CN108221970A - A kind of urban road under-traverse tunnel and city underground crossed construction technology - Google Patents

A kind of urban road under-traverse tunnel and city underground crossed construction technology Download PDF

Info

Publication number
CN108221970A
CN108221970A CN201810043994.3A CN201810043994A CN108221970A CN 108221970 A CN108221970 A CN 108221970A CN 201810043994 A CN201810043994 A CN 201810043994A CN 108221970 A CN108221970 A CN 108221970A
Authority
CN
China
Prior art keywords
tunnel
urban road
excavation
road under
construction technology
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810043994.3A
Other languages
Chinese (zh)
Inventor
王展望
刘杨
卫振
余洋
刘童
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sinohydro Bureau 11 Co Ltd
Sinohydro Bureau 11 Zhengzhou Co Ltd
Original Assignee
Sinohydro Bureau 11 Co Ltd
Sinohydro Bureau 11 Zhengzhou Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sinohydro Bureau 11 Co Ltd, Sinohydro Bureau 11 Zhengzhou Co Ltd filed Critical Sinohydro Bureau 11 Co Ltd
Priority to CN201810043994.3A priority Critical patent/CN108221970A/en
Publication of CN108221970A publication Critical patent/CN108221970A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/46Concrete or concrete-like piles cast in position ; Apparatus for making same making in situ by forcing bonding agents into gravel fillings or the soil
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D33/00Testing foundations or foundation structures

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The present invention discloses a kind of urban road under-traverse tunnel and city underground crossed construction technology, includes the following steps:Step 1:Foundation stabilization;Step 1.1:In place, the sinking of spudding according to Design Orientation position progress three axes agitating pile;Step 1.2:When drill bit arrival design height, start stirring 1 2min of whitewashing, brill is carried after the completion of whitewashing;Step 1.3:Sunk, whitewashed and put forward driller's sequence successively along Design Orientation position;Step 2:Deformation monitoring device is arranged in the subway tunnel and foundation pit periphery of preparation excavation;Step 3:Excavation of foundation pit;Step 3.1:Tunnel structure in foundation pit is carried out being divided into section for 4 meters by excavation section by section by width;Step 3.2:Piecewise carry out earth excavation, supporting and bed course;Step 3.3:Concrete floor pouring construction;Step 3.3:Preloading construction is carried out on concrete floor.Urban road under-traverse tunnel of the present invention can effectively prevent the protuberance of subway tunnel duct piece float upward and subway tunnel surrounding soil with city underground crossed construction technology.

Description

A kind of urban road under-traverse tunnel and city underground crossed construction technology
Technical field
The present invention relates to urban road under-traverse tunnel technical fields, and in particular to a kind of urban road under-traverse tunnel and city Subway crossed construction technology.
Background technology
When municipal tunnel is constructed with subway tunnel skewed crossing section, with the excavation of top municipal tunnel soil mass of foundation pit, subway The soil body that tunnel upper is stacked gradually is unloaded, and be easy to cause lower part subway tunnel duct piece float upward and surrounding soil protuberance, seriously Endanger safety of subway operation;Such as using conventional construction technical method, tunnel basis is reinforced and underground railway track is reinforced, nothing Method ensures that subway segment is non-rising, and subway is currently in operation state, and track can not be carried out and reinforced.
For example, Chinese invention patent application file 201110123666.2 is disclosed under a kind of shallow buried covered excavation longspan tunnel Existing high-speed railway construction method is worn, it is characterized in that this method includes following construction procedure:1) advance support and pre-reinforcement processing According to geology forecast result, the country rock for surrounding of holing is treated in advance, is reinforced using pipe canopy, ductule, and it is strong to improve country rock Degree, self-stable ability;2) partial excavation, short-delay blasting tunnel use partial excavation, excavation method based on three benching tunnelling methods, and according to The situation and actual monitored of country rock, which measure situation, to be increased the interim inverted arch of top bar, central post and carries out top bar to be divided to two excavations Or by CD method tissue excavation supporting operations;Simultaneously in order to be further reduced country rock convergent deformation, get out of a predicament or an embarrassing situation in three steps construction when It is divided to or so two staggeredly to excavate;The rock emulsion explosive of high brisance, low blasting speed is selected, is fried in the construction process using small medicine coil Medicine, more perforatings, few powder charge, periphery hole spacing are controlled within 50cm, and other borehole spacing controls are within 90cm, borehole depth For 1.2m~1.6m, powder charge line density is controlled in 0.5kg/m;It is be segmented using short-delay blasting more, to single hop explosive consumption into Row control not only also applies spaced loading side using the method for increasing explosion hop count on initiation net in single blasthole endoporus Method reduces primary neat quick-fried dose, it is ensured that the explosive charge of detonation within 10kg, is shaken with effective controlled blasting simultaneously in per 50ms Superposition;Strengthen monitoring of blasting vibration during bursting work, blasting vibration velocity control is made to be run in the joint debugging of earth's surface railway In allowed band;3) short step construction technology is used in the construction of short step excavation supporting construction, shaped steel arch is carried out in time after excavation Frame supporting, length of bench control is in 4~5m, and for inverted arch apart from face no more than 35m, lining cutting is not more than 60m apart from face; The loss of strictly control underground water is needed during above-mentioned construction and excavation, in advance using pipe canopy, grouting with small pipe, and according to excavation The groundwater condition of exposure, using curtain-grouting, Full-face pouring and radial grouting, these slurry injection techniques block underground water for selection Seepage channel, control underground water scatter and disappear, the type and proportioning of grouting serous fluid, according to the water yield situation of underground water selection adopt With cement, waterglass dual slurry or common sealing chemical grout, oiliness foaming polyurethane improves the effect of pre-grouting sealing Fruit;Construction monitoring in above-mentioned work progress is monitored using automatic, high precision and fixed inkstone absolute altitude accuracy monitoring method, i.e., in height After fast railroad track closing, high-precision light is laid along the high-speed railway in tunnel excavation axis and tunnel excavation coverage Fine grating static level, fiber grating bending-type bidirectional displacement sensor, the quasi-distributed temperature sensor of fiber grating, pass through Monitoring data are transmitted to main control computer by optical fiber in time, find the situation of change of earth's surface track in time;Simultaneously in earth's surface track It is upper to lay fixed reflecting prism, observe the exception of earth's surface track in time by Trigonometric Leveling with high precision total station Variation, it is ensured that find the influence that under-traverse tunnel is constructed to earth's surface high speed railway track in time;It is meanwhile perfect inside constructing tunnel Monitoring system, in addition to traditional country rock convergence and Vault settlement deformation monitoring is carried out, also using geological drilling rig in tunnel excavation model It encloses both sides and is drilled with water level monitoring hole, use the lost situation of water-level gauge monitoring underground water;Soil is buried between country rock and supporting construction Pressure cell changes the soil pressure of structure for measuring the soil body, grasps the situation of change of country rock internal stress in due course.
Existing high-speed railway construction method is worn in currently available technology under shallow buried covered excavation longspan tunnel, it is impossible to effective Tunnel basis and underground railway track are reinforced.
Based on as above technical problem of the existing technology, the present inventor combines experiences of construction and management for many years, proposes one Kind urban road under-traverse tunnel and city underground crossed construction technology.
Invention content
The present invention provides a kind of urban road under-traverse tunnel and city underground crossed construction technology, is added using rational ground Gu and heap support method can effectively prevent the protuberance of subway tunnel duct piece float upward and subway tunnel surrounding soil.
The present invention is achieved through the following technical solutions:
A kind of urban road under-traverse tunnel and city underground crossed construction technology, include the following steps:
Step 1:Foundation stabilization;
Step 1.1:In place, the sinking of spudding according to Design Orientation position progress three axes agitating pile;
Step 1.2:When drill bit arrival design height, start stirring whitewashing 1-2min, brill is carried after the completion of whitewashing;
Step 1.3:Sunk, whitewashed and put forward driller's sequence successively along Design Orientation position, the work until three axes agitating pile is constructed Sequence is completed;
Step 2:In subway tunnel and prepare the foundation pit periphery excavated arrangement deformation monitoring device, pass through electrical digital control instrument Device continues to monitor in subway tunnel and prepares the deformation on the foundation pit periphery excavated;
Step 3:Excavation of foundation pit;
Step 3.1:Tunnel structure in foundation pit is carried out being divided into section for 4 meters by excavation section by section by width;
Step 3.2:According to the division of step 3.1, piecewise carry out earth excavation, supporting and bed course;
Step 3.3:Treat that bed course work is completed in foundation pit, carries out concrete floor pouring construction, wherein, pour the deadline Control is within 3 days;
Step 3.3:Preloading construction is carried out on concrete floor, wherein, the weight of preloading is prefabricated reinforced concrete block.
Further, the speed that brill is carried in the step 1.2 is less than 0.5m/min.
Further, earth excavation carries out the excavation of the earthwork using backhoe digging machine and has bad luck in the step 3.2.
Further, the technique that the successively preloading of prefabricated reinforced concrete block is used in the step 3.3.
Further, the weight of prefabricated reinforced concrete block used in the step 3.3 is 5t.
Further, preloading construction is carried out using gantry crane lifting prefabricated reinforced concrete block in the step 3.3.
Further, the speed that brill is carried in the step 1.2 is 0.35m/min.
Further, it carries out in subway tunnel and prepares using robot measurement and/or hydrostatic level in the step 2 The deformation detection on the foundation pit periphery of excavation.
Compared with prior art, superior effect of the invention is:
Urban road under-traverse tunnel of the present invention and city underground crossed construction technology, by the way that ground is reasonably configured The step of reinforcing and preloading, can effectively prevent the subway tunnel duct piece float upward in under-traverse tunnel and city underground crossed construction With the protuberance of subway tunnel surrounding soil.
Specific embodiment
The specific embodiment of the invention is described in further detail below.
Embodiment 1
A kind of urban road under-traverse tunnel and city underground crossed construction technology, mainly include the following steps:
Step 1:Foundation stabilization;
Step 1.1:In place, the sinking of spudding according to Design Orientation position progress three axes agitating pile;
Step 1.2:When drill bit arrival design height, start stirring whitewashing 1-2min, brill is carried after the completion of whitewashing;
Step 1.3:Sunk, whitewashed and put forward driller's sequence successively along Design Orientation position, the work until three axes agitating pile is constructed Sequence is completed;
Step 2:In subway tunnel and prepare the foundation pit periphery excavated arrangement deformation monitoring device, pass through electrical digital control instrument Device continues to monitor in subway tunnel and prepares the deformation on the foundation pit periphery excavated;
Step 3:Excavation of foundation pit;
Step 3.1:Tunnel structure in foundation pit is carried out being divided into section for 4 meters by excavation section by section by width;
Step 3.2:According to the division of step 3.1, piecewise carry out earth excavation, supporting and bed course;
Step 3.3:Treat that bed course work is completed in foundation pit, carries out concrete floor pouring construction, wherein, pour the deadline Control is within 3 days;
Step 3.3:Preloading construction is carried out on concrete floor, wherein, the weight of preloading is prefabricated reinforced concrete block.
The speed that brill is carried in the step 1.2 is less than 0.5m/min.
Earth excavation carries out the excavation of the earthwork using backhoe digging machine and has bad luck in the step 3.2.
The technique that the successively preloading of prefabricated reinforced concrete block is used in the step 3.3.
The weight of prefabricated reinforced concrete block used in the step 3.3 is 5t.
Preloading construction is carried out using gantry crane lifting prefabricated reinforced concrete block in the step 3.3.
The speed that brill is carried in the step 1.2 is 0.35m/min.
It is carried out in subway tunnel using robot measurement and/or hydrostatic level in the step 2 and prepares the base excavated Cheat the deformation detection on periphery.By detecting in subway tunnel and preparing the deformation on the foundation pit periphery excavated in real time, sending out During raw emergency case, urgent consolidation measure is taken in time, ensures safety of subway operation.
Present invention is not limited to the embodiments described above, in the case of without departing substantially from the substantive content of the present invention, this field skill Any deformation, improvement, the replacement that art personnel are contemplated that each fall within protection scope of the present invention.

Claims (8)

1. a kind of urban road under-traverse tunnel and city underground crossed construction technology, which is characterized in that include the following steps:
Step 1:Foundation stabilization;
Step 1.1:In place, the sinking of spudding according to Design Orientation position progress three axes agitating pile;
Step 1.2:When drill bit arrival design height, start stirring whitewashing 1-2min, brill is carried after the completion of whitewashing;
Step 1.3:Sunk, whitewashed and put forward driller's sequence successively along Design Orientation position, until three axes agitating pile working procedure is complete Into;
Step 2:In subway tunnel and prepare the foundation pit periphery excavated arrangement deformation monitoring device, by electrical numerical control instrument, hold The deformation on foundation pit periphery excavated in continuous monitoring subway tunnel with preparation;
Step 3:Excavation of foundation pit;
Step 3.1:Tunnel structure in foundation pit is carried out being divided into section for 4 meters by excavation section by section by width;
Step 3.2:According to the division of step 3.1, piecewise carry out earth excavation, supporting and bed course;
Step 3.3:Treat that bed course work is completed in foundation pit, carries out concrete floor pouring construction, wherein, pour deadline control Within 3 days;
Step 3.3:Preloading construction is carried out on concrete floor, wherein, the weight of preloading is prefabricated reinforced concrete block.
2. urban road under-traverse tunnel according to claim 1 and city underground crossed construction technology, which is characterized in that institute The speed that brill is carried in step 1.2 is stated less than 0.5m/min.
3. urban road under-traverse tunnel according to claim 1 and city underground crossed construction technology, which is characterized in that institute Earth excavation in step 3.2 is stated to carry out the excavation of the earthwork using backhoe digging machine and have bad luck.
4. urban road under-traverse tunnel according to claim 1 and city underground crossed construction technology, which is characterized in that institute State the technique that the successively preloading of prefabricated reinforced concrete block is used in step 3.3.
5. urban road under-traverse tunnel according to claim 1 and city underground crossed construction technology, which is characterized in that institute The weight of prefabricated reinforced concrete block used in step 3.3 is stated as 5t.
6. urban road under-traverse tunnel according to claim 1 and city underground crossed construction technology, which is characterized in that institute It states in step 3.3 and preloading construction is carried out using gantry crane lifting prefabricated reinforced concrete block.
7. urban road under-traverse tunnel according to claim 1 and city underground crossed construction technology, which is characterized in that institute State carried in step 1.2 brill speed be 0.35m/min.
8. urban road under-traverse tunnel according to claim 1 and city underground crossed construction technology, which is characterized in that institute State the change for carrying out in subway tunnel and preparing the foundation pit periphery excavated in step 2 using robot measurement and/or hydrostatic level Shape detects.
CN201810043994.3A 2018-01-17 2018-01-17 A kind of urban road under-traverse tunnel and city underground crossed construction technology Pending CN108221970A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810043994.3A CN108221970A (en) 2018-01-17 2018-01-17 A kind of urban road under-traverse tunnel and city underground crossed construction technology

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810043994.3A CN108221970A (en) 2018-01-17 2018-01-17 A kind of urban road under-traverse tunnel and city underground crossed construction technology

Publications (1)

Publication Number Publication Date
CN108221970A true CN108221970A (en) 2018-06-29

Family

ID=62642026

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810043994.3A Pending CN108221970A (en) 2018-01-17 2018-01-17 A kind of urban road under-traverse tunnel and city underground crossed construction technology

Country Status (1)

Country Link
CN (1) CN108221970A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114908805A (en) * 2022-06-07 2022-08-16 中建七局安装工程有限公司 Strip drawing construction method for open cut tunnel with subway striding upwards

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101215838A (en) * 2007-12-28 2008-07-09 浙江环宇建设集团有限公司 Construction technique for foundation ditch on top of underground railway tunnel in soft soil area
CN103590425A (en) * 2013-11-28 2014-02-19 中铁二十局集团第五工程有限公司 Peaty soft soil stratum subway station construction technology
CN106638643A (en) * 2016-12-23 2017-05-10 中国建筑第四工程局有限公司 Water-stopping-curtain construction device and method
CN107245996A (en) * 2017-02-16 2017-10-13 昆山市交通工程有限公司 Soft soil roadbed cement mixing pile constructing process
CN206768889U (en) * 2017-05-27 2017-12-19 常州市测绘院 A kind of subway foundation pit automates DEFORMATION MONITORING SYSTEM

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101215838A (en) * 2007-12-28 2008-07-09 浙江环宇建设集团有限公司 Construction technique for foundation ditch on top of underground railway tunnel in soft soil area
CN103590425A (en) * 2013-11-28 2014-02-19 中铁二十局集团第五工程有限公司 Peaty soft soil stratum subway station construction technology
CN106638643A (en) * 2016-12-23 2017-05-10 中国建筑第四工程局有限公司 Water-stopping-curtain construction device and method
CN107245996A (en) * 2017-02-16 2017-10-13 昆山市交通工程有限公司 Soft soil roadbed cement mixing pile constructing process
CN206768889U (en) * 2017-05-27 2017-12-19 常州市测绘院 A kind of subway foundation pit automates DEFORMATION MONITORING SYSTEM

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114908805A (en) * 2022-06-07 2022-08-16 中建七局安装工程有限公司 Strip drawing construction method for open cut tunnel with subway striding upwards
CN114908805B (en) * 2022-06-07 2023-09-15 中建七局安装工程有限公司 Open cut tunnel strip drawing construction method for over-span subway

Similar Documents

Publication Publication Date Title
CN102287195B (en) Construction method of large-span tunnel passing through rapid transit railway with shallow tunneling process
CN106089217B (en) Major long tunnel rapid constructing method under complex geological condition
CN106194195A (en) Collapsible Loess District large cross-section tunnel three step is without remaining core soil in advance construction method
CN104196537A (en) Construction method of three parallel metro tunnels with ultra-small clear distance
CN107938656A (en) Complexity rebuilds base pit engineering pile base construction method
CN106285715B (en) Closely the construction method of first branch bored tunnel is worn in side to balancing earth-pressure shielding machine
CN103526748A (en) Technology for constructing deepwater bridge underwater pier large-diameter bored piles in bead-stringed type karst areas
CN109252868A (en) Hard-soft heterogeneous ground shield-tunneling construction boulder and basement rock protrusion processing method
CN109778869A (en) Foundation ditch construction method
CN110284885A (en) Shield inspection-pit construction method
CN110469332A (en) A kind of advance support consolidation method passing through Debris Flow Deposition body tunnel
CN112576265A (en) Sedimentation control method for old villages penetrated by shield
CN115539048A (en) Construction method for shallow-buried bias tunnel portal
CN113931637A (en) Shallow-buried water-rich softer rock tunnel construction method
CN111677521B (en) High-pressure gas pipe settlement control method for subway interval tunnel construction
CN108221970A (en) A kind of urban road under-traverse tunnel and city underground crossed construction technology
Shirlaw et al. A case study of two tunnels driven in the Singapore ‘Boulder Bed’and in grouted coral sands
CN115012957A (en) Safe and efficient tunneling construction process for large-section extra-long tunnel under complex condition
Masini et al. Ground response to mini-tunnelling plus ground improvement in the historical city centre of Rome
Liu et al. Numerical analysis and field monitoring tests on shallow tunnels under weak surrounding rock
CN113047873B (en) Large-diameter cylinder implantation method suitable for thick and hard top plate goaf or limestone karst cave treatment
Romani et al. The T3 stretch of Line C in Rome: TBM excavation
CN209339945U (en) Shield tunnel wears the crack ruggedized construction of karst region tunneling boring limestone formation
Ye et al. Monitoring and analysis of construction deformation of Jiulianshan Tunnel
Sato et al. Ground Measurement and Prediction with Large Shield Tunnelling Adjacent to Shinkan-sen Track

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information
CB02 Change of applicant information

Address after: 450001 No. 59 Lianhua street, hi tech Development Zone, Henan, Zhengzhou

Applicant after: China Power Construction Eleventh Bureau Engineering Co., Ltd.

Applicant after: SINOHYDRO Bureau 11 Co., Ltd.

Address before: 450001 No. 59 Lianhua street, hi tech Development Zone, Henan, Zhengzhou

Applicant before: China Hydropower eleventh Engineering Bureau (Zhengzhou) Co., Ltd.

Applicant before: SINOHYDRO Bureau 11 Co., Ltd.

RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20180629