CN107887931A - The more same period point auto-parallel systems of generating set - Google Patents

The more same period point auto-parallel systems of generating set Download PDF

Info

Publication number
CN107887931A
CN107887931A CN201711419496.6A CN201711419496A CN107887931A CN 107887931 A CN107887931 A CN 107887931A CN 201711419496 A CN201711419496 A CN 201711419496A CN 107887931 A CN107887931 A CN 107887931A
Authority
CN
China
Prior art keywords
bus
control unit
grid
generator
same period
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201711419496.6A
Other languages
Chinese (zh)
Inventor
马猛忠
杨建栋
周邦栋
李锋
张伯兴
张旭
黄凯
孙希龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SDIC QINZHOU ELECTRIC POWER Co Ltd
Original Assignee
SDIC QINZHOU ELECTRIC POWER Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SDIC QINZHOU ELECTRIC POWER Co Ltd filed Critical SDIC QINZHOU ELECTRIC POWER Co Ltd
Priority to CN201721837373.XU priority Critical patent/CN207753464U/en
Priority to CN201711419496.6A priority patent/CN107887931A/en
Publication of CN107887931A publication Critical patent/CN107887931A/en
Pending legal-status Critical Current

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • H02J3/38Arrangements for parallely feeding a single network by two or more generators, converters or transformers
    • H02J3/40Synchronising a generator for connection to a network or to another generator
    • H02J3/42Synchronising a generator for connection to a network or to another generator with automatic parallel connection when synchronisation is achieved

Landscapes

  • Engineering & Computer Science (AREA)
  • Power Engineering (AREA)
  • Supply And Distribution Of Alternating Current (AREA)

Abstract

The invention discloses a kind of more same period point auto-parallel systems of generating set, by being mounted on system side voltage measurement unit on I bus, II bus and each user's line for being connected on I, II bus, generating set is when grid-connected, by on generator treat and side voltage measurement unit is sensed with wherein any one system side voltage measurement unit, when meeting simultaneous interconnecting condition, cutting-in control unit is controlled in synchronous device, cutting-in control unit is opened each grid-connected disconnecting link/switch successively.Compared with prior art, as long as any one same period point in network system is normal, the paired running of generator can be achieved, substantially increase the grid connection efficiency of generating set, ensure that the stable operation for distribution in system side;The row swithes that the present invention is used to perform grid-connected action simultaneously are 2 so that one of row swithes failure in the system, the grid-connected of generator is nor affected on, and it is grid-connected more convenient and flexible in the selection of branch road.

