CN107974878B - A kind of rail yard track switch reinforcement means and structure - Google Patents

A kind of rail yard track switch reinforcement means and structure Download PDF

Info

Publication number
CN107974878B
CN107974878B CN201711227336.1A CN201711227336A CN107974878B CN 107974878 B CN107974878 B CN 107974878B CN 201711227336 A CN201711227336 A CN 201711227336A CN 107974878 B CN107974878 B CN 107974878B
Authority
CN
China
Prior art keywords
type construction
construction beam
switch
track switch
angle steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201711227336.1A
Other languages
Chinese (zh)
Other versions
CN107974878A (en
Inventor
李健源
陶强
黄光强
章继树
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Siyuan Survey and Design Group Co Ltd
Nanning Survey and Design Institute Co Ltd of China Railway Siyuan Survey and Design Group Co Ltd
Original Assignee
China Railway Siyuan Survey and Design Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Siyuan Survey and Design Group Co Ltd filed Critical China Railway Siyuan Survey and Design Group Co Ltd
Priority to CN201711227336.1A priority Critical patent/CN107974878B/en
Publication of CN107974878A publication Critical patent/CN107974878A/en
Application granted granted Critical
Publication of CN107974878B publication Critical patent/CN107974878B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B7/00Switches; Crossings
    • E01B7/10Frogs

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Machines For Laying And Maintaining Railways (AREA)

Abstract

A kind of rail yard track switch reinforcement means provided by the invention and structure, the described method includes: step 1, is arranged D type construction beam stringer in track switch two sides, and support the D type construction beam stringer using borehole column;Step 2, D type construction beam crossbeam is fixedly installed in switch tie bottom, and the both ends of the D type construction beam crossbeam are contacted with the D type construction beam stringer of the track switch two sides respectively;Step 3, the end of the D type construction beam stringer and the D type construction beam crossbeam is fastened by bracket and connecting plate.A kind of rail yard track switch reinforcement means provided by the invention ensure that safety, stationarity and comfort when train passes through track switch so that each component connection relationship is solid and reliable in rail yard track switch;Meanwhile the ruggedized construction good integrity obtained by the rail yard track switch reinforcement means, it is applicable to the reinforcing of different model track switch.

