CN107830848A - New the construction line-putting device and construction method in the digging process of road and bridge place - Google Patents

New the construction line-putting device and construction method in the digging process of road and bridge place Download PDF

Info

Publication number
CN107830848A
CN107830848A CN201711046933.4A CN201711046933A CN107830848A CN 107830848 A CN107830848 A CN 107830848A CN 201711046933 A CN201711046933 A CN 201711046933A CN 107830848 A CN107830848 A CN 107830848A
Authority
CN
China
Prior art keywords
expansion link
place
road
new
digging process
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201711046933.4A
Other languages
Chinese (zh)
Other versions
CN107830848B (en
Inventor
刘義
贾吉俊
李志强
郭继舟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China First Metallurgical Group Co Ltd
Original Assignee
China First Metallurgical Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China First Metallurgical Group Co Ltd filed Critical China First Metallurgical Group Co Ltd
Priority to CN201711046933.4A priority Critical patent/CN107830848B/en
Publication of CN107830848A publication Critical patent/CN107830848A/en
Application granted granted Critical
Publication of CN107830848B publication Critical patent/CN107830848B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01CMEASURING DISTANCES, LEVELS OR BEARINGS; SURVEYING; NAVIGATION; GYROSCOPIC INSTRUMENTS; PHOTOGRAMMETRY OR VIDEOGRAMMETRY
    • G01C15/00Surveying instruments or accessories not provided for in groups G01C1/00 - G01C13/00
    • G01C15/002Active optical surveying means
    • G01C15/004Reference lines, planes or sectors

Landscapes

  • Physics & Mathematics (AREA)
  • Engineering & Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • Radar, Positioning & Navigation (AREA)
  • Remote Sensing (AREA)
  • Road Paving Structures (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The present invention relates to road and bridge place to excavate field, and in particular to new the construction line-putting device and construction method in a kind of digging process of road and bridge place.New the construction line-putting device in a kind of digging process of road and bridge place, it is characterised in that:It includes two sets of supports, and the support includes A-frame, expansion link and spirit level, and the expansion link lower end is fixedly mounted on A-frame, and the spirit level is fixedly mounted on the middle part of expansion link;The expansion link upper end of one of support is provided with one or more laser lamp, and the expansion link upper end of another support is provided with white plastic disk.The present invention can safely and fast complete the construction line-putting work, and accurate indicating arrangement thing edge positions under the topographic features complicated and changeable such as mountain and hill, accurately instruct mechanical personnel to construct in real time.