Description

The more same period point auto-parallel systems of generating set
Technical field
The present invention relates to a kind of generating set auto-parallel device, and in particular to the more same period point auto-parallel systems of generating set System.
Background technology
In power plant, simultaneous interconnecting is a great operation before power plants generating electricity.Excitation, steam turbine, disconnecting link is needed to open Cooperation between each systems such as pass, DCS controls, finally realizes that generator stable is connected to the grid, stable electric power is sent into power network. Once misoperation, the abnormal accidents such as system fluctuation, vibration may be caused, can be caused when serious generator asynchronous it is grid-connected, hair Motor damage, the serious electrical accident of power network spring net.Generator synchronous grid-connected principle is:By gathering generator (or main transformer High-pressure side) voltage of voltage transformer (i.e. PT) in outlet and the voltage ratio of system side compared with, when reach impose a condition when (including During the conditions such as the voltage magnitudes of both sides, phase sequence, phase, frequency) reclosing command is sent, will by closing generator outlet breaker Generator and system grid connection, realize electrical energy transportation.Generator synchronous grid-connected system is the key of generator and power network paired running Equipment, the reliability of its function are most important.It is existing to have automatic synchronizing paralleling, same manually for generating set simultaneous interconnecting pattern Phase is grid-connected and automatic presynchronization is grid-connected, but no matter which kind of grid-connect mode used, generating set and network process be configured with phase The purpose that the synchronous device answered is automatically controlled with reaching.
As shown in figure 1, the partial electric connection figure of the conventional electric generators simultaneous interconnecting originally used for our company.From figure It is not difficult to find out, exporting disconnecting link 20011 (illustrating by row of I buses) by transformer unit in system side is led to 220KVI buses PT Automatic sub-synchronous device, i.e., as with treating that simultaneously side 1PT or 2PT carry out same period condition confirmation on generator.When grid-connected, when treating And side PT voltage magnitude, phase sequence, phase, frequency with during all same, synchronous device can just send closure and generate electricity on bus PT Machine exports the instruction of knife switch, could so complete the operation of generator connecting in parallel with system.Therefore, the PT in system side is also referred to as grid-connected Same period point, there was only the same period point during traditional generator auto-parallel.The generating set auto-parallel of only one same period point Although technology is connecting up and controlled relatively simple operation in operation, when PT or the generating set outlet being located in bus bar side When switch tool breaks down, generator will terminate arranged side by side with system, need to wait for can carrying out after troubleshooting terminates grid-connected.This Sample not only delays the set grid-connection time, make in system side for distribution fluctuation of service, reduce Business Economic Benefit;This Outside, the outlet of generator only has a row swithes, and connected mode is single, grid-connected to use underaction.
The content of the invention
To overcome drawbacks described above, the technical problems to be solved by the invention be to provide it is a kind of with multiple separate and The generating set auto-parallel system of same period point is netted, as long as the grid-connected system has one of them same period point normal work to can be achieved Generating set it is grid-connected.
To reach above-mentioned purpose, the present invention is achieved through the following technical solutions:
The more same period point auto-parallel systems of generating set, including for generator synchronous grid-connected network system and for controlling The synchronous device of network system auto-parallel, I bus that the network system includes being in parallel, II bus and it is connected on I bus, II N subscriber lines on bus, the network system also include the cutting-in control unit corresponding with the quantity of user's line, one with Branch where the output end of family line one cutting-in control unit of corresponding access, the input and generator outlet of cutting-in control unit Road connects, and the cutting-in control unit is arranged on and controls generator between I bus and II bus and under the control of synchronous device Perform grid-connected action;Be mounted on system side voltage measurement unit on I bus, II bus and each user's line, wherein n for >= 1 integer.
In such scheme, the cutting-in control unit may include a plug-in strip control unit, master control disconnecting link, secondary plug-in strip control Unit, a row swithes and secondary row swithes processed, wherein
Branch road connection where one end of plug-in strip control unit and generator outlet, its other end are divided into two Branch road:A wherein branch road is connected to after a row swithes on I bus, the input of another branch road and master switch connects Connect;The output end of the master switch is divided into two branch roads:Wherein a branch road is connected to II after secondary plug-in strip control unit Bus, another branch road are connected after secondary row swithes with corresponding user's line;On the branch road where generator outlet Installation needs and side voltage measurement unit.
In such scheme, it is further preferred that the value of the n is 2, that is, there are 2 user's lines to be connected on I bus, on II bus.
Beneficial effects of the present invention are:
1) present invention on I bus, II bus and each user's line for being connected on I, II bus by being mounted on system Side voltage measurement unit, generating set when grid-connected, by generator treat and side voltage measurement unit with it is wherein any one Individual system side voltage measurement unit is sensed, and when meeting simultaneous interconnecting condition, cutting-in control unit is entered in synchronous device Row control, so that cutting-in control unit opens each grid-connected disconnecting link/switch successively.Show with what an only same period point was sensed There is simultaneous interconnecting device to compare, as long as any one same period point (system side voltage measurement unit) in network system is normally, The paired running of generator can be achieved;And traditional interconnection technology can only be a same period point, once the same period point hair in system side Raw failure will be unable to carry out generator and net operation.The grid connection efficiency of generating set will be greatly improved using grid-connected system, And can guarantee that in system side for distribution stable operation, improve Business Economic Benefit;
