CN108108907A CN201711500143.9A CN201711500143A CN108108907A CN 108108907 A CN108108907 A CN 108108907A CN 201711500143 A CN201711500143 A CN 201711500143A CN 108108907 A CN108108907 A CN 108108907A
Authority
CN
China
Prior art keywords
maintenance
task items
task
item
fraction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201711500143.9A
Other languages
Chinese (zh)
Inventor
秦浦雄
汤志明
郑景立
高永铭
区浩嘉
林云秋
范西红
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangzhou Boehner Mass Mdt Infotech Ltd
Guangzhou Min Bo Information Technology Co Ltd
Guangzhou Zhongtian Installation Engineering Co Ltd
Guangzhou Energy Internet Co Ltd
Original Assignee
Guangzhou Boehner Mass Mdt Infotech Ltd
Guangzhou Min Bo Information Technology Co Ltd
Guangzhou Zhongtian Installation Engineering Co Ltd
Guangzhou Energy Internet Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangzhou Boehner Mass Mdt Infotech Ltd, Guangzhou Min Bo Information Technology Co Ltd, Guangzhou Zhongtian Installation Engineering Co Ltd, Guangzhou Energy Internet Co Ltd filed Critical Guangzhou Boehner Mass Mdt Infotech Ltd
Priority to CN201711500143.9A priority Critical patent/CN108108907A/en
Publication of CN108108907A publication Critical patent/CN108108907A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06316Sequencing of tasks or work
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06312Adjustment or analysis of established resource schedule, e.g. resource or task levelling, or dynamic rescheduling
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0637Strategic management or analysis, e.g. setting a goal or target of an organisation; Planning actions based on goals; Analysis or evaluation of effectiveness of goals
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/20Administration of product repair or maintenance
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Economics (AREA)
  • Strategic Management (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Tourism & Hospitality (AREA)
  • Theoretical Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • Marketing (AREA)
  • General Business, Economics & Management (AREA)
  • Physics & Mathematics (AREA)
  • Educational Administration (AREA)
  • Quality & Reliability (AREA)
  • Operations Research (AREA)
  • Game Theory and Decision Science (AREA)
  • Development Economics (AREA)
  • Health & Medical Sciences (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The present invention proposes the maintenance program system and method for a kind of multifactor consideration.Wherein maintenance program system includes mobile terminal and server, and mobile terminal is established the link with server by network.In the system, input module is to server incoming task item;Arithmetic element scores respectively to the tasks leave time of task items, distance, electrical equipment maintenance project, required electric fittings and maintenance unit alarm number, and the total score of the weight calculation task items by each fraction item;Schedule unit carries out scheduling to the multiple task items from high to low according to the total score of multiple tasks item by total score;The multiple tasks item of scheduled is sent to the mobile terminal by sending module.The present invention takes into full account the situation of comprehensive maintenance company and electricity consumption enterprise, it realizes the automatic editing of maintenance task items, solves the decision problem of maintenance task scheduling priority, while reducing missing inspection, the probability of false detection of maintenance task, the work efficiency of maintenance company is improved, increases the satisfaction of client.

Description

The maintenance program system and method for multifactor consideration
Technical field
The present invention relates to a kind of program system, the maintenance program system and method for more particularly to a kind of multifactor consideration.
Background technology
Electrical maintenance company needs to provide the electric room of hundreds and thousands of household electric enterprises equipment maintenance work, layout every month Maintenance task is always to perplex the hard nut to crack of maintenance company, task layout it is not in place, unreasonable, the efficiency of decision-making is low all Cause maintenance company work efficiency low, can not just guarantee the quality to the regular maintenance service of electricity consumption enterprise completion on time, cause client couple Service is discontented with;How layout, the Optimization Work plan of maintenance task is carried out in a short time, and long-standing problem maintenance company.
The content of the invention
The purpose of the present invention is in view of the above-mentioned problems existing in the prior art, it is proposed that a kind of maintenance row of multifactor consideration Journey system and method takes into full account the situation of comprehensive maintenance company and electricity consumption enterprise, realizes the automatic editing of maintenance task items, solution The certainly decision problem of maintenance task scheduling priority.
A kind of maintenance program system of multifactor consideration, which is characterized in that the system comprises:
Server and mobile terminal, the server are established the link with the mobile terminal by network;
The server includes:
Input module, for the server incoming task item, the task items to include organization, and task starts day Phase, job end day phase, tasks leave time, unit address, electrical equipment maintenance project, required electric fittings;
Processing module for carrying out scheduling to multiple tasks item, further comprises:
1) arithmetic element, for the tasks leave time to the task items, distance, electrical equipment maintenance project is required Electric fittings and maintenance unit alarm number score respectively, obtain the fraction a of corresponding tasks leave time, point of distance Number b, the fraction c of electrical equipment maintenance project, the fraction e of fraction d and maintenance unit the alarm number of required electric fittings, and count Calculate the total score u of the task items:
U=α a+ β b+ χ c+ δ d+ ε e,
α is the weight of the tasks leave time, and β is the weight of the distance, and χ is the electrical equipment maintenance project Weight, δ be it is described needed for electric fittings weight, ε be the maintenance unit alert number weight, 0<α,β,χ,δ,ε<1 and α + β+χ+δ+ε=1
2) schedule unit, for the total score u according to multiple task items, by the total score from high to low to described more A task items carry out scheduling;
Sending module, for the multiple tasks item of scheduled to be sent to the mobile terminal;
Memory module, for storing standby electric fittings information table, maintenance unit warning information table, the task items information And the data message during the server operation;
The mobile terminal includes:
Receiving module, for receiving the multiple tasks item for the scheduled that the server is sent;
Display module, for showing the multiple tasks item of the scheduled.
Further, the standby electric fittings information table and subsequent safeguard of the maintenance unit warning information table update Including increasing, rewriting, replacing update.
Another aspect of the present invention provides a kind of operating method of the maintenance program system of above-mentioned multifactor consideration, wherein logical The input module is crossed to the server incoming task item, the task items include organization, Task Initiation Date, task Close Date, the tasks leave time, unit address, electrical equipment maintenance project, required electric fittings, the server is to described Multiple tasks item carries out scheduling, which is characterized in that further comprises the steps:
A. to the tasks leave time of the task items, distance, electrical equipment maintenance project, required electric fittings and dimension Declaration form position alarm number scores respectively, obtains the fraction a of corresponding tasks leave time, the fraction b of distance, electrical equipment dimension The fraction c of guarantor's project, the fraction e of fraction d and maintenance unit the alarm number of required electric fittings, and by the power of each fraction item The total score u of task items described in re-computation;
B. according to the total score u of multiple task items, by being carried out from high to low to the multiple task items for the total score Scheduling;
C. the multiple task items of scheduled are sent to the mobile terminal.
Beneficial effects of the present invention:
By the systems and methods of the present invention, take into full account the situation of comprehensive maintenance company and electricity consumption enterprise, realize The automatic editing of maintenance task items solves the decision problem of maintenance task scheduling priority, and missing inspection, the flase drop for reducing maintenance task are general While rate, the work efficiency of maintenance company is improved, increases the satisfaction of client.
Description of the drawings
Fig. 1 is a kind of block diagram of the maintenance program system of multifactor consideration of one embodiment of the invention.
Fig. 2 is the maintenance scheduling grade form of one embodiment of the invention.
Fig. 3 is a kind of flow of the operating method of the maintenance program system of multifactor consideration of one embodiment of the invention Figure.
Specific embodiment
It hereinafter, will the present invention is described in detail in conjunction with the accompanying drawings and embodiments.Following embodiment is not to the present invention Limitation.Without departing from the spirit and scope of the invention, various changes and advantages that will be apparent to those skilled in the art all by It is included in the invention.
Fig. 1 is a kind of block diagram of the maintenance program system of multifactor consideration of an embodiment according to the present invention.The present invention The maintenance program system of multifactor consideration include mobile terminal 1 and server 2, mobile terminal 1 moved with server 2 by GSM Dynamic network establishes the link.
As shown in Figure 1, mobile terminal 1 includes receiving module 11 and display module 12.Although it is moved not shown in the application Other modules in terminal 1, but those skilled in the art are known, certainly comprising well known processor, input in the mobile terminal 1 The modules such as output module.
Receiving module 11 is used to receive the multiple tasks item for the scheduled that the server 2 is sent.
Display module 12 is used to show the multiple tasks item of the scheduled.
As shown in Figure 1, server 2 includes input module 21, processing module 22, sending module 23 and memory module 24.
Input module 21 is used for the 2 incoming task item of server, and the task items include organization, and task starts Date, job end day phase, tasks leave time, unit address, electrical equipment maintenance project, required electric fittings and and task The relevant information of item.
Mould 22 is handled to be used to carry out scheduling to multiple tasks item.
Specifically, processing module 22 further comprises arithmetic element 26 and schedule unit 26.
Arithmetic element 26 is used for the tasks leave time to the task items, distance, electrical equipment maintenance project, required electricity Gas accessory and maintenance unit alarm number score respectively, obtain the fraction a of corresponding tasks leave time, the fraction of distance B, the fraction c of electrical equipment maintenance project, the fraction e of fraction d and maintenance unit the alarm number of required electric fittings, and calculate The total score u of the task items:
U=α a+ β b+ χ c+ δ d+ ε e,
α is the weight of the tasks leave time, and β is the weight of the distance, and χ is the electrical equipment maintenance project Weight, δ be it is described needed for electric fittings weight, ε be the maintenance unit alert number weight, 0<α,β,χ,δ,ε<1 and α + β+χ+δ+ε=1
Specifically, as shown in Fig. 2, for one embodiment of the invention maintenance scheduling grade form, arithmetic element 26 is according to institute It states maintenance scheduling grade form to calculate the total score u of multiple tasks item, now equipped with n-th task items, be scored with maintenance scheduling Table is that foundation scores:
According to the tasks leave time of n-th task items, the tasks leave time of n-th task items comment for the first time Point, obtain corresponding fraction a;
According to the unit address of n-th task items, second is carried out to the distance of n-th task items and is scored, is corresponded to Fraction b;
According to the quantity of the electrical equipment maintenance project of n-th task items, to the electrical equipment maintenance item of n-th task items Mesh carries out third time scoring, obtains corresponding fraction c;
According to electric fittings needed for n-th task items and standby electric fittings information table, to the required electricity of n-th task items Gas accessory carries out the 4th scoring, obtains corresponding fraction d;
According to the organization and maintenance unit warning information table of n-th task items, to the maintenance unit of n-th task items Alarm number carries out the 5th scoring, obtains corresponding fraction e;
The calculation formula of a of n-th task items of summary, b, c, five gained scorings of d, e and task items total score:U=α A+ β b+ χ c+ δ d+ ε e can obtain the total score of n-th task items.
Wherein, α is the weight of the tasks leave time, and β is the weight of the distance, and χ is the electrical equipment maintenance The weight of project, δ be it is described needed for electric fittings weight, ε be the maintenance unit alert number weight, 0<α,β,χ,δ, ε<1 and alpha+beta+χ+δ+ε=1;Above-mentioned weight α, β, χ, the size of δ, ε determine by maintenance company according to business demand, and by inputting Module 21 is input in server 2, the foundation that the total score as task items calculates.
Wherein, obtained by the GIS-Geographic Information System that the distance is installed as server 2 calculates, specifically, passing through a task The unit address information of item, can obtain the distance between maintenance company and task items target unit in GIS-Geographic Information System.
Similarly, it can obtain the total score of (n+1)th task items.
Schedule unit 26 is used for the total score u according to multiple task items, by the total score from high to low to described more A task items carry out scheduling, specifically, for example according to bubbling method carry out the total score of a task items and the total score of another task items into Row comparison, and so on complete scheduling to multiple tasks item, scheduling order by total score arrangement from high to low.Wherein, task Gained total score is higher represents that corresponding task item is more urgent, and the relative importance value that task items needs perform is higher.
The maintenance scheduling grade form can be carried out according to the actual conditions of maintenance company by the input module 21 of server 2 Subsequently standards of grading are changed, using the scheduling foundation as server 2 to the multi-task item, the maintenance scheduling grade form is deposited It is stored in the memory module of server 2.
Sending module 23, for the multiple task items of scheduled to be sent to the mobile terminal 1, specifically, scheduling As soon as unit 26 often completes the scheduling of time task items, sending module 23 sends the data of the task items after a scheduling, reaches clothes The purpose of business device 2 and 1 synchronizing information of mobile terminal.
Memory module 24, for storing standby electric fittings information table, maintenance unit warning information table, maintenance scheduling scoring Table, the data message during the task items information and the server operation.Wherein, standby electric fittings letter Breath table is electrical for recording relevant informations, the standby such as the existing rear species and quantity for matching somebody with somebody electric fittings of maintenance company, storage location Accessory information table can be carried out by the input module 21 of server 2 it is subsequent safeguard update include increase, rewrite, replace update; Wherein, the maintenance unit warning information table is for recording, electricity consumption business unit title, the alarm number of electricity consumption enterprise, accuses The relevant informations such as alert content, maintenance unit warning information table can carry out subsequent maintenance more by the input module 21 of server 2 It is new to include increasing, rewrite, replace update.
Fig. 3 is a kind of stream of the operating method of the maintenance program system of multifactor consideration of an embodiment according to the present invention Cheng Tu.The step of the method for the present invention is described in detail below according to Fig. 3.
Input module 21 is to the 2 incoming task item of server, and the task items include organization, and task starts day Phase, job end day phase, tasks leave time, unit address, electrical equipment maintenance project, required electric fittings and and task items Relevant information (201).
Processing module 22 stores task items in a storage module, and carries out scheduling to multiple tasks item.Specifically include as Lower step:
Arithmetic element 25 is to the tasks leave time of the task items, distance, and electrical equipment maintenance project is required electrically to match somebody with somebody Part and maintenance unit alarm number score respectively, obtain fraction a, the fraction b of distance of corresponding tasks leave time, electricity The fraction c of gas equipment maintenance project, the fraction e of fraction d and maintenance unit the alarm number of required electric fittings, and by each point The total score u (202) of task items described in several weight calculations;
Schedule unit 26 is according to the total score u of multiple task items, by the total score from high to low to the multiple Business item carries out scheduling (203);
The multiple task items of scheduled are sent to the mobile terminal 1 (204) by sending module 23.
The receiving unit 11 of mobile terminal 1 receives the multiple tasks item for the scheduled that server 2 is sent, and maintenance staff can press The maintenance task items performed next time are determined according to the sortord of the multiple tasks item of scheduled, and then optimize maintenance plan.
By the systems and methods of the present invention, take into full account the situation of comprehensive maintenance company and electricity consumption enterprise, realize The automatic editing of maintenance task items solves the decision problem of maintenance task scheduling priority, and missing inspection, the flase drop for reducing maintenance task are general While rate, the work efficiency of maintenance company is improved, increases the satisfaction of client.
It is only presently preferred embodiments of the present invention in summary, is not used for limiting the practical range of the present invention.That is Fan Yiben The equivalent changes and modifications that the content of patent application the scope of the claims is made should all belong to the technology scope of the present invention.

Claims (3)

1. a kind of maintenance program system of multifactor consideration, which is characterized in that the system comprises:
Server and mobile terminal, the server are established the link with the mobile terminal by network;
The server includes:
Input module, for the server incoming task item, the task items include organization, Task Initiation Date, Job end day phase, tasks leave time, unit address, electrical equipment maintenance project, required electric fittings;
Processing module for carrying out scheduling to multiple tasks item, further comprises:
1) arithmetic element, for the tasks leave time to the task items, distance, electrical equipment maintenance project is required electrical Accessory and maintenance unit alarm number score respectively, obtain fraction a, the fraction b of distance of corresponding tasks leave time, The fraction c of electrical equipment maintenance project, the fraction e of fraction d and maintenance unit the alarm number of required electric fittings, and calculate institute State the total score u of task items:
U=α a+ β b+ χ c+ δ d+ ε e,
α is the weight of the tasks leave time, and β is the weight of the distance, and χ is the power of the electrical equipment maintenance project Weight, δ be it is described needed for electric fittings weight, ε be the maintenance unit alert number weight, 0<α,β,χ,δ,ε<1 and alpha+beta + χ+δ+ε=1;
2) schedule unit, for the total score u according to multiple task items, by the total score from high to low to the multiple Business item carries out scheduling;
Sending module, for the multiple tasks item of scheduled to be sent to the mobile terminal;
Memory module, for storing standby electric fittings information table, maintenance unit warning information table, the task items information and Data message during the server operation;
The mobile terminal includes:
Receiving module, for receiving the multiple tasks item for the scheduled that the server is sent;
Display module, for showing the multiple tasks item of the scheduled.
2. the maintenance program system of a kind of multifactor consideration according to claim 1, which is characterized in that the standby is electrical Accessory information table and the maintenance unit warning information table it is subsequent safeguard update includes increase, rewrite, replace update.
3. a kind of operating method of the maintenance program system of multifactor consideration according to claim 1 and 2, wherein passing through institute Input module is stated to the server incoming task item, the task items include organization, Task Initiation Date, and task terminates On the date, the tasks leave time, unit address, electrical equipment maintenance project, required electric fittings, the server is to the multiple Task items carry out scheduling, which is characterized in that further comprise the steps:
A. to the tasks leave time of the task items, distance, electrical equipment maintenance project, required electric fittings and maintenance list Position alarm number scores respectively, obtains the fraction a of corresponding tasks leave time, the fraction b of distance, electrical equipment maintenance item Purpose fraction c, the fraction e of fraction d and maintenance unit the alarm number of required electric fittings, and based on the weight of each fraction item Calculate the total score u of the task items;
B. according to the total score u of multiple task items, scheduling is carried out to the multiple task items from high to low by the total score;
C. the multiple task items of scheduled are sent to the mobile terminal.
CN201711500143.9A 2017-12-31 2017-12-31 The maintenance program system and method for multifactor consideration Pending CN108108907A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711500143.9A CN108108907A (en) 2017-12-31 2017-12-31 The maintenance program system and method for multifactor consideration

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711500143.9A CN108108907A (en) 2017-12-31 2017-12-31 The maintenance program system and method for multifactor consideration

Publications (1)

Publication Number Publication Date
CN108108907A true CN108108907A (en) 2018-06-01

Family

ID=62215553

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711500143.9A Pending CN108108907A (en) 2017-12-31 2017-12-31 The maintenance program system and method for multifactor consideration

Country Status (1)

Country Link
CN (1) CN108108907A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109597820A (en) * 2018-12-07 2019-04-09 万翼科技有限公司 Customer information synchronous method, device and computer readable storage medium
CN109712266A (en) * 2018-11-21 2019-05-03 斑马网络技术有限公司 Battery electricity consumption behavior evaluation method, apparatus, storage medium and electronic equipment
CN113066543A (en) * 2021-04-12 2021-07-02 北京药明津石医药科技有限公司 Clinical research coordinator scheduling method, device, computer equipment and storage medium
CN114971353A (en) * 2022-06-09 2022-08-30 安徽丰士通电子科技有限公司 Automatic maintenance system based on chip mounter