Description

New the construction line-putting device and construction method in the digging process of road and bridge place
Technical field
The present invention relates to road and bridge place to excavate field, and in particular to new in a kind of digging process of road and bridge place The construction line-putting device and construction method.
Background technology
Accurate control to works edge positions elevation during the excavation construction of road and bridge place is individual very spine The problem of hand.Traditional construction unwrapping wire is using indicating arrangement thing edge positions the methods of the line in kind that for example limes, drawing plastics red line And elevation.But in the changeable area with a varied topography such as mountain and hill, artificial unwrapping wire in kind, which does not only exist potential safety hazard, to be also inconvenient to survey Amount personnel operate unwrapping wire on the spot.Because traditional construction line-putting method can not monitor excavation degree in real time, place excavation is easily caused Excessively, mechanical personnel's machine-team is wasted;Or place excavation degree is inadequate, repeated measurement is put after missing marker in digging process Sample, delay excavation progress, increase survey crew's work load.So how to monitor place in real time excavates degree, one-shot measurement is put Sample can instruct and control place to excavate overall process construction, and accurate place of effectively excavating avoids mechanical personnel from wasting, in road bridge It is particularly important in beam construction previous work.
The content of the invention
For above-mentioned technical problem, applied it is an object of the invention to provide new in a kind of digging process of road and bridge place Work actinobacillus device and construction method, the present invention can safely and fast complete to apply under the topographic features complicated and changeable such as mountain and hill Work setting-out work, and accurate indicating arrangement thing edge positions, accurately instruct mechanical personnel to construct in real time.
To achieve the above object, the technical solution used in the present invention is:
New the construction line-putting device in a kind of digging process of road and bridge place, it is characterised in that:It includes two sets of supports, described Support includes A-frame, expansion link and spirit level, and the expansion link lower end is fixedly mounted on A-frame, the spirit level It is fixedly mounted on the middle part of expansion link;The expansion link upper end of one of support is provided with one or more laser lamp, another The expansion link upper end of individual support is provided with white plastic disk.
The laser lamp is arranged on expansion link by screwing type buckle, and laser lamp can be around flexible by screwing type buckle Bar rotates in a circumferential direction.
The white plastic disk is arranged on expansion link by screwing type buckle, and white plastic disk passes through screwing type card Button can rotate in a circumferential direction around expansion link.
The laser lamp of the expansion link upper end installation is two.
The A-frame is height-adjustable tripod.
The construction method of new the construction line-putting device in the digging process of road and bridge place, it is characterised in that it includes following Step:
A, surveying and locating determines each angular coordinate in place and positions sign, determines that laser lamp and white plastic disk are located at each angle point Position;
B, A-frame is laid in each corner location, after making A-frame center alignment angle point, is installed on A-frame Expansion link, then spirit level is installed on expansion link, and expansion link is adjusted according to spirit level;Finally in the upper end of each expansion link The corresponding laser lamp of installation or white plastic disk;
C, according to works sideline and elevation adjustable telescopic rod, laser lamp and white plastic disc centre elevation is made to reach default height Journey;
D, laser lamp is opened, laser beam direction and works sideline direction one are made according to works sideline direction rotary laser lamp Cause, fixed laser lamp;
E, white plastic disk direction is adjusted, is allowed to face laser beam direction and fixation;
F, laser lamp is opened in the digging process of place, is excavated according to the mechanical artificial progress place of laser beam instruction until white There is the incident point of laser beam in plastic disc center, represents place on this sideline direction and excavates in place;
G, F is repeated the above steps until place excavation completion, reservation corner location, are removed new in the digging process of receipts road and bridge place Type the construction line-putting device.
If white plastic disk receives the laser beam from multiple directions in the step E, white plastic disk is adjusted Direction, all laser beams is collected in central point on white plastic disk can fixed white plastic disc.
The beneficial effects of the invention are as follows:The present invention, which breaches Traditional Man material object unwrapping wire, needs repeated measurement and can not be on the scene The shortcomings that real-time instruction machinery personnel construct in ground digging process, can pacify under the topographic features complicated and changeable such as mountain and hill It is complete to be rapidly completed the construction line-putting work, and accurate indicating arrangement thing edge positions, accurately instruct mechanical personnel to construct in real time.Effectively Solves the problems, such as changeable regional the construction line-putting difficulty with a varied topography, energy real-time instruction construction is excessively opened so as to avoid place Dig, saved mechanical artificial resource.Other apparatus of the present invention are simple in construction(Easy to carry, i.e. frame is used, that is, tears open to walk, be environmentally friendly Efficiently), easy to operate, cost is cheap, safety and environmental protection, has very strong practicality and extensive generalization.(1)The present apparatus is used instead Laser beam sign sideline, position, elevation, it can not only avoid excavating caused by material object sign is disturbed by place excavation construction Error, and can avoid, because of repeated measurement setting-out in digging process caused by marker is lost, substantially increasing place excavation Accuracy, saved survey crew's time.(2)The distance for setting Site Design angle point can be by tripod outside foundation ditch Erection is enclosed, laser projects sideline in the air, coordinates Sopwith staff sign elevation, avoids and manually go to put sideline at complicated landform on the spot, carry The high security and convenience of surveying setting-out.(3)Due to laser beam real-time display edge positions, mechanical driver can with when Quarter is reminded, and avoids the excessive excavation of machinery, so as to reduce unnecessary mechanical one-shift, saves the warp of place excavation Take.