2) row swithes for being used to perform grid-connected action in the cutting-in control unit designed in the present invention are 2 so that this One of row swithes failure in system, the grid-connected of generator is nor affected on, and he it is grid-connected more square in the selection of branch road Just and flexibly.
Brief description of the drawings
Fig. 1 is the partial electric connection figure of traditional 1 generating set auto-parallel.
When Fig. 2 is 3 same period points, the electrical connection diagram of 1 generating set auto-parallel.
When Fig. 3 is 3 same period points, the electrical connection diagram of 2 generating set auto-parallels.
1st, system side voltage measurement unit, 2, treat and side voltage measurement unit, 3, plug-in strip control units, 4, secondary lock Knife control unit, 5, row swithes, 6, secondary row swithes, 7, master control disconnecting link, 8, cutting-in control unit.
Embodiment
Embodiment 1
The more same period point auto-parallel systems of generating set, including for generator synchronous grid-connected network system and for controlling The synchronous device of network system auto-parallel.Composition and the same period used in the prior art in the synchronous device main body are simultaneously Net device is the same.Except that:Each electrically detection component, control chopper switch on the improved cutting-in control unit 8 of institute The increase and connection of adaptability are done, and does adaptable logic control instruction in controller on synchronous device and improves.The electricity I bus that net system includes being in parallel, II bus and it is connected on I bus, the n subscriber lines on II bus.
The network system also includes the cutting-in control unit 8 corresponding with the quantity of user's line.As shown in Fig. 2 it is one Electrical connection diagram corresponding to subscriber lines during one group of generator connecting in parallel with system, i.e. n=1.The corresponding access one of one subscriber lines is grid-connected Branch road connection where the output end of control unit 8, the input and generator outlet of cutting-in control unit 8.Described and network control Unit 8 processed is arranged between I bus and II bus and controls generator to perform grid-connected action under the control of synchronous device. System side voltage measurement unit 1 is mounted on I bus, II bus and each user's line.The system side voltage measurement unit 1 The same period point of PT points as in network system, specially generator connecting in parallel with system.It is not difficult to find out from Fig. 2, even if on two buses User's line is only connected to, also there are 3 same period points in this simultaneous interconnecting system, is in I bus, II bus and user's line successively On.
In the present embodiment, the cutting-in control unit 8 includes a plug-in strip control unit 3, master control disconnecting link 7, secondary plug-in strip 4, row swithes 5 of control unit and secondary row swithes 6.One end of plug-in strip control unit 3 goes out with generator Branch road connection where mouthful, its other end are divided into two branch roads:It is female that a wherein branch road is connected to I after a row swithes 5 On line, the input of another branch road and master switch connects.The output end of the master switch is divided into two branch roads:Wherein one Bar branch road be connected to after secondary plug-in strip control unit 4 II bus, another branch road after secondary row swithes 6 with it is corresponding User's line connects.Installation needs simultaneously side voltage measurement unit 2 on the branch road where generator outlet, treats simultaneously side voltage measurement list Member 2 is on installation generator outlet and the PT corresponding with the PT points in system side.
Said system side voltage measurement unit 1 and treat and side voltage measurement unit 2 be specifically existing structure voltage it is mutual Sensor and supporting electric components.
4, row swithes 5 of a plug-in strip control unit 3, master control disconnecting link 7, secondary plug-in strip control unit of above-mentioned use Model, quantity and the composition of the electrical equipment used with secondary row swithes 6 enter according to the magnitude of voltage on I bus, II bus Row selection.
The present invention is when in use:1) when on the system side voltage measurement unit 1 on I bus and II bus and two buses Each way switch disconnecting link it is normal when, treat and side voltage measurement unit 2 preferentially with the system side voltage measurement unit 1 on I bus Carry out correspondingly, when the parameter obtained after corresponding mutual inductance meets the condition of simultaneous interconnecting, lock of synchronous device remote control 3, row swithes 5 of knife control unit, master switch and secondary plug-in strip control unit 4 are opened, and generator performs and net operation;
2) when the switch tool on the system side voltage measurement unit 1 or bus on I bus and II bus breaks down, Treat and side voltage measurement unit 2 carries out corresponding with the system side voltage measurement unit 1 on user's line, obtained after corresponding mutual inductance When parameter meets the condition of simultaneous interconnecting, 3, row swithes 5 of plug-in strip control unit of synchronous device remote control, master Control switch, secondary plug-in strip control unit 4 and secondary row swithes 6 are opened, and generator performs and net operation.
Embodiment 2
As shown in figure 3, the more same period point auto-parallel systems of generating set and embodiment 1 except that, the n's It is worth for 2.That is two user's lines are connected on I bus, on II bus, and have two generators to carry out simultaneous interconnecting in simultaneous interconnecting There are 3 same period points in system, be on I bus, II bus and user's line successively.Certainly, distribution demand is supplied according to power network, The user's line accessed on two buses can be multiple, therefore the same period point quantity where it in system side of simultaneous interconnecting also corresponds to Increase, can further improve the reliability of simultaneous interconnecting.
Explanation embodiments of the present invention are these are only, are not intended to limit the invention, for those skilled in the art For, within the spirit and principles of the invention, any modification, equivalent substitution and improvements made etc., it should be included in this hair Within bright protection domain.

Claims (3)

1. the more same period point auto-parallel systems of generating set, including for generator synchronous grid-connected network system and for controlling electricity The synchronous device of net system auto-parallel, I bus that the network system includes being in parallel, II bus and is connected on I bus, II female N subscriber lines on line, it is characterised in that:The network system also includes the cutting-in control list corresponding with the quantity of user's line First (8), the output end of a subscriber lines one cutting-in control unit (8) of corresponding access, the input of cutting-in control unit (8) with Branch road connection where generator outlet, the cutting-in control unit (8) are arranged between I bus and II bus and in the same period Control generator performs grid-connected action under the control of device;System side is mounted on I bus, II bus and each user's line Voltage measurement unit (1), wherein n are >=1 integer.
2. the more same period point auto-parallel systems of generating set according to claim 1, it is characterised in that:The cutting-in control Unit (8) includes a plug-in strip control unit (3), master control disconnecting link (7), secondary plug-in strip control unit (4), a row swithes (5) and secondary row swithes (6), wherein the branch road where one end of the once plug-in strip control unit (3) and generator outlet Connection, its other end are divided into two branch roads:A wherein branch road is connected on I bus after a row swithes (5), another The input of branch road and master switch connects;The output end of the master switch is divided into two branch roads:Wherein a branch road is through two Be connected to after secondary plug-in strip control unit (4) on II bus, another branch road after secondary row swithes (6) with corresponding user Line connects;Installation needs simultaneously side voltage measurement unit (2) on the branch road where generator outlet.
3. the more same period point auto-parallel systems of generating set according to claim 1 or 3, it is characterised in that:The value of the n For 2.
CN201711419496.6A 2017-12-25 2017-12-25 The more same period point auto-parallel systems of generating set Pending CN107887931A (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
CN201721837373.XU CN207753464U (en) 2017-12-25 2017-12-25 The more same period point auto-parallel systems of generating set
CN201711419496.6A CN107887931A (en) 2017-12-25 2017-12-25 The more same period point auto-parallel systems of generating set

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN201721837373.XU CN207753464U (en) 2017-12-25 2017-12-25 The more same period point auto-parallel systems of generating set
CN201711419496.6A CN107887931A (en) 2017-12-25 2017-12-25 The more same period point auto-parallel systems of generating set

Publications (1)

Publication Number Publication Date
CN107887931A true CN107887931A (en) 2018-04-06

Family

ID=69419866

Family Applications (2)

Application Number Title Priority Date Filing Date
CN201721837373.XU Active CN207753464U (en) 2017-12-25 2017-12-25 The more same period point auto-parallel systems of generating set
CN201711419496.6A Pending CN107887931A (en) 2017-12-25 2017-12-25 The more same period point auto-parallel systems of generating set

Family Applications Before (1)

Application Number Title Priority Date Filing Date
CN201721837373.XU Active CN207753464U (en) 2017-12-25 2017-12-25 The more same period point auto-parallel systems of generating set

Country Status (1)

Country Link
CN (2) CN207753464U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110556875A (en) * 2018-05-31 2019-12-10 深圳中广核工程设计有限公司 Unit synchronization system for large power plant
CN111934353A (en) * 2020-07-03 2020-11-13 华电电力科学研究院有限公司 Method for obtaining false synchronization grid-connected signals of unit and optimizing synchronization grid-connected signals based on different wiring modes

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN207753464U (en) * 2017-12-25 2018-08-21 国投钦州发电有限公司 The more same period point auto-parallel systems of generating set
CN110011353B (en) * 2019-03-19 2022-12-27 上海唐银投资发展有限公司 Parallel operation control system and method for diesel generator power supply and distribution system

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20010064511A (en) * 1999-12-29 2001-07-09 김형국 Test device for Generator automatic synchronizer
CN106099973A (en) * 2016-06-29 2016-11-09 华能重庆两江燃机发电有限责任公司 A kind of Rhizoma Sparganii M701F4 type 3 simultaneous interconnecting implementation methods of unit gas turbine transformer unit
CN106684927A (en) * 2017-03-30 2017-05-17 山东中实易通集团有限公司 Grid-connected system for large generator sets in isolated grid system and grid-connected method
CN207753464U (en) * 2017-12-25 2018-08-21 国投钦州发电有限公司 The more same period point auto-parallel systems of generating set

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20010064511A (en) * 1999-12-29 2001-07-09 김형국 Test device for Generator automatic synchronizer
CN106099973A (en) * 2016-06-29 2016-11-09 华能重庆两江燃机发电有限责任公司 A kind of Rhizoma Sparganii M701F4 type 3 simultaneous interconnecting implementation methods of unit gas turbine transformer unit
CN106684927A (en) * 2017-03-30 2017-05-17 山东中实易通集团有限公司 Grid-connected system for large generator sets in isolated grid system and grid-connected method
CN207753464U (en) * 2017-12-25 2018-08-21 国投钦州发电有限公司 The more same period point auto-parallel systems of generating set

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
刘佩芬 等: "3/2接线条件下大型电厂同步***的设计与运行", 陕西电力, vol. 36, no. 10, pages 40 - 42 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110556875A (en) * 2018-05-31 2019-12-10 深圳中广核工程设计有限公司 Unit synchronization system for large power plant
CN111934353A (en) * 2020-07-03 2020-11-13 华电电力科学研究院有限公司 Method for obtaining false synchronization grid-connected signals of unit and optimizing synchronization grid-connected signals based on different wiring modes
CN111934353B (en) * 2020-07-03 2022-07-05 华电电力科学研究院有限公司 Method for obtaining false synchronization grid-connected signals of unit and optimizing synchronization grid-connected signals

Also Published As

Publication number Publication date
CN207753464U (en) 2018-08-21

Similar Documents

Publication Publication Date Title
CN107887931A (en) The more same period point auto-parallel systems of generating set
CN104882906B (en) A kind of distributed micro-grid black starting-up control system and method based on photovoltaic and energy storage
CN104362579B (en) The method for improving cluster wind power plant interconnection reclosing success rate
CN108886256A (en) For by wind power plant by the method for feed electric power to power supply network and with the wind power plant of black starting-up
CN105281357A (en) Diesel generator set and island microgrid connecting structure
CN106356905A (en) Alternating-current and direct-current double-bus controllable power transmission system
CN103532168A (en) Distributed power generating grid-connected control circuit
CN204992611U (en) Photovoltaic contravariant single phase alternating current and box with a net
CN206992714U (en) The wiring construction and wiring system of small steam turbine generator access high-voltage Auxiliary electric system
CN106786594B (en) A kind of alternating current-direct current mixing distribution system containing important load
CN204577857U (en) A kind of 110kV transformer station adopting novel wire connecting way
Kim et al. A study on the effect of the high-penetration photovoltaic system on an increase in overvoltage of distribution feeders
CN110224432A (en) A kind of box-type substation and its microgrid system control method
CN203536975U (en) Distributed power generating grid-connected control circuit
CN203481822U (en) Closed loop power supply model of medium voltage 10 kilovolt power distribution network
CN108964112A (en) The wiring construction and its operation method of small steam turbine generator access high-voltage Auxiliary electric system
CN104578004B (en) Low-voltage power supply failure with automatic load balancing function quickly isolates device
CN208209526U (en) Marine wind electric field and island microgrid joint-monitoring system
CN102331559B (en) In-situ test system for electric motors
JP4046674B2 (en) Distribution system protection system
CN112952895A (en) Alternating current micro-grid based on forward and reverse direction impedance relay protection
CN105024346B (en) A kind of modeling method of micro-capacitance sensor protection system
CN205753438U (en) A kind of distributed poverty alleviation in west area photovoltaic electric station grid connection facility
CN214895549U (en) Control detection device for wind power variable pitch high-low voltage ride through
CN105187004B (en) A kind of photovoltaic generation counter current protection

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination