CN107826989B - A kind of double tower for indirect cool tower installation hangs the installation method of adhering bar part - Google Patents

A kind of double tower for indirect cool tower installation hangs the installation method of adhering bar part Download PDF

Info

Publication number
CN107826989B
CN107826989B CN201711082431.7A CN201711082431A CN107826989B CN 107826989 B CN107826989 B CN 107826989B CN 201711082431 A CN201711082431 A CN 201711082431A CN 107826989 B CN107826989 B CN 107826989B
Authority
CN
China
Prior art keywords
tower
welded tube
bar part
indirect cool
adhering bar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201711082431.7A
Other languages
Chinese (zh)
Other versions
CN107826989A (en
Inventor
罗胜
娄祥顺
罗会田
程国华
马运涛
王德
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China National Chemical Engineering Third Construction Co Ltd
Original Assignee
China National Chemical Engineering Third Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China National Chemical Engineering Third Construction Co Ltd filed Critical China National Chemical Engineering Third Construction Co Ltd
Priority to CN201711082431.7A priority Critical patent/CN107826989B/en
Publication of CN107826989A publication Critical patent/CN107826989A/en
Application granted granted Critical
Publication of CN107826989B publication Critical patent/CN107826989B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C23/00Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
    • B66C23/16Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes with jibs supported by columns, e.g. towers having their lower end mounted for slewing movements
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C23/00Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
    • B66C23/62Constructional features or details
    • B66C23/72Counterweights or supports for balancing lifting couples
    • B66C23/78Supports, e.g. outriggers, for mobile cranes

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)
  • Working Measures On Existing Buildindgs (AREA)
  • Jib Cranes (AREA)

Abstract

The invention discloses a kind of double towers for indirect cool tower installation to hang the installation method of adhering bar part, comprising the following steps: 1) according to tower crane own dimensions and double tower hang between spacing dimension, determine the blank size of attachment rod piece;2) Lift-on/Lift-off System that itself is hung using double tower is used for the attachment rod piece on respective tower crane in the lower section assembly welding of corresponding tower crane;3) it successively welds the support lug for connecting adhering bar part from bottom to top on the inside of the tower body of indirect cool tower, while welding support lug, also welds the attachment frame for connecting adhering bar part with the position of indirect cool tower tower body same level on tower crane;4) tower crane lifting system is utilized, from bottom to top successively fixes one end of adhering bar part with support lug, the other end is fixed with attachment frame.Installation cost can reduce using method of the invention, ensure that in indirect cool tower tower that double tower is hung while the safe distance of operation, and ensure the implementation of tower crane Demolition Scheme.

