China
Prior art keywords
track
fixture block
elevator
bracket
rail system
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201711497377.2A
Other languages
Chinese (zh)
Other versions
CN108002185B (en
Inventor
贾才骏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Hanshen Co ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201711497377.2A priority Critical patent/CN108002185B/en
Publication of CN108002185A publication Critical patent/CN108002185A/en
Application granted granted Critical
Publication of CN108002185B publication Critical patent/CN108002185B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66BELEVATORS; ESCALATORS OR MOVING WALKWAYS
    • B66B11/00Main component parts of lifts in, or associated with, buildings or other structures
    • B66B11/02Cages, i.e. cars
    • B66B11/0206Car frames
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66BELEVATORS; ESCALATORS OR MOVING WALKWAYS
    • B66B7/00Other common features of elevators
    • B66B7/02Guideways; Guides
    • B66B7/023Mounting means therefor

Landscapes

  • Engineering & Computer Science (AREA)
  • Civil Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Structural Engineering (AREA)
  • Lift-Guide Devices, And Elevator Ropes And Cables (AREA)

Abstract

The present invention relates to a kind of elevator rail system and its application method, including a plurality of tracks, the bracket of connection carriage and track and multiple fixture blocks being used for the one-to-one cooperation of track;Fixture block is slidably connected by the fixture block slide on bracket with bracket.The beneficial effects of the invention are as follows:By when elevator is installed, a plurality of tracks is laid with advance, and by setting multiple fixture blocks that can coordinate with track and being connected fixture block with lift car by bracket, during so that replacing track, it is only necessary to change the replacement that track can be achieved in guide rail and the fixture block coordinated with it, replace quick and convenient, it is poor to overcome existing worker's construction environment when original rail system replaces track, the easy heatstroke of summer high-temperature, time-consuming for replacement, the defects such as efficiency is low.In addition, it can be determined to be laid with the track of respective numbers according to the design service life of elevator so that the service life of elevator maximizes.

Description

A kind of elevator rail system and its application method
Technical field
The present invention relates to elevator rail system, more particularly to a kind of elevator rail system and its application method.
Background technology
More and more with the application of elevator, more people have enjoyed the facility of elevator, but for elevator, electricity The later stage maintenance and repair cost of ladder is higher, and some components of especially elevator are expired due to the use of the service life, it is necessary to be replaced When, limited be subject to hoistway environment, replace inconvenience, difficulty of construction is big, long in time limit.Such as the service life of elevator rail and electricity Humidity, temperature and frequency of use etc. are closely related in stair shaft, once and elevator rail deforms or damages, it is necessary in time more Change, but existing track is replaced arrangement and method for construction and relatively fallen behind, and can only be manually entered in elevator and carry out the dismounting of old track and new rail The laying in road, and due to narrow space in elevator, there are worker's construction environment is poor, the easy heatstroke of summer high-temperature replaces that time-consuming, The defects such as efficiency is low.Therefore, it is necessary to a kind of new elevator rail system to substitute original system for being difficult to replace track.
The content of the invention
The technical problems to be solved by the invention are to provide the elevator rail system and its application method for being conveniently replaceable track, Solve the problems, such as that the track of existing elevator rail system replaces hardly possible, it is replaced rapidly and efficiently with track, is saved labour turnover Feature.
The technical solution that the present invention solves above-mentioned technical problem is as follows, a kind of elevator rail system for being conveniently replaceable track, Including be laid in elevator a plurality of tracks, on lift car be used for connect the carriage and the track bracket and Multiple fixture blocks being used for multiple one-to-one cooperations of track on the bracket;The fixture block passes through arranged on the support Fixture block slide on frame is slidably connected with the bracket;The fixture block is equipped with the open slot coordinated with the track;The support Frame is equipped with the track opening for being used for track insertion;Mouth of the mouth of the track opening away from more than the open slot away from;Institute Track is stated to be T-shaped, it includes the fixed part fixed with elevator and the guide part coordinated with the open slot.
Further, track protective case is arranged with the guide part;Twice of wall thickness of the track protective case is led with described The sum of thickness to portion be less than the track opening mouth away from.
Preferably, the track protective case inner wall is coated with xeraphium.By the effect of xeraphium, it can prevent track from giving birth to Rust.
Further, the track protective case is removable sealing shroud.Track protective case is arranged to removable so that more When switching tracks, replace more efficient.
Preferably, the track is multigroup by being divided into using sequencing, and track described in every group is equipped with and is marked with the track Initial use date and the label or mark of service life.It is effective easy to be carried out to track use state by label and mark Record, prevents from using wrong track, also allows for being quickly found out replaceable track when replacing.
Further, the fixed part is fixed by connecting bolt with elevator.
Preferably, the fixed part is integrally formed with the guide part.
Further preferably, the fixture block slide is set perpendicular to the fixed part;The fixture block is by tightening bolt and institute Fixture block slide is stated to fix.
The present invention also proposes a kind of application method for the elevator rail system for being conveniently replaceable track, includes the following steps:
Attachment rail, first by the track by being divided into multiple track groups using sequencing, each track groups are at least wrapped Two tracks are included, then each track groups are laid in elevator and are in two offside of carriage;
Bracket, is fixedly mounted in carriage by mounting bracket and fixture block first, during installation, keeps track opening to be occupied with track Middle alignment;Fixture block slide is installed on bracket again, finally fixture block is installed on fixture block slide, during installation, keeps fixture block Open slot and track align center;
Determine track;The track groups used are chosen, the corresponding each fixture block of the track groups are slid into each with the track groups The position of track cooperation and fixation;Sliding remaining fixture block makes it be in position and the fixation of non-cooperation with corresponding track.
The beneficial effects of the invention are as follows:By when elevator is installed, being laid with a plurality of tracks in advance, and by set it is multiple can Fixture block is connected with lift car with the fixture block of track cooperation and by bracket so that when replacing track, it is only necessary to change guide rail And the replacement of track can be achieved in the fixture block coordinated with it, replacement is quick and convenient, when overcoming original rail system replacement track Existing worker's construction environment is poor, the easy heatstroke of summer high-temperature, and time-consuming for replacement, the defects such as efficiency is low.In addition, can be according to elevator Design service life and determine to be laid with the track of respective numbers so that the service life of elevator maximizes.
Brief description of the drawings
Fig. 1 is the structure diagram of the elevator rail system for being conveniently replaceable track of the present invention;
Fig. 2 is the structure diagram after one Post Orbit of elevator rail system conversion in Fig. 1;
Fig. 3 be Fig. 1 in fixture block slide be arranged on bracket on after structure diagram;
Fig. 4 is the structure diagram that Fig. 1 middle orbits are equipped with track protective case;
Fig. 5 is the structure diagram of Fig. 1 middle orbits;
In figure, track 1, bracket 2, fixture block 3, fixture block slide 4, open slot 5, track opening 6, fixed part 7, guide part 8, rail Pipe protection set 9, label 10, tighten bolt 11, connection bolt 12, carriage 13, elevator 14.
Embodiment
The principle and features of the present invention will be described below with reference to the accompanying drawings, and the given examples are served only to explain the present invention, and It is non-to be used to limit the scope of the present invention.
The elevator rail system of track is conveniently replaceable as shown in Fig. 1~5, including a plurality of rail being laid in elevator 14 Road 1, the bracket 2 for being used on lift car 13 connecting carriage 13 and track 1 and it is multiple on the bracket 2 be used for it is multiple The fixture block 3 of 1 one-to-one cooperation of track;Fixture block 3 is slidably connected by the fixture block slide 4 on bracket 2 with bracket 2;On fixture block 3 Equipped with the open slot 5 coordinated with track 1;Bracket 2, which is equipped with, is used for the track opening 6 that track 1 is inserted into;The mouth of track opening 6 away from More than open slot 5 mouth away from;Track 1 is T-shaped, it includes what is coordinated with the fixed part 7 of the fixation of elevator 14 and with open slot 5 Fixed part 7 is divided into two parts by guide part 8, guide part 8 perpendicular to the middle part of fixed part 7.
Track protective case 9 is arranged with guide part 8;Twice of the wall thickness and the sum of the thickness of guide part 8 of track protective case 9 are small In track opening 6 mouth away from.
9 inner wall of track protective case is coated with xeraphium (not shown).By the effect of xeraphium, it can prevent track 1 from giving birth to Rust.In addition, lubricant can be also equipped with track protective case 9.
Track protective case 9 is removable sealing shroud.Track protective case 9 is arranged to removable so that when replacing track 1, Replace more efficient.For example, track protective case 9 is a kind of TR thin rubber set, it can be scratched and pulled down by blade.
Track 1 is multigroup by being divided into using sequencing, and every group of track 1, which is equipped with, is marked with the 1 initial use date of track With the label 10 or mark of service life.By label 10 and mark, easy to effectively be recorded to 1 use state of track, prevent Only with wrong track 1, also allow for being quickly found out replaceable track 1 when replacing.Label 10 or mark are preferably disposed within each track 1 Sustained height position, easy to be quickly found out.The initial use date of above-mentioned track 1 is artificial mark, for example, when replacing, more Marked on the track 1 changed and replace the date, which can be the initial use date of track 1.
Fixed part 7 is fixed by connecting bolt 12 with elevator 14.Preferably, the one of fixed part 7 and guide part 8 into Type.
Fixture block slide 4 is set perpendicular to fixed part 7;Fixture block 3 is fixed by tightening bolt 11 with fixture block slide 4.
In addition, the application method of the present invention, includes the following steps:
Attachment rail 1 first, by track 1 by being divided into multiple track groups using sequencing, each track groups include at least Two tracks 1, then each track groups are laid in elevator 14 and are in 13 liang of offsides of carriage.
Bracket 2, is fixedly mounted in carriage 13 by then mounting bracket 2 and fixture block 3 first, during installation, keeps track to open Mouth 6 and 1 align center of track;Fixture block slide 4 is installed on carrier 2 again, finally fixture block 3 is installed on fixture block slide 4, peace During dress, the open slot 5 and 1 align center of track of fixture block 3 are kept.
Finally determine track 1;The track groups used are chosen, the corresponding each fixture block 3 of the track groups is slid into and the track The position of the cooperation of each track 1 of group and fixation;Sliding remaining fixture block 3 makes it be in the position of non-cooperation simultaneously with corresponding track 1 It is fixed.
For example, track 1 has six, six tracks 1 can be divided for three track groups, each track groups it is each in 13 both sides of carriage It is distributed a track 1.When rail system using needing replacing for a period of time, such as, the service life of each track groups is 10 years, Then need replacing a Post Orbit 1 within every ten years, the service life of elevator can then arrange five track groups if 50 years, need altogether Replace four Post Orbits 1 so that elevator service life maximizes.The method for replacing track 1 uses the above method, herein not Repeat again.
The foregoing is merely presently preferred embodiments of the present invention, is not intended to limit the invention, it is all the present invention spirit and Within principle, any modification, equivalent replacement, improvement and so on, should all be included in the protection scope of the present invention.

Claims (9)

  1. A kind of 1. elevator rail system for being conveniently replaceable track, it is characterised in that:It is a plurality of in elevator (14) including being laid on Track (1), be used to connect the bracket (2) of the carriage (13) and the track (1) and multiple set on lift car (13) In the fixture block (3) being used for the one-to-one cooperation of multiple tracks (1) on the bracket (2);The fixture block (3) by arranged on Fixture block slide (4) on the bracket (2) is slidably connected with the bracket (2);The fixture block (3) is equipped with and the track (1) open slot (5) coordinated;The bracket (2) is equipped with the track opening (6) for being used for the track (1) insertion;The track Be open (6) mouth of the mouth away from more than the open slot (5) away from;The track (1) is T-shaped, it includes solid with elevator (14) Fixed fixed part (7) and the guide part (8) coordinated with the open slot (5).
  2. 2. the elevator rail system according to claim 1 for being conveniently replaceable track, it is characterised in that:The guide part (8) On be arranged with track protective case (9);Twice of the wall thickness and the sum of the thickness of the guide part (8) of the track protective case (9) are small In the track opening (6) mouth away from.
  3. 3. the elevator rail system according to claim 2 for being conveniently replaceable track, it is characterised in that:The track protective case (9) inner wall is coated with xeraphium.
  4. 4. the elevator rail system according to claim 2 for being conveniently replaceable track, it is characterised in that:The track protective case (9) it is removable sealing shroud.
  5. 5. the elevator rail system according to claim 1 for being conveniently replaceable track, it is characterised in that:The track (1) by It is divided into using sequencing multigroup, track (1) described in every group, which is equipped with, is marked with the initial use date of the track (1) and using year The label (10) or mark of limit.
  6. 6. the elevator rail system according to any one of claims 1 to 5 for being conveniently replaceable track, it is characterised in that:It is described Fixed part (7) is fixed with elevator (14) by connecting bolt (12).
  7. 7. the elevator rail system according to any one of claims 1 to 5 for being conveniently replaceable track, it is characterised in that:It is described Fixed part (7) is integrally formed with the guide part (8).
  8. 8. the elevator rail system according to any one of claims 1 to 5 for being conveniently replaceable track, it is characterised in that:It is described Fixture block slide (4) is set perpendicular to the fixed part (7);The fixture block (3) is by tightening bolt (11) and the fixture block slide (4) it is fixed.
  9. A kind of 9. application method of the elevator rail system as claimed in claim 1 for being conveniently replaceable track, it is characterised in that:Bag Include following steps:
    Attachment rail (1), first by the track (1) by being divided into multiple track groups using sequencing, each track groups are at least Including two tracks (1), then each track groups are laid in elevator (14) and are in (13) two offside of carriage;
    Bracket (2), is fixedly mounted in carriage (13) by mounting bracket (2) and fixture block (3) first, during installation, keeps track to open Mouth (6) and track (1) align center;Fixture block slide (4) is installed on bracket (2) again, fixture block (3) is finally installed on fixture block On slide (4), during installation, the open slot (5) and track (1) align center of fixture block (3) are kept;
    Determine track (1);The track groups used are chosen, the corresponding each fixture block (3) of the track groups is slid into and the track groups The position of each track (1) cooperation and fixation;Sliding remaining fixture block (3) makes it be in the position of non-cooperation with corresponding track (1) It is and fixed.
CN201711497377.2A 2017-12-31 2017-12-31 Elevator track system and using method thereof Active CN108002185B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711497377.2A CN108002185B (en) 2017-12-31 2017-12-31 Elevator track system and using method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711497377.2A CN108002185B (en) 2017-12-31 2017-12-31 Elevator track system and using method thereof

Publications (2)

Publication Number Publication Date
CN108002185A true CN108002185A (en) 2018-05-08
CN108002185B CN108002185B (en) 2020-08-25

Family

ID=62049392

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711497377.2A Active CN108002185B (en) 2017-12-31 2017-12-31 Elevator track system and using method thereof

Country Status (1)

Country Link
CN (1) CN108002185B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112478982A (en) * 2020-11-24 2021-03-12 沪东中华造船(集团)有限公司 Method for installing vertical guide rail of ship elevator
CN113860123A (en) * 2021-10-29 2021-12-31 杭州奥立达电梯有限公司 Top-hung single-portal-frame six-rail elevator safety car frame equipment

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006256836A (en) * 2005-03-18 2006-09-28 Toshiba Elevator Co Ltd Guide rail oiling device of elevator
CN1902117A (en) * 2003-12-19 2007-01-24 奥蒂斯电梯公司 Car fall-prevention apparatus
CN101336202A (en) * 2006-02-08 2008-12-31 株式会社日立制作所 Elevator apparatus and guiding apparatus therewith
CN205998808U (en) * 2016-08-26 2017-03-08 浙江西子重工机械有限公司 A kind of slide block elevator guide shoe
CN107187992A (en) * 2017-06-23 2017-09-22 浙江西子重工机械有限公司 A kind of detachable slide block type elevator guide shoe

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1902117A (en) * 2003-12-19 2007-01-24 奥蒂斯电梯公司 Car fall-prevention apparatus
JP2006256836A (en) * 2005-03-18 2006-09-28 Toshiba Elevator Co Ltd Guide rail oiling device of elevator
CN101336202A (en) * 2006-02-08 2008-12-31 株式会社日立制作所 Elevator apparatus and guiding apparatus therewith
CN205998808U (en) * 2016-08-26 2017-03-08 浙江西子重工机械有限公司 A kind of slide block elevator guide shoe
CN107187992A (en) * 2017-06-23 2017-09-22 浙江西子重工机械有限公司 A kind of detachable slide block type elevator guide shoe

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112478982A (en) * 2020-11-24 2021-03-12 沪东中华造船(集团)有限公司 Method for installing vertical guide rail of ship elevator
CN113860123A (en) * 2021-10-29 2021-12-31 杭州奥立达电梯有限公司 Top-hung single-portal-frame six-rail elevator safety car frame equipment
CN113860123B (en) * 2021-10-29 2023-08-25 杭州奥立达电梯有限公司 Safety sedan frame of top-hung single-portal frame six-rail elevator

Also Published As

Publication number Publication date
CN108002185B (en) 2020-08-25

Similar Documents

Publication Publication Date Title
CN108002185A (en) A kind of elevator rail system and its application method
CN111086532A (en) Super subway system and operation mode thereof
WO2009119950A1 (en) Ventilation system and method of subway station based on comparison between indoor and outdoor air
CN104532690A (en) Method for prefabricating and constructing separated rail structure
CN112884185A (en) Distribution network resource first-aid repair optimal scheduling method based on tabu search algorithm
CN211468220U (en) Contact net suspension installation device in assembled subway station
CN107747257B (en) Vibration-damping compression-resistant anti-slip sleeper for subsequent transport of power transmission bottle truck of shield tunneling machine and construction method of vibration-damping compression-resistant anti-slip sleeper
CN105780614A (en) Composite cement track slab ground roll bracket
CN207955663U (en) A kind of brake apparatus of monorail crane crusing robot
CN105984821B (en) Boom hoisting in a kind of Wind turbines cabin used on demand
CN101920876A (en) Repairing platform device for elevator pit
CN205871788U (en) Condact rail supports base temporarily
CN112297958B (en) Method for replacing whole dropper in whole anchor section of 350km/h high-speed rail contact network
CN202225204U (en) Steel-structure overhauling work platform of depot of urban railway transit vehicles
CN115559765A (en) Tunnel pipeline ventilation unit for building engineering
CN106120487A (en) Composite cement guidance tape ground roll bracket
CN208968352U (en) A kind of Air-Cooling Island cleaning device
CN209398923U (en) Segmental timbering
CN105926377A (en) Composite cement road plate ground roller bracket
CN201817158U (en) Overhauling platform device of pit of elevator
CN201882073U (en) Modularized pipe row of brake system
CN219197391U (en) Emergency evacuation platform for rail transit
CN214585132U (en) Positioning pin fixing structure for double-rail sliding shoe type steel rail ultrasonic flaw detector
CN113700497B (en) A modular joint installation design structure for arc aluminum plate of track traffic
CN219731481U (en) Rail assembly structure for inspection pit

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20200730

Address after: 201900, No. 258, Yue Yue Road, Shanghai, Baoshan District

Applicant after: SHANGHAI HANSHEN Co.,Ltd.

Address before: 430074 Hongshan high school, Hongshan District, Hubei, Wuhan

Applicant before: Jia Caijun

GR01 Patent grant
GR01 Patent grant
PE01 Entry into force of the registration of the contract for pledge of patent right
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of invention: An elevator track system and its usage method

Effective date of registration: 20230417

Granted publication date: 20200825

Pledgee: China Minsheng Banking Corp Shanghai branch

Pledgor: SHANGHAI HANSHEN CO.,LTD.