CN108005024A - A kind of indentation project under construction flood water-bound and its construction method - Google Patents

A kind of indentation project under construction flood water-bound and its construction method Download PDF

Info

Publication number
CN108005024A
CN108005024A CN201810074598.7A CN201810074598A CN108005024A CN 108005024 A CN108005024 A CN 108005024A CN 201810074598 A CN201810074598 A CN 201810074598A CN 108005024 A CN108005024 A CN 108005024A
Authority
CN
China
Prior art keywords
baffle
baffle plate
plate unit
supporting rod
bound
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810074598.7A
Other languages
Chinese (zh)
Inventor
林金华
段岳强
洪族智
林志军
付文辉
石常齐
薛华坤
祝勇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC First Highway Engineering Co Ltd
CCCC First Highway Xiamen Engineering Co Ltd
Original Assignee
CCCC First Highway Engineering Co Ltd
CCCC First Highway Xiamen Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC First Highway Engineering Co Ltd, CCCC First Highway Xiamen Engineering Co Ltd filed Critical CCCC First Highway Engineering Co Ltd
Priority to CN201810074598.7A priority Critical patent/CN108005024A/en
Publication of CN108005024A publication Critical patent/CN108005024A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/10Dams; Dykes; Sluice ways or other structures for dykes, dams, or the like
    • E02B3/106Temporary dykes

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Building Environments (AREA)

Abstract

The invention belongs to technical field of buildings, a kind of more particularly to indentation project under construction flood water-bound, including baffle, L-type ear wall positioned at baffle both sides, and the support system for being fixedly connected with baffle with horizontal earth's surface, the baffle is made of multiple baffle plate units, the baffle plate unit back side has two ribs diagonally intersected to be fixedly connected with the baffle plate unit back side, ribs center is welded with one piece of fixed articulated slab, the fixed articulated slab includes welding plate, the welding plate back side is equipped with two triangle faggings being arranged in parallel, the right-angle side of the triangle fagging is vertically arranged with welding plate, a keyhole is equipped with each triangle fagging, hinged movable bolt is equipped between two keyholes, the hinged movable bolt is flexibly connected with support system, the present invention has simple in structure, the advantages of easy to use.

Description

A kind of indentation project under construction flood water-bound and its construction method
Technical field
The invention belongs to technical field of buildings, more particularly to a kind of indentation project under construction flood water-bound and its construction party Method.
Background technology
In building field, the situation in pocket construction is frequently encountered, in case of rainstorm weather easily causes surface flow Have little time to exhaust, constantly collect, eventually flow in construction site, form waterlogging, hinder construction, cause unnecessary loss, be Prevent waterlogging construction party more using anti-waterflooding the methods of accumulation sandbag, time-consuming, laborious, construction inconvenience and waterproof is not tight, and sandbag There are some potential safety problems when accumulation is higher.
The content of the invention
The object of the present invention is to provide a kind of indentation project under construction flood water-bound and its construction method, can exist to indentation Build engineering and carry out waterproofing protection, do not influence duration and construction speed.
To reach above-mentioned purpose, the technical solution adopted by the present invention is:
A kind of indentation project under construction flood water-bound, including baffle, the L-type ear wall positioned at baffle both sides, and by baffle and water The support system that level land table is fixedly connected, the baffle are made of multiple baffle plate units, and each baffle plate unit is rectangle, baffle list Rearwardly fold forms otic placode at the edge on first each side, respectively upper ear plate, lower ear plate, left otic placode and auris dextra plate, the ear Plate is vertically arranged with baffle edge, and fixing threaded hole is equipped with each otic placode, and adjacent screen unit passes through the fixation on otic placode Screw hole has two ribs diagonally intersected with fixation, the baffle plate unit back side is bolted, and ribs are welded with baffle plate unit Connect, ribs center is welded with one piece of fixed articulated slab, and the fixed articulated slab is also rectangle, the fixed articulated slab bag Welding plate is included, the welding plate back side is equipped with two triangle faggings being arranged in parallel, and the right-angle side of the triangle fagging is vertically arranged with welding plate, A keyhole is equipped with each triangle fagging, hinged movable bolt, the hinged movable bolt and support are equipped between two keyholes System is flexibly connected.
Further, the baffle plate unit lower ear plate of baffle bottom is located at earth's surface depression edge lower part, baffle plate unit lower ear plate To be fixed by fixation kit and earth's surface depression edge, fixation kit includes the ground anchor bolt being arranged on baffle plate unit lower ear plate, Press strip and spring are additionally provided between ground anchor bolt and baffle plate unit lower ear plate, spring is located on the upside of press strip, and the length of spring is more than The length of ground anchor bolt, ground anchor bolt top are equipped with nut.
Further, the support system includes the branch of the supporting rod and fixed supporting rod positioned at each baffle plate unit back side Support angle steel, supporting rod one end is on hinged movable bolt, and the supporting rod other end is fixed and is welded in support angle steel, supporting rod or so Both sides are also welded with reinforcement web member, and the support angle steel is located at the right angle corner on the upside of earth's surface depression edge, and support angle steel is Right angle support angle steel, forms a right angled triangle, supporting rod is right angle trigonometry between baffle plate unit, supporting rod and horizontal earth's surface The bevel edge of shape.
Further, water expandable waterstop, the L-type are additionally provided between the L-type ear wall and the otic placode of baffle plate unit Ear wall is poured for armored concrete and formed.
Further, each otic placode outer surface of the baffle plate unit is equipped with the rubber strip that thickness is 1cm, the rubber Fixing threaded hole also is provided with bar.
Further, the baffle plate unit width is 60cm, length 100cm.
A kind of construction method of indentation project under construction flood water-bound, comprises the following steps:
1st, construction lofting, digs out recessed earth's surface in engineering access way mouth and constructs, and installs ground anchor bolt;
2nd, the concrete L-type ear wall of both sides is poured;
3rd, in each L-type ear, water expandable waterstop is placed in side within the walls;
4th, assembled first layer baffle plate unit, is fixed by the nut on the otic placode at left and right sides of each baffle plate unit;
5th, the compressing press strip of the nut on ground anchor bolt is screwed so as to compress the lower ear plate in orlop baffle plate unit;
6th, support angle steel is placed at the corner that recessed earth's surface constructs, one end of supporting rod is installed, and it is put on hinged work Dynamic bolt, the supporting rod other end are welded with support angle steel, and are welded in supporting rod the right and left and strengthened web member, form support system;
7th, decided whether that second layer baffle plate unit plate is installed according to the height of water level;
8th, after water level decreasing, first remove support system, remove again ground anchor bolt, remove baffle plate unit plate between fixing bolt, tear open Except baffle plate unit;
9th, after guard system is removed, construct in depression earth's surface and be laid with steel plate, can carry out freely being open to traffic, pedestrian;
10th, the situation of water blocking that needs is run into again, is removed steel plate, is repeated the above process hair phenomena such as rainwater being avoided to pour in down a chimney It is raw, it ensure that the security of the lives and property in construction.
Present invention has the advantage that:Since baffle is made of multiple baffle plate units in the present invention, actually using In, need to select suitable baffle plate unit quantity according to what is used and adapt to the baffle of length and height to make and adapt to actually make Needs, and due to being equipped with rubber strip between adjacent screen unit, between baffle plate unit and L-shaped ear wall, leakproofness is very It is good, water expandable waterstop is equipped between baffle and L-shaped ear wall, can be with the micro- error of adjust automatically, and the baffle of baffle bottom Unit stretch into earth's surface depression edge bottom after fixed again by ground anchor bolt, for convenience and reduce error caused by hole not to Problem, using press strip and the otic placode of spring suppression baffle bottom, has dual protective effect, when baffle plate unit is multiple, Supporting rod is equipped with each baffle plate unit back side, one end of supporting rod is arranged on hinged movable bolt, and the supporting rod other end is arranged on In support angle steel, and support angle steel is positioned at the right angle corner on the upside of earth's surface depression edge, and connection is more firm, baffle plate unit, Between supporting rod and horizontal earth's surface formed a right angled triangle, supporting rod be right angled triangle bevel edge, the structure of triangle It is more advantageous to stability.
Brief description of the drawings
Fig. 1 is schematic structural view of the invention.
Fig. 2 is the partial enlarged view of A in Fig. 1.
Fig. 3 is the partial enlarged view of B in Fig. 1.
Fig. 4 is the partial enlarged view of C in Fig. 1.
Fig. 5 is the structure diagram of baffle plate unit.
Fig. 6 is side structure schematic view when baffle plate unit uses.
1st, L-type ear wall;11st, water expandable waterstop;2nd, baffle plate unit;21st, fixing threaded hole;22nd, ribs;23rd, it is fixed Articulated slab;231st, welding plate;232nd, triangle fagging;2321st, keyhole;233rd, hinged movable bolt;24th, otic placode;25th, rubber strip;3rd, prop up Support body system;31st, support angle steel;32nd, supporting rod;4th, fixation kit;41st, ground anchor bolt;42nd, press strip;43rd, spring;44th, nut; 5th, horizontal earth's surface;51st, earth's surface depression edge.
Embodiment
As shown in the figure, a kind of indentation project under construction flood water-bound, including baffle, the L-type ear wall 1 positioned at baffle both sides, And the support system 3 for being fixedly connected with baffle with horizontal earth's surface, the baffle are made of multiple baffle plate units 2, the L-type ear It is additionally provided with water expandable waterstop 11 and rubber strip 25 between wall 1 and the otic placode of baffle plate unit 2, water expandable waterstop 11 can be with The micro- error of adjust automatically, easy to use, the L-type ear wall 1 is reinforced concrete structure, and each baffle plate unit 2 is rectangle, baffle 2 width of unit is 60cm, and length 100cm, rearwardly fold forms connection otic placode 24 at the edge on 2 each side of baffle plate unit, Respectively upper ear plate, lower ear plate, left otic placode and auris dextra plate, the otic placode 24 are vertically arranged with baffle edge, on each otic placode 24 Fixing threaded hole 21 is equipped with, 24 outer surface of each otic placode of baffle plate unit 2 is equipped with the rubber strip 25 that thickness is 1cm, the rubber Fixing threaded hole 21 also is provided with adhesive tape 25, adjacent screen unit 2 causes connection and sealing more to step up due to the presence of rubber strip 25 Close, adjacent screen unit 2 by the fixing threaded hole 21 on otic placode 24 and is bolted fixation, and 2 back side of baffle plate unit has two Diagonally intersecting ribs 22, ribs 22 are welded with baffle plate unit 2, and 22 center of ribs is welded with one piece of fixation Articulated slab 23, the fixed articulated slab 23 are also rectangle, and the fixed articulated slab 23 includes welding plate 231, and the welding plate back side is equipped with two A triangle fagging 232 being arranged in parallel, right-angle side and the welding plate 231 of the triangle fagging 232 are vertically arranged, each triangle fagging Be equipped with a keyhole 2321 on 232, be equipped with hinged movable bolt 233 between two keyholes 2321, the hinged movable bolt 233 with Support system 3 is flexibly connected;Further, the support system 3 includes 32 He of supporting rod positioned at each 2 back side of baffle plate unit The support angle steel 31 of fixed supporting rod 32, for 32 one end of supporting rod on hinged movable bolt 233,32 other end of supporting rod fixes weldering It is connected in support angle steel 31, when baffle plate unit 2 is multilayer, the supporting rod 32 of each baffle plate unit 2 is solid with support angle steel 31 Fixed connection, the support angle steel 31 are located at the right angle corner on the upside of earth's surface depression edge, and support angle steel 31 is right angle strut angle Steel 31, in this way, support angle steel 31 does not both have to fix, can also reach good fixation, need not in total When being removed, it is possible to reduce workload;A right angle trigonometry is formed between baffle plate unit 2, supporting rod 32 and horizontal earth's surface 5 Shape, supporting rod 32 are the bevel edge of right angled triangle, and the structure of triangle is more advantageous to stability;When mounted, baffle bottom 2 lower ear plate of baffle plate unit is located at earth's surface depression 51 lower part of edge, and 2 lower ear plate of baffle plate unit is recessed by fixation kit 4 and earth's surface Edge 51 is fixed, and fixation kit 4 includes the ground anchor bolt 41 being arranged on 2 lower ear plate of baffle plate unit, and 2 lower ear plate of baffle plate unit leads to Cross ground anchor bolt 41 to fix baffle plate unit 2 and earth's surface depression edge 51, between 2 lower ear plate of baffle plate unit and ground anchor bolt 41 also Equipped with press strip 42 and spring 43, spring 43 is located at the upside of press strip 42, and the length of spring 43 is more than the length of ground anchor bolt 41, earth anchor The top of bolt 41 is equipped with nut 44, for convenience and hole caused by reduction error not to the problem of, using press strip 42 and spring 43 The otic placode 24 of baffle bottom is suppressed, there is dual protective effect.
A kind of construction method of indentation project under construction flood water-bound, when specifically used, first, construction lofting, in engineering Access way mouth digs out recessed earth's surface and constructs, and installs ground anchor bolt 41, then pours the concrete L-type ear wall 1 of both sides;Each Place water expandable waterstop 11 in the inner side of L-type ear wall 1;Assembled first layer baffle plate unit 2 again, passes through each baffle plate unit 2 or so Nut on the otic placode 24 of both sides is fixed;The compressing press strip 42 of the nut on ground anchor bolt 41 is screwed so as to compress orlop baffle list Lower ear plate in member 2;Support angle steel 31 is placed at the corner that recessed earth's surface constructs, one end of supporting rod 32 is installed, and made It puts on hinged movable bolt 233, and 32 other end of supporting rod is welded with support angle steel 31, and is added in the welding of 32 the right and left of supporting rod Strong web member, forms support system 3;Decided whether that 2 plate of second layer baffle plate unit is installed according to the height of water level;After water level decreasing, First remove support system 3, remove again ground anchor bolt 41, remove 2 plate of baffle plate unit between fixing bolt, remove baffle plate unit;It is anti- After protecting system is removed, construct in depression earth's surface and be laid with steel plate, can carry out freely being open to traffic, pedestrian;Running into again needs to keep off The situation of water, removes steel plate, repeats the above process generation phenomena such as rainwater being avoided to pour in down a chimney, and ensure that lives and properties in construction Safety.

Claims (7)

  1. A kind of 1. indentation project under construction flood water-bound, it is characterised in that:Including baffle, the L-type ear wall positioned at baffle both sides, with And the support system for being fixedly connected with baffle with horizontal earth's surface, the baffle are made of multiple baffle plate units, each baffle plate unit For rectangle, rearwardly fold forms otic placode at the edge on each side of baffle plate unit, be respectively upper ear plate, lower ear plate, left otic placode and Auris dextra plate, the otic placode are vertically arranged with baffle edge, and fixing threaded hole is equipped with each otic placode, and adjacent screen unit passes through Fixing threaded hole on otic placode has two ribs diagonally intersected, ribs with fixation, the baffle plate unit back side is bolted Welded with baffle plate unit, ribs center is welded with one piece of fixed articulated slab, and the fixed articulated slab is also rectangle, described Fixed articulated slab includes welding plate, and the welding plate back side is equipped with two triangle faggings being arranged in parallel, the right-angle side of the triangle fagging and Welding plate is vertically arranged, and a keyhole is equipped with each triangle fagging, and hinged movable bolt is equipped between two keyholes, described hinged Movable bolt is flexibly connected with support system.
  2. 2. indentation project under construction flood water-bound as claimed in claim 1, it is characterised in that:Positioned at the baffle list of baffle bottom First lower ear plate is located at earth's surface depression edge department lower part, and baffle plate unit lower ear plate is fixed by fixation kit and earth's surface depression edge, Fixation kit includes the ground anchor bolt being arranged on baffle plate unit lower ear plate, is also set between baffle plate unit lower ear plate and ground anchor bolt There are press strip and spring, spring is located on the upside of press strip, and the length of spring is more than the length of ground anchor bolt, and spiral shell is equipped with the top of ground anchor bolt Cap.
  3. 3. indentation project under construction flood water-bound as claimed in claim 2, it is characterised in that:The support system includes being located at The support angle steel of the supporting rod at each baffle plate unit back side and fixed supporting rod, supporting rod one end is on hinged movable bolt, branch The strut other end is fixed and is welded in support angle steel, and supporting rod the right and left is also welded with reinforcement web member, the support angle steel position On the upside of earth's surface depression edge, support angle steel is right angle support angle steel, and one is formed between baffle plate unit, supporting rod and horizontal earth's surface A right angled triangle, supporting rod are the bevel edge of right angled triangle.
  4. 4. indentation project under construction flood water-bound as claimed in claim 3, it is characterised in that:The L-type ear wall and baffle list Water expandable waterstop is additionally provided between the otic placode of member, the L-type ear wall is poured for armored concrete and formed.
  5. 5. indentation project under construction flood water-bound as claimed in claim 4, it is characterised in that:Each ear of the baffle plate unit Plate outer surface is equipped with the rubber strip that thickness is 1cm, and fixing threaded hole also is provided with the rubber strip.
  6. 6. indentation project under construction flood water-bound as claimed in claim 3, it is characterised in that:The baffle plate unit width is 60cm, length 100cm.
  7. A kind of 7. construction method of indentation project under construction flood water-bound as described in claim 1-6 is any, it is characterised in that Comprise the following steps:
    (1)Construction lofting, digs out recessed earth's surface in engineering access way mouth and constructs, and installs ground anchor bolt;
    (2)Pour the concrete L-type ear wall of both sides;
    (3)In each L-type ear, water expandable waterstop is placed in side within the walls;
    (4)Assembled first layer baffle plate unit, is fixed by the nut on the otic placode at left and right sides of each baffle plate unit;
    (5)The compressing press strip of the nut on ground anchor bolt is screwed so as to compress the lower ear plate in orlop baffle plate unit;
    (6)Support angle steel is placed at the corner that recessed earth's surface constructs, one end of supporting rod is installed, and it is put on hinged work Dynamic bolt, the supporting rod other end are welded with support angle steel, and are welded in supporting rod the right and left and strengthened web member, form support system;
    (7)Decided whether that second layer baffle plate unit plate is installed according to the height of water level.
CN201810074598.7A 2018-01-25 2018-01-25 A kind of indentation project under construction flood water-bound and its construction method Pending CN108005024A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810074598.7A CN108005024A (en) 2018-01-25 2018-01-25 A kind of indentation project under construction flood water-bound and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810074598.7A CN108005024A (en) 2018-01-25 2018-01-25 A kind of indentation project under construction flood water-bound and its construction method

Publications (1)

Publication Number Publication Date
CN108005024A true CN108005024A (en) 2018-05-08

Family

ID=62066311

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810074598.7A Pending CN108005024A (en) 2018-01-25 2018-01-25 A kind of indentation project under construction flood water-bound and its construction method

Country Status (1)

Country Link
CN (1) CN108005024A (en)

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201817814U (en) * 2010-09-17 2011-05-04 中国十七冶集团有限公司 Adjustable fixed support of vertical surface sheet steel form
CN205276208U (en) * 2016-01-08 2016-06-01 福州轨道交通设计院有限公司 Prevent flooding breakwater
KR101698916B1 (en) * 2015-12-11 2017-01-24 주식회사 우노 method of making temporary water protection wall using apparatus for temporary water protection
CN206346208U (en) * 2017-01-04 2017-07-21 赵剑芳 Movable type combination waterproof cofferdam
CN206570984U (en) * 2016-04-28 2017-10-20 文登蓝岛建筑工程有限公司 Wall under a kind of anti-wall leakage
CN206595803U (en) * 2017-03-28 2017-10-27 艾司匹技电机(苏州)有限公司 A kind of understructure being easily installed for Brushless DC motor
CN206591827U (en) * 2017-03-20 2017-10-27 中冶建工集团有限公司 A kind of shear wall aluminum alloy mould plate inclined support structure
CN207794005U (en) * 2018-01-25 2018-08-31 中交第一公路工程局有限公司 A kind of indentation project under construction flood water-bound

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201817814U (en) * 2010-09-17 2011-05-04 中国十七冶集团有限公司 Adjustable fixed support of vertical surface sheet steel form
KR101698916B1 (en) * 2015-12-11 2017-01-24 주식회사 우노 method of making temporary water protection wall using apparatus for temporary water protection
CN205276208U (en) * 2016-01-08 2016-06-01 福州轨道交通设计院有限公司 Prevent flooding breakwater
CN206570984U (en) * 2016-04-28 2017-10-20 文登蓝岛建筑工程有限公司 Wall under a kind of anti-wall leakage
CN206346208U (en) * 2017-01-04 2017-07-21 赵剑芳 Movable type combination waterproof cofferdam
CN206591827U (en) * 2017-03-20 2017-10-27 中冶建工集团有限公司 A kind of shear wall aluminum alloy mould plate inclined support structure
CN206595803U (en) * 2017-03-28 2017-10-27 艾司匹技电机(苏州)有限公司 A kind of understructure being easily installed for Brushless DC motor
CN207794005U (en) * 2018-01-25 2018-08-31 中交第一公路工程局有限公司 A kind of indentation project under construction flood water-bound

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
张世凤;王谷丰;武旭南;徐宁;: "一种地下工程新型防水外墙水平施工缝作法", 《膨胀剂与膨胀混凝土》, no. 03, pages 16 - 18 *

Similar Documents

Publication Publication Date Title
CN204691106U (en) The waterproof construction of a kind of metal roofing board and U-shaped gutter joint portion
CN210713552U (en) Roof structure with inverted concrete slab protection layer
CN206346208U (en) Movable type combination waterproof cofferdam
CN207794005U (en) A kind of indentation project under construction flood water-bound
CN214737834U (en) Simple fastener type steel pipe operation platform
CN108005024A (en) A kind of indentation project under construction flood water-bound and its construction method
CN206554318U (en) Wall is built in a kind of room
CN209538214U (en) A kind of late poured band structure of outer wall of basement
CN109356224A (en) A kind of skyscraper rainwater-collecting self-loopa utilizes system
CN206189694U (en) Assembled room lid
CN207419545U (en) Basement roof aseismatic joint
CN212248384U (en) Sealing device for post-cast strip of top plate of underground chamber
CN206625107U (en) A kind of new road discharge structure
CN203613826U (en) Mobile house
CN207469528U (en) A kind of construction wall steel structure frame
CN209799341U (en) Scaffold board flat plate device for steel pipe external scaffold
CN106759526A (en) Purlin protection preprocess method is enclosed before a kind of Brace in Deep Footing Groove beam demolition blasting
CN210421517U (en) Building masonry structure
CN111576648A (en) Waterproof structure
CN208415538U (en) A kind of trapping structure for building expansion joint waterproof
CN209603196U (en) Sole plate post-poured strip structure
CN207974506U (en) A kind of regularization hard protection device for elevator
CN208379644U (en) A kind of post-cast strip built for basement
CN207846461U (en) One kind plus pier Foundation Supported with Composite Soil Nailing
CN203347080U (en) Low-span steel roof joint construction at high-low spans of steel structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information

Address after: 100000 Shitong International Building, Zhoujiajing Courtyard, Guanzhuang, Chaoyang District, Beijing

Applicant after: CHINA FIRST HIGHWAY ENGINEERING Co.,Ltd.

Applicant after: CCCC FIRST HIGHWAY XIAMEN ENGINEERING Co.,Ltd.

Address before: 100000 Shitong International Building, Zhoujiajing Courtyard, Guanzhuang, Chaoyang District, Beijing

Applicant before: CCCC FIRST HIGHWAY ENGINEERING Co.,Ltd.

Applicant before: CCCC FIRST HIGHWAY XIAMEN ENGINEERING Co.,Ltd.

CB02 Change of applicant information