CN108018773A - A kind of self-propelled telescopic interim overline bridge - Google Patents

A kind of self-propelled telescopic interim overline bridge Download PDF

Info

Publication number
CN108018773A
CN108018773A CN201711327163.0A CN201711327163A CN108018773A CN 108018773 A CN108018773 A CN 108018773A CN 201711327163 A CN201711327163 A CN 201711327163A CN 108018773 A CN108018773 A CN 108018773A
Authority
CN
China
Prior art keywords
bridge
type structure
step type
forge piece
floorings
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201711327163.0A
Other languages
Chinese (zh)
Other versions
CN108018773B (en
Inventor
杨晖
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
NINGBO ROABY TECHNOLOGY INDUSTRIAL GROUP Co Ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201711327163.0A priority Critical patent/CN108018773B/en
Publication of CN108018773A publication Critical patent/CN108018773A/en
Application granted granted Critical
Publication of CN108018773B publication Critical patent/CN108018773B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D15/00Movable or portable bridges; Floating bridges
    • E01D15/12Portable or sectional bridges
    • E01D15/124Folding or telescopic bridges; Bridges built up from folding or telescopic sections
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/005Piers, trestles, bearings, expansion joints or parapets specially adapted for portable or sectional bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/12Grating or flooring for bridges; Fastening railway sleepers or tracks to bridges
    • E01D19/125Grating or flooring for bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

A kind of self-propelled telescopic interim overline bridge, belongs to road traffic facility field.It is by being by hoistable platform,The body of a bridge,Supporting cylinder,What supporting rack and wheel formed,The hoistable platform and hoistable platform at overline bridge both ends have identical structure with lower part,It is symmetric,The body of a bridge can shorten interim overline bridge when not in use,Fly stair can be put on hoistable platform,Entire length can be reduced,Save space,It is readily transported the interim overline bridge of bed rearrangement,The device is before the mounting,Floorings are the state folded,During installation,Two people are needed to operate at the same time,Next fly stair is put in one end of installation site,Then a wherein people fixes one end of overline bridge,Another people pulls the other end,Until whole pontic is fully deployed,Unload another balcony stair,Starting hydraulic pump at this time makes supporting cylinder enter working status,After the body of a bridge rises to operational height,Pedestrian can be climbed up overline bridge by fly stair and go to road opposite.

Description

A kind of self-propelled telescopic interim overline bridge
Technical field
The present invention relates to a kind of self-propelled telescopic interim overline bridge, the interim day of special construction is specifically employed Bridge, the body of a bridge can stretch in length direction, belong to road traffic facility field.
Background technology
With the development of society, the increase of urban population quantity, the quantity of private car is consequently increased, and gives urban road band Carry out very big burden, traffic congestion has been normality, very big to pressure caused by traffic police especially in festivals or holidays and commuter time, In prior art, cross street for solution pedestrian and conflict with what vehicle travelled on road, overpass early has occurred in The busiest section in many cities, but existing overline bridge is fixed mostly, such as runs into removal and expansion is repaired roads it is necessary to day of dismantling Bridge, causes very big waste, if building new overline bridge not in time, very big problem can be brought to traffic, can not be solved very well Road congestion phenomenon.
The content of the invention
For above-mentioned deficiency, the present invention provides a kind of self-propelled telescopic interim overline bridge.
The present invention is achieved by the following technical solutions:A kind of self-propelled telescopic interim overline bridge, is by day bridge Ladder, hoistable platform, the body of a bridge, supporting cylinder, supporting rack and wheel composition, the hoistable platform and hoistable platform at overline bridge both ends with Lower part has identical structure, is symmetric, the body of a bridge by handrail A, handrail B, frame A, frame B, floorings A and Floorings B compositions, there is cylindrical slider and track structure, the cylindrical slider is installed on frame on the frame A On the track of frame A, it is connected through the hinge between cylindrical slider and frame B, is connected through the hinge between frame A and frame B, bridge One end of panel A has forge piece of step type structure, and forge piece of step type structure is having through hole on body of a bridge length direction, perpendicular to bridge There is rectangular notch structure on the direction in face, one end opposite with forge piece of step type structure is coupling part, can be with hoistable platform, floorings The coupling part of B is connected through the hinge, and one end of floorings B has forge piece of step type structure, and forge piece of step type structure is perpendicular to bridge floor There is rectangular preiection structure, rectangular preiection structure is having through hole, floorings B ladders on body of a bridge length direction on direction The projection portion of type structure and the rectangular notch part of floorings A forge piece of step type structure just coordinate, and floorings A leads to floorings B Hinge connection is crossed, one end opposite with floorings B forge piece of step type structure is coupling part, can be with the connection of hoistable platform, floorings A Part is connected through the hinge, and one end of handrail A has forge piece of step type structure, and forge piece of step type structure has on body of a bridge length direction Through hole, there is rectangular notch structure on the direction perpendicular to bridge floor, and one end opposite with forge piece of step type structure is coupling part, can It is connected through the hinge with frame A, one end of handrail B has forge piece of step type structure, and forge piece of step type structure is on the direction perpendicular to bridge floor With rectangular preiection structure, rectangular preiection structure is having through hole on body of a bridge length direction, handrail B forge piece of step type structure Projection portion and the rectangular notch part of handrail A forge piece of step type structure just coordinate, and handrail A is connected through the hinge with handrail B, with helping The opposite one end of hand B forge piece of step type structure is coupling part, can be connected through the hinge with the coupling part of hoistable platform, handrail A, often Have between two frame A and be connected through the hinge between two frames B, two frame B, the lower surface of hoistable platform is rectangle and peace Equipped with four supporting cylinders and four supporting rods, the bottom of supporting rod is provided with wheel, and four supporting cylinders are distributed on liter Four corners of platform lower surface, the center for being located proximate to hoistable platform of supporting rod are dropped, but does not interfere the fortune of supporting cylinder Dynamic, fly stair carries balustrade, and fly stair and balustrade are aluminum alloy materials, and stairwell surface is 5mm with thickness Rubber pad.
The usefulness of the invention is that the body of a bridge can shorten interim overline bridge when not in use, and fly stair can be put into liter Dropping on platform, it is possible to reduce entire length, saves space, is readily transported the interim overline bridge of bed rearrangement, in the congested in traffic period, people Group's densely band, when road construction can build temporarily does overline bridge use, easy to pedestrian by, it is convenient and efficient, can effectively solve Certainly traffic congestion phenomenon.
Brief description of the drawings
Accompanying drawing 1 is the structural representation of the present invention, and attached drawing 2 is body of a bridge partial enlarged view, and attached drawing 3 is the mechanism of floorings A Schematic diagram, attached drawing 4 are the structure schematic diagram of floorings B, and attached drawing 5 is the structure diagram of frame A, and attached drawing 6 is handrail A's Structure diagram, attached drawing 7 are the structure diagram of handrail B.
In figure, 1, the body of a bridge, 101, handrail A, 102, frame A, 103, floorings A, 104, floorings B, 105, frame B, 106th, handrail B, 107, cylindrical slider, 2, hoistable platform, 3, balustrade, 4, fly stair, 5, supporting rack, 6, wheel, 7, Supporting cylinder.
It can be seen that the shape of floorings A and floorings B cooperation positions from attached drawing 4.
Embodiment
A kind of self-propelled telescopic interim overline bridge, be by fly stair 4, hoistable platform 2, the body of a bridge 1, supporting cylinder 7, What supporting rack 5 and wheel 6 formed, the hoistable platform 2 and hoistable platform 2 at overline bridge both ends have identical structure with lower part, are in Symmetrical, the body of a bridge is by handrail A101, handrail B106, frame A102, frame B105, floorings A103 and floorings B104 compositions, there is cylindrical slider 107 and track structure, the cylindrical slider 107 is pacified on the frame A102 On the track of frame A102, it is connected through the hinge between cylindrical slider 107 and frame B105, cylindrical slider 107 can Slide, be connected through the hinge between frame A102 and frame B105, frame B105 can be rotated around frame A102, bridge floor in orbit One end of plate A103 has forge piece of step type structure, and forge piece of step type structure is having through hole on body of a bridge length direction, perpendicular to There is rectangular notch structure on the direction of bridge floor, one end opposite with forge piece of step type structure is coupling part, can be with hoistable platform 2, bridge The coupling part of panel B104 is connected through the hinge, and one end of floorings B104 has forge piece of step type structure, and forge piece of step type structure is being hung down Directly in having rectangular preiection structure on the direction of bridge floor, rectangular preiection structure is having through hole on body of a bridge length direction, The projection portion of floorings B104 forge piece of step type structure and the rectangular notch part of floorings A103 forge piece of step type structure just coordinate, bridge Panel A103 is connected through the hinge with floorings B104, and one end opposite with floorings B104 forge piece of step type structure is coupling part, It can be connected through the hinge with the coupling part of hoistable platform, floorings A103, one end of handrail A has forge piece of step type structure, ladder Type structure is having through hole on body of a bridge length direction, has rectangular notch structure on the direction perpendicular to bridge floor, with rank The opposite one end of trapezoidal-structure is coupling part, can be connected through the hinge with frame A, and one end of handrail B106 has stepped tie Structure, forge piece of step type structure have rectangular preiection structure on the direction perpendicular to bridge floor, and rectangular preiection structure is grown perpendicular to the body of a bridge There are through hole, the projection portion of handrail B106 forge piece of step type structure and the rectangular notch portion of handrail A101 forge piece of step type structure on degree direction Divide and just coordinate, handrail A101 is connected through the hinge with handrail B106, and one end opposite with handrail B106 forge piece of step type structure is company Socket part point, can be connected through the hinge with the coupling part of hoistable platform 2, handrail A101, have two between each two frame A102 It is connected through the hinge between frame B105, two frame B105, the lower surface of hoistable platform 2 for rectangle and is provided with four supports Hydraulic cylinder 7 and four supporting racks 5, for supporting cylinder 7 when not working, length is less than the length of supporting rack 5, supporting rack 5 Bottom is provided with wheel 6, and lighter when the device can be made to walk, four supporting cylinders 7 are distributed on 2 lower surface of hoistable platform Four corners, more steady when making support, supporting rack 5 is located proximate to the center of hoistable platform 2, but does not interfere support hydraulic pressure The movement of cylinder 7, fly stair 4 carry balustrade 3, and fly stair 4 and balustrade 3 are aluminum alloy materials, can mitigate day The weight of bridge ladder, 4 surface of fly stair prevent from falling down damage body when pedestrian from going upstairs with the rubber pad that thickness is 5mm.
Before the mounting, floorings are the state folded to the device, during installation, need two people to operate at the same time, in installation position Next fly stair is put in the one end put, and then a wherein people fixes one end of overline bridge, and another people pulls the other end, until whole Pontic is fully deployed, and unloads another balcony stair, and starting hydraulic pump at this time makes supporting cylinder enter working status, on the body of a bridge After being raised to operational height, pedestrian can be climbed up overline bridge by fly stair and go to road opposite.
For the ordinary skill in the art, according to the present invention teaching, do not depart from the principle of the present invention with In the case of spirit, the changes, modifications, replacement and the modification that are carried out to embodiment still fall within protection scope of the present invention it It is interior.

Claims (4)

  1. A kind of 1. self-propelled telescopic interim overline bridge, it is characterised in that:Described self-propelled telescopic interim overline bridge be by What fly stair, hoistable platform, the body of a bridge, supporting cylinder, supporting rack and wheel formed, the hoistable platform at overline bridge both ends and lifting Platform has identical structure with lower part, is symmetric, the body of a bridge be by handrail A, handrail B, frame A, frame B, Floorings A and floorings B compositions, there is cylindrical slider and track structure, cylindrical slider is installed on frame A on frame A Track on, be connected through the hinge between cylindrical slider and frame B, be connected through the hinge between frame A and frame B, bridge floor One end of plate A has forge piece of step type structure, and forge piece of step type structure is having through hole on body of a bridge length direction, perpendicular to bridge floor Direction on have rectangular notch structure, one end opposite with forge piece of step type structure is coupling part, can be with hoistable platform, floorings B Coupling part be connected through the hinge, one end of floorings B has forge piece of step type structure, and forge piece of step type structure is perpendicular to the side of bridge floor There is rectangular preiection structure upwards, rectangular preiection structure is having through hole on body of a bridge length direction, and floorings B is stepped The projection portion of structure and the rectangular notch part of floorings A forge piece of step type structure just coordinate, and floorings A passes through with floorings B Hinge connection, one end opposite with floorings B forge piece of step type structure are coupling part, can be with hoistable platform, the connecting portion of floorings A Divide and be connected through the hinge.
  2. A kind of 2. self-propelled telescopic interim overline bridge as claimed in claim 1, it is characterised in that the one of the handrail A End has forge piece of step type structure, and forge piece of step type structure is having through hole on body of a bridge length direction, perpendicular to the direction of bridge floor On have rectangular notch structure, one end opposite with forge piece of step type structure is coupling part, can be connected through the hinge with frame A, handrail B One end there is forge piece of step type structure, forge piece of step type structure has rectangular preiection structure, rectangular preiection on the direction perpendicular to bridge floor Structure is having through hole, projection portion and the handrail A forge piece of step type structure of handrail B forge piece of step type structure on body of a bridge length direction Rectangular notch part just coordinate, handrail A is connected through the hinge with handrail B, and one end opposite with handrail B forge piece of step type structure is Coupling part, can be connected through the hinge with the coupling part of hoistable platform, handrail A, there is two frame B between each two frame A, It is connected through the hinge between two frame B.
  3. 3. a kind of self-propelled telescopic interim overline bridge as claimed in claim 1, it is characterised in that the hoistable platform Rectangle is in lower surface and is provided with four supporting cylinders and four supporting rods, and the bottom of supporting rod is provided with wheel, four branch Support hydraulic cylinder is distributed on four corners of hoistable platform lower surface, and supporting rod is located proximate to the center of hoistable platform, but does not do Relate to the movement of supporting cylinder.
  4. A kind of 4. self-propelled telescopic interim overline bridge as claimed in claim 1, it is characterised in that the fly stair band There is balustrade, fly stair is aluminum alloy materials with balustrade, and stairwell surface is with the rubber pad that thickness is 5mm.
CN201711327163.0A 2017-12-13 2017-12-13 A kind of self-propelled telescopic interim overline bridge Expired - Fee Related CN108018773B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711327163.0A CN108018773B (en) 2017-12-13 2017-12-13 A kind of self-propelled telescopic interim overline bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711327163.0A CN108018773B (en) 2017-12-13 2017-12-13 A kind of self-propelled telescopic interim overline bridge

Publications (2)

Publication Number Publication Date
CN108018773A true CN108018773A (en) 2018-05-11
CN108018773B CN108018773B (en) 2019-08-30

Family

ID=62073402

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711327163.0A Expired - Fee Related CN108018773B (en) 2017-12-13 2017-12-13 A kind of self-propelled telescopic interim overline bridge

Country Status (1)

Country Link
CN (1) CN108018773B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110565502A (en) * 2019-09-16 2019-12-13 长安大学 Folding bridge and use method thereof
CN111119028A (en) * 2020-01-14 2020-05-08 王朝曙 Movable folding overbridge

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20080244841A1 (en) * 2007-04-09 2008-10-09 Lanigan John J Modular pedestrian bridge and system
JP2009281065A (en) * 2008-05-22 2009-12-03 River Corporation:Kk Connection bridge between landing bridge and ship
CN201593160U (en) * 2009-11-26 2010-09-29 广州大学 Movable and telescopic passenger foot bridge
CN102433832A (en) * 2011-12-07 2012-05-02 北京市三一重机有限公司 Combined overpass and bridge body module of the same
CN202416153U (en) * 2011-12-07 2012-09-05 北京市三一重机有限公司 Crawler-type urban pedestrian bridge
CN106593471A (en) * 2016-12-22 2017-04-26 中铁五局集团有限公司 Moveable trestle with stepping type self-walking truss structure for large-section tunnel invert construction
CN106638272A (en) * 2017-02-27 2017-05-10 辽宁工程技术大学 Self-moving type vehicular bridge for striding over belt conveyors
CN106758756A (en) * 2016-12-10 2017-05-31 徐州乐泰机电科技有限公司 A kind of interim overline bridge of Split type telescopic

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20080244841A1 (en) * 2007-04-09 2008-10-09 Lanigan John J Modular pedestrian bridge and system
JP2009281065A (en) * 2008-05-22 2009-12-03 River Corporation:Kk Connection bridge between landing bridge and ship
CN201593160U (en) * 2009-11-26 2010-09-29 广州大学 Movable and telescopic passenger foot bridge
CN102433832A (en) * 2011-12-07 2012-05-02 北京市三一重机有限公司 Combined overpass and bridge body module of the same
CN202416153U (en) * 2011-12-07 2012-09-05 北京市三一重机有限公司 Crawler-type urban pedestrian bridge
CN106758756A (en) * 2016-12-10 2017-05-31 徐州乐泰机电科技有限公司 A kind of interim overline bridge of Split type telescopic
CN106593471A (en) * 2016-12-22 2017-04-26 中铁五局集团有限公司 Moveable trestle with stepping type self-walking truss structure for large-section tunnel invert construction
CN106638272A (en) * 2017-02-27 2017-05-10 辽宁工程技术大学 Self-moving type vehicular bridge for striding over belt conveyors

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110565502A (en) * 2019-09-16 2019-12-13 长安大学 Folding bridge and use method thereof
CN110565502B (en) * 2019-09-16 2024-04-12 长安大学 Folding bridge and application method thereof
CN111119028A (en) * 2020-01-14 2020-05-08 王朝曙 Movable folding overbridge

Also Published As

Publication number Publication date
CN108018773B (en) 2019-08-30

Similar Documents

Publication Publication Date Title
CN111254796B (en) Single-side integral hoisting long-span overbridge for multiple railway business lines and construction method
CN105113388B (en) Formwork and bracket combining structure of vase pier of viaduct and application method
CN108004927B (en) Double-limb triangular hanging basket and construction method for cantilever beam section of large-span continuous rigid frame bridge
JP2007120077A (en) Erection method of elevated road bridge, and its facility
CN104594204B (en) Urban light rail viaduct mountain type U beam Construction Supporting System and construction method
CN113235472A (en) Concrete placement platform truck is contained to apron
CN108118620B (en) Integral self-climbing integrated platform for bridge tower construction and construction method thereof
CN107044090A (en) A kind of construction method of dual deck bridge
CN108018773A (en) A kind of self-propelled telescopic interim overline bridge
CN110453613A (en) A kind of cantilever method construction of Large span girder bridge box beam tunneling boring
CN210262739U (en) Bridge drainage pipe installation trolley system
CN214993219U (en) Concrete placement platform truck is contained to apron
CN204475184U (en) Urban light rail viaduct mountain type U beam Construction Supporting System
CN104929033A (en) Bridge structure similar to double-layer structure
CN106639303B (en) Elevator dedicated hydraulic creeping formwork frame body
CN111472255A (en) Lifting pedestrian bridge
CN107724225A (en) A kind of suspension type monorail Long span track girder system
CN219240333U (en) Trolley for construction of cover culvert
CN215714714U (en) Hanging basket equipment for installing bridge guardrail
CN116378711A (en) Shallow-buried underground excavation tunnel separated trolley device and construction method
CN214882871U (en) Steel construction overpass that can build fast
CN205188823U (en) Construction of light rail prestressing force bent cap and end -blocking work platform
KR100970959B1 (en) Method for Construction of Extension Culvert in State Guarantying Footway and Driveway
CN207812257U (en) A kind of suspension type monorail Long span track girder system
CN206829182U (en) A kind of Combined formwork support system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information
CB02 Change of applicant information

Address after: 315111 No. 45, Jing Da Road, five Township, Yinzhou District, Ningbo, Zhejiang.

Applicant after: Li Qinghua

Address before: 315153 No. 20 Shijian North Road, Shijiao Street, Haishu District, Ningbo City, Zhejiang Province

Applicant before: Li Qinghua

GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20191128

Address after: 315040 No.96, hibiscus Road, Ningbo high tech Zone, Ningbo, Zhejiang Province

Patentee after: Ningbo Roaby Technology Industrial Group Co., Ltd.

Address before: 315111 No. 45 Jingda Road, Five Townships, Yinzhou District, Ningbo City, Zhejiang Province

Patentee before: Li Qinghua

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190830