Brief description of the drawings
Fig. 1 is new the construction line-putting schematic device in the digging process of road and bridge place.
Fig. 2 is the schematic top plan view that new the construction line-putting device is in use in the digging process of road and bridge place.
Fig. 3 is that new the construction line-putting device excavates application in Mountainous areas place in the digging process of road and bridge place Elevational schematic view.
Brief description of the drawings:1- spirit levels;2- screwing type buckles;3- laser lamps;4- expansion links;5- white plastic disks;6- tri- Angle support;7- laser beams.
Embodiment
For a better understanding of the present invention, technical scheme is done further with reference to embodiment and accompanying drawing Explanation(As Figure 1-3).
Embodiment one
New the construction line-putting device in a kind of digging process of road and bridge place, it includes two sets of supports, and the support includes three Angle support 6, expansion link 4 and spirit level 1(The spirit level 1 is preferably portable spirit level), the lower end of expansion link 4 is fixedly mounted On A-frame 6, the spirit level 1 is fixedly mounted on the middle part of expansion link 4;The upper end of expansion link 4 peace of one of support Equipped with one or more laser lamp 3, the upper end of expansion link 4 of another support is provided with white plastic disk 5.
The laser lamp 3 is arranged on expansion link 4 by screwing type buckle 2, and laser lamp 3 can be with by screwing type buckle 2 Rotated in a circumferential direction around expansion link 4.
The white plastic disk 5 is arranged on expansion link 4 by screwing type buckle 2, and white plastic disk 5 is by screwing Formula buckle 2 can rotate in a circumferential direction around expansion link 4.
The laser lamp 3 of the upper end of expansion link 4 installation is two.
The A-frame 6 is height-adjustable tripod.
The construction method of new the construction line-putting device in the digging process of road and bridge place, it comprises the following steps:
A, surveying and locating determines each angular coordinate in place and positions sign, determines that laser lamp 3 and white plastic disk 5 are located at each angle The position of point(Laser lamp 3 and white plastic disk 5 arranged crosswise);
B, A-frame 6 is laid in each corner location, after making the center of A-frame 6 alignment angle point, pacified on A-frame 6 Expansion link 4 is filled, then spirit level 1 is installed on expansion link 4, and expansion link 4 is adjusted according to spirit level 1;Finally in each expansion link 4 Upper end corresponding laser lamp 3 or white plastic disk 5 are all installed;
C, according to works sideline and elevation adjustable telescopic rod 4, laser lamp 3 and the center elevation of white plastic disk 5 is made to reach pre- If elevation(And check level);
D, laser lamp 3 is opened, according to works sideline direction rotary laser lamp 3(Horizontal direction)Make the direction of laser beam 7 and knot Structure thing sideline direction is consistent,(After checking direction)Fixed laser lamp 3;
E, the direction of white plastic disk 5 is adjusted, is allowed to face the direction of laser beam 7 and fixation;
F, laser lamp 3 is opened in the digging process of place, indicates that mechanical artificial progress place is excavated until white according to laser beam 7 There is the incident point of laser beam 7 in the center of color plastic disc 5, represents place on this sideline direction and excavates in place;
G, F is repeated the above steps until completion is excavated in place(White plastic circle corresponding to being projected when all laser beams 7 The accurate excavation in the center interval scale place of disk 5 is in place), retain corner location, remove and receive in the digging process of road and bridge place newly Type the construction line-putting device(Carry out next process).
If white plastic disk 5 receives the laser beam 7 from multiple directions, adjustment white plastic circle in the step E The direction of disk 5, all laser beams 7 is collected in central point on white plastic disk 5 can fixed white plastic disc 5.
If running into strong sunray, when there is the unsharp problem in the position of laser beam 7 in air, site operation can be allowed Personnel wear sunglasses, can so make what laser beam 7 became apparent to be presented in workmen's eye.
Embodiment two
Need to excavate to the absolute altitude of laser beam 7 shown in Fig. 3, design corner location on one and accompanying drawing 3, such as design in conjunction with the embodiments and be The position of rightmost side white plastic disk 5, then need to excavate two hillside.One white plastic disk 5 can be first set by first mountain Excavate in place on slope;Second hillside is excavated again, until laser beam 7 is incident upon rightmost side white plastic disk 5 and represents place height Journey is excavated in place.Due to can monitor in real time place excavate degree, can effective guiding construction, avoid excavate excessively or excavate not Enough repeated measurements.
The right model described above for being only the Application Example of the present invention, the present invention can not being limited with this certainly Enclose, therefore the equivalence changes made according to scope of the present invention patent, still belong to protection scope of the present invention.

