing of item data each in the data form;
Processing unit, when being completed for the equal typing of each item data in the data form, by the number of typing completion According to list as project data;
Wherein, the server includes the project data according to preset algorithm generation real-time engineering progress:
The server receives the project data;
Each item data in the project data is parsed as source data;
Using preset algorithm output result is obtained using the source data as input parameter;
The output result is converted into the form of progress bar or report as real-time engineering progress.
Another aspect of the present invention provides a kind of project construction managing and control system, including:At least one mobile terminal and service Device, the mobile terminal are connect with the server using wireless mode, wherein:
The mobile terminal real-time reception data inputting input by user instructs and is sent to data inputting instruction The server;
The server receives the data inputting instruction, searches the default mould to match with data inputting instruction Plate, and the default template is returned into the mobile terminal;
The mobile terminal receives the default template and the default template is parsed, and obtains data form;
The mobile terminal receives operation of the user to the data form, obtains project data, and by the engineering number According to being sent to the server;
The project data is generated real-time engineering progress by the server according to preset algorithm.
It can be seen via above technical scheme that compared with prior art, the invention discloses a kind of project construction management and control Method, apparatus and managing and control system, the method packet are applied to the mobile terminal in project construction managing and control system, the project construction Managing and control system includes at least one mobile terminal and server, and the mobile terminal is connected with the server using wireless mode It connects, the method includes:The instruction of real-time reception data inputting input by user, and data inputting instruction is sent to described Server;Receive the whois lookup to the default template that matches of data inputting instruction;To the default mould Plate is parsed, and obtains corresponding data form;Operation of the user to the data form is received, obtains project data;By institute State project data and be sent to the server, the project data for the server according to preset algorithm generate real-time engineering into The foundation of degree.As can be seen that in the present invention, since user can be defeated in real time according to required default template by mobile terminal Enter data so that server can generate real-time engineering progress so that higher level's management and control department can understand current reality in real time Progress, and due to not having to manually recorded data, the workload of typing personnel is alleviated, is improved work efficiency.
Description of the drawings
In order to illustrate more clearly about the embodiment of the present invention or technical scheme of the prior art, to embodiment or will show below There is attached drawing needed in technology description to be briefly described, it should be apparent that, the accompanying drawings in the following description is only this The embodiment of invention, for those of ordinary skill in the art, without creative efforts, can also basis The attached drawing of offer obtains other attached drawings.
Fig. 1 is a kind of flow diagram of project construction management-control method disclosed by the invention;
Fig. 2 is that a kind of structure of project construction control device disclosed by the invention is intended to;
Fig. 3 is a kind of structure diagram of project construction managing and control system disclosed by the invention.
Specific embodiment
Below in conjunction with the attached drawing in the embodiment of the present invention, the technical solution in the embodiment of the present invention is carried out clear, complete Site preparation describes, it is clear that described embodiment is only part of the embodiment of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, those of ordinary skill in the art are obtained every other without making creative work Embodiment shall fall within the protection scope of the present invention.
Illustratively of the invention thinking first.
In the present invention, FRP platform of the managing and control system based on J2EE frameworks is developed, using distributed and multi tier architecture With B/S frameworks.The built-in ripe component of a large amount of engineering construction scenes implementation management of FRP platforms, supports the quick exploitation of function And security deployment.Systems organization and design are carried out using configurationization, modularization thought, improve stability, the high scalability of system, It is developed using light methods frame, application component uses Oracle 10g using ripe development platform, database.
Using component- based development theory, component design meets high reliability and scalability, rationally designs component grain Degree, and consider the factor of system performance, autgmentability etc., deployment, maintenance and management are taken into account, component interface is stablized, Ensure the scalability of interface configured transmission and content.The report tool of use can easily make various printing reports, meet Routine work needs;And it can flexibly show statistics, analysis result, Added Management people by various ways such as table, charts Member carries out decision;In addition, the report-building tool of plug-in type can download installation automatically, the program of manually installed deployment is eliminated.
In the prior art, field personnel is needed in work progress at the scene, then manually recorded related data is returned To office space by data inputting to system, this obviously cannot meet the specific progress of major executives' real time inspection engineering with And corresponding work plan is formulated according to the situation of real-time engineering.
Therefore, existing mode can not be met the needs of users.
The present invention provides a kind of method, apparatus and system of project construction management and control, below to technical scheme of the present invention It describes in detail.
Referring to Fig. 1, Fig. 1 is a kind of flow diagram of project construction management-control method provided by the invention.
The method of a kind of project construction management and control provided by the invention, applied to the mobile end in project construction managing and control system End, the project construction managing and control system include at least one mobile terminal and server, the mobile terminal and the server It is connected using wireless mode, the method includes:
The data inputting instruction input by user of S101, real-time reception, and data inputting instruction is sent to the clothes Business device;
In the embodiment of the present invention, mobile terminal is used with server to be wirelessly connected.Such as:4G.
In construction site, user uses mobile terminal, input data typing instruction, mobile terminal real-time reception user input Data inputting instruction, and be sent to server.
S102, receive the whois lookup to the default template to match with data inputting instruction;
In the server of the present invention, a variety of default templates are prefixed, since in this field, various data are corresponding default Template number is more, and in each default template required typing data entry it is also more, therefore, set in default template It is extremely complex on meter.In the present invention, with reference to existing working experience and the correlation properties of system, a variety of default moulds are devised Plate, including:The default template such as goods and materials, technology, archives.The progress of having further included makes a report on template.
Mobile terminal instructs data inputting input by user, is sent in server, after server receives instruction, from Matching default template is found in a variety of default templates and returns to mobile terminal.
The default template that mobile terminal reception is returned from server.For example, shaft tower progress template, project progress template.
S103, the default template is parsed, obtains corresponding data form;
S104, operation of the user to the data form is received, obtains project data;
After mobile terminal receives default template, preset template is parsed, corresponding data form is obtained, actually makes In, the data form according to the parsing of shaft tower progress template mainly includes essential information and shaft tower information.
User can carry out typing bar using mobile terminal in real time in real time according to the construction of project construction situation, such as tower bar The essential information of tower and shaft tower information, generate corresponding project data.
Wherein, the operation for receiving user to the data form, obtains project data and includes:
The data form is shown in the display interface of the mobile terminal;
User is received to be operated according to the typing of item data each in the data form;
When the equal typing of each item data in the data form is completed, the data form that typing is completed is as engineering Data.
Wherein, the server includes the project data according to preset algorithm generation real-time engineering progress:
The server receives the project data;
Each item data in the project data is parsed as source data;
Using preset algorithm output result is obtained using the source data as input parameter;
The output result is converted into the form of progress bar or report as real-time engineering progress.
S105, the project data is sent to the server, the project data is the server according to default Algorithm generates the foundation of real-time engineering progress.
After the completion of user is to the default template operation in mobile terminal, it can be completed by the typing for receiving user's transmission Template data, is sent in server by instruction after the instruction for receiving the completion, and server is called according to the template data Preset algorithm, automatically generates project progress.
It should be noted that if shaft tower data form, can be sent in the mail server specified, mail server It keeps connecting with the server with mobile terminal being connected in the present invention, the mail in server timing scan mail server, If shaft tower data form, then corresponding shaft tower data are parsed after automatic download, and shaft tower progress is generated after summarizing automatically Information, the shaft tower progress msg can be report or report, for characterizing project progress, be stored in memory space, so that Higher authority can transfer the report or report in real time, understand project progress situation in real time.
If other data forms, according to preset algorithm, project progress is generated, the project progress information can be Chart or progress bar so that the real-time project progress situation of higher authority's more intuitive understanding.
In actual use, server is configured with engineering statistics module, by by the template data that mobile terminal is sent into The technological means such as row excavation, statistical analysis, engineering site situation is intuitively showed in a manner of figure, report, strengthens corporate decision Macroscopical management and control of the layer to Process of Engineering Construction, including project progress, safety inspection problem rectification statistics, the rectification of quality examination problem Statistics, chronicle of events etc..The progress for checking each engineering, safety, quality, chronicle of events information are drilled through layer by layer.
In actual use, server is also configured with comprehensive management module, from the angle of project entirety, with list, figure Etc. forms the file and data of professions various in project management process are analyzed and are showed respectively, including project profile, item The contents such as mesh portion management information, engineering address list, management file.File and data can by construction site by user's root According to actual conditions typing.
In actual use, server is configured with handling of goods and materials module, for being specially managed to project goods and materials, construction Project management department works out engineering material inventory, and record arrival/return of goods information according to live practice of construction situation and schedule.System The content that system is made a report on according to construction, automatically generates goods and materials and flows to record sheet.
In actual use, also configure Management of engineering schedule module, be the core content of system, from project milestone/ Level-one plan, two level plan, three-level plan, site operation progress are made a report on, project process gunter drawing, engineering construction weekly, monthly magazine Etc. multi-angles real-time, effective management and control is carried out to engineering project progress, ensure that Engineering Project Construction runs smooth.
It should be noted that realize function based on the data that above-mentioned module is sent all in accordance with mobile terminal.
It can be seen via above technical scheme that compared with prior art, the invention discloses a kind of project construction management and control Method, the method includes:Receive the data inputting instruction that user inputs at project construction scene;Referred to according to the data inputting It enables, the default template to match with data inputting instruction is obtained from server;User is received to the default template Operation, obtains template data;The template data is sent in server so that the server is according to the template data Automatically generate project progress.As can be seen that in the present invention, since user can be according to goal-selling reality at project construction scene When input data so that server can generate project progress in real time so that higher level's management and control department can understand current in real time Actual progress, and due to not having to manually recorded data, the workload of typing personnel is alleviated, is improved work efficiency.
On the basis of above-described embodiment, the method further includes:
The picture typing instruction that user inputs at project construction scene is received, the picture typing instruction includes project construction Mark;
The picture that user is called to specify, the mark of the picture and the project construction is sent in server, is made The server is obtained according to the mark generation and the corresponding file of the mark, and picture storage is pressed from both sides to this document In.
In the embodiment of the present invention, the acceptable picture of typing in real time, picture can be the photographing module shooting by mobile terminal It uploads automatically afterwards, after uploading onto the server, the mark of server project construction according to included in photo, to automatically save Into corresponding file.If having been set up corresponding file before, can be stored automatically under this document folder.
In actual use, user inputs picture typing and instructs, the mark of the project construction including needing upload pictures, such as Project progress is to the mark in some stage.Server is identified according to this, automatically stores photo into corresponding file.
Alternatively, when project construction is to a certain stage, representational picture is shot, to record the completion situation in this stage. Server can also automatically generate corresponding file to store according to corresponding mark.
In query process afterwards, corresponding picture or photograph can be directly found according to the mark of project construction Piece, convenient management in the future.
On the basis of above-described embodiment, the method further includes::
Shaft tower flatness computations input by user are received, the shaft tower flatness computations include shaft tower position Information;
The shaft tower flatness computations are sent in server so that the server is smooth according to the shaft tower Degree computations transfer the flatness parameter to match with the shaft tower location information;
Receive the flatness parameter returned by the server;
It receives the flatness data that user inputs according to the flatness parameter and user is called to be joined according to the flatness The shaft tower picture that number is specified;
The shaft tower picture and the flatness data are sent in server so that the server calls are preset Smooth algorithm be calculated according to the flatness data and the shaft tower picture and match with the shaft tower location information Flatness information;
Receive and show the flatness information that the server is sent.
In the embodiment of the present invention, the flatness of shaft tower can also be calculated automatically.When needing to detect the smooth of shaft tower position When whether degree meets construction criteria, directly can also in the terminal it guard such as shaft tower flatness computations, it would be desirable to count After the location information input for calculating flatness, which is sent in server.
Server pre-sets shaft tower flatness algorithm and parameter, can be called according to the location information of shaft tower preset Shaft tower flatness algorithm and the flatness parameter to match with shaft tower location information.
Mobile terminal receive server return flatness parameter, by user by flatness parameter be modified or fill in The flatness data and corresponding shaft tower picture are sent to server by the flatness data of the match parameters.
Server combines preset smooth algorithm according to flatness data and carries out operation to shaft tower picture, obtains the shaft tower figure The flatness information of piece, returns to client.
Client shows the flatness information in display module.
As can be seen that in the embodiment of the present invention, the relevant information of shaft tower flatness can be immediately arrived at the scene so that existing Field personnel can adjust shaft tower flatness according to relevant information, eliminate the complicated processes when not being inconsistent standardization, constructed again, Construction cost is greatly saved, improves work efficiency.
It should be noted that in the present invention, server is also connected with capital construction integral system.
In actual use, be provided with safety management module, mould data in the block by capital construction integral system propelling data, Including safety risk management, Safety Management, emergent and accident treatment etc..System provides look facility, similary with fuzzy Inquiry, the function of advanced search.
Server is additionally provided with quality management module, the data of the module by capital construction integral system propelling data, including Quality gate, WHS quality controls, receipt control, defect management etc..System provides look facility, equally with fuzzy query, advanced The function of retrieval.
On the basis of above-described embodiment, the method further includes:
Receive positioning instruction input by user;
According to the positioning instruction, GPS module is called;
It receives current location information and the location information is sent in display module and show.
In the embodiment of the present invention, mobile terminal has navigation feature.It can automatically provide and lead according to the current location of user Air route line according to positioning instruction input by user, calls GPS module, by preset map and current position in display module It puts and is shown in display module.
In embodiments of the present invention, since the scene of many project constructions is in more remote mountain area, and these are regional Often without signal, therefore, the above method in the embodiment of the present invention supports offline mode, can prestore default Template will need the picture uploaded storage in the terminal, when that normally can connect network, is being uploaded, is facilitating use The use at family.
On the basis of above-described embodiment, the method further includes:
Receive the realtime graphic at the project construction scene acquired using acquisition module;
The realtime graphic and acquisition module mark are sent in server so that server generation with Each acquisition module identifies corresponding real-time video.
Power transmission project construction field mostly in the wild, inclement condition and job location span is big, mainly to working at height, close Key construction part and dangerous operation point carry out key monitoring.Pin hole is selected to take the photograph according to the actual conditions system front end video camera at scene Camera, video camera only need one hand-held or are fixedly mounted on a tripod, it is possible to which construction site is monitored in real time. Field video signal is transferred to by mobile network such as 3G, 4G in server after video module encodes, video monitoring clothes Business branch center shows live video after being connected to server.
As can be seen that the embodiment of the present invention can facilitate administrative staff or technology with the condition of construction at real time inspection scene Personnel are disposed or are instructed according to on-site actual situations.
Certainly, the mobile terminal in the embodiment of the present invention is preferably provided with acquisition module, to scene realtime graphic into Row acquisition.
Referring to Fig. 2, another aspect of the present invention provides a kind of device of project construction management and control, including:
Data inputting command reception module 201, for the instruction of real-time reception data inputting input by user, and by the number The server is sent to according to typing instruction;
Template receiving module 202, for receive the whois lookup to match with data inputting instruction Default template;
Parsing module 203 for being parsed to the default template, obtains corresponding data form;
Project data generation module 204 for receiving operation of the user to the data form, obtains project data;
Project data sending module 205, for the project data to be sent to the server, the project data is The server generates the foundation of real-time engineering progress according to preset algorithm.
Preferably, it further includes:
Computations receiving module, for receiving shaft tower flatness computations input by user, the shaft tower flatness Computations include shaft tower location information;
Parameter receiving module, for the shaft tower flatness computations to be sent to server, so that the server The flatness parameter to match with the shaft tower location information is transferred according to the shaft tower flatness computations;It receives by described The flatness parameter that server returns;
Parameter input module, for receiving flatness data that user inputs according to the flatness parameter and calling user The shaft tower picture specified according to the flatness parameter;
Parameter sending module, for the shaft tower picture and the flatness data to be sent in server, so that The preset smooth algorithm of server calls according to the flatness data and the shaft tower picture be calculated with it is described The flatness information that shaft tower location information matches;
Parameter display module, for receiving and showing the flatness information of the server transmission.
Preferably, the project data generation module includes:
Display unit, for the data form to be shown in the display interface of the mobile terminal;
Input receiving unit operates for receiving user according to the typing of item data each in the data form;
Processing unit, when being completed for the equal typing of each item data in the data form, by the number of typing completion According to list as project data;
Wherein, the server includes the project data according to preset algorithm generation real-time engineering progress:
The server receives the project data;
Each item data in the project data is parsed as source data;
Using preset algorithm output result is obtained using the source data as input parameter;
The output result is converted into the form of progress bar or report as real-time engineering progress.
Referring to Fig. 3, another aspect of the present invention provides a kind of system of project construction management and control, including:
At least one mobile terminal 1 and server 2, the mobile terminal are connect with the server using wireless mode, Wherein:
The mobile terminal real-time reception data inputting input by user instructs and is sent to data inputting instruction The server;
The server receives the data inputting instruction, searches the default mould to match with data inputting instruction Plate, and the default template is returned into the mobile terminal;
The mobile terminal receives the default template and the default template is parsed, and obtains data form;
The mobile terminal receives operation of the user to the data form, obtains project data, and by the engineering number According to being sent to the server;
The project data is generated real-time engineering progress by the server according to preset algorithm.
It should be noted that above-mentioned side may be used in the device and managing and control system of a kind of project construction management and control of the present embodiment A kind of method of project construction management and control in method embodiment, the whole technical solutions being used to implement in above method embodiment, The function of modules can be implemented according to the method in above method embodiment, and specific implementation process can refer to above-mentioned Associated description in embodiment, details are not described herein again.
It can be seen via above technical scheme that compared with prior art, the invention discloses a kind of project construction management and control System, the system receive the data inputting instruction that user inputs at project construction scene;It is instructed according to the data inputting, from The default template to match with data inputting instruction is obtained in server;Operation of the user to the default template is received, Obtain template data;The template data is sent in server so that the server is automatic according to the template data Generate project progress.As can be seen that in the present invention, since user can be defeated in real time according to goal-selling at project construction scene Enter data so that server can generate project progress in real time so that higher level's management and control department can understand current reality in real time Progress, and due to not having to manually recorded data, the workload of typing personnel is alleviated, is improved work efficiency.
As can be seen that the present invention performance analysis essentially from Yunnan Power Grid Company construction site management economic benefit and Social benefit.
In terms of economic benefit, implementation achievement of the invention will directly apply to the engineering construction scene of Yunnan Power Grid Company Management, realizes the collect statistics of construction site business datum, and output information report is changed into a large amount of data by manually counting System generates, and is provided a convenient for administrator's layer statistical data, information reporting, has saved cost, improves every management work Efficiency and quality so as to push the standardization and fine-grained management at engineering construction scene, can directly bring managerial economy Benefit.
In terms of social benefit, construction of the invention and practice and extension can improve Yunnan Power Grid Company personnel at different levels and crowd The information system management consciousness and level of more unit of taking part in building users of service, can be Yunnan Power Grid Company or even entire engineering construction pipe Reason industry brings advanced computer software management experience.
Each embodiment is described by the way of progressive in this specification, the highlights of each of the examples are with other The difference of embodiment, just to refer each other for identical similar portion between each embodiment.For device disclosed in embodiment For, since it is corresponded to the methods disclosed in the examples, so description is fairly simple, related part is said referring to method part It is bright.
It can directly be held with reference to the step of method or algorithm that the embodiments described herein describes with hardware, processor The combination of capable software module or the two is implemented.Software module can be placed in random access memory (RAM), memory, read-only deposit Reservoir (ROM), electrically programmable ROM, electrically erasable ROM, register, hard disk, moveable magnetic disc, CD-ROM or technology In any other form of storage medium well known in field.
The foregoing description of the disclosed embodiments enables professional and technical personnel in the field to realize or use the present invention. A variety of modifications of these embodiments will be apparent for those skilled in the art, it is as defined herein General Principle can be realized in other embodiments without departing from the spirit or scope of the present invention.Therefore, it is of the invention The embodiments shown herein is not intended to be limited to, and is to fit to and the principles and novel features disclosed herein phase one The most wide range caused.

Claims (10)

  1. A kind of 1. method of project construction management and control, which is characterized in that applied to the mobile terminal in project construction managing and control system, institute It states project construction managing and control system and includes at least one mobile terminal and server, the mobile terminal uses nothing with the server Line mode connects, the method includes:
    Real-time reception data inputting instruction input by user, and data inputting instruction is sent to the server;
    Receive the whois lookup to the default template that matches of data inputting instruction;
    The default template is parsed, obtains corresponding data form;
    Operation of the user to the data form is received, obtains project data;
    The project data is sent to the server, the project data generates real for the server according to preset algorithm When project progress foundation.
  2. 2. it according to the method described in claim 1, it is characterized in that, further includes:
    Picture typing instruction input by user is received, the picture typing instruction includes the mark of project construction;
    The picture that user is called to specify, is sent to server, so that described by the mark of the picture and the project construction Server according to it is described mark determine with the corresponding file of the mark, and by the picture store to this document folder in.
  3. 3. it according to the method described in claim 1, it is characterized in that, further includes:
    Shaft tower flatness computations input by user are received, the shaft tower flatness computations include shaft tower position letter Breath;
    The shaft tower flatness computations are sent to server, so that the server is calculated according to the shaft tower flatness The flatness parameter to match with the shaft tower location information is transferred in instruction;Receive the flatness returned by the server Parameter;
    It receives the flatness data that user inputs according to the flatness parameter and user is called to be referred to according to the flatness parameter Fixed shaft tower picture;
    The shaft tower picture and the flatness data are sent in server, so that the server calls are preset flat Whole algorithm is calculated according to the flatness data and the shaft tower picture and is put down with what the shaft tower location information matched Whole degree information;
    Receive and show the flatness information that the server is sent.
  4. 4. 1 method according to claim, which is characterized in that the operation for receiving user to the data form obtains Include to project data:
    The data form is shown in the display interface of the mobile terminal;
    User is received to be operated according to the typing of item data each in the data form;
    When the equal typing of each item data in the data form is completed, the data form that typing is completed is as engineering number According to.
  5. 5. according to the method described in claim 4, it is characterized in that, the server by the project data according to preset algorithm Generation real-time engineering progress includes:
    The server receives the project data;
    Each item data in the project data is parsed as source data;
    Using preset algorithm output result is obtained using the source data as input parameter;
    The output result is converted into the form of progress bar or report as real-time engineering progress.
  6. 6. it according to the method described in claim 1, it is characterized in that, further includes:
    Receive the realtime graphic at the project construction scene acquired using acquisition module;
    The realtime graphic and acquisition module mark are sent to server so that the server is according to described real-time Image and the generation of acquisition module mark identify corresponding real-time video with each acquisition module.
  7. 7. a kind of device of project construction management and control, which is characterized in that including:
    Data inputting command reception module, for the instruction of real-time reception data inputting input by user, and by the data inputting Instruction is sent to the server;
    Template receiving module, for receive the whois lookup to the default mould that matches of data inputting instruction Plate;
    Parsing module for being parsed to the default template, obtains corresponding data form;
    Project data generation module for receiving operation of the user to the data form, obtains project data;
    Project data sending module, for the project data to be sent to the server, the project data is the clothes Business device generates the foundation of real-time engineering progress according to preset algorithm.
  8. 8. device according to claim 7, which is characterized in that further include:
    Computations receiving module, for receiving shaft tower flatness computations input by user, the shaft tower flatness calculates Instruction includes shaft tower location information;
    Parameter receiving module, for the shaft tower flatness computations to be sent to server so that the server according to The shaft tower flatness computations transfer the flatness parameter to match with the shaft tower location information;It receives by the service The flatness parameter that device returns;
    Parameter input module, for receive flatness data that user inputs according to the flatness parameter and call user according to The shaft tower picture that the flatness parameter is specified;
    Parameter sending module, for the shaft tower picture and the flatness data to be sent in server, so that described The preset smooth algorithm of server calls is calculated and the shaft tower according to the flatness data and the shaft tower picture The flatness information that location information matches;
    Parameter display module, for receiving and showing the flatness information of the server transmission.
  9. 9. device according to claim 7, which is characterized in that the project data generation module includes:
    Display unit, for the data form to be shown in the display interface of the mobile terminal;
    Input receiving unit operates for receiving user according to the typing of item data each in the data form;
    Processing unit, when being completed for the equal typing of each item data in the data form, by the tables of data of typing completion Nonoculture is project data;
    Wherein, the server includes the project data according to preset algorithm generation real-time engineering progress:
    The server receives the project data;
    Each item data in the project data is parsed as source data;
    Using preset algorithm output result is obtained using the source data as input parameter;
    The output result is converted into the form of progress bar or report as real-time engineering progress.
  10. 10. a kind of project construction managing and control system, which is characterized in that including:At least one mobile terminal and server, the movement Terminal is connect with the server using wireless mode, wherein:
    The mobile terminal real-time reception data inputting input by user is instructed and is sent to data inputting instruction described Server;
    The server receives the data inputting instruction, searches the default template to match with data inputting instruction, and The default template is returned into the mobile terminal;
    The mobile terminal receives the default template and the default template is parsed, and obtains data form;
    The mobile terminal receives operation of the user to the data form, obtains project data, and the project data is sent out Give the server;
    The project data is generated real-time engineering progress by the server according to preset algorithm.
CN201611228511.4A 2016-12-27 2016-12-27 A kind of method, apparatus and managing and control system of project construction management and control Pending CN108241963A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611228511.4A CN108241963A (en) 2016-12-27 2016-12-27 A kind of method, apparatus and managing and control system of project construction management and control

