CN108086352A - A kind of highway hard rock Steep Slope Embankment anchor rod foundation Anti-slide Pile Retaining Structure - Google Patents

A kind of highway hard rock Steep Slope Embankment anchor rod foundation Anti-slide Pile Retaining Structure Download PDF

Info

Publication number
CN108086352A
CN108086352A CN201810102513.1A CN201810102513A CN108086352A CN 108086352 A CN108086352 A CN 108086352A CN 201810102513 A CN201810102513 A CN 201810102513A CN 108086352 A CN108086352 A CN 108086352A
Authority
CN
China
Prior art keywords
pile
anchor rod
foundation
hard rock
friction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810102513.1A
Other languages
Chinese (zh)
Inventor
高立
字学强
李正波
王建富
侯云昌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yunnan New Innovation Traffic Construction Ltd By Share Ltd
Original Assignee
Yunnan New Innovation Traffic Construction Ltd By Share Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yunnan New Innovation Traffic Construction Ltd By Share Ltd filed Critical Yunnan New Innovation Traffic Construction Ltd By Share Ltd
Priority to CN201810102513.1A priority Critical patent/CN108086352A/en
Publication of CN108086352A publication Critical patent/CN108086352A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C3/00Foundations for pavings
    • E01C3/04Foundations produced by soil stabilisation
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • E02D29/0225Retaining or protecting walls comprising retention means in the backfill
    • E02D29/0233Retaining or protecting walls comprising retention means in the backfill the retention means being anchors
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • E02D29/0225Retaining or protecting walls comprising retention means in the backfill
    • E02D29/0241Retaining or protecting walls comprising retention means in the backfill the retention means being reinforced earth elements
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • E02D29/0258Retaining or protecting walls characterised by constructional features
    • E02D29/0275Retaining or protecting walls characterised by constructional features cast in situ
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/74Means for anchoring structural elements or bulkheads
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/74Means for anchoring structural elements or bulkheads
    • E02D5/80Ground anchors
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2200/00Geometrical or physical properties
    • E02D2200/16Shapes
    • E02D2200/1628Shapes rectangular
    • E02D2200/1635Shapes rectangular made from single element
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0004Synthetics
    • E02D2300/0006Plastics
    • E02D2300/0007PVC
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0026Metals
    • E02D2300/0029Steel; Iron
    • E02D2300/0034Steel; Iron in wire form
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0084Geogrids

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Architecture (AREA)
  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Abstract

The invention belongs to highway subgrade construction technical fields, a kind of highway hard rock Steep Slope Embankment anchor rod foundation Anti-slide Pile Retaining Structure are specifically disclosed, including friction pile cantilever segment, antiskid pile foundation, foundation anchor system, substrate footing foundation backfill soil body TGXG system after stake.The cantilever segment is designed as rectangle and the rectangle with the edge of a wing as the case may be.The foundation anchor system is divided into horizontal anchor rod system and vertical anchor rod system, using the HRB400 reinforcement fabrications of a diameter of Φ 32.Present invention decreases difficulty of construction, the influences for saving project cost, shortening the duration, reducing Engineering.

