CN108049905A - A kind of totally-enclosed gate underground station platform fire ventilation smoke exhaust method of subway - Google Patents

A kind of totally-enclosed gate underground station platform fire ventilation smoke exhaust method of subway Download PDF

Info

Publication number
CN108049905A
CN108049905A CN201711071263.1A CN201711071263A CN108049905A CN 108049905 A CN108049905 A CN 108049905A CN 201711071263 A CN201711071263 A CN 201711071263A CN 108049905 A CN108049905 A CN 108049905A
Authority
CN
China
Prior art keywords
tunnel
air hose
station
smoke
valve
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201711071263.1A
Other languages
Chinese (zh)
Other versions
CN108049905B (en
Inventor
史聪灵
李建
吕敬民
胥旅
石杰红
何理
车洪磊
伍彬彬
赵晨
侯正波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Academy of Safety Science and Technology CASST
Original Assignee
China Academy of Safety Science and Technology CASST
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Academy of Safety Science and Technology CASST filed Critical China Academy of Safety Science and Technology CASST
Priority to CN201711071263.1A priority Critical patent/CN108049905B/en
Publication of CN108049905A publication Critical patent/CN108049905A/en
Application granted granted Critical
Publication of CN108049905B publication Critical patent/CN108049905B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F1/00Ventilation of mines or tunnels; Distribution of ventilating currents
    • E21F1/003Ventilation of traffic tunnels

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Ventilation (AREA)

Abstract

The present invention relates to Fire Ventilation smoke evacuation technical field more particularly to a kind of totally-enclosed gate underground station platform fire ventilation smoke exhaust methods of subway.This method includes:Auxiliary smoke evacuation tunnel is chosen one as from upstream side tunnel and downlink side tunnel, several rows of cigarette valve is set above gate, the exhaust smoke valve for opening auxiliary smoke evacuation tunnel side is discharged fume, it opens upstream side running tunnel wind turbine and downlink side running tunnel wind turbine is discharged fume, it opens station tunnel exhaust fan to discharge fume, opens the big system fan in station and discharge fume.The totally-enclosed gate underground station platform fire ventilation smoke exhaust method of subway of the present invention, the flue gas generated during fire can in time be excluded, effectively increase smoke exhaust efficiency, and ensured personnel safety.

Description

A kind of totally-enclosed gate underground station platform fire ventilation smoke exhaust method of subway
Technical field
The present invention relates to Fire Ventilation smoke evacuation technical field more particularly to a kind of subway totally-enclosed gate underground station stations Platform Fire Ventilation smoke exhaust method.
Background technology
In existing Metro Design, the underground station of the totally-enclosed platform door system of typical case generally sets four running tunnel wind Machine, often two, end, spare each other, is respectively used to the smoke evacuation of uplink and downlink tunnel ventilation.Two rail head track bottom exhaust fans are set, Often hold one.Two public area smoke exhaust fans are set, often hold one.After fire occurs for station platform, set in some designing schemes It is fixed only to open the smoke evacuation of station public area smoke exhaust fan, it is set in some designing schemes and opens each running tunnel in station both ends Wind turbine auxiliary smoke evacuation also has the exhaust fan auxiliary smoke evacuation that station both ends are opened in the setting of some designing schemes.These designing schemes There are the problem of be all to fail to make full use of fan delivery, for example fail to open all running tunnel wind turbines simultaneously, fail rationally Distribution rail bottom and the air quantity of rail top row mouth, so that exhaust smoke level is maximum and then obtains optimal smoke discharging effect.
Meanwhile in order to which tunnel smoke evacuation system is made to reach higher smoke exhaust efficiency as far as possible, the underground of current totally-enclosed gate It in the platform fire Model Design at station, is typically designed and opens certain amount gate, for example open all gates in both sides and live Dynamic door opens all gate dodge gates in one side, opens each two fan gates dodge gate of head and the tail, opens end door etc..In view of fire After calamity occurs, there may be a large amount of crowds on platform to fail to evacuate, and opening gate may cause personnel to fall to Gui Hang areas to make Into secondary injury.In addition, either gate dodge gate or end door, height is relatively low, is usually two meters or so, only works as platform When smoke layer height is reduced to dodge gate or end door height, flue gas could be excluded by dodge gate or end door, this causes tunnel to lead to Wind smoke evacuation system auxiliary smoke exhaust efficiency is relatively low.
The content of the invention
(1) technical problems to be solved
The object of the present invention is to provide a kind of totally-enclosed gate underground station platform fire ventilation smoke exhaust method of subway, solutions Certainly existing in the prior art to fail to make full use of fan delivery, smoke discharging effect is bad, tunnel ventilation smoke evacuation system auxiliary smoke evacuation effect The problem of rate is relatively low.
(2) technical solution
In order to solve the above technical problem, the present invention provides a kind of totally-enclosed gate underground station platform fires of subway Ventilation smoke exhaust method, while control tunnel ventilation smoke evacuation system, subway concourse platform ventilation smoke extraction system and gate ventilation smoke exhaust system System carries out Fire Ventilation smoke evacuation, wherein the tunnel ventilation smoke evacuation system includes running tunnel ventilation smoke extraction system and station tunnel Ventilation smoke extraction system, the subway concourse platform ventilation smoke extraction system include station hall layer ventilation smoke extraction system and station layer ventilation smoke exhaust system System, the gate ventilation smoke extraction system include upstream side gate ventilation smoke extraction system and downlink side gate ventilation smoke exhaust system System;
This method specifically comprises the following steps:
Auxiliary smoke evacuation tunnel is chosen one as from upstream side tunnel and downlink side tunnel;
When selecting the upstream side tunnel as auxiliary smoke evacuation tunnel, upstream side gate and downlink side platform are closed Door opens the upstream side exhaust smoke valve being arranged on above the upstream side gate, passes through the gate ventilation smoke extraction system pair It discharges fume in the auxiliary smoke evacuation tunnel;
Upstream side running tunnel wind turbine and downlink side running tunnel wind turbine are separately turned on, by adjusting smoke discharging pipe air-valve It opens and closes, the upstream side running tunnel wind turbine and downlink side running tunnel wind turbine is made to arrange simultaneously the auxiliary smoke evacuation tunnel Cigarette;
Station tunnel exhaust fan is opened, opens uplink siding track valve against the wind, closes downlink siding track valve, upstream side against the wind respectively Flange of rail air-valve and downlink side flange of rail air-valve arrange the auxiliary smoke evacuation tunnel by the station tunnel ventilation smoke extraction system Cigarette;
The big system fan in station is opened, opens station layer smoke discharging pipe air-valve, station hall layer smoke discharging pipe air-valve is closed, passes through The subway concourse platform ventilation smoke extraction system discharges fume to platform public area.
Further, the running tunnel ventilation smoke extraction system includes being correspondingly arranged at upstream side tunnel left and right ends Two upstream side running tunnel ventilation smoke exhaust subsystems and be correspondingly arranged at two of downlink side tunnel left and right ends Downlink side running tunnel ventilation smoke exhaust subsystem;Each upstream side running tunnel ventilation smoke exhaust subsystem is included described in one Upstream side running tunnel wind turbine, each downlink side running tunnel ventilation smoke exhaust subsystem include a downlink side section Tunnel blower.
Specifically, the upstream side running tunnel ventilation smoke exhaust subsystem includes be connected with the upstream side tunnel first Main air hose is connected to first branch's air hose and second branch's air hose on the described first main air hose, wherein the upstream side Running tunnel wind turbine is arranged on second branch air hose;The downlink side running tunnel ventilation smoke exhaust subsystem includes and institute The second main air hose that downlink side tunnel is connected is stated, the 3rd branch's air hose and the 4th point are connected on the described second main air hose Branch wind pipe, wherein the downlink side running tunnel wind turbine is arranged on the 3rd branch's air hose;Second branch air hose with It is connected between 3rd branch's air hose by connecting air hose;
The keying by adjusting smoke discharging pipe air-valve, specifically includes:
It is separately turned on being arranged on the described first main air hose, second branch's air hose, the 3rd branch's air hose and connection air hose Smoke discharging pipe air-valve;
The smoke discharging pipe being arranged on the described second main air hose, first branch's air hose and the 4th branch's air hose is closed respectively Air-valve.
Further, the station tunnel ventilation smoke extraction system includes being correspondingly arranged at two at left and right sides of platform public area A station tunnel ventilation smoke exhaust subsystem, the station tunnel ventilation smoke exhaust subsystem includes the 3rd main air hose, the described 3rd It is connected to that uplink siding track is managed against the wind, upstream side flange of rail air hose, downlink siding track are managed against the wind and downlink side flange of rail wind on main air hose Pipe, wherein the station tunnel exhaust fan is arranged on the 3rd main air hose, the uplink siding track valve, uplink siding track against the wind Bottom air-valve, downlink siding track against the wind valve and downlink side flange of rail air-valve be correspondingly arranged at respectively the uplink siding track manage against the wind, upstream side Flange of rail air hose, downlink siding track manage against the wind and downlink side flange of rail air hose on.
Further, the station hall layer ventilation smoke extraction system includes being correspondingly arranged at two subway concourses at left and right sides of station hall layer Layer ventilation smoke exhaust subsystem, the station hall layer ventilation smoke exhaust subsystem include the 4th main air hose, in the described 4th main air hose difference Being connected, there are two quintafurcation air hoses;The station layer ventilation smoke extraction system includes being correspondingly arranged at two at left and right sides of station layer A station layer ventilation smoke exhaust subsystem, the station layer ventilation smoke exhaust subsystem include two the 6th branch's air hoses;Wherein, it is described The big system fan in station is arranged on the 4th main air hose, and a station is respectively equipped on each quintafurcation air hose Platform layer smoke discharging pipe air-valve is each respectively equipped with a station hall layer smoke discharging pipe air-valve on six branch air hose.
Specifically, it is described to be discharged fume by the subway concourse platform ventilation smoke extraction system to platform public area, it further includes:
The smoke discharging pipe air-valve being arranged on the 4th main air hose is opened, by the big system fan in the station to platform It discharges fume public area.
Further, the upstream side gate ventilation smoke extraction system includes the upstream side gate and is arranged on institute State the upstream side exhaust smoke valve above upstream side gate;The downlink side gate ventilation smoke extraction system includes downlink side station Platform door and the downlink side exhaust smoke valve being arranged on above the downlink side gate.
(3) advantageous effect
The above-mentioned technical proposal of the present invention has the following advantages that:
The totally-enclosed gate underground station platform fire ventilation smoke exhaust method of subway provided by the invention, by upstream side The top of gate and downlink side gate sets exhaust smoke valve respectively, and auxiliary smoke evacuation tunnel side is opened during platform fire Exhaust smoke valve, on the one hand it is possible to prevente effectively from opening gate, and then avoid the secondary injury that personnel is caused to fall from gate, On the other hand, since exhaust smoke valve is arranged on above gate, and it sets height far above the height of gate, it is contemplated that fire The flue gas of generation can effectively improve smoke exhaust efficiency ceiling is assembled the characteristics of by opened smoke-discharging valve.
The totally-enclosed gate underground station platform fire ventilation smoke exhaust method of subway provided by the invention, in the platform fire phase Between, at the same open setting AT STATION the upstream side running tunnel wind turbine of both sides and downlink side running tunnel wind turbine as smoke exhaust fan It uses, so that running tunnel fan delivery doubles, the flue gas for being conducive to generate during fire excludes in time.
The totally-enclosed gate underground station platform fire ventilation smoke exhaust method of subway provided by the invention, in the platform fire phase Between, while open station tunnel exhaust fan and used for smoke exhaust fan, and close rail top and the rail of non-auxiliary smoke evacuation tunnel side Bottom air-valve, reduce station rail top and the flange of rail fan delivery loss, and in view of flue gas be heated rise the characteristics of, also simultaneously close off The flange of rail air-valve of auxiliary smoke evacuation tunnel side so that the station tunnel exhaust fan being arranged at left and right sides of platform public area can be only To auxiliary smoke evacuation tunnel rail jacking row smoke evacuation, so as to effectively improve smoke exhaust efficiency.
Description of the drawings
Fig. 1 is tunnel ventilation smoke evacuation system schematic diagram in the embodiment of the present invention;
Fig. 2 is subway concourse platform ventilation smoke extraction system schematic diagram in the embodiment of the present invention;
Fig. 3 is upstream side gate ventilation smoke extraction system schematic diagram in the embodiment of the present invention.
Specific embodiment
To make the purpose, technical scheme and advantage of the embodiment of the present invention clearer, below in conjunction with the embodiment of the present invention In attached drawing, the technical solution in the embodiment of the present invention is clearly and completely described, it is clear that described embodiment is The part of the embodiment of the present invention, instead of all the embodiments.Based on the embodiments of the present invention, ordinary skill people Member's all other embodiments obtained on the premise of creative work is not made, belong to the scope of protection of the invention.
The embodiment of the present invention provides a kind of totally-enclosed gate underground station platform fire ventilation smoke exhaust method of subway, is standing During platform fire, while control tunnel ventilation smoke evacuation system, subway concourse platform ventilation smoke extraction system and gate ventilation smoke extraction system Carry out Fire Ventilation smoke evacuation.
As shown in Figure 1, tunnel ventilation smoke evacuation system includes running tunnel ventilation smoke extraction system and station tunnel ventilation smoke exhaust System, wherein, running tunnel ventilation smoke extraction system includes two uplink lateral areas for being correspondingly arranged at upstream side tunnel left and right ends Between tunnel ventilation smoke evacuation subsystem and be correspondingly arranged at downlink side tunnel left and right ends two downlink side running tunnels ventilation Smoke evacuation subsystem, station tunnel ventilation smoke extraction system include being correspondingly arranged at two station tunnels at left and right sides of platform public area Ventilation smoke exhaust subsystem.
Wherein, being arranged on the upstream side running tunnel ventilation smoke exhaust subsystem of upstream side tunnel left end includes and upstream side tunnel The main air hose M1 that road is connected and branch the air hose N1 and N2 being connected respectively with main air hose M1, wherein the row of being equipped on main air hose M1 Smoke pipeline air-valve D7, on branch air hose N1 be equipped with smoke discharging pipe air-valve D4, be respectively equipped on branch air hose N2 silencer C2, Upstream side running tunnel wind turbine B2 and smoke discharging pipe air-valve D3, branch air hose N1 and N2 are connected respectively with ventilating shaft E2.It is arranged on down The downlink side running tunnel ventilation smoke exhaust subsystem of row side tunnel left end include the main air hose M2 that is connected with downlink side tunnel and Branch the air hose N3 and N4 being connected respectively with main air hose M2, wherein smoke discharging pipe air-valve D8 is equipped on main air hose M2, in branch Air hose N4 is equipped with smoke discharging pipe air-valve D1, and silencer C1, downlink side running tunnel wind turbine are respectively equipped on branch air hose N3 B1 and smoke discharging pipe air-valve D2, branch air hose N3 and N4 are connected respectively with ventilating shaft E1.Between branch air hose N2 and branch air hose N3 It is connected by connecting air hose N5, smoke discharging pipe air-valve D6 is equipped on connection air hose N5.
Wherein, being arranged on the upstream side running tunnel ventilation smoke exhaust subsystem of upstream side tunnel right end includes and upstream side tunnel The main air hose M3 that road is connected and branch the air hose N6 and N7 being connected respectively with main air hose M3, wherein the row of being equipped on main air hose M3 Smoke pipeline air-valve D14 is equipped with smoke discharging pipe air-valve D10 on branch air hose N6, silencer is respectively equipped on branch air hose N7 C5, upstream side running tunnel wind turbine B3 and smoke discharging pipe air-valve D11, branch air hose N6 and N7 are connected respectively with ventilating shaft E5.It sets In downlink side tunnel, the downlink side running tunnel ventilation smoke exhaust subsystem of right end includes the main air hose M4 being connected with downlink side tunnel And branch the air hose N8 and N9 being connected respectively with main air hose M4, wherein smoke discharging pipe air-valve D16 is equipped on main air hose M4, Branch air hose N9 is equipped with smoke discharging pipe air-valve D12, and silencer C6, downlink side running tunnel are respectively equipped on branch air hose N8 Wind turbine B4 and smoke discharging pipe air-valve D13, branch air hose N8 and N9 are connected respectively with ventilating shaft E6.Branch air hose N7 and branch air hose N8 Between be connected by connecting air hose N10, connection air hose N10 on be equipped with smoke discharging pipe air-valve D15.
Wherein, being arranged on the station tunnel ventilation smoke exhaust subsystem on the left of platform public area includes main air hose M5, main air hose M5 respectively with uplink siding track pipe N11, upstream side flange of rail air hose N12, downlink siding track pipe N13 and downlink side flange of rail air hose against the wind against the wind N14 is connected, wherein silencer C6, station tunnel exhaust fan A1 and smoke discharging pipe air-valve D5 are respectively equipped on main air hose M5, Main air hose M5 is connected with ventilating shaft E3.In uplink siding track pipe N11, upstream side flange of rail air hose N12, downlink siding track pipe N13 against the wind against the wind With uplink siding track valve D17, upstream side flange of rail air-valve D18, downlink siding track against the wind are correspondingly provided on downlink side flange of rail air hose N14 respectively Valve D20 and downlink siding track valve D19 against the wind against the wind.
Wherein, being arranged on the station tunnel ventilation smoke exhaust subsystem on the right side of platform public area includes main air hose M6, main air hose M6 respectively with uplink siding track pipe N15, upstream side flange of rail air hose N16, downlink siding track pipe N17 and downlink side flange of rail air hose against the wind against the wind N18 is connected, wherein silencer C4, station tunnel exhaust fan A2 and smoke discharging pipe air-valve D9 are respectively equipped on main air hose M6, Main air hose M6 is connected with ventilating shaft E4.In uplink siding track pipe N15, upstream side flange of rail air hose N16, downlink siding track pipe N17 against the wind against the wind With uplink siding track valve D21, upstream side flange of rail air-valve D22, downlink siding track against the wind are correspondingly provided on downlink side flange of rail air hose N18 respectively Valve D24 and downlink side flange of rail air-valve D23 against the wind.
As shown in Fig. 2, subway concourse platform ventilation smoke extraction system includes station hall layer ventilation smoke extraction system and station layer ventilation smoke exhaust System, station hall layer ventilation smoke extraction system include being correspondingly arranged at two station hall layer ventilation smoke exhaust subsystems at left and right sides of station hall layer System, station layer ventilation smoke extraction system include being correspondingly arranged at two station layer ventilation smoke exhaust subsystems at left and right sides of station layer,
Wherein, be arranged on station hall layer ventilation smoke exhaust subsystem on the left of station hall layer include main air hose M7 and with main air hose M7 Branch the air hose N18 and N19 connected respectively is respectively equipped with silencer C7, the big system fan F1 in station and station on main air hose M7 Room layer main pipeline air-valve D25, main air hose M7 are connected with ventilating shaft E7, and station hall layer is correspondingly provided with respectively on branch air hose N18 and N19 Smoke discharging pipe air-valve D27 and D28.
Wherein, being arranged on the station layer ventilation smoke exhaust subsystem on the left of station layer includes point being connected respectively with main air hose M7 Branch wind pipe N22 and N23 are correspondingly provided with station layer smoke discharging pipe air-valve D29 and D30 respectively on branch air hose N22 and N23.
Wherein, be arranged on station hall layer ventilation smoke exhaust subsystem on the right side of station hall layer include main air hose M8 and with main air hose M8 Branch the air hose N20 and N21 connected respectively is respectively equipped with silencer C8, the big system fan F2 in station and station on main air hose M8 Room layer main pipeline air-valve D26, main air hose M8 are connected with ventilating shaft E8, and station hall layer is correspondingly provided with respectively on branch air hose N20 and N21 Smoke discharging pipe air-valve D31 and D32.
Wherein, being arranged on the station layer ventilation smoke exhaust subsystem on the right side of station layer includes point being connected respectively with main air hose M8 Branch wind pipe N24 and N25 are correspondingly provided with station layer smoke discharging pipe air-valve D33 and D34 respectively on branch air hose N24 and N25.
Gate ventilation smoke extraction system includes upstream side gate ventilation smoke extraction system and downlink side gate ventilation smoke exhaust System.As shown in figure 3, upstream side gate ventilation smoke extraction system includes upstream side gate and is arranged on upstream side gate One row's upstream side exhaust smoke valve of top, wherein upstream side exhaust smoke valve are from left to right followed successively by K1, K2, K3, K4, K5, K6 ....Together Reason, downlink side gate ventilation smoke extraction system are included under downlink side gate and the row being arranged on above downlink side gate Row side exhaust smoke valve.Wherein, upstream side gate and downlink side gate should including platform dodge gate, platform fixed door and platform Anxious door, as shown in figure 3, in upstream side gate, platform dodge gate is respectively from left to right G1, G2, G3, G4 ..., platform Fixed door is respectively from left to right H1, H2, H3 ..., and platform escape door is J1.
The totally-enclosed gate underground station platform fire ventilation smoke exhaust method of subway then described in the embodiment of the present invention, specifically Include the following steps:
According to Fires Occurred, auxiliary smoke evacuation tunnel is chosen one as from upstream side tunnel and downlink side tunnel.
When selecting upstream side tunnel as auxiliary smoke evacuation tunnel, platform dodge gate G1, G2, G3, G4 ... are closed, is closed Platform fixed door H1, H2, H3 ..., close platform escape door J1, while open upstream side exhaust smoke valve K1, K2, K3, K4, K5, K6 ..., so that gate ventilation smoke extraction system discharges fume to auxiliary smoke evacuation tunnel.
Upstream side running tunnel wind turbine B2 and B3 are opened, opened smoke-discharging pipeline air-valve D7, D3, D14 and D11 close smoke evacuation Pipeline air-valve D4 and D10.Meanwhile open downlink side running tunnel wind turbine B1 and B4, opened smoke-discharging pipeline air-valve D6, D2, D15 and D13, close smoke discharging pipe air-valve D8, D1, D16 and D12 so that running tunnel ventilation smoke extraction system to upstream side station tunnel into Row smoke evacuation.
Station tunnel exhaust fan A1 and A2 are opened, opened smoke-discharging pipeline air-valve D5 and D9 open uplink siding track valve against the wind D17 and D21 closes downlink siding track valve D20 and D24 against the wind, closes the upstream side flange of rail air-valve D18 and D22, closes the downlink side flange of rail Air-valve D19 and D23, so that station tunnel ventilation smoke extraction system discharges fume to upstream side station tunnel.
The big system fan F1 and F2 in station is opened, opens station hall layer main pipeline air-valve D25 and D26, opens station layer smoke evacuation Pipeline air-valve D29, D30, D33 and D34 close station hall layer smoke discharging pipe air-valve D27, D28, D31 and D32, so that subway concourse platform Ventilation smoke extraction system discharges fume to platform public area.
Similarly, if select downlink side tunnel as auxiliary smoke evacuation tunnel, operation principle and selection upstream side tunnel It is identical during as auxiliary smoke evacuation tunnel, it is no longer repeated herein.
In conclusion the totally-enclosed gate underground station platform fire ventilation smoke exhaust side of subway described in the embodiment of the present invention Method by setting exhaust smoke valve respectively in the top of upstream side gate and downlink side gate, and is opened during platform fire The exhaust smoke valve of auxiliary smoke evacuation tunnel side, can effectively improve smoke exhaust efficiency, while by closing upstream side gate and downlink side Gate avoids the secondary injury that personnel is caused to fall from gate, support personnel's safety.
The totally-enclosed gate underground station platform fire ventilation smoke exhaust method of subway described in the embodiment of the present invention, in platform During fire, while open setting two upstream side running tunnel wind turbines of both sides and two downlink side running tunnel wind AT STATION Machine is used as smoke exhaust fan so that running tunnel fan delivery doubles, be more favorable for the flue gas generated during fire and When exclude.
The totally-enclosed gate underground station platform fire ventilation smoke exhaust method of subway described in the embodiment of the present invention, in platform It during fire, while opens and two station tunnel exhaust fans of both sides AT STATION is set to be used for smoke exhaust fan, and close Rail valve and the flange of rail air-valve against the wind of non-auxiliary smoke evacuation tunnel side, reduce station rail top and the loss of flange of rail fan delivery, and consider The characteristics of being heated rising to flue gas also simultaneously closes off the flange of rail air-valve of auxiliary smoke evacuation tunnel side so that be arranged on platform public area The station tunnel exhaust fan of the left and right sides can be only to auxiliary smoke evacuation tunnel rail jacking row smoke evacuation, so as to effectively improve smoke evacuation effect Rate.
Finally it should be noted that:The above embodiments are merely illustrative of the technical solutions of the present invention, rather than its limitations;Although The present invention is described in detail with reference to the foregoing embodiments, it will be understood by those of ordinary skill in the art that:It still may be used To modify to the technical solution recorded in foregoing embodiments or carry out equivalent substitution to which part technical characteristic; And these modification or replace, do not make appropriate technical solution essence depart from various embodiments of the present invention technical solution spirit and Scope.

Claims (8)

1. a kind of totally-enclosed gate underground station platform fire ventilation smoke exhaust method of subway, which is characterized in that while control tunnel Road ventilation smoke extraction system, subway concourse platform ventilation smoke extraction system and gate ventilation smoke extraction system carry out Fire Ventilation smoke evacuation, wherein The tunnel ventilation smoke evacuation system includes running tunnel ventilation smoke extraction system and station tunnel ventilation smoke extraction system, the subway concourse station Platform ventilation smoke extraction system includes station hall layer ventilation smoke extraction system and station layer ventilation smoke extraction system, the gate ventilation smoke exhaust system System includes upstream side gate ventilation smoke extraction system and downlink side gate ventilation smoke extraction system;
This method specifically comprises the following steps:
Auxiliary smoke evacuation tunnel is chosen one as from upstream side tunnel and downlink side tunnel;
When selecting the upstream side tunnel as auxiliary smoke evacuation tunnel, upstream side gate and downlink side gate are closed, is opened The upstream side exhaust smoke valve being arranged on above the upstream side gate is opened, by the gate ventilation smoke extraction system to described auxiliary Smoke evacuation tunnel is helped to discharge fume;
Upstream side running tunnel wind turbine and downlink side running tunnel wind turbine are separately turned on, by adjusting opening for smoke discharging pipe air-valve It closes, the upstream side running tunnel wind turbine and downlink side running tunnel wind turbine is made to arrange simultaneously the auxiliary smoke evacuation tunnel Cigarette;
Station tunnel exhaust fan is opened, opens uplink siding track valve against the wind, closes downlink siding track valve, the upstream side flange of rail against the wind respectively Air-valve and downlink side flange of rail air-valve discharge fume to the auxiliary smoke evacuation tunnel by the station tunnel ventilation smoke extraction system;
The big system fan in station is opened, opens station layer smoke discharging pipe air-valve, station hall layer smoke discharging pipe air-valve is closed, by described Subway concourse platform ventilation smoke extraction system discharges fume to platform public area.
2. the totally-enclosed gate underground station platform fire ventilation smoke exhaust method of subway according to claim 1, feature It is, the running tunnel ventilation smoke extraction system includes being correspondingly arranged at two upstream sides of upstream side tunnel left and right ends Running tunnel ventilation smoke exhaust subsystem and two downlink side section tunnels for being correspondingly arranged at downlink side tunnel left and right ends Road ventilation smoke exhaust subsystem;Each upstream side running tunnel ventilation smoke exhaust subsystem includes a upstream side section tunnel Road wind turbine, each downlink side running tunnel ventilation smoke exhaust subsystem include a downlink side running tunnel wind turbine.
3. the totally-enclosed gate underground station platform fire ventilation smoke exhaust method of subway according to claim 2, feature It is, the upstream side running tunnel ventilation smoke exhaust subsystem includes the first main air hose being connected with the upstream side tunnel, First branch's air hose and second branch's air hose are connected on the first main air hose, wherein the upstream side running tunnel wind Machine is arranged on second branch air hose;The downlink side running tunnel ventilation smoke exhaust subsystem includes and the downlink side tunnel The second main air hose that road is connected, the 3rd branch's air hose and the 4th branch's air hose are connected on the described second main air hose, Described in downlink side running tunnel wind turbine be arranged on the 3rd branch's air hose;Second branch air hose and the 3rd branch's wind It is connected between pipe by connecting air hose.
4. the totally-enclosed gate underground station platform fire ventilation smoke exhaust method of subway according to claim 3, feature It is, the keying by adjusting smoke discharging pipe air-valve specifically includes:
It is separately turned on the row being arranged on the described first main air hose, second branch's air hose, the 3rd branch's air hose and connection air hose Smoke pipeline air-valve;
The smoke discharging pipe wind being arranged on the described second main air hose, first branch's air hose and the 4th branch's air hose is closed respectively Valve.
5. the totally-enclosed gate underground station platform fire ventilation smoke exhaust method of subway according to claim 1, feature It is, two station tunnels that the station tunnel ventilation smoke extraction system includes being correspondingly arranged at left and right sides of platform public area lead to Wind smoke evacuation subsystem, the station tunnel ventilation smoke exhaust subsystem include the 3rd main air hose, on the 3rd main air hose respectively It is connected with that uplink siding track is managed against the wind, upstream side flange of rail air hose, downlink siding track are managed against the wind and downlink side flange of rail air hose, wherein the vehicle Tunnel exhaust fan of standing is arranged on the 3rd main air hose, the uplink siding track valve, upstream side flange of rail air-valve, downlink side against the wind Rail against the wind valve and downlink side flange of rail air-valve be correspondingly arranged at respectively the uplink siding track manage against the wind, upstream side flange of rail air hose, downlink Siding track manage against the wind on downlink side flange of rail air hose.
6. the totally-enclosed gate underground station platform fire ventilation smoke exhaust method of subway according to claim 1, feature It is, the station hall layer ventilation smoke extraction system includes being correspondingly arranged at two station hall layer ventilation smoke exhausts at left and right sides of station hall layer System, the station hall layer ventilation smoke exhaust subsystem include the 4th main air hose, are respectively connected with that there are two the in the 4th main air hose Quintafurcation air hose;The station layer ventilation smoke extraction system includes being correspondingly arranged at two station layers ventilation at left and right sides of station layer Smoke evacuation subsystem, the station layer ventilation smoke exhaust subsystem include two the 6th branch's air hoses;Wherein, the big system wind in the station Machine is arranged on the 4th main air hose, and a station layer smoke discharging pipe is respectively equipped on each quintafurcation air hose Air-valve is each respectively equipped with a station hall layer smoke discharging pipe air-valve on six branch air hose.
7. the totally-enclosed gate underground station platform fire ventilation smoke exhaust method of subway according to claim 6, feature It is, it is described to be discharged fume by the subway concourse platform ventilation smoke extraction system to platform public area, it further includes:
The smoke discharging pipe air-valve being arranged on the 4th main air hose is opened, it is public to platform by the big system fan in the station It discharges fume in area.
8. the totally-enclosed gate underground station platform fire ventilation smoke exhaust method of subway according to claim 1, feature It is, the upstream side gate ventilation smoke extraction system includes the upstream side gate and is arranged on the upstream side platform The upstream side exhaust smoke valve of door top;The downlink side gate ventilation smoke extraction system includes downlink side gate and setting Downlink side exhaust smoke valve above the downlink side gate.
CN201711071263.1A 2017-11-03 2017-11-03 A kind of totally-enclosed gate underground station platform fire ventilation smoke exhaust method of subway Active CN108049905B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711071263.1A CN108049905B (en) 2017-11-03 2017-11-03 A kind of totally-enclosed gate underground station platform fire ventilation smoke exhaust method of subway

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711071263.1A CN108049905B (en) 2017-11-03 2017-11-03 A kind of totally-enclosed gate underground station platform fire ventilation smoke exhaust method of subway

Publications (2)

Publication Number Publication Date
CN108049905A true CN108049905A (en) 2018-05-18
CN108049905B CN108049905B (en) 2019-04-16

Family

ID=62118673

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711071263.1A Active CN108049905B (en) 2017-11-03 2017-11-03 A kind of totally-enclosed gate underground station platform fire ventilation smoke exhaust method of subway

Country Status (1)

Country Link
CN (1) CN108049905B (en)

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108952788A (en) * 2018-08-16 2018-12-07 中国安全生产科学研究院 A kind of method of underground station train fire ventilation smoke exhaust
CN109139079A (en) * 2018-09-17 2019-01-04 中铁四院集团西南勘察设计有限公司 Subway tunnel ventilating system
CN109252885A (en) * 2018-10-25 2019-01-22 中国安全生产科学研究院 A kind of subway underground station an island platform Fire Ventilation smoke evacuation system and method
CN110118099A (en) * 2019-06-03 2019-08-13 中国安全生产科学研究院 A kind of Fire Ventilation smoke exhaust method of sub-interchange platform
CN110295939A (en) * 2019-07-08 2019-10-01 中铁第四勘察设计院集团有限公司 Road cooperates with platform smoke exhaust system to a kind of overall height gate standard subway station rail against the wind
CN111256287A (en) * 2020-01-21 2020-06-09 中国安全生产科学研究院 Distributed smoke exhaust system for subway station platform and air volume adjusting method
CN111255727A (en) * 2020-03-17 2020-06-09 中铁第四勘察设计院集团有限公司 Subway train platform and smoke exhaust method thereof
CN111980742A (en) * 2020-08-14 2020-11-24 中国安全生产科学研究院 Fire ventilation and smoke exhaust system and method for platform of separated island type subway underground station
CN112253207A (en) * 2020-11-06 2021-01-22 天津大学 Intensive subway ventilation and smoke exhaust system
CN112282823A (en) * 2020-11-06 2021-01-29 天津大学 Regional control subway platform smoke exhaust method
CN112523773A (en) * 2020-12-11 2021-03-19 广州地铁设计研究院股份有限公司 Subway station environmental control system with wind pavilions arranged at single end
CN112983527A (en) * 2021-03-30 2021-06-18 中国安全生产科学研究院 Integrated station tunnel ventilation system and smoke exhaust method thereof
CN113339037A (en) * 2021-07-16 2021-09-03 广州地铁设计研究院股份有限公司 Point type exhaust and smoke exhaust station tunnel ventilation system without rail top air duct
CN114198128A (en) * 2021-12-02 2022-03-18 中国安全生产科学研究院 System and method for ventilating and discharging smoke of fire disaster in atrium type subway station

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06264697A (en) * 1993-03-12 1994-09-20 Tetsuharu Ono Air-conditioning method for subway station
RU2463452C1 (en) * 2011-04-07 2012-10-10 Учреждение Российской академии наук Институт горного дела Сибирского отделения РАН Method of tunnel ventilation
CN203097921U (en) * 2013-02-22 2013-07-31 中铁第四勘察设计院集团有限公司 System integrating function of heat dissipation of shielded-gate-type subway station tunnels with function of smoke exhaust of platform public area
CN203925558U (en) * 2014-06-24 2014-11-05 中铁第四勘察设计院集团有限公司 The short interval ventilation smoke exhaust structure of subway
CN104775840A (en) * 2015-04-10 2015-07-15 天津大学 Long and big subway tunnel longitudinal ventilation and smoke discharging system with mutually-standby smoke discharging air passages at two sides
CN205638522U (en) * 2016-05-27 2016-10-12 北京交科公路勘察设计研究院有限公司 Tunnel side direction is concentrated to discharge fume and is converted concentrated fume extractor in top to
CN205805596U (en) * 2016-06-28 2016-12-14 上海市隧道工程轨道交通设计研究院 Subway tunnel ventilation fume control system

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06264697A (en) * 1993-03-12 1994-09-20 Tetsuharu Ono Air-conditioning method for subway station
RU2463452C1 (en) * 2011-04-07 2012-10-10 Учреждение Российской академии наук Институт горного дела Сибирского отделения РАН Method of tunnel ventilation
CN203097921U (en) * 2013-02-22 2013-07-31 中铁第四勘察设计院集团有限公司 System integrating function of heat dissipation of shielded-gate-type subway station tunnels with function of smoke exhaust of platform public area
CN203925558U (en) * 2014-06-24 2014-11-05 中铁第四勘察设计院集团有限公司 The short interval ventilation smoke exhaust structure of subway
CN104775840A (en) * 2015-04-10 2015-07-15 天津大学 Long and big subway tunnel longitudinal ventilation and smoke discharging system with mutually-standby smoke discharging air passages at two sides
CN205638522U (en) * 2016-05-27 2016-10-12 北京交科公路勘察设计研究院有限公司 Tunnel side direction is concentrated to discharge fume and is converted concentrated fume extractor in top to
CN205805596U (en) * 2016-06-28 2016-12-14 上海市隧道工程轨道交通设计研究院 Subway tunnel ventilation fume control system

Cited By (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108952788A (en) * 2018-08-16 2018-12-07 中国安全生产科学研究院 A kind of method of underground station train fire ventilation smoke exhaust
CN109139079A (en) * 2018-09-17 2019-01-04 中铁四院集团西南勘察设计有限公司 Subway tunnel ventilating system
CN109252885A (en) * 2018-10-25 2019-01-22 中国安全生产科学研究院 A kind of subway underground station an island platform Fire Ventilation smoke evacuation system and method
CN110118099A (en) * 2019-06-03 2019-08-13 中国安全生产科学研究院 A kind of Fire Ventilation smoke exhaust method of sub-interchange platform
CN110118099B (en) * 2019-06-03 2020-04-07 中国安全生产科学研究院 Fire ventilation and smoke exhaust method for subway transfer station platform
CN110295939A (en) * 2019-07-08 2019-10-01 中铁第四勘察设计院集团有限公司 Road cooperates with platform smoke exhaust system to a kind of overall height gate standard subway station rail against the wind
CN111256287A (en) * 2020-01-21 2020-06-09 中国安全生产科学研究院 Distributed smoke exhaust system for subway station platform and air volume adjusting method
CN111255727A (en) * 2020-03-17 2020-06-09 中铁第四勘察设计院集团有限公司 Subway train platform and smoke exhaust method thereof
CN111980742A (en) * 2020-08-14 2020-11-24 中国安全生产科学研究院 Fire ventilation and smoke exhaust system and method for platform of separated island type subway underground station
CN111980742B (en) * 2020-08-14 2021-07-13 中国安全生产科学研究院 Fire ventilation and smoke exhaust system and method for platform of separated island type subway underground station
CN112253207A (en) * 2020-11-06 2021-01-22 天津大学 Intensive subway ventilation and smoke exhaust system
CN112282823A (en) * 2020-11-06 2021-01-29 天津大学 Regional control subway platform smoke exhaust method
CN112523773A (en) * 2020-12-11 2021-03-19 广州地铁设计研究院股份有限公司 Subway station environmental control system with wind pavilions arranged at single end
CN112983527A (en) * 2021-03-30 2021-06-18 中国安全生产科学研究院 Integrated station tunnel ventilation system and smoke exhaust method thereof
CN113339037A (en) * 2021-07-16 2021-09-03 广州地铁设计研究院股份有限公司 Point type exhaust and smoke exhaust station tunnel ventilation system without rail top air duct
CN113339037B (en) * 2021-07-16 2021-12-28 广州地铁设计研究院股份有限公司 Point type exhaust and smoke exhaust station tunnel ventilation system without rail top air duct
CN114198128A (en) * 2021-12-02 2022-03-18 中国安全生产科学研究院 System and method for ventilating and discharging smoke of fire disaster in atrium type subway station
CN114198128B (en) * 2021-12-02 2022-08-19 中国安全生产科学研究院 System and method for ventilating and discharging smoke of fire disaster in atrium type subway station

Also Published As

Publication number Publication date
CN108049905B (en) 2019-04-16

Similar Documents

Publication Publication Date Title
CN108049905A (en) A kind of totally-enclosed gate underground station platform fire ventilation smoke exhaust method of subway
CN109252885B (en) A kind of subway underground station an island platform Fire Ventilation smoke evacuation system and method
CN108533305B (en) The ventilation smoke exhaust method of train fire in a kind of Subway Tunnel
CN108952788B (en) A kind of method of underground station train fire ventilation smoke exhaust
CN206889006U (en) A kind of subway tunnel ventilating system
CN105318477A (en) Non-ventilation-pipeline inducing type ventilation and smoke exhaust system and ventilation and smoke exhaust method thereof
CN110295939A (en) Road cooperates with platform smoke exhaust system to a kind of overall height gate standard subway station rail against the wind
CN108035759A (en) A kind of underground railway tunnel fire ventilation smoke extraction system and method
KR101191592B1 (en) Selective point extraction ventilation method applied to active control
CN107261359A (en) A kind of inter-city passenger rail underground station public area is combined smoke evacuation system and smoke exhaust method
CN109139079A (en) Subway tunnel ventilating system
CN205858397U (en) Inclined shaft and positive hole ventilating system in constructing tunnel
CN106123241A (en) A kind of city indoor substation transformer chamber ventilation noise reduction system
CN102519110B (en) Subway platform ventilation and smoke removal distribution structure in station with opened-closed system
WO2018032498A1 (en) Method and system for pressurizing, supplying air, and blocking smoke in high-rise building stairwell
CN106762853A (en) A kind of denoising device for industrial fan
CN207278289U (en) The ventilating system of city tunnel
CN110778351B (en) Combined ventilation and smoke exhaust method for urban underground intercommunication tunnel
CN210599057U (en) Full-height platform door system subway station rail top air channel is platform system of discharging fume in coordination
CN207315426U (en) A kind of compound smoke evacuation system in inter-city passenger rail underground station public area
CN207437115U (en) A kind of underground railway tunnel fire ventilation smoke extraction system
CN105020833A (en) Workshop ventilation device
CN102513323B (en) Fume exhaust layout structure for subway platform and screen door system
CN210217035U (en) Annular pipe network system applied to building fire protection and smoke exhaust
CN107725090A (en) A kind of subterranean tunnel ventilating system and its implementation

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information

Inventor after: Shi Congling

Inventor after: Hou Zhengbo

Inventor after: Li Jian

Inventor after: Lv Jingmin

Inventor after: Xu Xuan

Inventor after: Shi Jiehong

Inventor after: He Li

Inventor after: Che Honglei

Inventor after: Wu Binbin

Inventor after: Zhao Chen

Inventor before: Shi Congling

Inventor before: Hou Zhengbo

Inventor before: Li Jian

Inventor before: Lv Jingmin

Inventor before: Xu Lv

Inventor before: Shi Jiehong

Inventor before: He Li

Inventor before: Che Honglei

Inventor before: Wu Binbin

Inventor before: Zhao Chen

CB03 Change of inventor or designer information
GR01 Patent grant