CN108049876A - A kind of construction method of compound stratum tunneling close range down bored tunnel - Google Patents

A kind of construction method of compound stratum tunneling close range down bored tunnel Download PDF

Info

Publication number
CN108049876A
CN108049876A CN201711114638.8A CN201711114638A CN108049876A CN 108049876 A CN108049876 A CN 108049876A CN 201711114638 A CN201711114638 A CN 201711114638A CN 108049876 A CN108049876 A CN 108049876A
Authority
CN
China
Prior art keywords
tunnel
shield
monitoring
construction
bored tunnel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201711114638.8A
Other languages
Chinese (zh)
Inventor
丁智
洪哲浩
张霄
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang University City College ZUCC
Original Assignee
Zhejiang University City College ZUCC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang University City College ZUCC filed Critical Zhejiang University City College ZUCC
Priority to CN201711114638.8A priority Critical patent/CN108049876A/en
Publication of CN108049876A publication Critical patent/CN108049876A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/003Linings or provisions thereon, specially adapted for traffic tunnels, e.g. with built-in cleaning devices
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/08Lining with building materials with preformed concrete slabs
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/06Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining
    • E21D9/0607Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining the shield being provided with devices for lining the tunnel, e.g. shuttering
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/12Devices for removing or hauling away excavated material or spoil; Working or loading platforms
    • E21D9/124Helical conveying means therefor

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Environmental & Geological Engineering (AREA)
  • Civil Engineering (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The present invention relates to a kind of construction method of compound stratum tunneling close range down bored tunnel, including:Constructing tunnel prepares;Come in and go out line bored tunnel preparation of construction;Monitoring measurement preparation before passing through;Control measure during shield crossing;Section of jurisdiction reinforces in shield tunnel;Monitoring frequency controls;Control is maked an inspection tour in hole.The beneficial effects of the invention are as follows:The method of the present invention step is simple, design is reasonable and construction is simple is convenient, and input cost is relatively low, and Practical Project operation implementation is strong;It can be improved down by the method for the invention and wear drivage efficiency, control attitude of shield machine, so as to reduce the possibility that accident occurs for tunnel, favourable basis is laid for follow-up successfully pass through;Practical value is high and using effect is good, compared to bored tunnel construction method is worn under existing, shortens the construction period, larger to reduce construction cost.

Description

A kind of construction method of compound stratum tunneling close range down bored tunnel
Technical field
It is near more particularly, to a kind of compound stratum shield the invention belongs to shield tunnel construction and reinforcement protection technical field The construction method of bored tunnel is worn under distance.
Background technology
In recent years, as city underground and the Large scale construction of related municipal works, the application of shield tunnel at home are got over Come more.It is the construction stage that Shield Construction Technique difficulty is big, process is more complicated that bored tunnel is worn under shield machine.Once processing is not When the soil body easily caves in or is lost in or even makes shield out of hand between structure.
Shield machine has many difficult points in through section work progress.For example it be easy to cause and backbreaks in shield tunneling process, partially From line direction, shield-tunneling construction is affected greatly;For another example shield shaping section of jurisdiction leak is more serious, ensures waterproof construction matter Amount avoids the leakage of underground water, can if dealing with improperly for ensuring that safety of subway operation and protection ambient enviroment are most important It further increases and destroys or even tunnel cave, life threatening and property safety can be caused.
Shield machine over long distances, on tunneled under earth pressure balance pattern in soft lower hard compound stratum, be easy to cause cutterhead and soil Storehouse mud lining can aggravate the abrasion of cutter, and periphery hobboing cutter is larger in the impact load suffered by soft or hard boundary position, be easy to cause rolling The cutter ring of knife bursts apart, and cutter is lost the job function, and the cleaning mud cake that opens a position can cause surface subsidence, influence ground and bored tunnel Safety.
The content of the invention
The purpose of the present invention is overcoming deficiency of the prior art, a kind of compound stratum tunneling close range down tunneling is provided The construction method in tunnel, method and step is simple, and design is rationally and easy construction, construction effect are good, can be to bored tunnel and shield It is effectively reinforced, the cycle is short and at low cost.
The purpose of the present invention is what is be achieved through the following technical solutions:
The construction method of this compound stratum tunneling close range down bored tunnel, comprises the following steps:
1) constructing tunnel prepares;
Amount of 1-1) being unearthed control:The amount of being unearthed is carried out before driving to control and make a record;Using high pressure water dabbing machine or other Mechanical dabbing machine carries out high pressure water cleaning to intending repairing section of jurisdiction ring progress dabbing to the surface after dabbing, until exposing coarse Strong surface;
1-2) synchronous grouting;
1-3) secondary grouting:Ring carries out secondary grouting after driving;
2) come in and go out line bored tunnel preparation of construction;
2-1) preliminary bracing:Shield bored tunnel preliminary bracing before driving, which will construct, to be completed;
2-2) advanced tubule is constructed:Advanced tubule is placed according to design requirement, using roof-bolter by advanced tubule It squeezes into, advanced tubule tail end is welded on steelframe;Aperture outside sealer occlusion catheter is used after advanced tubule installation, and it is pre- Stay grouting port;
2-3) preliminary bracing backfill slip casting behind;
2-4) reinforced in bored tunnel:According to reinforcement criteria reinforce in hole before shield crossing, using full framing pair Tunnel is reinforced, and shield can pass through after the completion of reinforcing;
3) monitoring measurement preparation before passing through;
3-1) monitoring and controlling:Tunnel monitoring project is ground settlement, Vault settlement, horizontal convergence and Tunnel Apparent observation;Stull axle power is set in full framing, the stull axle power of support system is monitored using pressure gauge, when passing through According to stress variation situation whether to being reinforced again in bored tunnel hole, carried out when need to reinforce in hole using No. 25 I-steel Transversely strengthening;
3-2) monitoring point is set:Tunnel layout of the monitoring points:Ground settlement, Vault settlement and horizontal convergence are laid, by shadow Ring section center line and lay a ground settlement point, first with the impact drilling when monitoring point is embedded, be then placed in subsidence survey point, measuring point with Separation layer between road surface is set, can start to measure after tested point complete stability;Full framing layout of the monitoring points:Pacify on full framing Pressure gauge is filled, initial value is taken and makes a record;
4) control measure during shield crossing;
4-1) shield driving state modulator:During tunneling construction, controlled according to the boring parameter drafted;Management soil amount, Screw conveyor rotating speed is determined according to cutterhead rotating speed;Strengthen monitoring during shield crossing bored tunnel, and according to monitoring number According to continuing to optimize and adjust boring parameter, constantly improve construction technology;
4-2) grouting and reinforcing controls;
4-3) secondary grouting controls:Added according to left line grouting and reinforcing region and right line grouting and reinforcing region institute's partition domain Gu;
5) section of jurisdiction reinforces in shield tunnel:Bored tunnel carries out median septum after the completion of shield driving and interim inverted arch is removed When, Shield simultaneously reinforces shaping section of jurisdiction, is reinforced using No. 20 channel steels;
6) monitoring frequency controls:It is monitored in real time in shield tunneling process, monitoring data notify shield when being more than early warning value Unit stops construction, evacuates personnel, and carries out consolidation process in bored tunnel hole;
7) control is maked an inspection tour in hole:Twenty four hours is observed in bored tunnel hole, and observation preliminary bracing surface whether there is Situations such as cracking, mud or slurry infiltration, as found to report and shutting down processing.
As preferred:In the step 7), when bored tunnel preliminary bracing deforms or hard stop during crack;When dark When substantial amounts of foam mud occurs for preliminary bracing of holing, cement grout is gushed out, hard stop, and carry out slip casting to gushing out position It reinforces, sondage checks whether still have foam mud, cement grout to gush out into a ring again after the completion of reinforcing, if there is then shutting down, such as It is no then at this slip casting have cavity, then continue sondage into.
The beneficial effects of the invention are as follows:
(1) method and step is simple, design is reasonable and construction is simple is convenient, and input cost is relatively low, and Practical Project operation is implemented Property is strong.
(2) it can be improved down by the method for the invention and wear drivage efficiency, attitude of shield machine be controlled, so as to reduce tunnel The possibility of generation accident lays favourable basis for follow-up successfully pass through.
(3) practical value is high and using effect is good, compared to bored tunnel construction method is worn under existing, shortens construction work It is phase, larger to reduce construction cost.
(4) it is widely applicable, all bored tunnel constructions can be effectively applicable to and shield reinforces the particularly ground such as compound stratum The geology of matter situation complexity has ensured that shield is subsequently passed through that everything goes well with your work and carried out.
Description of the drawings
Fig. 1 is the method flow block diagram of the present invention;
Fig. 2 is shield tunnel and the field wire vertical section relational graph that comes in and goes out;
Fig. 3 is that tunnel full framing reinforces schematic diagram;
Fig. 4 is that I-steel reinforces schematic diagram in hole;
Fig. 5 is shield consolidation grouting area schematic;
Fig. 6 is that Shield shaping section of jurisdiction reinforces schematic diagram;
Reference sign:Advanced tubule 1;Isolation pile 2;Full framing 3;No. 25 I-steel 4;Zuo Xian grouting and reinforcings area Domain 5;Right line grouting and reinforcing region 6;No. 20 channel steels 7.
Specific embodiment
The present invention is described further with reference to embodiment.The explanation of following embodiments is only intended to help to understand this Invention.It should be pointed out that for those skilled in the art, without departing from the principle of the present invention, also Can to the present invention some improvement and modification can also be carried out, these improvement and modification also fall into the protection domain of the claims in the present invention It is interior.
The construction method technological process of compound stratum tunneling close range down bored tunnel as shown in Figure 1.Shield crossing It is preceding according to reinforcement criteria reinforce in hole, using the method for supporting between 1 close tunnel of advanced tubule, using such as Fig. 3 institutes The full framing 3 shown reinforces its tunnel, and shield can pass through after the completion of reinforcing.And stull axis is set in full framing 3 Power is monitored support system using pressure gauge, the stull axle power of main monitoring system, according to stress variation situation when passing through Whether to being reinforced again in bored tunnel hole, during if you need to reinforce, in hole using No. 25 I-steel 4 as shown in Figure 4 into Row transversely strengthening.Using secondary grouting reinforcement measure as shown in Figure 5, reinforcing scope is left line grouting and reinforcing region 5 and right line Grouting and reinforcing region 6 respectively 60 ° above and below tunnel horizontal axis, amounts to 120 °.Bored tunnel carries out after the completion of shield driving When median septum and interim inverted arch are removed, Shield simultaneously reinforces shaping section of jurisdiction, uses 3 20 as shown in Figure 6 Number channel steel 7, which reinforce, prevents shaping segment deformation.It is as follows:
1. constructing tunnel prepares
The 1-1. amount of being unearthed controls
Special messenger is arranged to carry out this before driving to control and make a record.
Using high pressure water dabbing machine or other machinery dabbing machine to intending repairing section of jurisdiction ring progress dabbing, and to the table after dabbing Face carries out high pressure water cleaning, it is ensured that all cleans up sludge, the oil stain on section of jurisdiction, until exposing coarse strong surface.
1-2. synchronous grouting
The presetting period is 4.5~5h after synchronous grouting presses first wife's composition and division in a proportion mixing, and first wife's composition and division in a proportion is adjusted before driving, will Presetting period is controlled in 3.5~4h.
1-3. secondary grouting
Ring carries out secondary grouting after driving, prevents tunnel decompression.
2. come in and go out line bored tunnel preparation of construction
2-1. preliminary bracing
Shield bored tunnel preliminary bracing before driving must complete construction.
2-2. advanced tubules are constructed
Advanced tubule 1 is placed according to design requirement, is directly squeezed into using roof-bolter, 1 protruded length 0.3 of advanced tubule ~0.4m, strictly by design requirement, tail end is welded on steelframe outer limb.Advanced tubule 1 is led after installing with sealer closure Aperture outside pipe, and reserved grouting port.
2-3. preliminary bracings backfill slip casting behind
After 8~12m is completed in preliminary bracing, it is necessary to backfill slip casting behind is carried out, to consolidate scall and filling after hogback Gap that may be present, and stratum loosening and ground settlement are reduced to greatest extent.
It is reinforced in 2-4. bored tunnels
It must carry out reinforcing in hole according to reinforcement criteria before shield crossing, using full framing 3 as shown in Figure 3 to tunnel It is reinforced, stent spacing control shield after the completion of 0.5 × 0.6m, reinforcing can pass through.
3. monitoring measurement preparation before passing through
3-1. monitoring and controlling
Tunnel monitoring project is:Ground settlement, Vault settlement, horizontal convergence and the apparent observation of Tunnel. Full framing 3 sets stull axle power, support system is monitored using pressure gauge, the stull axle power of main monitoring system is worn According to stress variation situation whether to being reinforced again in bored tunnel hole when more, used in hole such as Fig. 4 institutes during if you need to reinforce No. 25 I-steel 4 shown carry out transversely strengthening.
3-2. monitoring points are set
Tunnel layout of the monitoring points:Ground settlement, Vault settlement and horizontal convergence are laid by spacing 5m, in impacted section Line lays a ground settlement point every 5m.First subsidence survey point is then placed in, measuring point is adopted with the impact drilling when monitoring point is embedded With 22 reinforcing bars of Φ, length 800mm.Separation layer is set between measuring point and road surface, it is ensured that measuring point and lower part soil solidifying and top road Face separates.After tested point complete stability, you can start to measure.
3 layout of the monitoring points of full framing:Pressure gauge is installed on full framing 3, before first 9m sections between 3 pressure gauges It is remaining to be laid by spacing 1.8m away from for 0.9m, it takes initial value and makes a record, if the axle power for measuring stull is smaller, The laying distance of pressure gauge is adjusted to 5m mono-.
4. the control measure during shield crossing
4-1. shield driving state modulators
During tunneling construction, controlled in strict accordance with the boring parameter drafted.
Stringent soil buret reason, screw conveyor rotating speed is determined according to cutterhead rotating speed.Per the control of the ring amount of being unearthed in 64m3Within, Reduce soil disturbance.
Shield axial line control off-design axis is not more than ± 20mm, forbids excess correction, snakelike swing when passing through.
Strengthen monitoring during shield crossing bored tunnel, and continued to optimize according to monitoring data and adjust driving ginseng Number, constantly improve construction technology.
4-2. grouting and reinforcings control
Synchronous grouting serous fluid of mending strictly presses cement:Fine sand:Flyash:Bentonite:Water=250:765:270:105:540 Match ratio carries out mix;
Synchronous grouting pressure controls:Top grouting pressure is 1.0~1.5bar, and lower part is 1.0~2.0bar, per ring slip casting Amount control is in 4.8~5.5m3
4-3. secondary groutings control
It is reinforced according to left line grouting and reinforcing region 5 as shown in Figure 5 and right 6 partition domains in line grouting and reinforcing region, Totally 120 °.Secondary grouting match ratio is in strict accordance with 1:1 carries out mix;The control of secondary grouting pressure is in 0.2~0.3MPa, the note per ring Slurry amount is controlled in 4.8m2Left and right.
5. section of jurisdiction reinforces in shield tunnel
When bored tunnel carries out median septum and the dismounting of interim inverted arch after the completion of shield driving, Shield is right simultaneously Shaping section of jurisdiction is reinforced, and using 3 No. 20 channel steels 7 reinforce prevents shaping segment deformation.
6. monitoring frequency controls
It is monitored in real time in shield tunneling process, monitoring frequency is no more than 20~30 minutes once, before and after shield driving Implement real-time monitoring (to monitor once and make a record before every ring driving, make a record when driving is monitored again after finishing, two Secondary record carries out comparison and checks whether the size of changing value meets the requirements), when the monitoring frequency after shield driving is 1 time/4 small. Shield unit is notified to stop construction when being more than early warning value such as monitoring data immediately, personnel is evacuated, and carries out bored tunnel hole in time Interior consolidation process, vault sinking amount must not exceed 40mm, and haunch everywhere convergent must not exceed 25mm, when measurement data is accumulated over permitting Perhaps report and shut down immediately during scope.
7. control is maked an inspection tour in hole
It arranges to be observed in bored tunnel hole when special messenger 24 is small, observer is divided into 3 people, and configures intercom, 1 people Monitoring room is arranged in, 1 people is arranged at bored tunnel well head, and 1 people is arranged at driving.Main detection preliminary bracing surface whether there is Cracking, mud, slurry infiltration situation etc. such as find to report immediately and shut down processing.
Processing method:
1) when bored tunnel preliminary bracing deforms or hard stop during crack.
2) when substantial amounts of foam mud occurs for bored tunnel preliminary bracing, cement grout is gushed out, hard stop, and to gushing Go out position and carry out grouting and reinforcing, sondage checks whether still have foam mud, cement grout to gush out into a ring again after the completion of reinforcing, such as Still hard stop sometimes, such as no longer when, illustrating at this that slip casting is not full is free hole, can continue sondage into.
The solution of the present invention is suitable for wearing bored tunnel construction under compound stratum shield, and shield and bored tunnel are added Gu.The present invention is using CRD method excavation constructions, the supporting between close tunnel using advanced tubule 1, and preliminary bracing is using behind The method for backfilling 3 supporting of grouting support combination full framing and No. 20 7 reinforcing shield sections of jurisdiction of channel steel, and during shield crossing Boring parameter and grouting and reinforcing are controlled, there are the advantages such as stability is high, speed of application is fast.And can guarantee construction quality, it ensures Everything goes well with your work carries out for follow-up shield crossing.

Claims (2)

1. a kind of construction method of compound stratum tunneling close range down bored tunnel, which is characterized in that comprise the following steps:
1) constructing tunnel prepares:
Amount of 1-1) being unearthed control:The amount of being unearthed is carried out before driving to control and make a record;Using high pressure water dabbing machine or other machinery Dabbing machine carries out high pressure water cleaning to intending repairing section of jurisdiction ring progress dabbing to the surface after dabbing, until exposing coarse strong Surface;
1-2) synchronous grouting;
1-3) secondary grouting:Ring carries out secondary grouting after driving;
2) come in and go out line bored tunnel preparation of construction:
2-1) preliminary bracing:Shield bored tunnel preliminary bracing before driving, which will construct, to be completed;
2-2) advanced tubule is constructed:Advanced tubule (1) is placed according to design requirement, using roof-bolter by advanced tubule (1) squeeze into, advanced tubule (1) tail end is welded on steelframe;With outside sealer occlusion catheter after advanced tubule (1) installation Aperture, and reserved grouting port;
2-3) preliminary bracing backfill slip casting behind;
2-4) reinforced in bored tunnel:According to reinforcement criteria reinforce in hole before shield crossing, using full framing (3) to tunnel Road is reinforced, and shield can pass through after the completion of reinforcing;
3) monitoring measurement preparation before passing through:
3-1) monitoring and controlling:Tunnel monitoring project is ground settlement, Vault settlement, horizontal convergence and Tunnel are apparent Observation;Stull axle power is set in full framing (3), the stull axle power of support system is monitored using pressure gauge, when passing through According to stress variation situation whether to being reinforced again in bored tunnel hole, No. 25 I-steel (4) are used when need to reinforce in hole Carry out transversely strengthening;
3-2) monitoring point is set:Tunnel layout of the monitoring points:Ground settlement, Vault settlement and horizontal convergence are laid, at impacted section Center line lays a ground settlement point, and first subsidence survey point, measuring point and road surface are then placed in the impact drilling when monitoring point is embedded Between separation layer is set, can start to measure after tested point complete stability;Full framing (3) layout of the monitoring points:On full framing (3) Pressure gauge is installed, initial value is taken and makes a record;
4) control measure during shield crossing:
4-1) shield driving state modulator:During tunneling construction, controlled according to the boring parameter drafted;Management soil amount, according to Cutterhead rotating speed determines screw conveyor rotating speed;During shield crossing bored tunnel strengthen monitoring, and according to monitoring data into Row optimizes and adjusts boring parameter to improve construction technology;
4-2) grouting and reinforcing controls;
4-3) secondary grouting controls:It is carried out according to left line grouting and reinforcing region (5) and right line grouting and reinforcing region (6) institute's partition domain It reinforces;
5) section of jurisdiction reinforces in shield tunnel:When bored tunnel carries out median septum and the dismounting of interim inverted arch after the completion of shield driving, Shield simultaneously reinforces shaping section of jurisdiction, is reinforced using No. 20 channel steels (7);
6) monitoring frequency controls:It is monitored in real time in shield tunneling process, shield unit is notified when monitoring data are more than early warning value Stop construction, evacuate personnel, and carry out consolidation process in bored tunnel hole;
7) control is maked an inspection tour in hole:Twenty four hours is observed in bored tunnel hole, observation preliminary bracing surface whether there is cracking, Situations such as mud or slurry infiltration, as found to report and shutting down processing.
2. the construction method of compound stratum tunneling close range down bored tunnel according to claim 1, it is characterised in that: In the step 7), when bored tunnel preliminary bracing deforms or hard stop during crack;When bored tunnel preliminary bracing is sent out When raw substantial amounts of foam mud, cement grout are gushed out, hard stop, and grouting and reinforcing is carried out to gushing out position, after the completion of reinforcing Sondage checks whether still have foam mud, cement grout to gush out into a ring again, if there is then shutting down, as without if there is slip casting at this Cavity, then continue sondage into.
CN201711114638.8A 2017-11-13 2017-11-13 A kind of construction method of compound stratum tunneling close range down bored tunnel Pending CN108049876A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711114638.8A CN108049876A (en) 2017-11-13 2017-11-13 A kind of construction method of compound stratum tunneling close range down bored tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711114638.8A CN108049876A (en) 2017-11-13 2017-11-13 A kind of construction method of compound stratum tunneling close range down bored tunnel

Publications (1)

Publication Number Publication Date
CN108049876A true CN108049876A (en) 2018-05-18

Family

ID=62119258

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711114638.8A Pending CN108049876A (en) 2017-11-13 2017-11-13 A kind of construction method of compound stratum tunneling close range down bored tunnel

Country Status (1)

Country Link
CN (1) CN108049876A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109184756A (en) * 2018-10-17 2019-01-11 中建八局轨道交通建设有限公司 For removing the device and method of negative endless tube piece in shield dark-excavated passageway
CN111335903A (en) * 2020-04-26 2020-06-26 粤水电轨道交通建设有限公司 Construction method for penetrating dense building group downwards in stratum of joint zone
CN111720125A (en) * 2020-05-15 2020-09-29 龙德建设有限公司 Construction process for tunnel underpass highway
CN112855262A (en) * 2021-01-15 2021-05-28 大连交通大学 Method for removing middle partition wall of newly-built subway station close-contact underpass existing station by PBA construction method

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002295172A (en) * 2001-03-30 2002-10-09 Taisei Corp Tunnel exterior lining method
CN101126318A (en) * 2007-09-28 2008-02-20 中铁二局股份有限公司 Shield construction method for three-line parallel under-passing trunk railway tunnel
CN101899977A (en) * 2010-02-04 2010-12-01 上海隧道工程股份有限公司 Ultra-shallow earth-covered subway shield traversing operation tunnel construction method of
CN103161470A (en) * 2011-12-13 2013-06-19 上海市基础工程有限公司 Construction method for shield machine to penetrate through large caliber pipeline in long distance
CN106285715A (en) * 2016-10-26 2017-01-04 中铁十局集团城市轨道工程有限公司 The construction method of a just bored tunnel is worn in balancing earth-pressure shielding machine closely side
CN206129278U (en) * 2016-10-26 2017-04-26 中铁十一局集团城市轨道工程有限公司 Earth pressure balance shield machine closely inclines and just props up undercut tunnel's construction structures

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002295172A (en) * 2001-03-30 2002-10-09 Taisei Corp Tunnel exterior lining method
CN101126318A (en) * 2007-09-28 2008-02-20 中铁二局股份有限公司 Shield construction method for three-line parallel under-passing trunk railway tunnel
CN101899977A (en) * 2010-02-04 2010-12-01 上海隧道工程股份有限公司 Ultra-shallow earth-covered subway shield traversing operation tunnel construction method of
CN103161470A (en) * 2011-12-13 2013-06-19 上海市基础工程有限公司 Construction method for shield machine to penetrate through large caliber pipeline in long distance
CN106285715A (en) * 2016-10-26 2017-01-04 中铁十局集团城市轨道工程有限公司 The construction method of a just bored tunnel is worn in balancing earth-pressure shielding machine closely side
CN206129278U (en) * 2016-10-26 2017-04-26 中铁十一局集团城市轨道工程有限公司 Earth pressure balance shield machine closely inclines and just props up undercut tunnel's construction structures

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109184756A (en) * 2018-10-17 2019-01-11 中建八局轨道交通建设有限公司 For removing the device and method of negative endless tube piece in shield dark-excavated passageway
CN109184756B (en) * 2018-10-17 2020-08-25 中建八局轨道交通建设有限公司 Device and method for removing negative ring duct piece in shield tunneling channel
CN111335903A (en) * 2020-04-26 2020-06-26 粤水电轨道交通建设有限公司 Construction method for penetrating dense building group downwards in stratum of joint zone
CN111720125A (en) * 2020-05-15 2020-09-29 龙德建设有限公司 Construction process for tunnel underpass highway
CN112855262A (en) * 2021-01-15 2021-05-28 大连交通大学 Method for removing middle partition wall of newly-built subway station close-contact underpass existing station by PBA construction method
CN112855262B (en) * 2021-01-15 2023-03-03 大连交通大学 Method for removing middle partition wall of newly-built subway station close-contact underpass existing station by PBA construction method

Similar Documents

Publication Publication Date Title
CN108049876A (en) A kind of construction method of compound stratum tunneling close range down bored tunnel
CN100501124C (en) Construction method for tunnel contact passage in shield section of underground railway
CN105804758B (en) Across constructing metro tunnel method on the rectangular top pipe of the shallow small spacing of earthing big cross section
CN102562099B (en) Method for carrying out rapid face excavation construction of loess tunnel by double rows of small conduits
CN102606167B (en) Settlement control construction method for transverse grouting guide pipe of shallow underground excavation tunnel
CN106437726B (en) Shallow-depth-excavation tunnel crosses ground fissure crushed zone construction method
CN108678776B (en) Sandy clay geological tunnel roof collapse treatment method
CN105370290A (en) Rectifying and reinforcing method of shield tunnels
CN106050245A (en) Supporting structure for zero distance underneath pass of existing station of rectangular tunnel section and construction method
CN106988750B (en) Implementation mode of ultra-short-distance underpass of existing station of large-span interval tunnel
CN105697033A (en) Construction method for treating rock mass cavity without formworks in tunneling
CN203961994U (en) Under balancing earth-pressure shielding machine, wear the concealed tunneling structure of having runed shield tunnel
CN109488334A (en) Deep hole grouting reinforcement means and equipment in shield tunnel
CN107542470A (en) Existing railway Business Line construction method is worn under the shallow tunnel of karst broken region
CN106014449A (en) Construction method of double-track small-clear distance large-section jointed rock mass subway tunnel
CN108533278A (en) Major diameter slurry shield earthing balances Integrated Receiver construction under the operating mode of complex environment highly permeable stratum
CN103628885A (en) Tunnel exit cover-excavation construction method of Ultra-shadow buried tunnel
CN110110489A (en) A kind of lithostratigraphy shield tunnel pressure from surrounding rock calculation method
CN203321531U (en) Lining processing structure for underground cavern after collapse of top arch
CN102817621B (en) Comprehensive construction method applicable to controlling arch basement sedimentation for tunnel in unfavorable geological conditions
CN104533451A (en) Tunnel advance pre-supporting technology used in discrete gravelly soil and broken surrounding rock
CN103993885A (en) Construction method for underground excavation tunnel side-direction hole opening supporting system
CN101793154A (en) Method for grouting for stopping up water by using geological parameters of tunnel surrounding rocks and setting relief holes
CN109386293A (en) The sealed reception construction method of large section rectangular top pipe
CN112901207A (en) Treatment method for collapse in tunnel during arch change of secondary lining in sulfate corrosion section of operation tunnel

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20180518