Description

A kind of rail yard track switch reinforcement means and structure
Technical field
The present invention relates to railway construction technical fields, more particularly, to a kind of rail yard track switch reinforcement means and knot Structure.
Background technique
Track switch is a kind of weakness of line connection equipment and track for making rolling stock be transferred to another station track from a station track One of link, usually AT STATION, marshalling yard is largely laid with.There is track switch, the handling capacity of route can be given full play to.Even Single-track railway, laying a switch build one section of cross wires for being greater than train length, so that it may split train.Track switch is on rail track It plays an important role.
Implement the continuous development of " Ping Gaili " engineering and each urban construction, railway Grade Separation Project along with China railways Quantity be increasing, on the basis of existing railway working line, not cut off traffic as principle, can generally use jacking Build frame bridge.Since urban planning road network is influenced by many factors, it inevitably will appear road from railway switch Area below by the case where.The structure design comparison of track switch is complicated, very sensitive to the vertical and horizontal displacement of route, commonly The vertical stability chosen horizontal lift beam reinforcing and be difficult to ensure switch structure of I-steel.
Traditionally generally handled using following two method: first is that adjustment highway layout line position, avoids railway switch area, this Sample can be using conventional track strengthening mode, but influences on urban road network planning very big;It is changed to second is that track switch is temporarily moved Except road construction coverage, restore to the original state after frame jacking construction, but be affected to railway operation.
The existing construction method suitable for switch area track strengthening includes: to connect stringer using U-bolt with crossbeam, Stringer is placed on caisson apical cap beam.But entire reinforcement system snap fit part is more, integral reinforcing effect is poor, it is difficult to meet track switch The high request of stationarity;And stringer span is limited, frame jack-in process must remove the caisson in coverage, to switch structure Stability influence it is big.
Summary of the invention
For the above technical issues, the present invention provides a kind of rail yard track switch reinforcement means and structure.
In a first aspect, the present invention provides a kind of rail yard track switch reinforcement means, comprising: step 1, be arranged in track switch two sides D type construction beam stringer, and the D type construction beam stringer is supported using borehole column;Step 2, it is fixedly installed in switch tie bottom D type construction beam crossbeam, and the both ends of the D type construction beam crossbeam are vertical with the D type construction beam of the track switch two sides respectively Beam contact;Step 3, by bracket and connecting plate by the end of the D type construction beam stringer and the D type construction beam crossbeam Fastening.
Wherein, after the step 3 further include: be laid with steel between the D type construction beam crossbeam and the switch tie Plate, and the D type construction beam crossbeam is connect with the Interal fixation;And limit angle is respectively provided at the both ends of the switch tie Switch tie fixation is limited on the steel plate by steel.
Wherein, limit angle steel is respectively provided at the both ends of the switch tie to specifically include: being respectively provided with cross at the both ends of the switch tie To limit angle steel and longitudinal spacing angle steel, and the cross spacing angle steel and the longitudinal spacing angle steel are bolted on On the steel plate.
Wherein, after the both ends of the switch tie are respectively provided with cross spacing angle steel and longitudinal spacing angle steel further include: described Clog weedtree in gap between cross spacing angle steel and the switch tie, and the longitudinal spacing angle steel and the switch tie it Between gap in clog weedtree.
Wherein, the rail yard track switch reinforcement means, which is characterized in that further include: it is arranged on the switch tie and hangs Beam-and-rail, and be fixedly connected with the hanger rail beam, the D type construction beam crossbeam and the switch tie with U-bolt.
Wherein, after the step 3 further include: goat is set on the D type construction beam crossbeam, and uses angle steel The goat is fixed on the D type construction beam crossbeam.
Wherein, the rail yard track switch reinforcement means, further includes: be arranged between the switch tie and the steel plate exhausted Listrium.
Wherein, the rail yard track switch reinforcement means, further includes: Framed underpass bridge, and frame are carried out after the completion of reinforcing Ruggedized equipment is removed after the completion of bridge formation jacking.
Second aspect, the present invention provide a kind of rail yard track switch ruggedized construction, comprising: the D type of track switch two sides is arranged in Construction beam stringer supports the borehole column of the D type construction beam stringer;It is fixed at the D type construction beam of switch tie bottom Crossbeam, and the both ends of the D type construction beam crossbeam are contacted with the D type construction beam stringer of the track switch two sides respectively;Institute The both ends for stating D type construction beam crossbeam are equipped with connecting plate, the connecting plate by the end of the D type construction beam crossbeam with The D type construction beam stringer is fixedly connected;And in the company of the D type construction beam crossbeam and the D type construction beam stringer Connect place's setting bracket.
Wherein, the rail yard track switch ruggedized construction, further includes: be fixed at the D type construction beam crossbeam With the steel plate between the switch tie;And the cross spacing angle steel and longitudinal spacing angle steel of the switch tie end are set, and institute One right-angle side of a right-angle side and the longitudinal spacing angle steel for stating cross spacing angle steel is fixed on the steel plate.
A kind of rail yard track switch reinforcement means provided by the invention and structure are constructed by the way that D type is arranged in track switch two sides Just beam stringer crosses switch tie bottom setting D type construction beam crossbeam, and passes through bracket and connecting plate for D type construction beam stringer It is fixedly connected with D type construction beam crossbeam, so that each component connection relationship is solid and reliable in rail yard track switch, ensure that train Pass through safety, stationarity and the comfort when track switch;Meanwhile the reinforcing knot obtained by the rail yard track switch reinforcement means Structure good integrity is applicable to the reinforcing of different model track switch.
Detailed description of the invention
In order to more clearly explain the embodiment of the invention or the technical proposal in the existing technology, to embodiment or will show below There is attached drawing needed in technical description to be briefly described, it should be apparent that, the accompanying drawings in the following description is this hair Bright some embodiments for those of ordinary skill in the art without creative efforts, can be with root Other attached drawings are obtained according to these attached drawings.
Fig. 1 is the flow chart of rail yard track switch reinforcement means provided in an embodiment of the present invention;
Fig. 2 is the plan view of rail yard track switch ruggedized construction provided in an embodiment of the present invention;
Fig. 3 is the cross-sectional view of rail yard track switch ruggedized construction shown in Fig. 2;
Fig. 4 is the switch tie and D type construction beam crossbeam of vertical main track in rail yard track switch ruggedized construction shown in Fig. 2 Connection relationship cross-section diagram;
Fig. 5 is the connection of inclined switch tie and D type construction beam crossbeam in rail yard track switch ruggedized construction shown in Fig. 2 Relationship cross-section diagram;
Fig. 6 is the plan view of switch tie and D type construction beam crossbeam in rail yard track switch ruggedized construction shown in Fig. 2;
Wherein, 1-D type construction beam stringer;2-D type construction beam crossbeam;3- hanger rail beam;4- bracket;5-U type bolt; 6- railway switch;7- angle steel;8- caisson;9- pre-embedded bolt;10- connecting plate;11- insulation board;12- tongue;13- stock rail; 14- switch tie;15- steel plate;161- cross spacing angle steel;162- longitudinal spacing angle steel;17- connection bolt;18- weedtree.
Specific embodiment
In order to make the object, technical scheme and advantages of the embodiment of the invention clearer, below in conjunction with the embodiment of the present invention In attached drawing, technical solution in the embodiment of the present invention is explicitly described, it is clear that described embodiment is the present invention A part of the embodiment, instead of all the embodiments.Based on the embodiments of the present invention, those of ordinary skill in the art are not having Every other embodiment obtained under the premise of creative work is made, shall fall within the protection scope of the present invention.
Fig. 1 is the flow chart of rail yard track switch reinforcement means provided in an embodiment of the present invention, as shown in Figure 1, this method Include: step 1, D type construction beam stringer is set in track switch two sides, and the D type construction beam stringer is supported using borehole column; Step 2, switch tie bottom be fixedly installed D type construction beam crossbeam, and the both ends of the D type construction beam crossbeam respectively with it is described The D type construction beam stringer of track switch two sides contacts;Step 3, by bracket and connecting plate by the D type construction beam stringer and institute State the end fastening of D type construction beam crossbeam.
Wherein, bracket refers to the local structure of cantilever end and drop in beam end, also known as corbel.The effect of bracket is linking cantilever Beam and drop in beam, and transmit the load from drop in beam.Herein due to the mutual overlap joint of beam, centre there is provision of force-transmission support seat to pass Biggish vertically and horizontally counter-force is passed, therefore bracket height has weakened to the half less than deck-molding, but transmitted again biggish perpendicular Straight and horizontal reacting force, this just makes it the weak part in superstructure.
Specifically, D type construction beam stringer 1 is set in track switch two sides combined with Figure 1 and Figure 2, and D is supported using borehole column 8 Type construction beam stringer 1, for example, the borehole column 8 manually built up supports D type construction beam stringer 1, track switch needs at general one Build 4 borehole columns 8.Then 4 bottom of switch tie setting D type construction beam crossbeam 2 is crossed, that is, D type construction beam crossbeam 2 passes through The bottom of entire switch tie 4 is then not required to that entire track switch can be reinforced track switch progress subregion, and can be adapted for different shaped Number track switch.Then, which is tightened together with switch tie 4.
As described in Figure 3, the end of D type construction beam crossbeam 2 and D type construction beam stringer 1 are connected to connecting plate 10 Together, for example, being connected to the end of connecting plate 10 and D type construction beam crossbeam 2 and D type construction beam stringer 1 by bolt Together.And bracket 4 is arranged in the end of D type construction beam crossbeam 2 and the junction of D type construction beam stringer 1, for example, will Two right-angle sides of bracket 4 pass through bolt respectively and are connected with the end of D type construction beam crossbeam 2 and D type construction beam stringer 1, into And improve the reliability of entire track switch.
In embodiments of the present invention, by the way that D type construction beam stringer is arranged in track switch two sides, switch tie bottom setting D is crossed Type construction beam crossbeam, and be fixedly connected with D type construction beam stringer with D type construction beam crossbeam with connecting plate by bracket, So that each component connection relationship is solid and reliable in rail yard track switch, safety when train passes through track switch, stationarity ensure that And comfort;Meanwhile the ruggedized construction good integrity obtained by the rail yard track switch reinforcement means, it is applicable to different shaped The reinforcing of number track switch.
In addition, pre-embedded bolt 9 can be arranged at the top of borehole column 8, to be fixed on borehole column 8 using the pre-embedded bolt 9 The lower section of D type construction beam stringer 1, to play a supporting role.Can also the top of D type construction beam stringer 1 and borehole column 8 it Between rubber pad is set, to prevent D type construction beam stringer 1 from sliding with borehole column 8.
On the basis of the above embodiments, after the step 3 further include: the D type construction beam crossbeam 2 with It is laid with steel plate 15 between the switch tie 4, and the D type construction beam crossbeam 2 is fixedly connected with the steel plate 15;And institute The both ends for stating switch tie 4 are respectively provided with limit angle steel, and the switch tie 4 fixation is limited on the steel plate 15.
Wherein, angle steel is commonly called as angle bar, is that both sides are orthogonal at angular strip steel.There are equal leg angle and inequilateral angle Point of steel.
Specifically, in conjunction with Fig. 3 and Fig. 4, steel plate 15 is laid between D type construction beam crossbeam 2 and switch tie 4, that is, steel plate 15 It is disposed longitudinally on the top of D type construction beam crossbeam 2.And be fixed together D type construction beam crossbeam 2 with steel plate 15, For example, bolt hole is arranged in the corresponding position of steel plate 15 and D type construction beam crossbeam 2, and D type is constructed using connection bolt 17 Just beam crossbeam 2 and steel plate 15 are fixed.In the both ends of switch tie 4 setting limit angle steel, that is, use limit angle steel by 4 fixation steel plate of switch tie On 15, to realize the purpose limited to switch tie 4, guarantee the stability of track switch.
In embodiments of the present invention, by being laid with steel plate between D type construction beam crossbeam and switch tie, and switch tie is led to It crosses the fixed limitation of limit angle steel on the steel plate, realizes the purpose limited to switch tie, the stability of track switch is improved, so that train smooth Pass through track switch.
On the basis of the various embodiments described above, limit angle steel is respectively provided at the both ends of the switch tie 4 and is specifically included: described The both ends of switch tie 4 are respectively provided with cross spacing angle steel 161 and longitudinal spacing angle steel 162, and the cross spacing angle steel 161 and described Longitudinal spacing angle steel 162 is bolted on the steel plate 15.
Specifically, as Figure 4-Figure 6, cross spacing angle steel 161 and longitudinal spacing angle steel are respectively provided at the both ends of switch tie 4 162, that is, be both provided with cross spacing angle steel 161 and longitudinal spacing angle steel 162 in every one end of switch tie 4, and can be according to practical feelings The quantity of condition increase cross spacing angle steel 161 and longitudinal spacing angle steel 162.For example, when switch tie 4 is tilted to the left, 4 left side of switch tie The pressure being subject to is larger, several cross spacing angle steel 161 and longitudinal spacing angle steel 162 suitably can be arranged the left end of switch tie 4 more, So that switch tie 4 can be relatively stably fixed on steel plate 15, to guarantee the reliability of track switch.And in the corresponding positions of steel plate 15 Bolt hole is installed, and cross spacing angle steel 161 and longitudinal spacing angle steel 162 are each attached on steel plate 15 by bolt, into And the fixation of switch tie 14 is limited on steel plate 15, that is, the fixation of switch tie 14 is limited on D type construction beam crossbeam 2, to improve The stability of trouble.
On the basis of the various embodiments described above, cross spacing angle steel 161 and longitudinal direction are respectively provided at the both ends of the switch tie 14 After limiting angle steel 162 further include: between the cross spacing angle steel 161, the longitudinal spacing angle steel 162 and the trouble 14 Weedtree 18 is clogged in gap.
Specifically, in conjunction with Fig. 5 and Fig. 6, cross spacing angle steel 161 and longitudinal spacing angle have been respectively provided at the both ends of switch tie 14 After steel 162, also need to clog weedtree 18 in the gap between cross spacing angle steel 161, longitudinal spacing angle steel 162 and switch tie 14, that is, The gap between two ends of switch tie 14 and limit angle steel is clogged with weedtree 18, further to limit the position of switch tie 14 It is fixed, and then improve the stability of switch tie 14.
On the basis of the various embodiments described above, further includes: hanger rail beam 3 is set on the switch tie 14, and with U-bolt 5 The hanger rail beam 3, the D type construction beam crossbeam 2 and the switch tie 14 are fixedly connected;Correspondingly, the point on the switch tie Rail and stock rail are also secured on the D type construction beam crossbeam.
Wherein, U bolt, i.e. U-bolts, U-bolts English name are U-bolt, and criteria of right and wrong part, shape is U-shaped So also referred to as U-bolt, both ends have screw thread that can be mainly used for fixed tube such as water pipe or tablet such as vapour in conjunction with nut The leaf spring of vehicle, due to its fix the mode of object as people horseback, therefore referred to as U-bolts.
Specifically, hanger rail beam 3 is set on switch tie 14, for example, detaining rail with P50 rail 3-3-3-3 hanger rail beam 3, and in switch tie Hanger rail beam 3 is arranged on 14 to carry out between construction borehole column 8.Then, by switch tie 14, hanger rail beam 3 and D type construction beam crossbeam It is linked together with U-bolt;Correspondingly, the tongue 12 on switch tie 14 and stock rail 13 are also secured at D type construction beam crossbeam On 2, then D type construction beam crossbeam 2, switch tie, stock rail 13, tongue 12 and hanger rail beam 3 are linked to be an entirety, so that whole A track switch is more firm.
On the basis of the various embodiments described above, after the step 3 further include: in the D type construction beam crossbeam 2 Upper setting goat 6, and the goat 6 is fixed on the D type construction beam crossbeam 2 with angle steel 7.
Wherein, goat (switch machine/point machine) is the executing agency of switch control system;With In conversion locking point tongue or heart rail, the position and state of point tongue or heart rail in supervision interlocking area are indicated.
Specifically, goat 6 is arranged and the goat 6 is fixed on D on D type construction beam crossbeam 2, and with angle steel 7 On type construction beam crossbeam 2, that is, open up bolt hole in the corresponding position of angle steel 7 and D type construction beam crossbeam 2;Then, by angle Steel 7 is arranged at the lower edge of goat 6, and angle steel 7 is fixedly connected by blending bolt with D type construction beam crossbeam 2, so that turn-out track Machine 6 is fixed on D type construction beam crossbeam 2.
On the basis of the various embodiments described above, the rail yard track switch reinforcement means, further includes: in the switch tie 14 Insulation board 11 is set between the steel plate 15.Further include: Framed underpass bridge is carried out after the completion of reinforcing, and Framed underpass bridge is completed After remove ruggedized equipment.
Specifically, insulation board 11 is set between switch tie 14 and steel plate 15, for example, insulation board 11 is plank etc.;That is, branching off Pillow 14, insulation board 11, steel plate 15 and D type construction beam crossbeam 2 are set gradually under upper, thus make switch tie 14 and steel plate 15 it Between insulate, the influence to avoid steel plate 15 and D type construction beam crossbeam 2 to switch tie 14 improves the security performance of entire track switch.? After the completion of reinforcing to rail yard track switch, Framed underpass bridge construction is carried out, Framed underpass bridge removes track strengthening equipment afterwards in place, Restore route.In addition, above-mentioned construction procedure is only to illustrate technically feasible, the difference of sequence of construction can't be patent right Limiting factor.
Fig. 2 is the plan view of rail yard track switch ruggedized construction provided in an embodiment of the present invention, as shown in Fig. 2, the railway Yard track switch ruggedized construction includes: the D type construction beam stringer 1 that track switch two sides are arranged in, and supports the D type construction beam vertical The borehole column 8 of beam 1;It is fixed at the D type construction beam crossbeam 2 of 14 bottom of switch tie, and the D type construction beam crossbeam 2 Both ends are contacted with the D type construction beam stringer 1 of the track switch two sides respectively;It is all provided at the both ends of the D type construction beam crossbeam 2 There is connecting plate 10, the connecting plate 10 is fixed by the end of the D type construction beam crossbeam 2 and the D type construction beam stringer 1 Connection;And bracket 4 is equipped in the junction of the D type construction beam crossbeam 2 and the D type construction beam stringer 1.
Specifically, D type construction beam stringer 1 is set in track switch two sides, and supports D type construction beam vertical using borehole column 8 Beam 1, for example, the borehole column 8 manually built up supports D type construction beam stringer 1, track switch needs to build 4 boreholes at general one Column 8.Then 4 bottom of switch tie be arranged D type construction beam crossbeam 2, and the both ends of D type construction beam crossbeam 2 respectively with the road The D type construction beam stringer 1 of two sides of branching off contacts, that is, D type construction beam crossbeam 2 passes through the bottom of entire switch tie 4, then is not required to pair Track switch, which carries out subregion, to reinforce entire track switch, and can be adapted for the track switch of different model.And when switch tie 14 is vertical When the switch tie 14 of straight main track, as shown in figure 4, the underface of switch tie 14 is arranged in D type construction beam crossbeam 2;When switch tie 14 is to incline When oblique switch tie 14, as shown in figure 5, the side-lower of switch tie 14 is arranged in D type construction beam crossbeam 2.Then, which is constructed Just beam crossbeam 2 tightens together with switch tie 4.
As described in Figure 3, the end of D type construction beam crossbeam 2 and D type construction beam stringer 1 are connected to connecting plate 10 Together;And bracket 4 is arranged in the end of D type construction beam crossbeam 2 and the junction of D type construction beam stringer 1, for example, will Two right-angle sides of bracket 4 pass through bolt respectively and are connected with the end of D type construction beam crossbeam 2 and D type construction beam stringer 1, into And improve the reliability of entire track switch.
The rail yard track switch ruggedized construction on the basis of the above embodiments, further includes: be fixed at the D Steel plate 15 between type construction beam crossbeam 2 and the switch tie 14;And the cross spacing angle of 14 end of switch tie is set Steel 161 and longitudinal spacing angle steel 162, and a right-angle side of the cross spacing angle steel 161 and the longitudinal spacing angle steel 162 A right-angle side be fixed on the steel plate 15.
Specifically, in conjunction with Fig. 6, steel plate 15 is laid between D type construction beam crossbeam 2 and switch tie 4, that is, steel plate 15 is longitudinal The top of D type construction beam crossbeam 2 is set.And D type construction beam crossbeam 2 is fixed together with steel plate 15.And Cross spacing angle steel 161 and longitudinal spacing angle steel 162 are respectively provided in the end of switch tie 4, that is, are all arranged at the both ends of switch tie 4 There are cross spacing angle steel 161 and longitudinal spacing angle steel 162, and cross spacing angle steel 161 and longitudinal direction can be increased according to the actual situation Limit the quantity of angle steel 162.For example, when switch tie 4 is to by tilting, when train passes through track switch, the pressure that is subject on the right of switch tie 4 compared with Greatly, several cross spacing angle steel 161 and longitudinal spacing angle steel 162 suitably can be set the right end of switch tie 4, so that 4 energy of switch tie more It is enough to be relatively stably fixed on steel plate 15, to guarantee the reliability of track switch.And by cross spacing angle steel 161 and longitudinal spacing angle Steel 162 is each attached on steel plate 15, and then the fixation of switch tie 14 is limited on steel plate 15, that is, the fixation of switch tie 14 is limited in D type On construction beam crossbeam 2, to improve the stability of track switch.
Finally, it should be noted that the above embodiments are merely illustrative of the technical solutions of the present invention, rather than its limitations;Although Present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that: it still may be used To modify the technical solutions described in the foregoing embodiments or equivalent replacement of some of the technical features; And these are modified or replaceed, technical solution of various embodiments of the present invention that it does not separate the essence of the corresponding technical solution spirit and Range.

Claims (8)

1. a kind of rail yard track switch reinforcement means characterized by comprising
Step 1, D type construction beam stringer is set in track switch two sides, and the D type construction beam stringer is supported using borehole column;
Step 2, switch tie bottom be fixedly installed D type construction beam crossbeam, and the both ends of the D type construction beam crossbeam respectively with The D type construction beam stringer of the track switch two sides contacts;
Step 3, by bracket and connecting plate that the end of the D type construction beam stringer and the D type construction beam crossbeam is tight Gu;
After the step 3 further include: be laid with steel plate between the D type construction beam crossbeam and the switch tie, and by institute D type construction beam crossbeam is stated to connect with the Interal fixation;And it is respectively provided with limit angle steel at the both ends of the switch tie, it will The switch tie fixation is limited on the steel plate;
Further include: hanger rail beam is set on the switch tie, and with U-bolt by the hanger rail beam, the D type construction beam crossbeam And the switch tie is fixedly connected.
2. rail yard track switch reinforcement means according to claim 1, which is characterized in that be all provided at the both ends of the switch tie Limit angle steel is set to specifically include:
Cross spacing angle steel and longitudinal spacing angle steel are respectively provided at the both ends of the switch tie, and the cross spacing angle steel and described Longitudinal spacing angle steel is bolted on the steel plate.
3. rail yard track switch reinforcement means according to claim 2, which is characterized in that be all provided at the both ends of the switch tie After setting cross spacing angle steel and longitudinal spacing angle steel further include: in the gap between the cross spacing angle steel and the switch tie Weedtree is clogged, and clogs weedtree in the gap between the longitudinal spacing angle steel and the switch tie.
4. rail yard track switch reinforcement means according to claim 1, which is characterized in that also wrapped after the step 3 It includes: goat being set on the D type construction beam crossbeam, and the goat is fixed at the D type with angle steel and is applied Work is just on beam crossbeam.
5. rail yard track switch reinforcement means according to claim 2, which is characterized in that further include: the switch tie with Insulation board is set between the steel plate.
6. rail yard track switch reinforcement means according to claim 1-5, which is characterized in that further include: it reinforces Framed underpass bridge is carried out after the completion, and ruggedized equipment is removed after the completion of Framed underpass bridge.
7. a kind of rail yard track switch obtained using rail yard track switch reinforcement means described in any one of claims 1-6 is added Fixing structure characterized by comprising the D type construction beam stringer of track switch two sides is set, supports the D type construction beam vertical The borehole column of beam;
Be fixed at the D type construction beam crossbeam of switch tie bottom, and the both ends of the D type construction beam crossbeam respectively with it is described The D type construction beam stringer of track switch two sides contacts;
Connecting plate is equipped at the both ends of the D type construction beam crossbeam, and the connecting plate is by the D type construction beam crossbeam End is fixedly connected with the D type construction beam stringer;
And bracket is set in the junction of the D type construction beam crossbeam and the D type construction beam stringer.
8. rail yard track switch ruggedized construction according to claim 7, which is characterized in that further include:
The steel plate being fixed between the D type construction beam crossbeam and the switch tie;And it is arranged in the switch tie end Cross spacing angle steel and longitudinal spacing angle steel, and a right-angle side of the cross spacing angle steel and the longitudinal spacing angle steel One right-angle side is fixed on the steel plate.
CN201711227336.1A 2017-11-29 2017-11-29 A kind of rail yard track switch reinforcement means and structure Active CN107974878B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711227336.1A CN107974878B (en) 2017-11-29 2017-11-29 A kind of rail yard track switch reinforcement means and structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711227336.1A CN107974878B (en) 2017-11-29 2017-11-29 A kind of rail yard track switch reinforcement means and structure

Publications (2)

Publication Number Publication Date
CN107974878A CN107974878A (en) 2018-05-01
CN107974878B true CN107974878B (en) 2019-07-05

Family

ID=62008583

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711227336.1A Active CN107974878B (en) 2017-11-29 2017-11-29 A kind of rail yard track switch reinforcement means and structure

Country Status (1)

Country Link
CN (1) CN107974878B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110593030A (en) * 2019-09-12 2019-12-20 中铁二局第二工程有限公司 Line turnout area reinforcing system for D-shaped beam frame
CN114318962A (en) * 2021-12-23 2022-04-12 山东鲁道建设工程有限公司 Railway turnout area line reinforcing construction method
CN114318960A (en) * 2021-12-23 2022-04-12 山东鲁道建设工程有限公司 Construction method of spliced railway construction boundary beam

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN204417928U (en) * 2015-01-19 2015-06-24 平煤神马建工集团有限公司土建处 The most advanced and sophisticated frame rail reinforcement tools of rail yard point tongue
CN106049209A (en) * 2016-07-28 2016-10-26 中铁第四勘察设计院集团有限公司 Temporary steel rail supporting device for disassembling and replacing railway ballastless track supporting layers
CN206538637U (en) * 2017-02-13 2017-10-03 中铁十八局集团第四工程有限公司 A kind of track strengthening device for existing railway

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN204417928U (en) * 2015-01-19 2015-06-24 平煤神马建工集团有限公司土建处 The most advanced and sophisticated frame rail reinforcement tools of rail yard point tongue
CN106049209A (en) * 2016-07-28 2016-10-26 中铁第四勘察设计院集团有限公司 Temporary steel rail supporting device for disassembling and replacing railway ballastless track supporting layers
CN206538637U (en) * 2017-02-13 2017-10-03 中铁十八局集团第四工程有限公司 A kind of track strengthening device for existing railway

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
既有线道岔区顶进框架桥线路加固设计;吴炜;《甘肃科技》;20090630(第12期);第38-39页,第15页
横向加宽D16型施工便梁在岔区线路加固中的应用;刘吉元等;《钢结构》;20150430(第4期);第40-43页,第47页
站内道岔区顶进框架桥架空加固与防护技术;张克雷;《铁道建筑技术》;20150731(第7期);第75-77页

Also Published As

Publication number Publication date
CN107974878A (en) 2018-05-01

Similar Documents

Publication Publication Date Title
CN107974878B (en) A kind of rail yard track switch reinforcement means and structure
CN102979041B (en) Soft overhead reinforcing jacking method for construction of span box bridge of jacking block of underpass turnout group of railway
CN103437254B (en) Framed underpass bridge railway trouble district track strengthening device
CN109183530B (en) Line temporary overhead device and method for ballastless track disease remediation
CN108166336A (en) A kind of I-steel in length and breadth and D beams combined system reinforce the construction method of switch area
CN108149577B (en) A kind of steel bracket system and its installation method
JP2019502844A (en) Bevel tip rail railway
KR101399839B1 (en) Transition track structure of railway bridge deck end and Construction method
CN109098102A (en) Just beam ruggedized construction for switch section
CN106592449A (en) D-shaped beam reinforced existing double-railway line structure and construction method thereof
CN108342980B (en) Railway suspension bridge upper bearing type steel truss bridge deck structure
US8220095B2 (en) Highway overpass bridge modification system and method
CN209114262U (en) A kind of interim overhead device of route for non-fragment orbit Disease Treatment
CN102535358A (en) Construction technology for broadening and reforming rigidity matching system of hollow slab bridge
CN217298467U (en) Longitudinal connecting device for rail, rail plate beam and rail plate beam longitudinal connecting structure
KR101721043B1 (en) Suspended-type bridge joint apparatus and a method for installing the same
CN202450441U (en) Stiffness matching system for broadening and transforming hollow slab bridges
CN205857004U (en) A kind of construction beam
JP3954905B2 (en) Three-dimensional crossing method of plane intersection and viaduct
CN208917713U (en) Just beam ruggedized construction for switch section
CN203440720U (en) Line reinforcing device of railway turnout area in frame bridge jacking
CN209323280U (en) A kind of steel construction track suitable for magnetic floating traffic
CN109505230B (en) Integral beam falling prevention structure of pier on arch
CN112796232A (en) Reinforced structure for existing railway underpass frame bridge construction
CN110205875A (en) Existing Railway Line double crossover integrally inserts paving construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20210128

Address after: 530007 No.3, Gaoxin 5th Road, Gaoxin District, Nanning City, Guangxi Zhuang Autonomous Region

Patentee after: CHINA RAILWAY FOURTH GROUP NANNING SURVEY AND DESIGN INSTITUTE Co.,Ltd.

Patentee after: CHINA RAILWAY SIYUAN SURVEY AND DESIGN GROUP Co.,Ltd.

Address before: 430063 No. 745 Heping Avenue, Wuchang District, Hubei, Wuhan

Patentee before: CHINA RAILWAY SIYUAN SURVEY AND DESIGN GROUP Co.,Ltd.

TR01 Transfer of patent right