CN108035359A - A kind of slope excavating method - Google Patents

A kind of slope excavating method Download PDF

Info

Publication number
CN108035359A
CN108035359A CN201711439517.0A CN201711439517A CN108035359A CN 108035359 A CN108035359 A CN 108035359A CN 201711439517 A CN201711439517 A CN 201711439517A CN 108035359 A CN108035359 A CN 108035359A
Authority
CN
China
Prior art keywords
slope
mixing pile
cement mixing
ground
excavate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201711439517.0A
Other languages
Chinese (zh)
Inventor
冯艳
王勇
梅聪
祝佳兵
赵红敏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Zhongnan Engineering Corp Ltd
Original Assignee
PowerChina Zhongnan Engineering Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Zhongnan Engineering Corp Ltd filed Critical PowerChina Zhongnan Engineering Corp Ltd
Priority to CN201711439517.0A priority Critical patent/CN108035359A/en
Publication of CN108035359A publication Critical patent/CN108035359A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines
    • E02D17/207Securing of slopes or inclines with means incorporating sheet piles or piles

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The invention discloses a kind of slope excavating method, it includes following steps:1)The ground that excavation is treated using cement mixing pile is handled;During the cement mixing pile driving construction, I-steel is inserted into the cement mixing pile near top of the slope;2)The ground and cement mixing pile are excavated together after the age for treating cement mixing pile, form side slope.The present invention can solve the problems, such as that the gradient that allows to excavate of soft soil foundation itself is relatively delayed, weak soil self-strength is improved using mixing pile processing method, greatly increasing it allows to excavate slope ratio under conditions of municipal construction narrow field is met.The present invention, in the case where ensureing the stability condition of Permanent Slope, greatly reduces the excavated volume of soft soil foundation, reduces engineering construction work surface, shorten the duration of a project compared to traditional slope excavating measure.The slope ratio that allows to excavate that the present invention breaches soft soil foundation limits, and can strengthen the flexibility of Side slope designing project, have universality.

Description

A kind of slope excavating method
Technical field
The present invention relates to slope project technical field, more particularly to a kind of soft foundation slope excavating method.
Background technology
Soft foundation means what is be mainly made of mud, muck soil, rinse fill, miscellaneous fill or other high-compressibility soil layers Ground.This soft soil foundation cohesive strength and internal friction angle are smaller, it is allowed to it is relatively more slow to excavate slope.
Cement mixed pile technology is referred to using cement material as curing agent(Flyash, pulverized limestone, cement powder or cement mortar), Using specific deep-layer stirring equipment, while drilling, vaporific powder or slurries are sprayed into weak soil, on the spot by curing agent with Weak soil by the chemical reaction between the soil body and curing agent and physical reactions, ensures that foundation soil is hard in ground depths action of forced stirring Structure reaches the reinforcing body of certain intensity, water stability and globality, to improve deformation modulus and foundation strength, so as to meet A kind of Soil-cement method of foundation stabilization requirement.The application of cement mixing pile mainly has:, can in the softer soil of soil property To mitigate the sedimentation of ground, strengthen the bearing capacity of soil;Strengthen the robustness of soil, prevent sliding phenomenon;For due to Cave in and the cheat protuberance phenomenon of bottom of soil caused by excessively excavating can also take the technology of cement mixing pile to solve;Water Waterproof construction of the mud mixing pile as underground, can prevent water storage in current infiltration and ground foundation pit;Strengthen lateral weak soil pair The bearing capacity of foreign object, effectively solves the displacement problem of engineering pile.
Hydraulic engineering at present, traffic engineering, in civil engineering, mixing pile is mainly used in Soft Ground, enhancing ground Base bearing capacity, or applied in construction pit supporting construction, in slope excavating field of engineering technology, have no using mixing pile.Mesh In preceding urban water conservancy municipal works, limitation of the soft soil foundation because excavating place, it has to which design is excavated into its own opposite intensity Steeper slope ratio, if not handling direct excavation, side slope itself is difficult to keep its stability.Therefore how soft soil foundation causes It can excavate into steeper slope than as a great problem in urban water conservancy municipal works.
The content of the invention
The present invention is solution problems of the prior art, there is provided a kind of slope excavating method, concrete technical scheme is such as Under.
A kind of slope excavating method, it includes following steps:
1)The ground that excavation is treated using cement mixing pile is handled;
2)The ground and cement mixing pile are excavated together after the age for treating cement mixing pile, form side slope.
Further, above-mentioned steps 1)Also have steps of before:The physical parameter of the ground is obtained, according to described Physical parameter drafts intensity, diameter and the arrangement of cement mixing pile.
Further, the step 1)In, during the cement mixing pile driving construction, inserted in the cement mixing pile near top of the slope Enter I-steel.The insertion of I-steel can further improve the shearing strength of soft soil foundation.
The beneficial effects of the invention are as follows:The present invention is under conditions of municipal construction narrow field is met, with can solving weak soil The problem of allowing the excavation gradient relatively slow of base itself, weak soil self-strength is improved using mixing pile processing method, is greatly improved It allows to excavate slope ratio.The present invention compares traditional slope excavating measure, in the case where ensureing the stability condition of Permanent Slope, significantly Ground reduces the excavated volume of soft soil foundation, reduces engineering construction work surface, shortens the duration of a project.The present invention breaches weak soil Ground allows to excavate slope than limitation, can strengthen the flexibility of Side slope designing project, have universality;In addition, ground only needs Cement mixing pile processing is carried out before excavation, it is not necessary to handled when excavating so that excavation project is simple to operation.
Brief description of the drawings
Fig. 1 is the schematic diagram after soft foundation treatment by concrete stirring pole;
Fig. 2 is mixing pile horizontal layout schematic diagram;
Fig. 3 is edge slope structure schematic diagram after the completion of excavation.
In figure:1- cement mixing piles, 2- I-steel, 3- side slopes.
Embodiment
The present invention is described in further detail below in conjunction with the accompanying drawings.
Referring to Fig. 1-3, project under construction is to dig engineering positioned at Fuzhou City park lake body, and construction site limitation is larger.It is real Apply side slope soil property and be essentially muck soil, it is allowed to excavate slope than 1:5, design excavates slope than 1:1.5.Ground to be excavated is obtained first Relevant physical parameter, intensity, diameter and the arrangement of cement mixing pile 1 are specified according to relevant physical parameter(Using ability Cement mixing pile design, the construction technology of domain routine);According to the cement mixing pile constructing process of formulation on ground to be excavated Make cement mixing pile 1;After the age for waiting cement mixing pile, the ground and cement mixing pile 1 are opened together Dig, form side slope 3.Construction platform absolute altitude 4.3m, stake bottom -3 ~ -5m of absolute altitude.The project starts applying for mixing pile in April, 2017 Work, in May, 2017, mixing pile construction was completed, and in June, 2017 completes the construction of whole slope excavating.Construction period, whole side slope was each Item monitoring data are normal.
Preferably, in above-mentioned cement mixing pile in construction process, I-steel 2 is inserted into the cement mixing pile near top of the slope; It is further preferred that I-steel 2 is inserted into two rows of cement mixing piles farthest away from bottom of slope.The insertion of I-steel can be further Ground improves the shearing strength of soft soil foundation, while does not interfere with the excavation project of side slope.
Finally it should be noted that:The above embodiments are merely illustrative of the technical solutions of the present invention, rather than its limitations;Although The present invention is described in detail with reference to the foregoing embodiments, it will be understood by those of ordinary skill in the art that:It still may be used To modify to the technical solution described in foregoing embodiments, or equivalent substitution is carried out to which part technical characteristic; And these modification or replace, do not make appropriate technical solution essence depart from various embodiments of the present invention technical solution spirit and Scope.

Claims (3)

  1. A kind of 1. slope excavating method, it is characterised in that include following steps:
    1)The ground that excavation is treated using cement mixing pile is handled;
    2)The ground and cement mixing pile are excavated together after the age for treating cement mixing pile, form side slope.
  2. A kind of 2. slope excavating method according to claim 1, it is characterised in that above-mentioned steps 1)Also have before following Step:The physical parameter of the ground is obtained, intensity, diameter and the arrangement side of cement mixing pile are drafted according to the physical parameter Formula.
  3. A kind of 3. slope excavating method according to claim 1, it is characterised in that the step 1)In, the cement stirs When mixing pile driving construction, I-steel is inserted into the cement mixing pile near top of the slope.
CN201711439517.0A 2017-12-27 2017-12-27 A kind of slope excavating method Pending CN108035359A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711439517.0A CN108035359A (en) 2017-12-27 2017-12-27 A kind of slope excavating method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711439517.0A CN108035359A (en) 2017-12-27 2017-12-27 A kind of slope excavating method

Publications (1)

Publication Number Publication Date
CN108035359A true CN108035359A (en) 2018-05-15

Family

ID=62101442

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711439517.0A Pending CN108035359A (en) 2017-12-27 2017-12-27 A kind of slope excavating method

Country Status (1)

Country Link
CN (1) CN108035359A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109826201A (en) * 2019-02-01 2019-05-31 湖北省水利水电规划勘测设计院 A kind of weak soil foundation pit step method for protecting support

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN203755319U (en) * 2014-03-13 2014-08-06 中国水电顾问集团成都勘测设计研究院有限公司 Structure for preparing for fractured rock zone slope excavation
CN204825928U (en) * 2015-08-17 2015-12-02 江苏万邦建设集团有限公司 Excavation supporting
CN105155547A (en) * 2015-06-18 2015-12-16 中铁十八局集团第二工程有限公司 Construction method for deep foundation pit excavation on steep slope terrain
CN105350541A (en) * 2015-09-11 2016-02-24 华能澜沧江水电股份有限公司 Excavation method of highly-steep vertical toppling deformation side slope
CN106703044A (en) * 2017-01-11 2017-05-24 北京建工土木工程有限公司 Flow-plastic-shaped flushing and filling soil weak stratum sloping combination support method
CN106836186A (en) * 2016-12-26 2017-06-13 福建港湾岩土工程集团有限公司 A kind of construction technology of utilizing solidified earth from sludge
CN107268600A (en) * 2017-08-01 2017-10-20 江苏燕宁建设工程有限公司 Grouting strengthening method, pipe jacking construction method and application

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN203755319U (en) * 2014-03-13 2014-08-06 中国水电顾问集团成都勘测设计研究院有限公司 Structure for preparing for fractured rock zone slope excavation
CN105155547A (en) * 2015-06-18 2015-12-16 中铁十八局集团第二工程有限公司 Construction method for deep foundation pit excavation on steep slope terrain
CN204825928U (en) * 2015-08-17 2015-12-02 江苏万邦建设集团有限公司 Excavation supporting
CN105350541A (en) * 2015-09-11 2016-02-24 华能澜沧江水电股份有限公司 Excavation method of highly-steep vertical toppling deformation side slope
CN106836186A (en) * 2016-12-26 2017-06-13 福建港湾岩土工程集团有限公司 A kind of construction technology of utilizing solidified earth from sludge
CN106703044A (en) * 2017-01-11 2017-05-24 北京建工土木工程有限公司 Flow-plastic-shaped flushing and filling soil weak stratum sloping combination support method
CN107268600A (en) * 2017-08-01 2017-10-20 江苏燕宁建设工程有限公司 Grouting strengthening method, pipe jacking construction method and application

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109826201A (en) * 2019-02-01 2019-05-31 湖北省水利水电规划勘测设计院 A kind of weak soil foundation pit step method for protecting support

Similar Documents

Publication Publication Date Title
CN104988907A (en) Construction method of concrete pile
CN109440778A (en) Active inclined in two-way method for supporting and protecting row pile pit
CN107513994A (en) One kind segmentation becomes supporting rotary digging stake and its construction method without leave
CN104818713A (en) Profile steel cement soil pile construction method adaptive to various stratums
CN112323819A (en) Soft soil foundation pit bottom in-situ curing method and soft soil foundation pit bottom curing structure
CN105386610A (en) Protective construction method for natural-foundation ancient architectures at top of asymmetric deep foundation pit
JP2019015100A (en) Removing method of earth retaining wall
CN110055973A (en) Construction space foundation pit enclosure structure and water-stopping method under by high metal bridge in limited time
CN206800431U (en) A kind of sealing bottom type caisson wall
CN105625480A (en) Anti-floating method and structure for open-segment tunnel structure
CN108035359A (en) A kind of slope excavating method
CN114164726B (en) Local deep excavation backfill structural roadbed and rapid construction method
CN108797630A (en) A kind of muck foundation sluice foundation construction method
CN109440781A (en) Active inclination foundation pit supporting method with double rows of piles
CN103015430A (en) Long auger pressure filling steel reinforced cement-soil pile foundation pit water-resisting and supporting method
CN110318392A (en) A kind of major diameter cement earth pile method of construction
CN213897154U (en) Soft soil foundation pit bottom curing structure
JP4313070B2 (en) Sludge treatment method in ready-made pile construction and ground reinforcement structure obtained by the treatment method
CN205399410U (en) Dig first slip casting club -footed pile of drilling soon
CN108570979A (en) A kind of construction method for building antiseepage composite foundation on dolomite stratigraph
CN106703043A (en) Soft soil foundation pit construction method by using dynamic compaction block stone displacement instead of supporting
CN209907365U (en) Treatment structure of stepped easily-weathered soft sandstone layer foundation
JPS63315724A (en) Execution work of cast-in-place concrete pile with high yield strength
CN109440779A (en) Active X-shaped foundation pit supporting method with double rows of piles
CN102409668A (en) Cast-in-situ bored pile and expansion and compaction construction method thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20180515