CN108061491A - A kind of Pile Diameter is the bridge cylinder pile foundation blasting method of 1.4-1.6m - Google Patents

A kind of Pile Diameter is the bridge cylinder pile foundation blasting method of 1.4-1.6m Download PDF

Info

Publication number
CN108061491A
CN108061491A CN201711319184.8A CN201711319184A CN108061491A CN 108061491 A CN108061491 A CN 108061491A CN 201711319184 A CN201711319184 A CN 201711319184A CN 108061491 A CN108061491 A CN 108061491A
Authority
CN
China
Prior art keywords
hole
pile foundation
periphery
blasthole
keyhole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201711319184.8A
Other languages
Chinese (zh)
Inventor
周晨
黄永亮
邢海龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
No 2 Engineering Co Ltd of CCCC First Highway Engineering Co Ltd
Original Assignee
No 2 Engineering Co Ltd of CCCC First Highway Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by No 2 Engineering Co Ltd of CCCC First Highway Engineering Co Ltd filed Critical No 2 Engineering Co Ltd of CCCC First Highway Engineering Co Ltd
Priority to CN201711319184.8A priority Critical patent/CN108061491A/en
Publication of CN108061491A publication Critical patent/CN108061491A/en
Pending legal-status Critical Current

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F42AMMUNITION; BLASTING
    • F42DBLASTING
    • F42D1/00Blasting methods or apparatus, e.g. loading or tamping

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The present invention relates to the bridge cylinder pile foundation blasting methods that a kind of Pile Diameter is 1.4 1.6m, step is drilling, blasting charge, block blasthole mouth, detonation, boring method is to arrange a hollow hole of centre vertically along cylinder pile foundation center line, centered on cylinder pile foundation center line, blasthole inner ring is formed by radius of 0.13 0.17m, blasthole mesosphere is formed by radius of 0.33 0.37m, blasthole outer ring is formed by radius of 0.63 0.67m, 4 keyholes arranged vertically are evenly distributed on blasthole inner ring, 5 via holes arranged vertically are evenly distributed on blasthole mesosphere, 12 periphery holes being obliquely installed are evenly distributed on blasthole outer ring;The central axes of periphery hole and the angle of vertical direction are arccot10 arccot12, and the hole top of periphery hole is small compared with the distance of bottom hole to hollow hole of centre.Blasting quality of the present invention is high, construction efficiency is high, blasting cost is low.

Description

A kind of Pile Diameter is the bridge cylinder pile foundation blasting method of 1.4-1.6m
Technical field
The present invention relates to the bridge cylinder pile foundation blasting methods that a kind of Pile Diameter is 1.4-1.6m, belong to bridge construction skill Art field.
Background technology
Cylinder pile extensive use in science of bridge building, cylinder pile foundation excavate generally use blasting method construction, but existing Method blasting quality is poor, blasting cost is high, low construction efficiency, if method during cylinder pile foundation Excavation blasting is improper, generation it is quick-fried Broken shock wave, attenuation of seismic waves and slungshot can cause to damage to pile holes protecting wall, occur retaining wall across collapse, chip off-falling, cracking situations such as, by This destroys pile holes protecting wall effect, influences stake holes adjoining rock stability, and the slungshot of generation is also possible to above damage excavation area near main sidewalk Construction installation, equipment.Therefore, suitable blasting method must be selected during cylinder stake holes Excavation blasting, on the one hand improves explosion matter Amount reduces blasting cost, improves construction efficiency, on the other hand reduces concussion of blasting, avoids damage pile holes protecting wall and construction equipment.
The content of the invention
The technical problem to be solved by the present invention is to:It is poor, quick-fried to solve existing highway bridge cylinder pile foundation blasting method blasting quality The technical issues of breaking of high cost, low construction efficiency and the fragile pile holes protecting wall of concussion of blasting, construction equipment, provides a kind of pile foundation The bridge cylinder pile foundation blasting method of a diameter of 1.4-1.6m.
The technical solution adopted by the present invention to solve the technical problems is:
A kind of Pile Diameter is the bridge cylinder pile foundation blasting method of 1.4-1.6m, is comprised the following steps:
Drilling:Along cylinder pile foundation center line vertically arrangement one hollow hole of centre, centered on cylinder pile foundation center line, with 0.13-0.17m forms blasthole inner ring for radius, and big gun is formed centered on cylinder pile foundation center line, by radius of 0.33-0.37m Hole mesosphere forms blasthole outer ring, on the blasthole inner ring centered on cylinder pile foundation center line, using 0.63-0.67m as radius 4 keyholes arranged vertically are evenly distributed with, 5 via holes arranged vertically are evenly distributed on the blasthole mesosphere, 12 periphery holes being obliquely installed are evenly distributed on the blasthole outer ring;The central axes of the periphery hole and the folder of vertical direction Angle is arccot10-arccot12, and the bottom hole of hole top to the distance periphery hole of hollow hole of centre of the periphery hole arrives The distance of hollow hole of centre is small;
Blasting charge:Installation explosive, the explosive payload Q of keyhole in keyhole, via hole and periphery hole1=(0.23- 0.25)*r2Q*L* η, the explosive payload Q of via hole (3)2=(0.19-0.22) * r2Q*L* η, the explosive payload Q of periphery hole (4)3= (0.11-0.13)*r2q*L*η;The r is pile foundation radius (m), and the q is explosive specific charge (kg/m3), the L is average borehole Depth (m), the η are blast hole utilizing factor;The q according to《Blasting engineering volume two table 7-3》And country《(09) Budget of Underground Roadway Engineering By norm》And the lithology (f coefficients 8~10) of caisson blast working part determines, it can be according to live actual and the in work progress Quick-fried situation is once tried to be adjusted;
Block blasthole mouth:Block the aperture of the keyhole, via hole and periphery hole;
Detonation:It arranges initiation net, and detonates.
Preferably, the depth of the hollow hole of centre, keyhole, via hole and periphery hole is 1.2m, aperture 40- 45mm。
Preferably, the keyhole and via hole are using coupling continuous charging, and the periphery hole is using coupling spaced loading.
Preferably, the loaded length of the keyhole is 52-64cm, and the loaded length of the via hole is 47-53cm, institute The loaded length for stating periphery hole is 23-33cm.
Preferably, the blocking of the keyhole, via hole and periphery hole is first blocked with paper or soft fabric, then is blocked up with cohesive soil Plug.
Preferably, which is characterized in that the stemming length of the keyhole is 0.85-1 times of loaded length, the via hole Stemming length be 1.2-1.5 times of loaded length, the stemming length of the periphery hole is 1.5-2 times of loaded length.
Preferably, pile foundation Excavation blasting working face often has crevice water or infiltration, therefore the explosive for preferably selecting waterproof strong, If rock emulsion explosive water-resistance is strong, powder stick shaping, is easy to cutting division and power is moderate, if using No. 2 rock ammonium-antimony explosives, Water-proofing treatment must then be carried out.
Preferably, to improve demolition effect, the degree of fragmentation of rock is effectively improved, the stability of retaining wall is protected, makes keyhole Interior explosive detonates at first, then explosive initiation in via hole, the explosive initiation in last periphery hole.
Preferably, the initiation net uses millisecond delay electric detonator, and the section of the detonating capsule after keyhole powder charge is not 1, the section of the detonating capsule after via hole powder charge not Wei 3, the section of the detonating capsule after periphery hole powder charge Wei 5.
Preferably, the initiation net uses non-electrical Millisecond Nonel Tube Detonator, the section of the detonating capsule after keyhole powder charge Not Wei 1, the section of the detonating capsule after via hole powder charge not Wei 3, the section of the detonating capsule after periphery hole powder charge Wei 5.
The beneficial effects of the invention are as follows:
The Pile Diameter of the present invention is the bridge cylinder pile foundation blasting method of 1.4-1.6m, and step is drilling, blasting charge, blocks up Plug big gun eats dishes without rice or wine, detonates, and the boring method is to arrange a hollow hole of centre vertically along cylinder pile foundation center line, in cylinder pile foundation Blasthole inner ring is formed centered on heart line, by radius of 0.13-0.17m, centered on cylinder pile foundation center line, with 0.33-0.37m Blasthole mesosphere is formed for radius, blasthole outer ring, institute are formed centered on cylinder pile foundation center line, by radius of 0.63-0.67m It states and 4 keyholes arranged vertically is evenly distributed on blasthole inner ring, 5 vertical cloth are evenly distributed on the blasthole mesosphere The via hole put is evenly distributed with 12 periphery holes being obliquely installed on the blasthole outer ring;The central axes of the periphery hole with The angle of vertical direction is arccot10-arccot12, and the distance week to hollow hole of centre is pushed up in the hole of the periphery hole The distance of lateral opening bottom hole to hollow hole of centre is small.The method of the present invention can make full use of explosive energy, reduce explosive consumption, carry High construction efficiency has higher blasting quality and relatively low blasting cost;In addition, the present invention blasting method can mitigate it is quick-fried Broken vibration and slungshot can cause to damage to pile holes protecting wall, avoid the occurrence of retaining wall across collapse, chip off-falling, cracking situations such as, make stake holes country rock Stablize, moreover it is possible to avoid construction installation above damage excavation area near main sidewalk, equipment.
Description of the drawings
The present invention is further described with reference to the accompanying drawings and examples.
Fig. 1 is the pile foundation blasthole floor plan of the present invention;
Fig. 2 is the pile foundation blasthole section layout drawing of the present invention;
Fig. 3 is the pile foundation blast hole loading structure schematic diagram of the present invention;
Reference numeral in figure is:1- hollow hole of centre, 2- keyholes, 3- via holes, 4- periphery holes.
Specific embodiment
In conjunction with the accompanying drawings, the present invention is further explained in detail.These attached drawings are simplified schematic diagram, only with Illustration illustrates the basic structure of the present invention, therefore it only shows composition related to the present invention.
Embodiment 1
The present embodiment provides the bridge cylinder pile foundation blasting methods that a kind of Pile Diameter is 1.5m, comprise the following steps:
Drilling:As depicted in figs. 1 and 2, a hollow hole of centre 1 is arranged vertically along cylinder pile foundation center line, with cylinder pile foundation Blasthole inner ring is formed centered on center line, by radius of 0.15m, centered on cylinder pile foundation center line, using 0.35m as radius shape Into blasthole mesosphere, blasthole outer ring is formed centered on cylinder pile foundation center line, using 0.65m as radius, on the blasthole inner ring 4 keyholes arranged vertically 2 are evenly distributed with, 5 via holes arranged vertically are evenly distributed on the blasthole mesosphere 3,12 periphery holes being obliquely installed 4 are evenly distributed on the blasthole outer ring;The central axes of the periphery hole 4 and vertical direction Angle be arccot12, and the hole top of the periphery hole 4 to the distance periphery hole 4 of hollow hole of centre 1 bottom hole in The distance of heart emptying aperture 1 is small;
Blasting charge:Installation explosive, the explosive payload Q of keyhole 2 in keyhole 2, via hole 3 and periphery hole 41=0.14* r2* q*L* η, the explosive payload Q of via hole2=0.093*r2Q*L* η, the explosive payload Q of periphery hole3=0.07*r2q*L*η;The r is Pile foundation radius (m), the q are explosive specific charge (kg/m3), the L is average borehole depth (m), and the η is blast hole utilizing factor; The q of the present embodiment is 4.5kg/m3, η 0.8, Q1=0.25*r2* q*L* η=0.25*0.56m2*4.5kg/m3* 1.2m*0.8= 0.6kg, Q2=0.21*r2* q*L* η=0.21*0.56m2*4.5kg/m3* 1.2m*0.8=0.51kg, Q3=0.13*r2*q*L* η=0.13*0.56m2*4.5kg/m3* 1.2m*0.8=0.31kg;
The present embodiment selects rock emulsion explosive, and the explosive waterproof is strong, powder stick shaping, is easy to cutting division and power is fitted In;As shown in figure 3, the keyhole 2, using coupling continuous charging, loaded length 60cm, the via hole 3 is using coupling company Continuous powder charge, loaded length 40cm, the periphery hole 4 is using coupling spaced loading, loaded length 30cm;
Block blasthole mouth:The aperture of the keyhole 2, via hole 3 and periphery hole 4 is blocked, the present embodiment is first blocked with paper, It is blocked again with cohesive soil, the stemming length of the keyhole 2 is 60cm, and the stemming length of the via hole 3 is 50cm, the week Lateral opening 4 stemming length is 50cm;
Detonation:It arranges initiation net, and detonates;The present embodiment uses millisecond delay electric detonator initiation net, and keyhole 2 fills The section of detonating capsule after medicine not Wei 1, the section of the detonating capsule after 3 powder charge of via hole not Wei 3, the detonation after 4 powder charge of periphery hole The section of detonator not Wei 5, the explosive in keyhole 2 is made first to detonate, explosive in via hole 3 re-detonates, and the explosive in periphery hole 4 is most After detonate, this design can improve demolition effect, protect the stability of retaining wall.
Embodiment 2
The present embodiment provides the bridge cylinder pile foundation blasting methods that a kind of Pile Diameter is 1.6m, comprise the following steps:
Drilling:As depicted in figs. 1 and 2, a hollow hole of centre 1 is arranged vertically along cylinder pile foundation center line, with cylinder pile foundation Blasthole inner ring is formed centered on center line, by radius of 0.17m, centered on cylinder pile foundation center line, using 0.37m as radius shape Into blasthole mesosphere, blasthole outer ring is formed centered on cylinder pile foundation center line, using 0.67m as radius, on the blasthole inner ring 4 keyholes arranged vertically 2 are evenly distributed with, 5 via holes arranged vertically are evenly distributed on the blasthole mesosphere 3,12 periphery holes being obliquely installed 4 are evenly distributed on the blasthole outer ring;The central axes of the periphery hole 4 and vertical direction Angle be arccot10, and the hole top of the periphery hole 4 to the distance periphery hole 4 of hollow hole of centre 1 bottom hole in The distance of heart emptying aperture 1 is small;
Blasting charge:Installation explosive, the explosive payload Q of keyhole 2 in keyhole 2, via hole 3 and periphery hole 41=0.16* r2Q*L* η, the explosive payload Q of via hole2=0.11*r2Q*L* η, the explosive payload Q of periphery hole3=0.08*r2q*L*η;The q is fried Prescription consumes (kg/m3), the L is average borehole depth (m), and the η is blast hole utilizing factor;The q of the present embodiment is 4.5kg/m3, η For 0.8, Q1=0.23*r2* q*L* η=0.23*0.64m2*4.5kg/m3* 1.2m*0.8=0.64kg, Q2=0.19*r2*q*L* η=0.19*0.64m2*4.5kg/m3* 1.2m*0.8=0.53kg, Q3=0.12*r2* q*L* η=0.12*0.64m2*4.5kg/ m3* 1.2m*0.8=0.33kg;
The present embodiment selects rock emulsion explosive, and the explosive waterproof is strong, powder stick shaping, is easy to cutting division and power is fitted In;As shown in figure 3, the keyhole 2, using coupling continuous charging, loaded length 64cm, the via hole 3 is using coupling company Continuous powder charge, loaded length 42cm, the periphery hole 4 is using coupling spaced loading, loaded length 33cm;
Block blasthole mouth:The aperture of the keyhole 2, via hole 3 and periphery hole 4 is blocked, the present embodiment is first with soft fabric It blocking, then is blocked with cohesive soil, the stemming length of the keyhole 2 is 54cm, and the stemming length of the via hole 3 is 63cm, The stemming length of the periphery hole 4 is 66cm;
Detonation:It arranges initiation net, and detonates;The present embodiment uses non-electrical Millisecond Nonel Tube Detonator initiation net, slotting The section of detonating capsule after 2 powder charge of hole not Wei 1, the section of the detonating capsule after 3 powder charge of via hole not Wei 3, after 4 powder charge of periphery hole The section of detonating capsule not Wei 5, the explosive in keyhole 2 is made first to detonate, explosive in via hole 3 re-detonates, fried in periphery hole 4 Medicine finally detonates, this design can improve demolition effect, protect the stability of retaining wall.
Embodiment 3
The present embodiment provides the bridge cylinder pile foundation blasting methods that a kind of Pile Diameter is 1.4m, comprise the following steps:
Drilling:As depicted in figs. 1 and 2, a hollow hole of centre 1 is arranged vertically along cylinder pile foundation center line, with cylinder pile foundation Blasthole inner ring is formed centered on center line, by radius of 0.13m, centered on cylinder pile foundation center line, using 0.33m as radius shape Into blasthole mesosphere, blasthole outer ring is formed centered on cylinder pile foundation center line, using 0.63m as radius, on the blasthole inner ring 4 keyholes arranged vertically 2 are evenly distributed with, 5 via holes arranged vertically are evenly distributed on the blasthole mesosphere 3,12 periphery holes being obliquely installed 4 are evenly distributed on the blasthole outer ring;The central axes of the periphery hole 4 and vertical direction Angle be arccot11, and the hole top of the periphery hole 4 to the distance periphery hole 4 of hollow hole of centre 1 bottom hole in The distance of heart emptying aperture 1 is small;
Blasting charge:Installation explosive, the explosive payload Q of keyhole 2 in keyhole 2, via hole 3 and periphery hole 41=0.12* r2Q*L* η, the explosive payload Q of via hole2=0.08*r2Q*L* η, the explosive payload Q of periphery hole3=0.08*r2q*L*η;The q is fried Prescription consumes (kg/m3), the L is average borehole depth (m), and the η is blast hole utilizing factor;The q of the present embodiment is 4.5kg/m3, η For 0.8, Q1=0.24*r2* q*L* η=0.24*0.49m2*4.5kg/m3* 1.2m*0.8=0.52kg, Q2=0.22*r2*q*L* η=0.22*0.49m2*4.5kg/m3* 1.2m*0.8=0.47kg, Q3=0.11*r2* q*L* η=0.11*0.49m2*4.5kg/ m3* 1.2m*0.8=0.23kg;
The present embodiment selects rock emulsion explosive, and the explosive waterproof is strong, powder stick shaping, is easy to cutting division and power is fitted In;As shown in figure 3, the keyhole 2, using coupling continuous charging, loaded length 52cm, the via hole 3 is using coupling company Continuous powder charge, loaded length 38cm, the periphery hole 4 is using coupling spaced loading, loaded length 25cm;
Block blasthole mouth:The aperture of the keyhole 2, via hole 3 and periphery hole 4 is blocked, the present embodiment is first blocked with paper, It is blocked again with cohesive soil, the stemming length of the keyhole 2 is 52cm, and the stemming length of the via hole 3 is 46cm, the week Lateral opening 4 stemming length is 37.5cm;
Detonation:It arranges initiation net, and detonates;The present embodiment uses millisecond delay electric detonator initiation net, and keyhole 2 fills The section of detonating capsule after medicine not Wei 1, the section of the detonating capsule after 3 powder charge of via hole not Wei 3, the detonation after 4 powder charge of periphery hole The section of detonator not Wei 5, the explosive in keyhole 2 is made first to detonate, explosive in via hole 3 re-detonates, and the explosive in periphery hole 4 is most After detonate, this design can improve demolition effect, protect the stability of retaining wall.
Using above-mentioned desirable embodiment according to the invention as enlightenment, by above-mentioned description, relevant staff is complete Various changes and amendments can be carried out without departing from the scope of the technological thought of the present invention' entirely.The technology of this invention Property scope is not limited to the content on specification, it is necessary to determine its technical scope according to right.

Claims (10)

1. a kind of Pile Diameter is the bridge cylinder pile foundation blasting method of 1.4-1.6m, which is characterized in that is comprised the following steps:
Drilling:Along cylinder pile foundation center line vertically arrangement one hollow hole of centre (1), centered on cylinder pile foundation center line, with 0.13-0.17m forms blasthole inner ring for radius, and big gun is formed centered on cylinder pile foundation center line, by radius of 0.33-0.37m Hole mesosphere forms blasthole outer ring, on the blasthole inner ring centered on cylinder pile foundation center line, using 0.63-0.67m as radius 4 keyholes arranged vertically (2) are evenly distributed with, 5 auxiliary arranged vertically are evenly distributed on the blasthole mesosphere Hole (3) is evenly distributed with 12 periphery holes being obliquely installed (4) on the blasthole outer ring;The central axes of the periphery hole (4) with The angle of vertical direction is arccot10-arccot12, and the hole top of the periphery hole (4) to hollow hole of centre (1) distance compared with The distance of bottom hole to the hollow hole of centre (1) of the periphery hole (4) is small;
Blasting charge:Installation explosive, the explosive payload Q of keyhole (2) in keyhole (2), via hole (3) and periphery hole (4)1= (0.23-0.25)*r2Q*L* η, the explosive payload Q of via hole (3)2=(0.19-0.22) * r2Q*L* η, the explosive payload of periphery hole (4) Q3=(0.11-0.13) * r2q*L*η;The r is pile foundation radius (m), and the q is explosive specific charge (kg/m3), the L is average Borehole depth (m), the η are blast hole utilizing factor;
Block blasthole mouth:Block the aperture of the keyhole (2), via hole (3) and periphery hole (4);
Detonation:It arranges initiation net, and detonates.
2. Pile Diameter according to claim 1 is the bridge cylinder pile foundation blasting method of 1.4-1.6m, which is characterized in that The hollow hole of centre (1), keyhole (2), the depth of via hole (3) and periphery hole (4) are 1.2m, aperture 40-45mm.
3. Pile Diameter according to claim 1 or 2 is the bridge cylinder pile foundation blasting method of 1.4-1.6m, feature exists In the keyhole (2) and via hole (3) are using coupling continuous charging, and the periphery hole (4) is using coupling spaced loading.
4. according to the bridge cylinder pile foundation blasting method that claim 1-3 any one of them Pile Diameter is 1.4-1.6m, institute The loaded length of keyhole (2) is stated as 52-64cm, the loaded length of the via hole (3) is 47-53cm, the periphery hole (4) Loaded length be 23-33cm.
5. it is the bridge cylinder pile foundation blasting method of 1.4-1.6m according to claim 1-4 any one of them Pile Diameter, It being characterized in that, the blocking of the keyhole (2), via hole (3) and periphery hole (4) is first blocked with paper or soft fabric, then with sticky Soil blocks.
6. it is the bridge cylinder pile foundation blasting method of 1.4-1.6m according to claim 1-5 any one of them Pile Diameter, It is characterized in that, the stemming length of the keyhole (2) is 0.85-1 times of loaded length, the stemming length of the via hole (3) For 1.2-1.5 times of loaded length, the stemming length of the periphery hole (4) is 1.5-2 times of loaded length.
7. it is the bridge cylinder pile foundation blasting method of 1.4-1.6m according to claim 1-6 any one of them Pile Diameter, It is characterized in that, the explosive is rock emulsion explosive or No. 2 rock ammonium-antimony explosives Jing Guo water-proofing treatment.
8. it is the bridge cylinder pile foundation blasting method of 1.4-1.6m according to claim 1-7 any one of them Pile Diameter, It is characterized in that, the explosive in keyhole (2) detonates at first, then via hole (3) interior explosive initiation, in last periphery hole (4) Explosive initiation.
9. it is the bridge cylinder pile foundation blasting method of 1.4-1.6m according to claim 1-8 any one of them Pile Diameter, Be characterized in that, the initiation net uses millisecond delay electric detonator, the section of the detonating capsule after keyhole (2) powder charge not Wei 1, it is auxiliary Help the section of the detonating capsule after hole (3) powder charge not Wei 3, the section of the detonating capsule after periphery hole (4) powder charge Wei 5.
10. it is the bridge cylinder pile foundation blasting method of 1.4-1.6m according to claim 1-8 any one of them Pile Diameter, It is characterized in that, the initiation net uses non-electrical Millisecond Nonel Tube Detonator, and the section of the detonating capsule after keyhole (2) powder charge is not 1, the section of the detonating capsule after via hole (3) powder charge not Wei 3, the section of the detonating capsule after periphery hole (4) powder charge Wei 5.
CN201711319184.8A 2017-12-12 2017-12-12 A kind of Pile Diameter is the bridge cylinder pile foundation blasting method of 1.4-1.6m Pending CN108061491A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711319184.8A CN108061491A (en) 2017-12-12 2017-12-12 A kind of Pile Diameter is the bridge cylinder pile foundation blasting method of 1.4-1.6m

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711319184.8A CN108061491A (en) 2017-12-12 2017-12-12 A kind of Pile Diameter is the bridge cylinder pile foundation blasting method of 1.4-1.6m

Publications (1)

Publication Number Publication Date
CN108061491A true CN108061491A (en) 2018-05-22

Family

ID=62138384

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711319184.8A Pending CN108061491A (en) 2017-12-12 2017-12-12 A kind of Pile Diameter is the bridge cylinder pile foundation blasting method of 1.4-1.6m

Country Status (1)

Country Link
CN (1) CN108061491A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111707151A (en) * 2020-06-11 2020-09-25 武汉大学 One-time blasting excavation forming method for offshore rock-socketed pile foundation
CN112033243A (en) * 2020-09-16 2020-12-04 云南迪庆有色金属有限责任公司 Upward sector wave-shaped bottom-pulling blasting method
CN114719698A (en) * 2022-05-13 2022-07-08 中铁四局集团有限公司 Ultra-long lower step blasting construction method based on blasting refinement analysis

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
张春智: "巷道全断面开挖法中***技术参数的确定", 《中国矿山工程》 *
李梓源等: "大直径中空孔在穿越复杂环境控制***中的应用研究", 《铁道标准设计》 *
王为: "立交桥桥脚桩基岩石开挖***", 《***》 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111707151A (en) * 2020-06-11 2020-09-25 武汉大学 One-time blasting excavation forming method for offshore rock-socketed pile foundation
CN112033243A (en) * 2020-09-16 2020-12-04 云南迪庆有色金属有限责任公司 Upward sector wave-shaped bottom-pulling blasting method
CN114719698A (en) * 2022-05-13 2022-07-08 中铁四局集团有限公司 Ultra-long lower step blasting construction method based on blasting refinement analysis
CN114719698B (en) * 2022-05-13 2023-11-03 中铁四局集团有限公司 Ultra-long lower step blasting construction method based on blasting refinement analysis

Similar Documents

Publication Publication Date Title
CN107764144B (en) A kind of tunnel Millisecond Controlled Blasting method
CN108036684A (en) A kind of Pile Diameter is the bridge cylinder pile foundation blasting method of 1.7-1.9m
CN105333778B (en) Medium-deep hole large-section composite cut blasting structure and method
CN108132006B (en) Anti-clogging quick well formation undercut blast hole arragement construction and its blasting method
CN109115061B (en) Detonation control method for reducing blasting vibration
CN104634198B (en) Close on controlled blasting construction method in the massif excavation of highway limit
CN106091848B (en) It is a kind of to realize overlength, the method for high inclination-angle tunnel anchorage top bar explosion
CN105300203B (en) A kind of outlining blasting method excavated for batholith
CN102183184B (en) Blast method for realizing vibration attenuation and protection of early-age concrete lining during tunnel construction
CN103983147A (en) Permafrost region road tunnel peripheral hole blasting construction method
CN107478113B (en) A kind of UHV transmission line stake well one-pass molding blasting method
CN108007285A (en) A kind of stone head deep hole sublevel is segmented efficient Cut Blasting method
CN103968721B (en) Hole bottom energy gathering and dissipating device suitable for inclined blast hole and capable of improving blasting excavation flatness of foundation surface
CN103575172A (en) Novel roadway blasting construction method
CN109506529A (en) A kind of compound Cut Blasting method
CN107024154A (en) High slope deep hole blasting construction method under a kind of complex environment
CN108061491A (en) A kind of Pile Diameter is the bridge cylinder pile foundation blasting method of 1.4-1.6m
CN104482817B (en) A kind of deep-lying tunnel stress relieving presplit blasting method
CN102080545B (en) High-risk pillar open-air deep hole collaborative stoping method
CN104990471B (en) Extremely short-range blasting construction vibration absorbing method and vibration absorbing and energy gathering lancing cartridge
CN107762399A (en) Explosion coordinates rotary drilling rig deep layer one-step pore-creating construction method
CN102967191A (en) Blasting method for treatment of gob
CN104406470A (en) Deep-hole slotting blasting method for large-diameter freezing shaft in west cretaceous system soft rock area
CN108061492A (en) A kind of Pile Diameter is the bridge cylinder pile foundation blasting method of 0.8-1m
CN108088338A (en) A kind of Pile Diameter is the bridge cylinder pile foundation blasting method of 1.1-1.3m

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20180522