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104168318A (en) * 2014-08-18 2014-11-26 中国联合网络通信集团有限公司 Resource service system and resource distribution method thereof
CN106682743A (en) * 2016-12-15 2017-05-17 南京南瑞信息通信科技有限公司 Operation and maintenance work order scheduling management method and system in electric power telecommunication field

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104168318A (en) * 2014-08-18 2014-11-26 中国联合网络通信集团有限公司 Resource service system and resource distribution method thereof
CN106682743A (en) * 2016-12-15 2017-05-17 南京南瑞信息通信科技有限公司 Operation and maintenance work order scheduling management method and system in electric power telecommunication field

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109712266A (en) * 2018-11-21 2019-05-03 斑马网络技术有限公司 Battery electricity consumption behavior evaluation method, apparatus, storage medium and electronic equipment
CN109712266B (en) * 2018-11-21 2021-12-14 斑马网络技术有限公司 Storage battery electricity utilization behavior evaluation method and device, storage medium and electronic equipment
CN109597820A (en) * 2018-12-07 2019-04-09 万翼科技有限公司 Customer information synchronous method, device and computer readable storage medium
CN113066543A (en) * 2021-04-12 2021-07-02 北京药明津石医药科技有限公司 Clinical research coordinator scheduling method, device, computer equipment and storage medium
CN113066543B (en) * 2021-04-12 2022-04-19 上海药明津石医药科技有限公司 Clinical research coordinator scheduling method, device, computer equipment and storage medium
CN114971353A (en) * 2022-06-09 2022-08-30 安徽丰士通电子科技有限公司 Automatic maintenance system based on chip mounter

Similar Documents

Publication Publication Date Title
CN108108907A (en) The maintenance program system and method for multifactor consideration
CN106815709B (en) Service quick response center support system and method
CN106570778B (en) A kind of method that data integration based on big data is calculated with line loss analyzing
CN110782370A (en) Comprehensive operation and maintenance management platform for power dispatching data network
CN113298322B (en) Multi-dimensional optimized intelligent power work order dispatching method
CN104331770A (en) Intelligent management system of flexible production enterprise
CN108206587A (en) A kind of electricity consumption cruising inspection system and method
CN110852624A (en) Intelligent manufacturing management system facing enterprise execution layer and operation method thereof
Cheramin et al. Resilient NdFeB magnet recycling under the impacts of COVID-19 pandemic: Stochastic programming and Benders decomposition
US20210374632A1 (en) Supply chain forecasting system
CN108205709A (en) Maintenance task distribution system and method
CN108665283A (en) The recognition methods of hotel&#39;s house type price exception of OTA platforms and system
CN114819213A (en) Intelligent operation and maintenance management method and system for electric automobile public charging facility
CN110287228A (en) Implementation method based on dispatching of power netwoks domain equipment monitoring real-time data acquisition
CN113379391A (en) Work order processing method and device, electronic equipment and computer readable storage medium
CN105321083A (en) Large-area rapid household appliance maintenance network platform system and method
CN112633769A (en) Advanced plan scheduling system
JP5549952B2 (en) System and method for managing the life cycle of a batch in a production control system in real time
CN115330404A (en) System and method for electric power marketing inspection
Treuner et al. A survey of disruptions in aviation and aerospace supply chains and recommendations for increasing resilience
TWI354943B (en)
CN104850929A (en) MES for LED epitaxy and chip manufacture
CN110826941A (en) Intelligent pipe network system based on geographic information system
CN108564180A (en) A kind of maintenance program system and method
CN118339570A (en) System, apparatus and computer-implemented method for monitoring packages in transit through a logistics network

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20180601