Claims (7)

1. new the construction line-putting device in a kind of digging process of road and bridge place, it is characterised in that:It includes two sets of supports, institute Stating support includes A-frame(6), expansion link(4)And spirit level(1), the expansion link(4)Lower end is fixedly mounted on triangle branch Frame(6)On, the spirit level(1)It is fixedly mounted on expansion link(4)Middle part;The expansion link of one of support(4)Pacify upper end Equipped with one or more laser lamp(3), the expansion link of another support(4)Upper end is provided with white plastic disk(5).
2. new the construction line-putting device in the digging process of road and bridge place according to claim 1, it is characterised in that:Institute State laser lamp(3)Pass through screwing type buckle(2)Installed in expansion link(4)On, laser lamp(3)Pass through screwing type buckle(2)Can be with Around expansion link(4)Rotate in a circumferential direction.
3. new the construction line-putting device in the digging process of road and bridge place according to claim 2, it is characterised in that:Institute State white plastic disk(5)Pass through screwing type buckle(2)Installed in expansion link(4)On, white plastic disk(5)Pass through screwing type Buckle(2)Can be around expansion link(4)Rotate in a circumferential direction.
4. new the construction line-putting device in the road and bridge place digging process according to claim 1,2 or 3, its feature exist In:The expansion link(4)The laser lamp of upper end installation(3)For two.
5. new the construction line-putting device in the road and bridge place digging process according to claim 1,2 or 3, its feature exist In:The A-frame(6)For height-adjustable tripod.
6. the construction method of new the construction line-putting device in the digging process of road and bridge place according to claim 1, its It is characterised by that it comprises the following steps:
A, surveying and locating determines each angular coordinate in place and positions sign, determines laser lamp(3)With white plastic disk(5)It is located at The position of each angle point;
B, A-frame is laid in each corner location(6), make A-frame(6)After center alignment angle point, in A-frame (6)Upper installation expansion link(4), then in expansion link(4)Upper installation spirit level(1), and according to spirit level(1)Adjust expansion link(4); Finally in each expansion link(4)Upper end corresponding laser lamp is all installed(3)Or white plastic disk(5);
C, according to works sideline and elevation adjustable telescopic rod(4), make laser lamp(3)With white plastic disk(5)Center elevation Reach default elevation;
D, laser lamp is opened(3), according to works sideline direction rotary laser lamp(3)Make laser beam(7)Direction and works Sideline direction is consistent, fixed laser lamp(3);
E, white plastic disk is adjusted(5)Direction, it is allowed to face laser beam(7)Direction and fixation;
F, laser lamp is opened in the digging process of place(3), according to laser beam(7)It is straight to indicate that mechanical artificial progress place is excavated To white plastic disk(5)There is laser beam in center(7)Incident point, represent on this sideline direction place and excavate in place;
G, F is repeated the above steps until place excavation completion, reservation corner location, are removed new in the digging process of receipts road and bridge place Type the construction line-putting device.
7. the construction method of new the construction line-putting device in the digging process of road and bridge place according to claim 6, its It is characterised by:White plastic disk in the step E(5)If receive the laser beam from multiple directions(7), adjust white modeling Expect disk(5)Direction, make all laser beams(7)Collect in white plastic disk(5)Upper central point can fixed white plastics Disk(5).
CN201711046933.4A 2017-10-31 2017-10-31 Novel construction paying-off device and construction method in road and bridge site excavation process Active CN107830848B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711046933.4A CN107830848B (en) 2017-10-31 2017-10-31 Novel construction paying-off device and construction method in road and bridge site excavation process

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711046933.4A CN107830848B (en) 2017-10-31 2017-10-31 Novel construction paying-off device and construction method in road and bridge site excavation process

Publications (2)

Publication Number Publication Date
CN107830848A true CN107830848A (en) 2018-03-23
CN107830848B CN107830848B (en) 2020-08-14

Family

ID=61651209

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711046933.4A Active CN107830848B (en) 2017-10-31 2017-10-31 Novel construction paying-off device and construction method in road and bridge site excavation process

Country Status (1)

Country Link
CN (1) CN107830848B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108775895A (en) * 2018-07-30 2018-11-09 中国地质大学(武汉) A kind of tunnel straight line excavates intelligent positioning instrument and its application method
CN112157294A (en) * 2020-08-13 2021-01-01 北京机械设备研究所 Device and method for drilling mounting hole in equipment cabin
CN113107023A (en) * 2021-03-22 2021-07-13 中国五冶集团有限公司 Earth excavation pay-off

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001255146A (en) * 2000-03-08 2001-09-21 Topcon Corp Control system for construction machine by laser reference face
CN103471573A (en) * 2013-10-06 2013-12-25 中国二十二冶集团有限公司 Leveling reflector device and horizontal line quick releasing method thereof
US20150331159A1 (en) * 2008-11-17 2015-11-19 Faro Technologies, Inc. Markings on glass cube-corner retroreflector and method of measuring retroreflector orientation
CN205655835U (en) * 2016-05-12 2016-10-19 河南理工大学 Automatic centering and measuring total powerstation
CN206248090U (en) * 2016-12-15 2017-06-13 毕祥光 A kind of road and bridge construction measurement apparatus
CN206583454U (en) * 2017-03-31 2017-10-24 山西省第三建筑工程公司 A kind of groove earth excavation measure and control device

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001255146A (en) * 2000-03-08 2001-09-21 Topcon Corp Control system for construction machine by laser reference face
US20150331159A1 (en) * 2008-11-17 2015-11-19 Faro Technologies, Inc. Markings on glass cube-corner retroreflector and method of measuring retroreflector orientation
CN103471573A (en) * 2013-10-06 2013-12-25 中国二十二冶集团有限公司 Leveling reflector device and horizontal line quick releasing method thereof
CN205655835U (en) * 2016-05-12 2016-10-19 河南理工大学 Automatic centering and measuring total powerstation
CN206248090U (en) * 2016-12-15 2017-06-13 毕祥光 A kind of road and bridge construction measurement apparatus
CN206583454U (en) * 2017-03-31 2017-10-24 山西省第三建筑工程公司 A kind of groove earth excavation measure and control device

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108775895A (en) * 2018-07-30 2018-11-09 中国地质大学(武汉) A kind of tunnel straight line excavates intelligent positioning instrument and its application method
CN112157294A (en) * 2020-08-13 2021-01-01 北京机械设备研究所 Device and method for drilling mounting hole in equipment cabin
CN112157294B (en) * 2020-08-13 2023-08-01 北京机械设备研究所 Device and method for punching mounting holes in equipment cabin
CN113107023A (en) * 2021-03-22 2021-07-13 中国五冶集团有限公司 Earth excavation pay-off

Also Published As

Publication number Publication date
CN107830848B (en) 2020-08-14

Similar Documents

Publication Publication Date Title
CN107830848A (en) New the construction line-putting device and construction method in the digging process of road and bridge place
CN106192682A (en) Railway roadbed substrate 3D concrete paver and 3D pave method
CN108759799A (en) A kind of laser orientation system and application method for side slope sash beam setting-out
CN108049291A (en) A kind of asphalt concrete pavement 3D paves construction method
CN112305165B (en) Simulation model and method for evaluating stability of slope vegetation body
CN106017435A (en) Laser device and application method thereof
CN108375347A (en) A kind of FAST radio telescopes reflecting surface unit accuracy measurement system and method
CN205120090U (en) Instrument is used in soil survey and drawing
CN108896034A (en) Laser orientation instrument anti-deflection device for underground coal mine
CN109184702A (en) The measurement method of out break is controlled under the conditions of the more curves of Tunnel Engineering, minor radius
CN208505309U (en) For assisting the photoelectricity instrument of alignment in the thick forest of mountain area
CN104695290A (en) Installation method of railway concrete protection fences
CN206724958U (en) A kind of laser orientation instrument positioner
JP5769055B2 (en) Mirror adjustment jig and structural deformation detection system
CN107916938A (en) A kind of loading device for curve pipe curtain machine guider
CN204007595U (en) A kind of land surveying equipment
KR101469358B1 (en) Operation equipment for geographic information system and load ledger leveling of crowds and obstacles many urban
CN109113040B (en) It is measured in observation platform and its construction method and water in water and measures observation system
CN103868496B (en) Device and method for measuring vertical structure
CN205857131U (en) A kind of water channel situ forming with linear guidance device
Varnes et al. Deformation and control surveys: Slumgullion landslide
CN206037998U (en) Slope slope measurement device
CN110926436A (en) Method and auxiliary tool for surveying and paying-off of slope construction
KR101469359B1 (en) Operation method for geographic information system and load ledger leveling of crowds and obstacles many urban
CN217781667U (en) Roadbed construction lofting device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant