CN108049634A - The construction method of steel construction indirect cool tower cone segments - Google Patents
The construction method of steel construction indirect cool tower cone segments Download PDFInfo
- Publication number
- CN108049634A CN108049634A CN201711421666.4A CN201711421666A CN108049634A CN 108049634 A CN108049634 A CN 108049634A CN 201711421666 A CN201711421666 A CN 201711421666A CN 108049634 A CN108049634 A CN 108049634A
- Authority
- CN
- China
- Prior art keywords
- tripod
- construction
- cone segments
- inclination
- anchor point
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04H—BUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
- E04H12/00—Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
- E04H12/02—Structures made of specified materials
- E04H12/08—Structures made of specified materials of metal
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- Chemical & Material Sciences (AREA)
- Materials Engineering (AREA)
- Wood Science & Technology (AREA)
- Mechanical Engineering (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
A kind of construction method of steel construction indirect cool tower cone segments, including step:1) tripod surrounded by crossbeam and cant beam is made;2) tripod made of checking, pre-installed position is transported to after qualified;3) tripod is stood upside down and set;4) line that rises is installed in crossbeam both sides, and mobile anchor point is installed on corresponding ground;5) it is connected by the chain block line bottom that will rise with mobile anchor point;6) chain block, adjustment tripod angle of inclination are pulled;7) axis and the angle of inclination of tripod are observed by total powerstation, plumb aligner;8) after meeting design and code requirement, tripod is securely installed;9) step 3)~8 are repeated), remaining tripod circumference is installed;10) step 3)~9 are repeated), the remaining number of plies is installed, completes the construction of entire cone segments.Construction efficiency of the present invention is high, installation positioning is reliable;Drawing of rising is carried out to the line that rises with chain block and mobile anchor point, to complete the centering of tripod, and then realizes the installation of cone segments.
Description
Technical field
The present invention relates to steel construction indirect cool tower construction fields, are especially a kind of construction party of steel construction indirect cool tower cone segments
Method.
Background technology
Certain power plant creates the indirect cool tower of two steel construction types, it includes lower part cone segments, upper cylinder, reinforcing ring,
Broadening platform, upper tower cat ladder, peripheral protective aluminium sheet etc..The high 169.01m of head tower, the base diameter of lower part cone segments is 129.44m, height
Spend 55m, a diameter of 82m, the height 114.01m of upper cylinder.The indirect cool tower is by triangular mesh, reinforcing ring, broadening and outer
It goes along with sb. to guard him aluminium sheet to assemble, entire tower body is steel construction, and separate unit tower body steel structure weighs about 4102.2 tons, separate unit peripheral protective aluminium sheet
Weigh about 238 tons.Totally 5 layers of lower part centrum section, totally 13 layers of upper cylinder, every layer includes 36 groups of tripods, and single tripod is about
5.42 tons, wherein, have three layers reinforcing ring in Upper cylindrical body, about 166.45 tons of every layer of reinforcing ring, height respectively 90.08m,
125.16m and 160.24m.Entire tower body is sealed to form (about 42868 ㎡) by aluminium alloy contour plate.
Since the cone segments of above-mentioned steel construction indirect cool tower are there are angle of inclination, and heavier-weight, using conventional construction method
Its installation requirement can not be met, therefore, it is necessary to design a set of practicable arrangement and method for construction, to realize its installation.
The content of the invention
The technical problem to be solved by the present invention is to provide cold between a kind of construction efficiency height, the reliable steel construction of installation positioning
The construction method of tower cone segments carries out drawing of rising with chain block and mobile anchor point to the line that rises, to complete the centering of tripod,
And then realize the installation of cone segments.
The technical solution of the present invention is to provide a kind of construction method of steel construction indirect cool tower cone segments, including as follows
Step:
1) tripod is made, which is enclosed and made by a steel structure beam and two steel construction cant beams;
2) quality examination is carried out to several tripods to complete, carries it to steel construction indirect cool tower after qualified and pacify in advance
Holding position;
3) tripod is stood upside down and set;
4) line that rises is installed in crossbeam both sides, and mobile anchor point is installed on corresponding ground;
5) it is connected by the chain block line bottom that will rise with mobile anchor point;
6) chain block is pulled, adjusts the angle of inclination of tripod;
7) axis and the angle of inclination of tripod are observed by the total powerstation, the plumb aligner that set up in advance;
8) after axis and angle of inclination meet design and code requirement, tripod is securely installed by spot welding;
9) step 3)~8 are repeated), by the circumference installation by drawing of remaining tripod of this layer;
10) step 3)~9 are repeated), the tripod in the remaining number of plies is installed, is finally completed applying for entire cone segments
Work.
After more than structure, compared with prior art, the construction method of steel construction indirect cool tower cone segments of the present invention has
Advantages below:The present invention first installs single tripod, and then the line that rises is carried out by chain block and mobile anchor point
Rise drawing, to complete its centering, then remaining tripod is installed one by one again, the construction for being finally completed entire cone segments is made
Industry;The present invention is this higher to the modularization installation efficiency of cone segments, and it is reliable to install positioning.
Specific embodiment
The construction method of steel construction indirect cool tower cone segments of the present invention is made With reference to embodiment further detailed
Explanation:
In this embodiment, the construction method of steel construction indirect cool tower cone segments of the present invention, includes the following steps:
1) tripod is made, which is enclosed and made by a steel structure beam and two steel construction cant beams;
2) quality examination is carried out to several tripods to complete, carries it to steel construction indirect cool tower after qualified and pacify in advance
Holding position;
3) tripod is stood upside down by crane and set;
4) line that rises is installed in crossbeam both sides, and mobile anchor point is installed on corresponding ground;
5) it is connected by the chain block line bottom that will rise with mobile anchor point;
6) chain block is pulled, adjusts the angle of inclination of tripod;
7) axis and the angle of inclination of tripod are observed by the total powerstation, the plumb aligner that set up in advance;
8) after axis and angle of inclination meet design and code requirement, tripod is securely installed by spot welding;
9) step 3)~8 are repeated), by the circumference installation by drawing of remaining tripod of this layer;
10) step 3)~9 are repeated), the tripod in the remaining number of plies is installed, is finally completed applying for entire cone segments
Work.
The present invention first installs single tripod, is then risen by chain block and mobile anchor point to the line that rises
It draws, to complete its centering, then remaining tripod is installed one by one again, is finally completed the construction operation of entire cone segments;
The present invention is this higher to the modularization installation efficiency of cone segments, and it is reliable to install positioning.
Embodiment described above is only that the preferred embodiment of the present invention is described, not to the model of the present invention
It encloses and is defined, on the premise of design spirit of the present invention is not departed from, those of ordinary skill in the art are to the technical side of the present invention
The various modifications and improvement that case is made, should all fall within the scope of protection of the present invention.
Claims (1)
1. a kind of construction method of steel construction indirect cool tower cone segments, which is characterized in that include the following steps:
1) tripod is made, which is enclosed and made by a steel structure beam and two steel construction cant beams;
2) quality examination is carried out to several tripods to complete, is carried it after qualified to steel construction indirect cool tower and pre-install position
It puts;
3) tripod is stood upside down and set;
4) line that rises is installed in crossbeam both sides, and mobile anchor point is installed on corresponding ground;
5) it is connected by the chain block line bottom that will rise with mobile anchor point;
6) chain block is pulled, adjusts the angle of inclination of tripod;
7) axis and the angle of inclination of tripod are observed by the total powerstation, the plumb aligner that set up in advance;
8) after axis and angle of inclination meet design and code requirement, tripod is securely installed by spot welding;
9) step 3)~8 are repeated), by the circumference installation by drawing of remaining tripod of this layer;
10) step 3)~9 are repeated), the tripod in the remaining number of plies is installed, is finally completed the construction of entire cone segments.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201711421666.4A CN108049634A (en) | 2017-12-25 | 2017-12-25 | The construction method of steel construction indirect cool tower cone segments |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201711421666.4A CN108049634A (en) | 2017-12-25 | 2017-12-25 | The construction method of steel construction indirect cool tower cone segments |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108049634A true CN108049634A (en) | 2018-05-18 |
Family
ID=62131085
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201711421666.4A Pending CN108049634A (en) | 2017-12-25 | 2017-12-25 | The construction method of steel construction indirect cool tower cone segments |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108049634A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110409832A (en) * | 2019-08-07 | 2019-11-05 | 上海市机械施工集团有限公司 | A kind of construction method of tapered building structure |
CN110552542A (en) * | 2019-08-07 | 2019-12-10 | 上海市机械施工集团有限公司 | Construction method of conical building structure |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101852019A (en) * | 2010-06-11 | 2010-10-06 | 北京市机械施工有限公司 | Lifting mounting method for inclined steel roof |
CN101915567A (en) * | 2010-07-30 | 2010-12-15 | 陕西建工集团机械施工有限公司 | Method for measuring and positioning inclined structure of high-rise building |
CN105858435A (en) * | 2016-04-26 | 2016-08-17 | 中国海洋石油总公司 | Technology for hoisting strip-shaped inclined steel structures in place through single crane |
CN106759883A (en) * | 2016-11-30 | 2017-05-31 | 上海市机械施工集团有限公司 | The tower crane construction method of large-scale steel structure air cooling tower |
-
2017
- 2017-12-25 CN CN201711421666.4A patent/CN108049634A/en active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101852019A (en) * | 2010-06-11 | 2010-10-06 | 北京市机械施工有限公司 | Lifting mounting method for inclined steel roof |
CN101915567A (en) * | 2010-07-30 | 2010-12-15 | 陕西建工集团机械施工有限公司 | Method for measuring and positioning inclined structure of high-rise building |
CN105858435A (en) * | 2016-04-26 | 2016-08-17 | 中国海洋石油总公司 | Technology for hoisting strip-shaped inclined steel structures in place through single crane |
CN106759883A (en) * | 2016-11-30 | 2017-05-31 | 上海市机械施工集团有限公司 | The tower crane construction method of large-scale steel structure air cooling tower |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110409832A (en) * | 2019-08-07 | 2019-11-05 | 上海市机械施工集团有限公司 | A kind of construction method of tapered building structure |
CN110552542A (en) * | 2019-08-07 | 2019-12-10 | 上海市机械施工集团有限公司 | Construction method of conical building structure |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101263301B (en) | Method of mounting elements inside a wind generator tower | |
CN104018514B (en) | Large Towers kind equipment basis pre-embedded anchoring bolts inversion construction method | |
KR20080016478A (en) | Flangeless support structures | |
CN202398970U (en) | Steel cylinder folding tool | |
US10748666B2 (en) | Head module, large-scale container and method for manufacturing the both | |
CN108049634A (en) | The construction method of steel construction indirect cool tower cone segments | |
CN105345288A (en) | Power-driven chain block combination device for installing desulfurizing tower and installation method | |
CN105544994A (en) | Unloading device used for steel structure support and unloading method thereof | |
JPWO2012137671A1 (en) | Construction method of cylindrical tank | |
CN112609832A (en) | Nuclear power station nuclear island double-shell dome arch membrane forming construction method and construction jig frame | |
CN103903663B (en) | The manufacture method of tun especially steel containment vessel of nuclear power station | |
CN111852169B (en) | Method for mounting tower type exhaust funnel | |
CN110984642A (en) | Construction method for large-diameter hyperbolic cooling tower cylinder wall | |
CN202465194U (en) | Large-size modularized component transporting device of steel containment vessel of nuclear power station nuclear island | |
CN107267165B (en) | A kind of dry coke quenching furnace body is circular layout pre-embedded bolt fixed structure and installation method | |
CN108086784A (en) | The construction method of steel construction indirect cool tower upper cylinder | |
JP6018865B2 (en) | Construction method of cylindrical tank | |
CN107352464A (en) | A kind of hydraulic jacking device being flip-chip mounted for reducer among medium-and-large-sized case tank | |
CN210067466U (en) | Vertical storage tank flip-chip method roof construction location and support mould | |
WO2014208705A1 (en) | Method for constructing cylindrical tank | |
CN208083834U (en) | A kind of flange means for correcting | |
CN105064681A (en) | Installing method of steel structure foundation screw bolt | |
CN210739551U (en) | Flange pipeline centering device | |
CN206407077U (en) | The seaborne fixing device of module | |
CN104074366B (en) | A kind of underground nuclear power station reactor cavern containment dome installation structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
CB02 | Change of applicant information |
Address after: 230000 East Fozhang Road and North Tingyun Road Office Building, Hefei Economic and Technological Development Zone, Anhui Province Applicant after: China National Chemical Engineering Third Construction Co., Ltd. Address before: 232038 No. 98 Dongshan Road, Tianjiaan District, Huainan City, Anhui Province Applicant before: China National Chemical Engineering Third Construction Co., Ltd. |
|
CB02 | Change of applicant information | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20180518 |
|
RJ01 | Rejection of invention patent application after publication |