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611228511.4A CN108241963A (en) 2016-12-27 2016-12-27 A kind of method, apparatus and managing and control system of project construction management and control

Publications (1)

Publication Number Publication Date
CN108241963A true CN108241963A (en) 2018-07-03

Family

ID=62701648

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611228511.4A Pending CN108241963A (en) 2016-12-27 2016-12-27 A kind of method, apparatus and managing and control system of project construction management and control

Country Status (1)

Country Link
CN (1) CN108241963A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109447466A (en) * 2018-10-29 2019-03-08 广东电网有限责任公司 A kind of overall process visualization managing and control system based on Distribution Network Communication network construction
CN110163434A (en) * 2019-05-22 2019-08-23 国家电网有限公司 Power grid construction project builds the prediction technique and system of Goal time order in overall process
CN112163796A (en) * 2020-10-30 2021-01-01 深圳云联万企科技有限公司 Management system of digital engineering record form
CN112184938A (en) * 2020-08-14 2021-01-05 广西电网有限责任公司来宾供电局 Real-time management and reminding system for capital construction operation
CN112686774A (en) * 2020-12-17 2021-04-20 国网安徽省电力有限公司建设分公司 Data visualization power grid infrastructure management system

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109447466A (en) * 2018-10-29 2019-03-08 广东电网有限责任公司 A kind of overall process visualization managing and control system based on Distribution Network Communication network construction
CN109447466B (en) * 2018-10-29 2021-09-17 广东电网有限责任公司 Overall process visual management and control system based on power distribution network communication network construction
CN110163434A (en) * 2019-05-22 2019-08-23 国家电网有限公司 Power grid construction project builds the prediction technique and system of Goal time order in overall process
CN112184938A (en) * 2020-08-14 2021-01-05 广西电网有限责任公司来宾供电局 Real-time management and reminding system for capital construction operation
CN112163796A (en) * 2020-10-30 2021-01-01 深圳云联万企科技有限公司 Management system of digital engineering record form
CN112686774A (en) * 2020-12-17 2021-04-20 国网安徽省电力有限公司建设分公司 Data visualization power grid infrastructure management system

Similar Documents

Publication Publication Date Title
CN108241963A (en) A kind of method, apparatus and managing and control system of project construction management and control
US9674662B2 (en) Populating property values of event objects of an object-centric data model using image metadata
CN204791127U (en) Job site quality control information system
CN109146753A (en) Executing The Law While Managing Land dynamic visiting method and system based on 3S integrated technique
CN110223208A (en) A kind of garden safety monitoring system and method
CN108765239A (en) Land resource information management system
CN107784429A (en) construction quality management platform based on intelligent terminal data collection
CN107818402A (en) A kind of construction quality control system and method
CN105225071A (en) Based on the power communication identity management method of Quick Response Code
CN109905492A (en) Operation safety management system and method based on distributed modular data center
CN108495096B (en) Mobile law enforcement system and method
CN110852611A (en) Real-time management and control system for construction workers on capital construction project site
CN108574696A (en) A kind of command dispatching system and working method based on GIS map
CN113065756A (en) BIM-based project supervision informatization management system
CN115190278B (en) Monitoring system and method based on digital converter station
CN112598815A (en) Distribution network inspection method based on Internet
CN111860256A (en) Security detection method and device, computer equipment and storage medium
CN111784310A (en) Management system for informatization electric power engineering administration project and working method thereof
CN110830558A (en) Mobile inspection system for power monitoring equipment
CN114157687B (en) Concentrated transformer information display system and method based on cloud platform deployment
CN105741023A (en) Informationized steel plate quality testing system
CN105469324A (en) Data acquisition and entering and operation and maintenance management system and data entering method of power distribution network
CN113763587A (en) Electronic patrol method and patrol terminal
CN105139323A (en) Urban management communication information system
CN111652592A (en) Work examination management method and system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20180703

WD01 Invention patent application deemed withdrawn after publication