Description

A kind of highway hard rock Steep Slope Embankment anchor rod foundation Anti-slide Pile Retaining Structure
Technical field
The present invention relates to highway Steep Slope Embankment supporting construction more particularly to highway hard rock Steep Slope Embankment anchor rod foundation antiskids Stake, belongs to highway subgrade construction technical field.
Background technology
In recent years fast-developing highway engineering construction, makes Southwestern China mountain highway net progressively tend to be perfect, mountain highway Construction should avoid high embankment as far as possible, first, meet using reducing project cost on the premise of function, but high embankment It is serious to environmental disruption, especially it would become hard to recover behind the region of ecological environment frailty, destruction.During highway construction, Mostly reduce the coverage of high embankment with retaining wall combining form using stake, the form of retaining wall mainly has pile plate wall, gravity Formula retaining wall, soil nail wall, the form of stake mainly have a rectangular section artificial digging pile, circular cross-section cast-in-situ bored pile, retaining wall with Anchor pile is combined, and can play good closing slope effect.The anchorage depth of anchor pile should according to cantilever segment length, thrust size and Stake sectional dimension determines that the anchoring section of traditional anchor pile must be designed into certain depth and just can guarantee soil body stability after stake. But when anchoring section is located in hard rock stratum, the excavation difficulty of anchoring section will greatly increase, especially the hard of good integrity Rock, long construction period directly contribute the rise of engineering project overhead cost.The general lateral slope of ground in hard rock location is very steep, excavation Rock And Soil outward transport is difficult, is mostly arbitrarily abandoned the hillside near stake mouth, exerted a certain influence to environment.It is steep to be limited to hard rock Slope embankment friction pile difficulty of construction is big, project cost is high and is influenced caused by environment big so that mountain highway high embankment is set Meter and construction are obstructed again and again, and often high embankment is also the controlling paragraph of highway subgrade construction, it can be seen that, hard rock The design form of section friction pile anchoring section becomes the research emphasis and difficult point of Subgrade in Mountain Area engineering field.
In consideration of it, domestic and foreign scholars have carried out substantial amounts of research work regarding to the issue above, how to meet design requirement In the range of shorten anchoring depth become research emphasis.202787236 U of patent CN disclose a kind of new friction pile, It is mainly characterized in that the bottom of friction pile extends vertically, forms horizontal anchoring section, a sectional dimension can be reduced, improve friction pile Can, but transversary is even more to be difficult to excavate in hard rock, and the new friction pile disclosed in this patent is only applicable to soil-slope. 107447777 A of patent CN disclose point anchor anti-sliding piled barricade in a kind of hole, and the form of anchor cable is added by cantilever segment, can be contracted Short anchoring section depth, but anchoring section still needs certain depth could meet stability requirement, especially in steep slope subgrade Section, in order to which Rock And Soil on the outside of stake is made to reach certain thickness, it is necessary to increase the setting of anchoring section.
In conclusion to avoid the high embankment location embankment welding of hard rock, it is to receive well to set retaining wall between piles Domatic formula, but the excavation of friction pile anchoring section is answered that difficulty of construction is big, project cost is high, therefore, how rationally to shorten anchoring section It is arranged to for design challenges urgently to be resolved hurrily.
The content of the invention
Goal of the invention:Excavate that difficulty is big, project cost is high not during to overcome existing friction pile anchoring section in hard rock Foot improves the design form of friction pile, and the present invention provides highway hard rock Steep Slope Embankment anchor rod foundation anti-slide pile structure, anchorings Section is substantially shorter, form is simple, short construction period, effect on environment are small, can efficiently solve highway hard rock abrupt slope road The problem of dike friction pile stability and big difficulty of construction is highway engineering field hard rock Steep Slope Embankment support form and friction pile The innovation of design form.
Technical solution:To achieve the above object, technical scheme is as follows:
Highway hard rock Steep Slope Embankment anchor rod foundation anti-slide pile structure of the present invention, including:Friction pile cantilever segment, friction pile Basis, foundation anchor system, substrate footing foundation backfill soil body TGXG system after stake.Cantilever segment is as the case may be It is designed as rectangle(Suitable for gravity retaining wall between stake and inter-pile soil nail wall)With the rectangle with the edge of a wing(Suitable for pile plate wall).It is anti- Sliding pile basis should synchronously be poured with pile body, and the concrete grade of use is identical with pile body, and basis and pile concrete label be not low In C30.Foundation anchor system is divided into horizontal anchor rod system and vertical anchor rod system, using the HRB400 reinforcing bar systems of a diameter of Φ 32 Make.Footing foundation palpus hand excavation, ensures the smooth of step surface as far as possible.Soil body TGXG system is backfilled after stake using high Density PVC direction earthwork grille, breadth are not less than 5.0m, 50~80mm of mesh diameter.
The construction method of highway hard rock Steep Slope Embankment anchor rod foundation friction pile of the present invention, concretely comprises the following steps: 1. surveying and locating.According to the definite friction pile accurate location in design coordinate scene;2. the table of friction pile construction area is removed in levelling of the land Layer soil according to wide, the high excavation slope platform of design step, flattens antiskid pile foundation top surface platform, indicates four of friction pile Corner location is in order to pile foundation of accurately constructing.The horizontal distance of basic top surface platform outer edge and line of slope is not less than 2.0m, Chipping is answered at platform outer edge to slope surface, and outside 4% weathering is set;3. chisel sets basis.Manually using pneumatic pick or other are small Type rock drilling machine excavation foundation forbids explosion, the in vivo stepped forms of foundation excavation Cheng Xiangshan, width height ratio of steps 1.0:1.0. Footing step horizontal width 0.5m, afterbody berm width are not less than 1.0m, and platform classification must not drop below 3 grades;4. it constructs Vertical anchor rod system.According to friction pile arrangement of reinforcement, main reinforcement branch position is determined, corresponding main reinforcement position applies vertical armature boring, Boring direction is vertical, drillable length 4.15m.It constructs in time after pore-forming anchor pole, anchor pole exposure length is not less than 2.0m, in order to It is welded with pile body main reinforcement;5. the horizontal anchoring-bolt system of construction.The horizontal vertical spacing 1.0m of anchor pole, lateral arrangement two arrange, drillable length 12.15m, anchor pole direction and horizontal direction angle are 15 °.After pile body main reinforcement is welded, by horizontal termination point of anchor rod and pile body main reinforcement Welding;6. molding and casting concrete.According to pile body sectional dimension molding, concrete grade is not less than C30, and pile body must with basis Palpus one-time-concreting shaping, forbids to form horizontal construction joint, such as be poured because construction condition must be segmented, horizontal in two-step pouring The short muscle of cloth is reinforced at interface;7. breast boards is hung after pile strength reaches the 80% of design strength and backfills the soil body after wall, Backfill soil body wide bed TGXG, spacing 0.6m.
Highway hard rock Steep Slope Embankment anchor rod foundation friction pile of the present invention, its main feature is that:It is replaced with anchor rod foundation anti- Sliding pile anchoring section, anchor rod foundation horizontal cross section dimension are determined according to friction pile sectional dimension.Basis passes through horizontal direction anchor pole system System and vertical direction anchor rod system increase bending resistance, anti-pull-out property.Hard rock base surface chisel is set as inside stepped form, to increase The anti-slipping property energy of strong antiskid pile foundation.Laterally, vertical termination point of anchor rod and pile body main reinforcement are welded, so that pile body after casting concrete One is formed with massif.
The beneficial effects of the invention are as follows:1. reducing difficulty of construction, stake holes is excavated in hard rock location must use explosion, difficult To control construction quality, and engineering risk is higher.The present invention only needs artificial chisel to set friction pile basic platform, reduces construction Difficulty and risk are more advantageous to control construction quality;2. saving project cost, intensity of many hard rocks itself is high in nature It is traditional to cause economic waste with excavating stake holes in hard rock in general concrete strength.The present invention makes full use of hard Pile body and hard rock mass are linked as entirety by anchor pole, save project cost by rock condition;3. the duration is shortened, since chisel is set Friction pile square foundation amount is small, is not influenced between stake and stake, and excavation by troughs is not required, and shortens the duration, while also saves engineering Indirect expense;4. reducing the influence of Engineering, the rock mass side's amount excavated needed for the present invention is small, avoid abandon quarrel huddle unrest Phenomenon is put, influence of the engineering to natural environment is reduced from source.
Description of the drawings
Fig. 1 is the structural diagram of the present invention.
Fig. 2 excavates schematic diagram for hard rock slope.
Fig. 3 is friction pile foundation excavation schematic diagram.
Vertical and horizontal anchor pole schematic diagram based on Fig. 4.
Schematic diagram after the completion of Fig. 5 pours for pile body and basis.
Fig. 6 is hanging plate and backfills soil body schematic diagram after wall.
Figure label:1 friction pile cantilever segment, 2 antiskid pile foundation top surface platforms, 3 antiskid pile foundations, 4 antiskid pile foundations Plinth step, 5 vertical anchor rod systems, 6 horizontal anchor rod systems, 7 hard rock slope excavation lines, 8 TGXG systems, 9 friction piles Cantilever segment main reinforcement, 10 hillside, 11 breast boards.
Specific embodiment
Embodiment 1
Highway hard rock Steep Slope Embankment anchor rod foundation Anti-slide Pile Retaining Structure, including:After excavation slope step 7, chisel sets friction pile Basic top surface platform 2.After determining four corner locations of friction pile, artificial chisel sets friction pile footing step 4.Construction anchor rod system, Anchor rod system includes vertical anchor rod system 5 and horizontal anchor rod system 6.Antiskid pile foundation 3 and friction pile cantilever segment 1 are poured, treats stake When body intensity reaches the 80% of design load, hang breast boards and backfill the soil body after stake, while be laid with TGXG system 8.
Embodiment 2
The construction method of highway hard rock Steep Slope Embankment anchor rod foundation friction pile, concretely comprises the following steps:1. surveying and locating.According to setting Count the definite friction pile accurate location in coordinate scene;2. the topsoil of friction pile construction area is removed in levelling of the land, according to design step Wide, high excavation slope platform, flatten antiskid pile foundation top surface platform, indicate four corner locations of friction pile in order to accurate Construction pile foundation.The horizontal distance of basic top surface platform outer edge and line of slope is not less than 2.0m, at platform outer edge to slope surface Chipping is answered, and outside 4% weathering is set;3. chisel sets basis.Base is manually excavated using pneumatic pick or other gadding machine devices Plinth forbids explosion, the in vivo stepped forms of foundation excavation Cheng Xiangshan, width height ratio of steps 1.0:1.0.Footing step horizontal width 0.5m, afterbody berm width are not less than 1.0m, and platform classification must not drop below 3 grades;4. vertical anchor rod system of constructing.According to Friction pile arrangement of reinforcement determines main reinforcement branch position, and corresponding main reinforcement position applies vertical armature boring, and boring direction is vertical, is bored Hole length 4.15m.It constructs in time after pore-forming anchor pole, anchor pole exposure length is not less than 2.0m, in order to be welded with pile body main reinforcement;⑤ The horizontal anchoring-bolt system of construction.The horizontal vertical spacing 1.0m of anchor pole, lateral arrangement two arrange, drillable length 12.15m, anchor pole direction with Horizontal direction angle is 15 °.After pile body main reinforcement is welded, horizontal termination point of anchor rod and pile body main reinforcement are welded;6. molding simultaneously pours Concrete.According to pile body sectional dimension molding, concrete grade is not less than C30, and pile body is molded with the necessary one-time-concreting in basis, sternly Taboo form horizontal construction joint, such as poured because construction condition must be segmented, at the horizontal interface of two-step pouring the short muscle of cloth into Row is reinforced;7. breast boards is hung after pile strength reaches the 80% of design strength and backfills the soil body after wall, backfill soil body wide bed geotechnique Grid, spacing 0.6m.
Embodiment 3
Present invention reinforced earth back-pressure closing supporting construction as shown in Figure 1, after hard rock slope excavation line 7, chisel sets antiskid pile foundation Plinth top surface platform 2.After determining four corner locations of friction pile, artificial chisel sets friction pile footing step 4.Construction anchor rod system, anchor Lever system includes vertical anchor rod system 5 and horizontal anchor rod system 6.The anchoring section of traditional friction pile is replaced with anchor rod foundation, it is ensured that The excavation of anchoring section is reduced while antiskid stake body is stablized, difficulty of construction is reduced, saves project cost, while also reduce Destruction to ecological environment.Pile body and basis 1 are poured, when pile strength reaches the 80% of design load, breast boards is hung and backfills The soil body after stake, while it is laid with TGXG system 8.TGXG reduces the soil pressure for directly acting on pile body, is conducive to carry The stability of high supporting construction.
Certain mountainous area highway roadbed is located at Steep Slope Embankment location, lateral slope of ground 1:0.75, this section of path length is 219m, Stratum is limestone, and rate of decay is weaker, and slope table coating is thin, many places basement rock exposure.If with bridge or tunnel by the way that engineering is made Valency is high, and the construction period is long.Designing scheme is with roadbed semi-filling and semi-excavating by setting pile plate wall supporting and retaining system on the outside of roadbed.Anchor pile is using this Invention anchor rod foundation Anti-slide Pile Retaining Structure, is as follows:
(1)Surveying and locating.According to the definite friction pile accurate location in design coordinate scene;
(2)Levelling of the land.The topsoil of friction pile construction area is removed, the massif side slope within embankment is excavated according to design requirement, Platform wide 2m, high 1.3m flatten antiskid pile foundation top surface platform, and stake sectional dimension is 1.75m × 2.5m, indicates the four of friction pile A corner location is in order to pile foundation of accurately constructing.The horizontal distance of basic top surface platform outer edge and line of slope is not less than 2.0m, chipping at platform outer edge to slope surface, and outside 4% weathering is set;
(3)Chisel sets basis.Manually using pneumatic pick excavation foundation, the in vivo stepped forms of foundation excavation Cheng Xiangshan, width height ratio of steps For 1.0:1.0.Footing step horizontal width 0.5m, afterbody berm width are 1.25m, and platform is divided into 3 grades;
(4)It constructs vertical anchor rod system.According to friction pile arrangement of reinforcement, main reinforcement branch position is determined, corresponding main reinforcement position applies perpendicular To armature boring, boring direction is vertical, drillable length 4.15m.It constructs in time after pore-forming anchor pole, anchor pole exposure length is not less than 2.0m, in order to be welded with pile body main reinforcement;
(5)The horizontal anchoring-bolt system of construction.The horizontal vertical spacing 1.0m of anchor pole, lateral arrangement two arrange, drillable length 12.15m, anchor pole Direction and horizontal direction angle are 15 °.After pile body main reinforcement is bound, horizontal termination point of anchor rod and pile body main reinforcement are welded;
(6)Molding and casting concrete.According to pile body sectional dimension molding, concrete grade C35, pile body is once poured with basis Build up type;
(7)Breast boards is hung after pile strength reaches the 80% of design strength and backfills the soil body after wall, backfills soil body wide bed geotechnique's lattice Grid, spacing 0.6m.Thus the construction of anchor rod foundation friction pile retaining structure is completed.
Embodiment 4
A kind of highway hard rock Steep Slope Embankment anchor rod foundation Anti-slide Pile Retaining Structure, including friction pile cantilever segment 1, antiskid pile foundation Top surface platform 2, antiskid pile foundation 3, friction pile footing step 4, vertical anchor rod system 5, horizontal anchor rod system 6, TGXG system System 8, friction pile cantilever segment main reinforcement 9, hillside 10 and breast boards 11 are provided with friction pile footing step 4 on the hillside 10, described Antiskid pile foundation 3 is provided on friction pile footing step 4, the antiskid pile foundation 3 is provided with antiskid pile foundation top surface platform 2, Friction pile cantilever segment 1 is provided on the antiskid pile foundation top surface platform 2, is provided in the hillside 10 and antiskid pile foundation 3 Vertical anchor rod system 5, the hillside 10 and 3 intersection of antiskid pile foundation are provided with horizontal anchor rod system 6;
The friction pile cantilever segment 1 is internally provided with breast boards 11 and friction pile cantilever segment main reinforcement 9;
The vertical anchor rod system 5 and horizontal anchor rod system 6 are fixedly connected with friction pile cantilever segment main reinforcement 9;
The soil body is backfilled between the friction pile cantilever segment 1 and hillside 10 and is laid with TGXG system 8.
Further, the antiskid pile foundation 3 is synchronously poured with pile body, and the concrete grade of use is identical with pile body, basis It is not less than C30 with pile concrete label.
Further, the vertical anchor rod system 5 and horizontal anchor rod system 6 use the HRB400 reinforcing bar systems of a diameter of Φ 32 Make, vertical rock-bolt length 4m, exposure 2m, horizontal anchor pole 12m, exposure to pile body main reinforcement position.
Further, the vertical anchor rod system 5 and horizontal anchor rod system 6 are welded with friction pile cantilever segment main reinforcement 9.
Further, the friction pile footing step 4 uses hand excavation, ensures the smooth of step surface, foundation excavation into The in vivo stepped form in mountain, width height ratio of steps 1.0:1.0, footing step horizontal width 0.5m, afterbody berm width is not Less than 1.0m, platform classification must not drop below 3 grades.
Further, the TGXG system 8 uses high density polyvinyl-chloride direction earthwork grille, and breadth is not less than 5.0m, 50~80mm of mesh diameter.
Further, the friction pile cantilever segment 1 is rectangle or the rectangle with the edge of a wing.

Claims (7)

1. a kind of highway hard rock Steep Slope Embankment anchor rod foundation Anti-slide Pile Retaining Structure, which is characterized in that including friction pile cantilever Section(1), antiskid pile foundation top surface platform(2), antiskid pile foundation(3), friction pile footing step(4), vertical anchor rod system(5)、 Horizontal anchor rod system(6), TGXG system(8), friction pile cantilever segment main reinforcement(9), hillside(10)And breast boards(11), it is described Hillside(10)On be provided with friction pile footing step(4), the friction pile footing step(4)On be provided with antiskid pile foundation(3), The antiskid pile foundation(3)It is provided with antiskid pile foundation top surface platform(2), the antiskid pile foundation top surface platform(2)Upper setting There is friction pile cantilever segment(1), the hillside(10)With antiskid pile foundation(3)On be provided with vertical anchor rod system(5), the hillside (10)With antiskid pile foundation(3)Intersection is provided with horizontal anchor rod system(6);
The friction pile cantilever segment(1)It is internally provided with breast boards(11)With friction pile cantilever segment main reinforcement(9);
The vertical anchor rod system(5)With horizontal anchor rod system(6)With friction pile cantilever segment main reinforcement(9)It is fixedly connected;
The friction pile cantilever segment(1)And hillside(10)Between backfill the soil body and be laid with TGXG system(8).
2. highway hard rock Steep Slope Embankment anchor rod foundation Anti-slide Pile Retaining Structure according to claim 1, which is characterized in that The antiskid pile foundation(3)It is synchronously poured with pile body, the concrete grade of use is identical with pile body, basis and pile concrete mark Number be not less than C30.
3. highway hard rock Steep Slope Embankment anchor rod foundation Anti-slide Pile Retaining Structure according to claim 1, which is characterized in that The vertical anchor rod system(5)With horizontal anchor rod system(6)Using the HRB400 reinforcement fabrications of a diameter of Φ 32, vertical anchor pole is long Spend 4m, exposure 2m, horizontal anchor pole 12m, exposure to pile body main reinforcement position.
4. highway hard rock Steep Slope Embankment anchor rod foundation Anti-slide Pile Retaining Structure according to claim 1, which is characterized in that The vertical anchor rod system(5)With horizontal anchor rod system(6)With friction pile cantilever segment main reinforcement(9)Welding.
5. highway hard rock Steep Slope Embankment anchor rod foundation Anti-slide Pile Retaining Structure according to claim 1, which is characterized in that The friction pile footing step(4)Using hand excavation, ensure the smooth of step surface, the in vivo steps of foundation excavation Cheng Xiangshan Formula, width height ratio of steps 1.0:1.0, footing step horizontal width 0.5m, afterbody berm width are not less than 1.0m, platform point Grade must not drop below 3 grades.
6. highway hard rock Steep Slope Embankment anchor rod foundation Anti-slide Pile Retaining Structure according to claim 1, which is characterized in that The TGXG system(8)Using high density polyvinyl-chloride direction earthwork grille, breadth is not less than 5.0m, and mesh diameter 50~ 80mm。
7. highway hard rock Steep Slope Embankment anchor rod foundation Anti-slide Pile Retaining Structure according to claim 1, which is characterized in that The friction pile cantilever segment(1)Rectangle for rectangle or with the edge of a wing.
CN201810102513.1A 2018-02-01 2018-02-01 A kind of highway hard rock Steep Slope Embankment anchor rod foundation Anti-slide Pile Retaining Structure Pending CN108086352A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810102513.1A CN108086352A (en) 2018-02-01 2018-02-01 A kind of highway hard rock Steep Slope Embankment anchor rod foundation Anti-slide Pile Retaining Structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810102513.1A CN108086352A (en) 2018-02-01 2018-02-01 A kind of highway hard rock Steep Slope Embankment anchor rod foundation Anti-slide Pile Retaining Structure

Publications (1)

Publication Number Publication Date
CN108086352A true CN108086352A (en) 2018-05-29

Family

ID=62193696

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810102513.1A Pending CN108086352A (en) 2018-02-01 2018-02-01 A kind of highway hard rock Steep Slope Embankment anchor rod foundation Anti-slide Pile Retaining Structure

Country Status (1)

Country Link
CN (1) CN108086352A (en)

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108660866A (en) * 2018-06-10 2018-10-16 中铁二院工程集团有限责任公司 A kind of talus slide area high-speed railway resistant slide deformation subgrade strengthening structure
CN109024324A (en) * 2018-08-22 2018-12-18 长江勘测规划设计研究有限责任公司 Abrupt slope ladder culvert and construction method for pipeline free removal and protection
CN109680583A (en) * 2019-02-21 2019-04-26 中国电建集团贵阳勘测设计研究院有限公司 Processing method for road shoulder wall of steep rock road section
CN110195388A (en) * 2019-06-25 2019-09-03 四川省公路规划勘察设计研究院有限公司 Overhang widened structure Bang Shan highway and its construction method
CN110205889A (en) * 2019-06-11 2019-09-06 兰州铁道设计院有限公司 The method that the wide transformation of existing line base side is carried out using Combined piling slab-wall structure
CN110412240A (en) * 2019-05-14 2019-11-05 华北理工大学 Obturation and the three-dimensional analog simulation experimental rig of country rock interaction rule and method
CN111235970A (en) * 2020-03-17 2020-06-05 中铁二院工程集团有限责任公司 Prestressed pile slab wall filled embankment structure, embankment system and construction method
CN111287041A (en) * 2020-02-24 2020-06-16 河海大学 Novel soil retaining structure in limited space and construction process thereof
CN111749288A (en) * 2020-07-31 2020-10-09 安徽省交通建设股份有限公司 Load-reducing heightening structure of existing retaining wall and construction method thereof
CN112144548A (en) * 2020-08-29 2020-12-29 兰州理工大学 Semi-embedded multifunctional frame supporting structure and construction method thereof
CN114215961A (en) * 2021-12-13 2022-03-22 中铁西北科学研究院有限公司 Construction method suitable for pipeline engineering supporting structure in landslide area
CN115305977A (en) * 2022-07-01 2022-11-08 中冀建勘集团有限公司 Foundation reinforcement method for cliff-attached building
CN115897318A (en) * 2022-09-30 2023-04-04 中国电建集团贵州电力设计研究院有限公司 Ecological restoration method for partial collapse of semi-excavated and semi-filled road

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101148882A (en) * 2007-10-29 2008-03-26 中铁二院工程集团有限责任公司 Stable excavating method for cracked weak rock road cutting high slope
CN201125354Y (en) * 2007-11-23 2008-10-01 中铁二院工程集团有限责任公司 Steep hill road bed branch block reinforced structure
CN102352590A (en) * 2011-07-27 2012-02-15 河南省交通规划勘察设计院有限责任公司 Method for splicing highfill roadbed by adopting pile-sheet retaining wall
CN203296038U (en) * 2013-06-05 2013-11-20 中铁二院重庆勘察设计研究院有限责任公司 High embankment chair-type sheet-pile retaining wall structure
CN103806347A (en) * 2014-03-11 2014-05-21 四川省交通运输厅交通勘察设计研究院 Lateral pile-plank structure suitable for rocky abrupt-slope embankment
KR20140078395A (en) * 2012-12-17 2014-06-25 한국철도기술연구원 Anchored retaining wall of gravity block type, and constructing method for the same
CN205712170U (en) * 2016-06-22 2016-11-23 中铁二院工程集团有限责任公司 A kind of stake plate type retaining wall
CN106703050A (en) * 2016-11-30 2017-05-24 中铁二院昆明勘察设计研究院有限责任公司 Expansive soil road cutting side slope reinforced soil back-pressure seepage-preventive supporting structure and construction method thereof
CN106836244A (en) * 2017-01-17 2017-06-13 浙江工业大学 Method for protecting steep slope roadbed by combining anti-slide piles and gabion high retaining wall
CN207987960U (en) * 2018-02-01 2018-10-19 云南新创新交通建设股份有限公司 A kind of highway hard rock Steep Slope Embankment anchor rod foundation Anti-slide Pile Retaining Structure

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101148882A (en) * 2007-10-29 2008-03-26 中铁二院工程集团有限责任公司 Stable excavating method for cracked weak rock road cutting high slope
CN201125354Y (en) * 2007-11-23 2008-10-01 中铁二院工程集团有限责任公司 Steep hill road bed branch block reinforced structure
CN102352590A (en) * 2011-07-27 2012-02-15 河南省交通规划勘察设计院有限责任公司 Method for splicing highfill roadbed by adopting pile-sheet retaining wall
KR20140078395A (en) * 2012-12-17 2014-06-25 한국철도기술연구원 Anchored retaining wall of gravity block type, and constructing method for the same
CN203296038U (en) * 2013-06-05 2013-11-20 中铁二院重庆勘察设计研究院有限责任公司 High embankment chair-type sheet-pile retaining wall structure
CN103806347A (en) * 2014-03-11 2014-05-21 四川省交通运输厅交通勘察设计研究院 Lateral pile-plank structure suitable for rocky abrupt-slope embankment
CN205712170U (en) * 2016-06-22 2016-11-23 中铁二院工程集团有限责任公司 A kind of stake plate type retaining wall
CN106703050A (en) * 2016-11-30 2017-05-24 中铁二院昆明勘察设计研究院有限责任公司 Expansive soil road cutting side slope reinforced soil back-pressure seepage-preventive supporting structure and construction method thereof
CN106836244A (en) * 2017-01-17 2017-06-13 浙江工业大学 Method for protecting steep slope roadbed by combining anti-slide piles and gabion high retaining wall
CN207987960U (en) * 2018-02-01 2018-10-19 云南新创新交通建设股份有限公司 A kind of highway hard rock Steep Slope Embankment anchor rod foundation Anti-slide Pile Retaining Structure

Cited By (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108660866A (en) * 2018-06-10 2018-10-16 中铁二院工程集团有限责任公司 A kind of talus slide area high-speed railway resistant slide deformation subgrade strengthening structure
CN108660866B (en) * 2018-06-10 2024-01-05 中铁二院工程集团有限责任公司 Anti-slip deformation roadbed reinforcing structure of high-speed railway in rock mass landslide area
CN109024324B (en) * 2018-08-22 2023-10-24 长江勘测规划设计研究有限责任公司 Steep slope ladder culvert for dismantling-free and protection of pipeline and construction method
CN109024324A (en) * 2018-08-22 2018-12-18 长江勘测规划设计研究有限责任公司 Abrupt slope ladder culvert and construction method for pipeline free removal and protection
CN109680583A (en) * 2019-02-21 2019-04-26 中国电建集团贵阳勘测设计研究院有限公司 Processing method for road shoulder wall of steep rock road section
CN110412240A (en) * 2019-05-14 2019-11-05 华北理工大学 Obturation and the three-dimensional analog simulation experimental rig of country rock interaction rule and method
CN110205889A (en) * 2019-06-11 2019-09-06 兰州铁道设计院有限公司 The method that the wide transformation of existing line base side is carried out using Combined piling slab-wall structure
CN110205889B (en) * 2019-06-11 2021-03-02 兰州铁道设计院有限公司 Method for carrying out existing line roadbed slope width transformation by adopting combined pile slab wall structure
CN110195388A (en) * 2019-06-25 2019-09-03 四川省公路规划勘察设计研究院有限公司 Overhang widened structure Bang Shan highway and its construction method
CN111287041A (en) * 2020-02-24 2020-06-16 河海大学 Novel soil retaining structure in limited space and construction process thereof
CN111235970A (en) * 2020-03-17 2020-06-05 中铁二院工程集团有限责任公司 Prestressed pile slab wall filled embankment structure, embankment system and construction method
CN111749288A (en) * 2020-07-31 2020-10-09 安徽省交通建设股份有限公司 Load-reducing heightening structure of existing retaining wall and construction method thereof
CN112144548A (en) * 2020-08-29 2020-12-29 兰州理工大学 Semi-embedded multifunctional frame supporting structure and construction method thereof
CN114215961A (en) * 2021-12-13 2022-03-22 中铁西北科学研究院有限公司 Construction method suitable for pipeline engineering supporting structure in landslide area
CN114215961B (en) * 2021-12-13 2023-10-27 中铁西北科学研究院有限公司 Construction method suitable for landslide area pipeline engineering supporting structure
CN115305977A (en) * 2022-07-01 2022-11-08 中冀建勘集团有限公司 Foundation reinforcement method for cliff-attached building
CN115305977B (en) * 2022-07-01 2024-06-11 中冀建勘集团有限公司 Foundation reinforcement method for cliff building
CN115897318A (en) * 2022-09-30 2023-04-04 中国电建集团贵州电力设计研究院有限公司 Ecological restoration method for partial collapse of semi-excavated and semi-filled road

Similar Documents

Publication Publication Date Title
CN108086352A (en) A kind of highway hard rock Steep Slope Embankment anchor rod foundation Anti-slide Pile Retaining Structure
CN207987960U (en) A kind of highway hard rock Steep Slope Embankment anchor rod foundation Anti-slide Pile Retaining Structure
CN105239586B (en) Method for supporting foundation pit by adopting support structure
CN207003499U (en) A kind of anti-floating lifting device of underground tunnel upper excavation of foundation pit
CN206956742U (en) High precipitous rock roadbed side slope repair system
CN206308569U (en) It is a kind of to reinforce the road structure for punishing the solution cavity that underlies
CN109441456A (en) A kind of the tunnel structure and its construction method of weakness Facility-sliding strata
CN107503362A (en) A kind of compound antiskid piling wall retaining structure and construction method suitable for reservoir stability
CN109208545B (en) Construction method of artificial landscape overflow dam with energy dissipation effect
CN109750571A (en) A kind of road landslide emergency and permanent supporting and retaining system integral structure and construction method
CN113174958A (en) Construction method for foundation pit of adjacent road under poor ground condition
CN207211165U (en) A kind of compound antiskid piling wall retaining structure suitable for reservoir stability
CN108914954A (en) Slope support method of the pre support in conjunction with permanent support
CN106013178B (en) A kind of placement method of shallow buried type Karst surface collapse
CN102817298B (en) Construction method on frozen soil
CN109898556A (en) A kind of underground pipe gallery structure and sunk type construction method
CN204435407U (en) A kind of batter post group anchor formula rock foundation
CN113832991A (en) Reverse construction method of pile plate wall
CN111021378A (en) Highway subgrade slope broken line type anchoring pile retaining structure and construction method thereof
CN209195412U (en) A kind of tunnel structure suitable for weak Facility-sliding strata
CN110331735A (en) A kind of tower crane mounting structure for coastal region soft layer
CN202925538U (en) Rammer constructed on frozen soil
CN205382482U (en) Bored concrete pile structure with it spouts stake soon to add core enlarged footing
CN211773854U (en) Soil retaining structure permeates water with soil nail
CN107447794A (en) The anti-floating of excavation pit plays construction method in a kind of subway protection region

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination