CN108049396A - Cast-in-situ bored pile churning driven sleeve drilling construction method - Google Patents

Cast-in-situ bored pile churning driven sleeve drilling construction method Download PDF

Info

Publication number
CN108049396A
CN108049396A CN201711397918.4A CN201711397918A CN108049396A CN 108049396 A CN108049396 A CN 108049396A CN 201711397918 A CN201711397918 A CN 201711397918A CN 108049396 A CN108049396 A CN 108049396A
Authority
CN
China
Prior art keywords
sleeve
drilling
hole
cast
churning driven
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201711397918.4A
Other languages
Chinese (zh)
Inventor
李拥政
丁武聚
李永敬
彭绪
赵宝双
谷庆
白耀辉
段沛材
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway No 3 Engineering Group Co Ltd
Huadong Construction Co Ltd of China Railway No 3 Engineering Group Co Ltd
Original Assignee
China Railway No 3 Engineering Group Co Ltd
Huadong Construction Co Ltd of China Railway No 3 Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway No 3 Engineering Group Co Ltd, Huadong Construction Co Ltd of China Railway No 3 Engineering Group Co Ltd filed Critical China Railway No 3 Engineering Group Co Ltd
Priority to CN201711397918.4A priority Critical patent/CN108049396A/en
Publication of CN108049396A publication Critical patent/CN108049396A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/38Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
    • E02D5/385Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds with removal of the outer mould-pipes
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • E02D15/04Placing concrete in mould-pipes, pile tubes, bore-holes or narrow shafts
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • E02D15/06Placing concrete under water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/66Mould-pipes or other moulds
    • E02D5/665Mould-pipes or other moulds for making piles
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B17/00Drilling rods or pipes; Flexible drill strings; Kellies; Drill collars; Sucker rods; Cables; Casings; Tubings
    • E21B17/02Couplings; joints
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B7/00Special methods or apparatus for drilling
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0023Cast, i.e. in situ or in a mold or other formwork

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geology (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • Fluid Mechanics (AREA)
  • Environmental & Geological Engineering (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Physics & Mathematics (AREA)
  • Mechanical Engineering (AREA)
  • Earth Drilling (AREA)

Abstract

The invention discloses a kind of cast-in-situ bored pile churning driven sleeve drilling construction methods, it is related to bored pile construction, a kind of cast-in-situ bored pile churning driven sleeve drilling construction method is intended to provide, has the advantages that be convenient for taking out in the soil in sleeve, its key points of the technical solution are that:Step 1:Preparation of construction makes including fabrication of reinforcing cage, measurement and positioning setting-out, sleeve design;Step 2:Rotary drilling rig is in place, and sleeve rotating follow-up construction is driven by sleeve coupler using rotary drilling rig;Step 3:More bit change;Step 4:It fetches earth, drilled to designed elevation in sleeve;Step 5:Drilled-hole inspecting;Step 6:Borehole cleaning checks sediment thickness;Step 7:Place steel reinforcement cage, conduit;Step 8:Check sediment thickness, secondary pile hole cleaning;Step 9:Underwater concreting;Step 10:Churning driven extracts sleeve;Step 11:Pore-forming.

Description

Cast-in-situ bored pile churning driven sleeve drilling construction method
Technical field
The present invention relates to bored pile construction, more particularly to a kind of cast-in-situ bored pile churning driven sleeve drilling construction side Method.
Background technology
Embedded casing is the important construction procedure of bored pile construction, and the cylinder s buried depth is according to the geology of construction site Hydrologic condition determines that casing mainly plays positioning, drilling is oriented to, protects the effects that aperture, clearance hole endoporus extexine water.It buries at present If the main method of the long casing of major diameter has gravity press-in, jetting sinking and vibration-sunk etc., mainly utilize in the world at present Casing driver, one end connection churning driven drilling rod, one end connection drive sleeve.
It is miscellaneous to fill out but when constructing when in the deep miscellaneous fill layer containing a large amount of stones and brick, concrete construction rubbish Soil layer is widely distributed in 0 ~ 6m Layer thickness, generally buries casing using soil removal and replacement open cut, then using convolution drilling machine or impact Drilling machine construction drilled pile, since miscellaneous fill layer thickness is at 6 meters or so, it has not been convenient to soil removal and replacement, therefore cause constructional difficulties.
The content of the invention
The object of the present invention is to provide a kind of cast-in-situ bored pile churning driven sleeve drilling construction methods, have and are convenient for sleeve The advantages of interior soil takes out.
The present invention above-mentioned technical purpose technical scheme is that:
A kind of cast-in-situ bored pile churning driven sleeve drilling construction method, comprises the following steps:
Step 1:Preparation of construction makes including fabrication of reinforcing cage, measurement and positioning setting-out, sleeve design;
Step 2:Rotary drilling rig is in place, and sleeve rotating follow-up construction is driven by sleeve coupler using rotary drilling rig;
Step 3:More bit change;
Step 4:It fetches earth, drilled to designed elevation in sleeve;
Step 5:Drilled-hole inspecting;
Step 6:Borehole cleaning checks sediment thickness;
Step 7:Place steel reinforcement cage, conduit;
Step 8:Check sediment thickness, secondary pile hole cleaning;
Step 9:Underwater concreting;
Step 10:Churning driven extracts sleeve;
Step 11:Pore-forming.
By using above-mentioned technical proposal, by sleeve coupler sleeve rotating is driven to follow up using rotary drilling rig, make set Cylinder passes through the deep miscellaneous fill layer containing the building wastes such as a large amount of stones and brick, concrete, and sleeve replaces conventional bore afterwards in place Head fetches earth, and the drilling operation that fetches earth is completed in sleeve, until pore-forming, follow-up by installation steel reinforcement cage, pour underwater concrete, pours After using rotary drilling rig pull out sleeve pile, easy to operate, construction efficiency is high, and pile quality is good, saves cost.
The present invention is further set to:If the sleeve in step 1 includes hollow cylinder, is circumferentially opened in cylinder upper end Dry L-type slot and the circumferential several cutting tooths for being welded on cylinder lower end, direction and the drilling machine of the cutting tooth setting angle rotate Direction is consistent.
By using above-mentioned technical proposal, cut pin tooth block and arrange stone with the rotary squeezing of rotary digging sleeve, after facilitating sleeve in place Drill bit fetches earth.
The present invention is further set to:Sleeve coupler in step 2 includes rotation tooth plate, along rotating, tooth plate is circumferentially fixed And be connected with L-type slot notch snap-gauge, be arranged on rotation tooth plate upper end and the tooth that with drilling machine drilling rod axis pin is used to be connected Plate connecting plate offers the pin hole passed through for axis pin, the axis pin and pin hole tight fit on the truss plate connection plate.
By using above-mentioned technical proposal, sleeve coupler is with rotary digging sleeve L-type slot notch using the mode that is connected, energy It contacts with each other, is completely embedded when connector and sleeve being made to work, axis pin and pin hole tight fit prevent sleeve coupler from being taken off with sleeve From churning driven is empty to be bored.
The present invention is further set to:The rotation tooth plate is made of the Q345 steel plates of 60 × 60cm thickness 40mm.
By using above-mentioned technical proposal, Q345 steel plate comprehensive mechanical properties are good, and cryogenic property, plasticity and weldability are good Good, easy to process, the rotation tooth plate of thickness 40mm reduces the deformation of rotation tooth plate in use.
The present invention is further set to:After the notch snap-gauge is caught in the L-type slot of sleeve completely, the notch snap-gauge extends Cylinder 25mm.
By using above-mentioned technical proposal, notch snap-gauge extends cylinder 25mm, reduces notch snap-gauge and is driving cylinder rotation L-type slot is skidded off when turning so that rotary drilling rig is empty to be bored.
The present invention is further set to:The rotation follow-up construction of step 2 middle sleeve includes,
A. rotary digging sleeve orientation sets pile foundation center using total powerstation survey, makes rotary digging sleeve Xia Kou centers and stake position center weight It closes, sleeve is observed along line direction and the gradient in horizontal path direction using total powerstation during rotary digging sleeve orientation;
B. rotary digging sleeve follows up, and sleeve coupler rotation drives rotary digging sleeve rotating to bury sleeve, and drilling machine 5 ~ 8r/min of rotating speed is bored Mantle cylinder top surface is higher by level of ground water 2m, and is higher by construction ground 0.3m, and height should meet the requirement of mud face height in hole;
C. rotary digging sleeve orientation is checked, and after sleeve is buried, rotary digging bushing core position and rotary digging sleeve verticality are carried out It checks, rotary digging bushing core tolerance≤± 20mm, verticality≤1%.
By using above-mentioned technical proposal, during rotary digging sleeve orientation using total powerstation observe sleeve along line direction and The gradient in horizontal path direction, it is ensured that drill rod axis are overlapped with sleeve axis, complete the orientation works of rotary digging sleeve, rotary digging set Cylinder follow-up, the review of rotary digging sleeve orientation is all beneficial in the vertical insertion soil layer of sleeve, beneficial to pore-forming.
The present invention is further set to:It fetches earth, drill in step 4 middle sleeve and be specially to designed elevation:
A. after sleeve is buried, slowly reversion makes sleeve coupler exit L-type slot notch to rotary drilling rig, checks sleeve verticality and hole Position deviation;
B. the axis pin that sleeve coupler is connected with drilling rod is removed, axis pin is removed tapping and pulled out slowly;Sleeve coupler is unloaded, is replaced normal Cylinder drilling fetches earth;
C. rotary digging drilling pipe drilling row boring extracting soil, cylinder bores leaf of hinge open-angle and should not be too large during fetching earth, and meets stone and erratic boulder, Drill bit is taken to invert and increase drilling machine driving torque, is squeezed to hole wall periphery;
D. the loose caving ground such as deep miscellaneous fill layer is using static mud protecting wall drilling and forming hole, the following Muddy Bottoms of sleeve bottom Farinose argillic horizon drilling is control drilling parameter, ensures hole quality;
Should be first slow rear fast when e. creeping into, between specific gravity of mud control 1.05~1.10, sand factor is not more than 2%, creeps into There is the mud index of defined head and requirement in journey in retaining hole, with avalanche prevention hole;
F. crept into, drilled using low speed when starting to creep into or through deep miscellaneous fill layer and very soft sill clay intersection According to geological condition controlled footage speed in journey, vertical degree detection is carried out to drilling rod as the case may be;
G. in drilling process, the promotion speed and decrease speed of drilling rod are controlled;Drilling rod lifting speed is maintained at 0.75~ 0.80m/s。
By using above-mentioned technical proposal so that drilling rod prevents the hole that collapses during fetching earth, and ensures drilling rod vertical shift, carries High hole quality.
The present invention is further set to:Drilled-hole inspecting in step 5 is specially:Pore-forming inspection should be carried out after Completion of Drilling Hole, into Recovery hole position central point is answered in the detection of Kong Kongwei centers, is measured using dipstick metering inclined along circuit direction and horizontal path direction position Difference;Pore-forming Pore Diameter Detection uses cage inspecting hole device, and the detection of pore-forming gradient is detected using cage inspection hole device, and depth of pore forming detection is suitable It is directly measured using lining rope, hole depth should be measured along hole Zhou Jinhang, and first time borehole cleaning should be met the requirements of the standard after pore-forming.
By using above-mentioned technical proposal, pore-forming Pore Diameter Detection uses cage inspecting hole device, is subject to and examines hole device and pass through, Inspecting hole device should hang and put down gently slowly, prevent inspecting hole device is swung from destroying pit protection mud cake, convenient for follow-up concreting.
The present invention is further set to:Underwater concreting in step 9, using catheter perfusion, perfusion dummy pipe is tried Spell pressure testing, must not leak, the water pressure of pressure testing is 1.5 times of bottom hole hydrostatic pressure;Conduit bottom away from hole bottom distance 0.3m ~ 0.5m, the embedding concrete depth of conduit are not more than 6m, and not less than 2m.
By using above-mentioned technical proposal, try to spell pressure testing before catheter perfusion, reduce conduit leakage during slip casting, protect Card slip casting process is smoothed out.
The present invention is further set to:In step 10 churning driven extract sleeve be specially according to first rotating, after pull out order and apply Work, installation sleeve connector start to bore to dig and bore occlusion sleeve, and churning driven slowly rotates, and rotary speed is not more than 5r/min.
By using above-mentioned technical proposal, rotary digging sleeve pulls out speed should not be too fast, prevents the concrete completed to perfusion It causes to disturb, influences pile quality, while measure rotary digging sleeve inner concrete sedimentation situation.
In conclusion the invention has the advantages that:Containing the building wastes such as a large amount of stones and brick, concrete Deep miscellaneous fill layer in boring extracting soil when, drive sleeve rotating follow-up construction by using rotary drilling rig, subsequent more bit change, Facilitate in sleeve and fetch earth, drill to designed elevation, easy to operate, construction efficiency is high, and pile quality is good, saves cost.
Description of the drawings
Fig. 1 is the present embodiment cast-in-situ bored pile churning driven sleeve drilling construction method schematic diagram;
Fig. 2 is the structure diagram that the present embodiment is used to embody sleeve;
Fig. 3 is the enlarged structure schematic diagram in A portions in Fig. 2;
Fig. 4 is the present embodiment middle sleeve rotation follow-up construction method schematic diagram;
Fig. 5 is to fetch earth, drilled to the construction method schematic diagram of designed elevation in the present embodiment middle sleeve.
In figure, 1, cylinder;11st, L-type slot;12nd, cutting tooth;13rd, tooth plate is rotated;14th, notch snap-gauge;15th, truss plate connection plate; 16th, axis pin;17th, pin hole.
Specific embodiment
The present invention is described in further detail below in conjunction with attached drawing.
A kind of cast-in-situ bored pile churning driven sleeve drilling construction method, such as Fig. 1 comprise the following steps:
Step 1:Preparation of construction makes including fabrication of reinforcing cage, measurement and positioning setting-out, sleeve design.
Such as Fig. 2, sleeve design makes:Sleeve includes hollow cylinder 1, the circumferential several L-type slots for being opened in 1 upper end of cylinder 11(Such as Fig. 3)And the circumferential several steel alloy cutting tooths 12 for being welded on 1 lower end of cylinder, the direction of 12 setting angle of cutting tooth with Drilling machine direction of rotation is consistent, prevents that cutting tooth 12 drops during sleeve rotating.
Such as Fig. 3, rotary digging sleeve should have enough rigidity and intensity, select the Q345 steel plates processing of δ=20mm, made Into rear enclosure tube length 6m, internal diameter φ 0.87m are bigger 7cm than stake footpath.Rotary digging sleeve is suitable for reading to be cut using cutting machine along rotary digging sleeve is circumferential 15 × 10cm adjacent centers spacing is the L-type slot 11 of 47cm.Cutting tooth 12 is closed using the high-strength high-ductility hard of gear wheel shape Golden tooth, circumferentially disposed 6 along sleeve, center spacing 45.5cm;Cutting tooth 12 is embedded in sleeve bottom, using conventional arc weld into Row welding, welding current are stablized, it is ensured that the defects of weld seam is without slag inclusion, stomata, crackle.
Step 2:Such as Fig. 1, rotary drilling rig is in place, and rotary drilling rig model FR360D is connected using rotary drilling rig by sleeve It connects device and drives sleeve rotating follow-up construction.
Rotary drilling rig is specially in place:Drilling machine prepares in place, the locking situation of safety pin is checked before drilling machine walking, drilling machine is just Anti-inclining measure can be taken during position;Drilling machine drives to the hole to be constructed position, adjusts mast angle, operates hoist engine, will bore Head center is aligned with drill center, and is put into hole, is adjusted drilling machine verticality parameter, is made drilling rod vertical, drilling rod slope is less than 1%.The centrical deviation in sleeve coupler center and hole is not greater than 20mm;Drilling machine carries out test running afterwards in place, after working well Sleeve coupler is replaced, promotes sleeve coupler occlusion sleeve notch, align piles position prepares sleeve follow-up construction.
Such as Fig. 3, sleeve coupler includes rotation tooth plate 13, along rotation tooth plate 13 circumferentially fixed and be connected with L-type slot 11 Notch snap-gauge 14 is arranged on truss plate connection plate that is rotating 13 upper end of tooth plate and with drilling machine drilling rod axis pin 16 being used to be connected 15, the pin hole 17 passed through for axis pin 16, axis pin 16 and 17 tight fit of pin hole are offered on truss plate connection plate 15.
Such as Fig. 3, rotation tooth plate 13 is made of the Q345 steel plates of 60 × 60cm thickness 40mm, Q345 steel plates synthesis mechanical property Can be good, cryogenic property, plasticity and weldability are good, easy to process, on rotation tooth plate 13, along 13 center of rotation tooth plate The notch snap-gauge 14 of circumferential erecting and welding, notch snap-gauge 14 long 18cm, wide 3cm, 14 erecting and welding position of notch snap-gauge and rotary digging Sleeve 11 mouthfuls of correspondences of L-type slot suitable for reading, after being caught in 11 mouthfuls of the L-type slot of rotary digging sleeve completely, 14 exposed 25mm of notch snap-gauge.
Such as Fig. 3,11 notch of L-type slot of sleeve coupler and rotary digging sleeve uses the mode that is connected, can make sleeve connection Device and sleeve contact with each other when working, and are completely embedded, truss plate connection plate 15 is connected with drilling machine drilling rod using axis pin 16, axis pin 16 junctions can also set locking device(It is not shown in figure), if locking device is to be threaded in axis pin 16 to stretch out tooth plate company The locking nut at 15 both ends of fishplate bar prevents sleeve coupler from departing from sleeve, and rotary drilling rig is empty to be bored.
Such as Fig. 4, the follow-up construction of rotary digging sleeve:
A. rotary digging sleeve orientation sets pile foundation center using total powerstation survey, makes rotary digging sleeve Xia Kou centers and stake position center weight It closes, sleeve is observed along line direction and the gradient in horizontal path direction using total powerstation during rotary digging sleeve orientation, it is ensured that Drill rod axis are overlapped with sleeve axis, complete the orientation works of rotary digging sleeve;
B. rotary digging sleeve follows up, and sleeve coupler rotation drives rotary digging sleeve rotating to bury sleeve, 5 ~ 8r/min of drilling machine rotating speed.It bores Mantle cylinder top surface is higher by level of ground water 2m, and is higher by construction ground 0.3m, and what height should still meet mud face height in hole will It asks;
C. rotary digging sleeve orientation is checked, and after sleeve is buried, rotary digging bushing core position and rotary digging sleeve verticality are carried out It checks, rotary digging bushing core tolerance≤± 20mm, verticality≤1%.
Such as Fig. 1, step 3:More bit change.
Step 4:It fetches earth, drilled to designed elevation, such as Fig. 5 in sleeve, concrete operations are:
A. after sleeve is buried, slowly reversion makes sleeve coupler exit notch to rotary drilling rig, checks sleeve verticality and hole position partially Difference;
B. the axis pin that sleeve coupler is connected with drilling rod is removed, axis pin is removed tapping and pulled out slowly, prevents axis pin from dropping out pin hole suddenly;It unloads It traps coupling sleeve, replaces normal cylinder drilling and fetch earth;
C. rotary digging drilling pipe drilling row boring extracting soil, cylinder bores leaf of hinge open-angle and should not be too large during fetching earth, and meets stone and erratic boulder, Drill bit is taken to invert and increase drilling machine driving torque, is squeezed to hole wall periphery;
D. the loose caving ground such as deep miscellaneous fill layer is using static mud protecting wall drilling and forming hole, the following Muddy Bottoms of sleeve bottom Farinose argillic horizon drilling is control drilling parameter, ensures hole quality;
Should be first slow rear fast when e. creeping into, between specific gravity of mud control 1.05~1.10, sand factor is not more than 2%.It crept into There is the mud index of defined head and requirement in journey in retaining hole, with avalanche prevention hole;
F. crept into when starting to creep into or through deep miscellaneous fill layer and very soft sill clay intersection using low speed.It drilled According to geological condition controlled footage speed in journey, vertical degree detection is carried out to drilling rod as the case may be, prevents drilling rod because can not Governing factor and change, influence hole quality;
G. in drilling process, the promotion speed and decrease speed of drilling rod are controlled.Drilling bucket lifting speed is maintained at 0.75~ 0.80m/s。
Such as Fig. 1, step 5:Drilled-hole inspecting, specifically, pore-forming inspection should be carried out after Completion of Drilling Hole, pore-forming hole position centre bit It puts detection and answers recovery hole position central point, measured using dipstick metering along circuit direction and horizontal path direction position deviation.Pore-forming aperture Detection is subject to and examines hole device and pass through, inspecting hole device should hang and put down gently slowly, prevent inspecting hole device is swung from destroying shield using cage inspecting hole device Wall mudcake.Cage inspection hole device detection can be used in the detection of pore-forming gradient.Depth of pore forming detection preferably uses lining rope directly to measure, hole depth It should be measured along hole Zhou Jinhang.First time borehole cleaning should be met the requirements of the standard after pore-forming.
Step 6:Borehole cleaning checks sediment thickness.
Step 7:Place steel reinforcement cage, conduit.
Steel reinforcement cage is transported to construction site using special transport vehicle, and muscle cage carries out every preparation before hanging, will be attached to Soil on steel reinforcement cage removes clean, the shortening steel reinforcement cage placement time.Muscle cage is hung, and can use double lifting point or single suspension centre, suspension centre position Putting should be appropriate, generally at stirrup, for the steel reinforcement cage being relatively large in diameter, can take measures to be reinforced lifting point, to ensure It will not be deformed during reinforcement cage hoisting, hang and slowly transferred to designed elevation into Kong Shiying alignments drill center.If being hampered should stop Decentralization, ascertains the reason and is handled.Forbid raised pelter, collision and transfer by force.Muscle cage is installed in place, and should be adopted after inspection is errorless Reliable location measure is taken, prevents that framework of steel reinforcement floats or sinks in concreting process.
Step 8:Check sediment thickness, secondary pile hole cleaning.
Step 9:Underwater concreting.
Underwater concreting use catheter perfusion, perfusion dummy pipe carry out examination spell pressure testing, must not leak, the hydraulic pressure of pressure testing Power is 1.5 times of bottom hole hydrostatic pressure.Conduit bottom is not more than away from hole bottom distance 0.3m ~ 0.5m, the embedding concrete depth of conduit 6m, and not less than 2m.Underwater concrete has good mobility, and the slump generally requirement is in 200 ~ 220mm;Concrete is applied Work should be continuous, must not pause halfway.And should try one's best the break time for shortening and removing conduit, the time that pours per pile should not be too It is long, completion is preferably poured in 2h.
Step 10:Churning driven extracts sleeve.Sleeve is removed after concrete initial set, is carried out before final set, is pulled out using churning driven Except sleeve, according to first rotating, after pull out sequence construction, installation sleeve connector starts to bore to dig and bores occlusion sleeve, and churning driven is slow Rotation, rotary speed are not preferably greater than 5r/min, and rotary digging sleeve pulls out speed should not be too fast, prevent from making the coagulation that perfusion is completed with local methods Into disturbance, pile quality is influenced, while measures rotary digging sleeve inner concrete sedimentation situation.After sleeve is pulled out, sleeve connection is checked Device cylinder bores rotation tooth plate 13 and 14 welded condition of notch snap-gauge, generates and is welded with reinforcement in time at crack.
Step 11:Pore-forming.
By sleeve coupler sleeve rotating is driven to follow up using rotary drilling rig, sleeve is made to pass through containing a large amount of stones and brick The deep miscellaneous fill layer of the building wastes such as block, concrete, sleeve replace conventional bit and fetch earth, complete to fetch earth in sleeve afterwards in place Drilling operation until pore-forming, follow-up by installation steel reinforcement cage, poured underwater concrete, is pulled out after pouring using rotary drilling rig Sleeve pile, easy to operate, construction efficiency is high, and pile quality is good, saves cost.
In entire work progress, running check bit diameter, the timely soldering of serious wear, it is ensured that bit diameter satisfaction is applied Work requirement.Depth of pore forming is checked by measuring two methods of drilling tool and lining rope measurement, it is ensured that stake is long to be not less than designing pile length.It bores In and after pore-forming, mud property index is detected using densimeter, mud sand content meter, mud viscosimeter, adjusts mud in time The related index of mud of borehole cleaning must reach code requirement during performance, particularly whole hole.All steel are marched into the arena to have into field quality and be demonstrate,proved Bright, and rechecked, splice uses electric arc welding, and censorship and inspects by random samples at any time, and steel reinforcement cage processing dimension must be pressed strictly It is carried out according to design, related dimensional discrepancy must meet code requirement.
Personnel into people construction site must strictly observe safety management in construction site regulation, wear a safety helmet, non-constructor Member is not allowed into people construction site.Site operation electricity consumption has personal management, and the equipment such as distribution box, electric welding machine are respectively provided with ground connection, installation Earth leakage protective device prevents that the rainy day short-circuit.The instrument of construction usage, equipment should be checked that safety device is complete, churning driven master Elevator has the function of " free releasing ", ensures that rate of penetration is synchronous with steel wire rope, easy to operate freely.
After drilling machine is in place, drilling machine and corollary equipment should be checked comprehensively.Drilling machine is installed must be steady, secured. Drilling machine operation on 10 ° or more of slope is avoided, rotary machine, steering, T-shaped not travelled on the slope on direction, to prevent hair Raw danger of toppling.Drilling machine walking, drilling on weak ground should use steel subgrade case or laying steel plate.Bore operation Personnel pay attention to formation variation situation and machine run situation in hole, exception occur, stop to bore immediately.Drilling machine stops boring, it is necessary to by drill bit It proposes outside hole, must not be detained in hole, while cover well head.
Waste oil, waste water, the waste residue generated in construction is discharged by appointed place, to avoid pollution air and water source, drilling Mud during sealing of hole should be recycled and utilized by mud circulating purification system, and pay attention to preventing or reducing environmental pollution.It applies Workshop ground connection and reasonable arrangement, sets sedimentation basin, service rack etc., and construction site traffic is cleaned, and vehicle crew carries out into appearing on the scene Real name is registered.The waste materials such as the surface layer peat to place cleaning will transport to the place specified and be discarded in time.It is taken out in drilling Dregs be timely transported place, keep place clean and tidy.Site operation placing of material is neat, accomplish it is horizontal in a row, it is perpendicular embark on journey, granular media Material will build pond stacking if necessary, and material will set up railing stacking.Energy conservation and environmental protection mechanical equipment is selected, insulating noise is taken to arrange It applies, reduces noise, reducing influences surrounding enviroment.
It is that 15m long contrast tables are processed using conventional method and this method below:
Project Stake is long Drill duration It measures design side It measures reality side Exuberant coefficient
Conventional method 15 7.37 7.84 12.3 1.57
This method 15 1.46 7.84 8.2 1.05
It is constructed using conventional method, actual filling concrete side's amount is calculated by average value 12.3m3, needs C35 concrete 5178.3m 3, using this method construction pile foundation, actual perfusion side's amount is calculated by average value 8.2m3, needs C35 concrete 3452.2m3.
This method saves concrete 1726.1m3, saves man-hour 2105h, the cost-effective machinery 60.6 ten thousand yuan, reduced Working day cost improves work efficiency, and achieves excellent economic benefit with this method construction, and ensure that pile matter Amount, accelerates project progress.
It solves the problems, such as that construction speed is slow, accelerates project progress, peace and quiet are more early provided for surrounding cities resident Living environment, construct harmonious external social construction environment.
Sleeve and sleeve coupler can be reused simultaneously, improve the utilization rate of material, reduce steel energy consumption, carry The high security of construction operation, achieves good social benefit.
This specific embodiment is only explanation of the invention, is not limitation of the present invention, people in the art Member can as needed make the present embodiment the modification of no creative contribution after this specification is read, but as long as at this It is all protected in the right of invention be subject to Patent Law.

Claims (10)

1. a kind of cast-in-situ bored pile churning driven sleeve drilling construction method, which is characterized in that comprise the following steps:
Step 1:Preparation of construction makes including fabrication of reinforcing cage, measurement and positioning setting-out, sleeve design;
Step 2:Rotary drilling rig is in place, and sleeve rotating follow-up construction is driven by sleeve coupler using rotary drilling rig;
Step 3:More bit change;
Step 4:It fetches earth, drilled to designed elevation in sleeve;
Step 5:Drilled-hole inspecting;
Step 6:Borehole cleaning checks sediment thickness;
Step 7:Place steel reinforcement cage, conduit;
Step 8:Check sediment thickness, secondary pile hole cleaning;
Step 9:Underwater concreting;
Step 10:Churning driven extracts sleeve;
Step 11:Pore-forming.
2. cast-in-situ bored pile churning driven sleeve drilling construction method according to claim 1, it is characterised in that:In step 1 Sleeve include hollow cylinder(1), circumferential be opened in cylinder(1)Several L-type slots of upper end(11)And circumferentially it is welded on cylinder Body(1)Several cutting tooths of lower end(12), the cutting tooth(12)The direction of setting angle is consistent with drilling machine direction of rotation.
3. cast-in-situ bored pile churning driven sleeve drilling construction method according to claim 2, it is characterised in that:In step 2 Sleeve coupler include rotation tooth plate(13), along rotation tooth plate(13)It is circumferentially fixed and with L-type slot(11)The notch card of connection Plate(14), be arranged on rotation tooth plate(13)Upper end and with drilling machine drilling rod use axis pin(16)The truss plate connection plate of connection (15), the truss plate connection plate(15)On offer for axis pin(16)The pin hole passed through(17), the axis pin(16)With pin hole (17)Tight fit.
4. cast-in-situ bored pile churning driven sleeve drilling construction method according to claim 3, it is characterised in that:The rotation Tooth plate(13)It is made of the Q345 steel plates of 60 × 60cm thickness 40mm.
5. cast-in-situ bored pile churning driven sleeve drilling construction method according to claim 3, it is characterised in that:The notch Snap-gauge(14)The L-type slot of sleeve is caught in completely(11)Afterwards, the notch snap-gauge(14)Extend cylinder(1)25mm.
6. cast-in-situ bored pile churning driven sleeve drilling construction method according to claim 3, it is characterised in that:In step 2 Sleeve rotating follow-up construction includes,
A. rotary digging sleeve orientation sets pile foundation center using total powerstation survey, makes rotary digging sleeve Xia Kou centers and stake position center weight It closes, sleeve is observed along line direction and the gradient in horizontal path direction using total powerstation during rotary digging sleeve orientation;
B. rotary digging sleeve follows up, and sleeve coupler rotation drives rotary digging sleeve rotating to bury sleeve, and drilling machine 5 ~ 8r/min of rotating speed is bored Mantle cylinder top surface is higher by level of ground water 2m, and is higher by construction ground 0.3m, and height should meet the requirement of mud face height in hole;
C. rotary digging sleeve orientation is checked, and after sleeve is buried, rotary digging bushing core position and rotary digging sleeve verticality are carried out It checks, rotary digging bushing core tolerance≤± 20mm, verticality≤1%.
7. cast-in-situ bored pile churning driven sleeve drilling construction method according to claim 3, it is characterised in that:In step 4 It fetches earth, drill in sleeve and be specially to designed elevation:
A. after sleeve is buried, slowly reversion makes sleeve coupler exit L-type slot notch to rotary drilling rig, checks sleeve verticality and hole Position deviation;
B. the axis pin that sleeve coupler is connected with drilling rod is removed, axis pin is removed tapping and pulled out slowly;Sleeve coupler is unloaded, is replaced normal Cylinder drilling fetches earth;
C. rotary digging drilling pipe drilling row boring extracting soil, cylinder bores leaf of hinge open-angle and should not be too large during fetching earth, and meets stone and erratic boulder, Drill bit is taken to invert and increase drilling machine driving torque, is squeezed to hole wall periphery;
D. the loose caving ground such as deep miscellaneous fill layer is using static mud protecting wall drilling and forming hole, the following Muddy Bottoms of sleeve bottom Farinose argillic horizon drilling is control drilling parameter, ensures hole quality;
Should be first slow rear fast when e. creeping into, between specific gravity of mud control 1.05~1.10, sand factor is not more than 2%, creeps into There is the mud index of defined head and requirement in journey in retaining hole, with avalanche prevention hole;
F. crept into, drilled using low speed when starting to creep into or through deep miscellaneous fill layer and very soft sill clay intersection According to geological condition controlled footage speed in journey, vertical degree detection is carried out to drilling rod as the case may be;
G. in drilling process, the promotion speed and decrease speed of drilling rod are controlled;Drilling rod lifting speed is maintained at 0.75~ 0.80m/s。
8. cast-in-situ bored pile churning driven sleeve drilling construction method according to claim 3, it is characterised in that:In step 5 Drilled-hole inspecting be specially:Pore-forming inspection should be carried out after Completion of Drilling Hole, recovery hole position center is answered in the center detection of pore-forming hole position Point is measured using dipstick metering along circuit direction and horizontal path direction position deviation;Pore-forming Pore Diameter Detection uses cage inspecting hole device, into Hole gradient detection preferably uses lining rope directly to measure using cage inspection hole device detection, depth of pore forming detection, and hole depth should be along Kong Zhoujin Row measures, and first time borehole cleaning should be met the requirements of the standard after pore-forming.
9. cast-in-situ bored pile churning driven sleeve drilling construction method according to claim 3, it is characterised in that:In step 9 Underwater concreting, using catheter perfusion, perfusion dummy pipe carries out examination and spells pressure testing, must not leak, the water pressure of pressure testing is hole 1.5 times of bottom hydrostatic pressure;Away from hole bottom distance 0.3m ~ 0.5m, the embedding concrete depth of conduit is not more than 6m for conduit bottom, and Not less than 2m.
10. cast-in-situ bored pile churning driven sleeve drilling construction method according to claim 3, it is characterised in that:Step 10 Middle churning driven extract sleeve be specially according to first rotating, after pull out sequence construction, installation sleeve connector starts to bore to dig and bores occlusion Sleeve, churning driven slowly rotate, and rotary speed is not more than 5r/min.
CN201711397918.4A 2017-12-21 2017-12-21 Cast-in-situ bored pile churning driven sleeve drilling construction method Pending CN108049396A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711397918.4A CN108049396A (en) 2017-12-21 2017-12-21 Cast-in-situ bored pile churning driven sleeve drilling construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711397918.4A CN108049396A (en) 2017-12-21 2017-12-21 Cast-in-situ bored pile churning driven sleeve drilling construction method

Publications (1)

Publication Number Publication Date
CN108049396A true CN108049396A (en) 2018-05-18

Family

ID=62130543

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711397918.4A Pending CN108049396A (en) 2017-12-21 2017-12-21 Cast-in-situ bored pile churning driven sleeve drilling construction method

Country Status (1)

Country Link
CN (1) CN108049396A (en)

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109371974A (en) * 2018-10-25 2019-02-22 广西建工集团基础建设有限公司 A kind of PHC tubular pole implantation construction method suitable for hard geology
CN109371960A (en) * 2018-12-12 2019-02-22 河北庄重工程机械有限公司 A kind of SRP engineering method
CN110145232A (en) * 2019-05-23 2019-08-20 贵州建工集团第六建筑工程有限责任公司 A kind of construction method for not mending slurry churning driven borehole
CN110158579A (en) * 2019-04-26 2019-08-23 中国水利水电第九工程局有限公司 A kind of bored pile construction method
CN111021948A (en) * 2019-12-30 2020-04-17 深圳市盛业地下工程有限公司 Pile foundation combination equipment for rapid pore-forming of complex geology
CN111058767A (en) * 2019-12-06 2020-04-24 广东省基础工程集团有限公司 Construction method of rock-socketed cast-in-situ bored pile
CN111101865A (en) * 2019-12-30 2020-05-05 深圳市盛业地下工程有限公司 High efficiency drilling equipment
CN111608590A (en) * 2020-07-08 2020-09-01 辛秋娥 Improved rock taking drilling tool of rotary drilling machine
CN113137190A (en) * 2021-05-13 2021-07-20 中信国安建工集团有限公司 Rotary drilling rig drill rod component and rotary drilling rig
CN113338274A (en) * 2021-06-01 2021-09-03 中铁十八局集团有限公司 Anchor rod pile locator is built to underground space
CN113373925A (en) * 2021-06-02 2021-09-10 中交一公局第一工程有限公司 Method and device for installing steel sheet pile in sandstone stratum by rotary drilling rig

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3315924A1 (en) * 1982-07-12 1984-01-12 Bauakademie Der Deutschen Demokratischen Republik, Ddr 1125 Berlin Method and apparatus for making bored piles
CN201695949U (en) * 2010-06-11 2011-01-05 北京市三一重机有限公司 Casing driver and rotary drilling rig
CN103266599A (en) * 2013-05-13 2013-08-28 汇通路桥建设集团有限公司 Construction method of rotating drilling dry-drilled piles of sand soil interlayer foundation
CN104563126A (en) * 2014-12-22 2015-04-29 中铁十九局集团有限公司 Rotary drill drilling cast-in-place pile construction method

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3315924A1 (en) * 1982-07-12 1984-01-12 Bauakademie Der Deutschen Demokratischen Republik, Ddr 1125 Berlin Method and apparatus for making bored piles
CN201695949U (en) * 2010-06-11 2011-01-05 北京市三一重机有限公司 Casing driver and rotary drilling rig
CN103266599A (en) * 2013-05-13 2013-08-28 汇通路桥建设集团有限公司 Construction method of rotating drilling dry-drilled piles of sand soil interlayer foundation
CN104563126A (en) * 2014-12-22 2015-04-29 中铁十九局集团有限公司 Rotary drill drilling cast-in-place pile construction method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
上海铁路局: "《高速铁路施工工序管理要点 第一册 桥梁钻孔桩施工》", 30 September 2010, 中国铁道出版社 *

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109371974A (en) * 2018-10-25 2019-02-22 广西建工集团基础建设有限公司 A kind of PHC tubular pole implantation construction method suitable for hard geology
CN109371960A (en) * 2018-12-12 2019-02-22 河北庄重工程机械有限公司 A kind of SRP engineering method
CN110158579A (en) * 2019-04-26 2019-08-23 中国水利水电第九工程局有限公司 A kind of bored pile construction method
CN110145232B (en) * 2019-05-23 2020-09-25 贵州建工集团第六建筑工程有限责任公司 Construction method for rotary drilling hole without slurry supplement
CN110145232A (en) * 2019-05-23 2019-08-20 贵州建工集团第六建筑工程有限责任公司 A kind of construction method for not mending slurry churning driven borehole
CN111058767B (en) * 2019-12-06 2021-08-31 广东省基础工程集团有限公司 Construction method of rock-socketed cast-in-situ bored pile
CN111058767A (en) * 2019-12-06 2020-04-24 广东省基础工程集团有限公司 Construction method of rock-socketed cast-in-situ bored pile
CN111101865A (en) * 2019-12-30 2020-05-05 深圳市盛业地下工程有限公司 High efficiency drilling equipment
CN111021948A (en) * 2019-12-30 2020-04-17 深圳市盛业地下工程有限公司 Pile foundation combination equipment for rapid pore-forming of complex geology
CN111608590A (en) * 2020-07-08 2020-09-01 辛秋娥 Improved rock taking drilling tool of rotary drilling machine
CN111608590B (en) * 2020-07-08 2021-12-07 湖北旭腾建设工程有限公司 Improved rock taking drilling tool of rotary drilling machine
CN113137190A (en) * 2021-05-13 2021-07-20 中信国安建工集团有限公司 Rotary drilling rig drill rod component and rotary drilling rig
CN113338274A (en) * 2021-06-01 2021-09-03 中铁十八局集团有限公司 Anchor rod pile locator is built to underground space
CN113373925A (en) * 2021-06-02 2021-09-10 中交一公局第一工程有限公司 Method and device for installing steel sheet pile in sandstone stratum by rotary drilling rig

Similar Documents

Publication Publication Date Title
CN108049396A (en) Cast-in-situ bored pile churning driven sleeve drilling construction method
CN110424381A (en) A kind of process for rotary digging drilling hole stake
CN106400782B (en) A kind of construction method for going along with sb. to guard him hole-drilling interlocking pile using rotary drilling rig construction foundation pit
CN107524142A (en) A kind of holing with slurry wall protection cast-in-place pile construction method
CN113445498A (en) Construction process of karst hole pile foundation in complex geology
CN107938656A (en) Complexity rebuilds base pit engineering pile base construction method
CN107724383B (en) Rotary digging cast-in-place pile construction method
CN106320333B (en) Combined drainage type water filling pile device and construction method
CN102720186B (en) Underwater once pouring method for variable cross-section bored cast-in-place pile
CN106988302A (en) A kind of high inclination-angle competent bed rotary digging pile driving construction engineering method
CN106930276A (en) The deep hole blasting of rotary digging bored concrete pile and the construction method of conduit rotary digging removing obstacles
CN111395330B (en) Construction method for concrete cast-in-situ bored pile complete steel casing penetrating through underground gallery
CN103924585A (en) Novel method for constructing wind power rock-embedded pile
CN110805029A (en) Subway underground-excavated station drilling and grouting fender post construction method
CN110629747A (en) Full-casing full-rotation construction process for pile foundation under complex geological conditions
CN111705786A (en) Method for vertical combination construction of composite stratum underground continuous wall and cast-in-situ bored pile
CN107059848A (en) A kind of pile integral construction method
CN107653878A (en) Cast-in-situ bored pile is reusable to be longitudinally separated formula steel pile casting construction
CN113668564A (en) Construction method for supporting and reinforcing open-cut underground passage adjacent to subway station
CN203768925U (en) Seal device for dewatering well in foundation pit
CN108775036A (en) A kind of construction method for replacing bored concrete pile
CN114837209A (en) Construction method of deep sand layer large-diameter pile foundation in karst development area
CN107975376A (en) Tunneling shield push pipe and vertical duct connection structure and construction method
CN114635450A (en) Construction method for permanent steel pipe structural column of covered and excavated station
CN113404043A (en) Construction method of full-rotation full-casing drilling machine suitable for karst cave geology

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20180518

RJ01 Rejection of invention patent application after publication