Description

A kind of double tower for indirect cool tower installation hangs the installation method of adhering bar part
Technical field
The present invention relates to the mounting technique of indirect cool tower, in particular to a kind of double tower for indirect cool tower installation hangs nonstandard attachment The installation method of rod piece.
Background technique
Currently, indirect cool tower, needs to rely on during the installation process tower crane completion.Since the height of indirect cool tower is higher, in tower crane On be also required to carry out corresponding counter-measure, guarantee the stability of tower crane, the measure i.e. on tower crane installation attachment rod piece.Mesh Before, the attachment rod piece of tower crane is essentially all standard component, and standard component can not adapt between double tower when being applied to double tower system Safe distance, and when being commonly installed tower crane attachment, all it is that auxiliary installation is carried out using large-scale crane, causes cost excessively high Problem.
Summary of the invention
Technical problem to be solved by the invention is to provide a kind of double towers for indirect cool tower installation to hang adhering bar part Installation method, this method can reduce installation cost, ensure that in indirect cool tower tower that double tower is hung while the safe distance of operation, and Ensure the implementation of tower crane Demolition Scheme.
To achieve the above object, the present invention provides technical solution below: a kind of double tower for indirect cool tower installation hangs non- The installation method of mark attachment rod piece, comprising the following steps:
1) according to tower crane own dimensions and double tower hang between spacing dimension, determine attachment rod piece blank size;
2) Lift-on/Lift-off System that itself is hung using double tower is used for attached on respective tower crane in the lower section assembly welding of corresponding tower crane Rod piece;
3) support lug for connecting adhering bar part is successively welded from bottom to top on the inside of the tower body of indirect cool tower, While welding support lug, also welded with the position of indirect cool tower tower body same level for connecting adhering bar part on tower crane Attachment frame, the support lug in same level constructs simultaneously with attachment frame;
4) tower crane lifting system is utilized, is from bottom to top successively fixed one end of adhering bar part with support lug, separately One end is fixed with attachment frame, and adhering bar part of two tower cranes in same level is constructed simultaneously.
Preferably, one layer of adhering bar part is installed in the middle part of the conical section of indirect cool tower, is equipped at the top of conical section One layer of attachment rod piece, the cylindrical section of indirect cool tower are equipped with six layers of adhering bar part.
Preferably, every layer of adhering bar part is mounted on 4.
Preferably, it is mounted on the adhering bar part in the middle part of indirect cool tower conical section to fix by reinforcing truss with tower crane, institute It states and reinforces truss to be equipped with a pair of, each pair of reinforcement truss including two horizontal welded tube FG1, two oblique pull welded tube LG1, a level Welded tube FG2 and a connection welded tube, two horizontal welded tube FG1 are parallel to the horizontal plane, and one end of two horizontal welded tube FG1 Be welded on connection welded tube, the other end is welded in the middle part of the conical section of indirect cool tower on tower body, and make two horizontal welded tube FG1 it Between angle remain obtuse angle, the crossbeam of the middle part tower body of one end and indirect cool tower conical section of two oblique pull welded tube LG1 is hinged, separately One end is fixed with tube-welding is connect, and hinge joint of two oblique pull welded tube LG1 on indirect cool tower is located at two horizontal welded tubes The surface of FG1 pad;Horizontal welded tube FG2 is set between two horizontal welded tube FG1, and one end of horizontal welded tube FG2 with The cant beam of indirect cool tower tripod is fixed, the other end with connect welded tube spot welding;One end of the adhering bar part is fixed with tower crane, The other end is fixed with welded tube is connect.
Preferably, vertical ladder channel is fixedly installed on horizontal welded tube FG2.
Preferably, connection welded tube is fixedly installed with a root post far from one end of horizontal welded tube FG2, fixes on the column One end of a piece safety rope, the other end of safety rope and the cant beam of indirect cool tower tripod are fixed.
By adopting the above technical scheme, large-scale crane is not needed when the method applied in the present invention operation, reduces Anchored Bar The installation cost of part ensure that in indirect cool tower tower that double tower is hung while the peace of operation since attachment rod piece uses non-standard production Full distance, and ensure the implementation of tower crane Demolition Scheme.
Specific embodiment
The invention discloses the installation method that a kind of double tower for indirect cool tower installation hangs adhering bar part, feature exists In, comprising the following steps:
1) according to tower crane own dimensions and double tower hang between spacing dimension, determine attachment rod piece blank size;
2) Lift-on/Lift-off System that itself is hung using double tower is used for attached on respective tower crane in the lower section assembly welding of corresponding tower crane Rod piece;
3) support lug for connecting adhering bar part is successively welded from bottom to top on the inside of the tower body of indirect cool tower, While welding support lug, also welded with the position of indirect cool tower tower body same level for connecting adhering bar part on tower crane Attachment frame, the support lug in same level constructs simultaneously with attachment frame;
4) tower crane lifting system is utilized, is from bottom to top successively fixed one end of adhering bar part with support lug, separately One end is fixed with attachment frame, and adhering bar part of two tower cranes in same level is constructed simultaneously.
The present embodiment is by taking the indirect cool tower of 170m high as an example, and the conical section height of the indirect cool tower is 55m, and remainder is cylinder Section.Before adhering bar part is installed, indirect cool tower is divided into eight absolute altitudes, respectively+35.95m ,+55m ,+63.77m ,+ 90.8m,+107.62m,+125.16m,+142.70m,+160.24m.The tower crane in double tower crane system in the present invention is respectively First tower crane, the second tower crane, wherein the first tower crane installed at whole absolute altitudes attachment rod piece, the second tower crane only+55m ,+ It is installed at 90.8m ,+125.16m three.When installing adhering bar part, non-mark post is successively installed from low absolute altitude to high standard eminence Part, the adhering bar part construction and installation simultaneously when at installation+55m ,+90.8m ,+125.16m three, on two tower cranes.
When adhering bar part of the first tower crane of the invention at installation+35.95m, need to fix by reinforcing truss. Reinforce truss and be equipped with a pair, each pair of reinforcement truss includes two horizontal welded tube FG1, two oblique pull welded tube LG1, a horizontal welding Pipe FG2 and a connection welded tube, two horizontal welded tube FG1 are parallel to the horizontal plane, and one end weldering of two horizontal welded tube FG1 It connects on connection welded tube, the other end is welded in the middle part of the conical section of indirect cool tower on tower body, and is made between two horizontal welded tube FG1 Angle remain obtuse angle, the crossbeam of the middle part tower body of one end and indirect cool tower conical section of two oblique pull welded tube LG1 is hinged, another End with connect tube-welding and fix, hinge joint of two oblique pull welded tube LG1 on indirect cool tower is located at two horizontal welded tube FG1 The surface of pad;Horizontal welded tube FG2 is set between two horizontal welded tube FG1, and one end of horizontal welded tube FG2 and cold The cant beam of tower triangular frame is fixed, the other end with connect welded tube spot welding;One end of the adhering bar part is fixed with tower crane, another End with connect welded tube and fix.
The installation steps for reinforcing truss are as follows:
(1) after horizontal welded tube forming, it is solid to add temporary support to unilateral horizontal welded tube FG1, horizontal welded tube FG2 for ground group Fixed, and vertical ladder aisle is arranged on intermediate horizontal welded tube FG2, vertical ladder one end must spot welding and solid in connection welded tube upper surface It is fixed firm, the other end it is to be installed it is in place after in indirect cool tower beam surface upper spot welding and fixed, vertical ladder channel upper surface is full Spread steel springboard;
(2) column is welded close to the side of support lug in connection welded tube, arranges elongated safety rope in horizontal welded tube FG2, Safety rope one end and column are fixed, and the other end rear and indirect cool tower tripod cant beam in place to be installed is fixed;
(3) horizontal welded tube is lifted using 50 tons of truck cranes or with 75 tons of crawler cranes, and does drawing of rising and is fixedly connected with welded tube, guaranteed It is horizontal;
(4) company for installing oblique pull welded tube LG1 is welded and fixed on the crossbeam of the top of the position installation horizontal welded tube FG1 Fishplate bar, and hinge hole is set on connecting plate, then one of oblique pull welded tube LG1 for reinforcing truss side of lifting, and with cutting with scissors It connects in succession, after horizontal welded tube FG1 and horizontal welded tube FG2 lifting is in place, the other side oblique pull welded tube of the reinforcement truss is installed LG1, then integrated regulation reinforces the levelness of truss, it is ensured that tower crane attachment bar installation accuracy.Another reinforces the oblique of truss Welded tube LG1 is drawn also to install according to above-mentioned steps.
What has been described above is only a preferred embodiment of the present invention, it is noted that for those of ordinary skill in the art For, without departing from the concept of the premise of the invention, various modifications and improvements can be made, these belong to the present invention Protection scope.

Claims (6)

1. the installation method that a kind of double tower for indirect cool tower installation hangs adhering bar part, which is characterized in that including following step It is rapid:
1) according to tower crane own dimensions and double tower hang between spacing dimension, determine attachment rod piece blank size;
2) Lift-on/Lift-off System that itself is hung using double tower is used for the Anchored Bar on respective tower crane in the lower section assembly welding of corresponding tower crane Part;
3) it successively welds the support lug for connecting adhering bar part from bottom to top on the inside of the tower body of indirect cool tower, is welding While support lug, also welded with the position of indirect cool tower tower body same level for connecting the attached of adhering bar part on tower crane Frame, the support lug in same level construct simultaneously with attachment frame;
4) tower crane lifting system is utilized, is from bottom to top successively fixed one end of adhering bar part with support lug, the other end It is fixed with attachment frame, adhering bar part of two tower cranes in same level is constructed simultaneously.
2. the double tower according to claim 1 for indirect cool tower installation hangs the installation method of adhering bar part, feature Be, one layer of adhering bar part be installed in the middle part of the conical section of the indirect cool tower, be equipped at the top of conical section one layer it is attached Rod piece, the cylindrical section of indirect cool tower six layers of adhering bar part are installed.
3. the double tower according to claim 2 for indirect cool tower installation hangs the installation method of adhering bar part, feature It is, every layer of adhering bar part is mounted on 4.
4. the double tower according to claim 3 for indirect cool tower installation hangs the installation method of adhering bar part, feature It is, is mounted on the adhering bar part in the middle part of indirect cool tower conical section and is fixed by reinforcing truss with tower crane, the reinforcement truss Equipped with a pair, each pair of reinforcement truss include two horizontal welded tube FG1, two oblique pull welded tube LG1, a horizontal welded tube FG2 with And a connection welded tube, two horizontal welded tube FG1 are parallel to the horizontal plane, and one end of two horizontal welded tube FG1 is welded on company It connects on welded tube, the other end is welded in the middle part of the conical section of indirect cool tower on tower body, and makes the angle between two horizontal welded tube FG1 Obtuse angle is remained, the crossbeam of the middle part tower body of one end and indirect cool tower conical section of two oblique pull welded tube LG1 is hinged, the other end and company It connects tube-welding to fix, hinge joint of two oblique pull welded tube LG1 on indirect cool tower is located at two horizontal welded tube FG1 pads Surface;Horizontal welded tube FG2 is set between two horizontal welded tube FG1, and one end of horizontal welded tube FG2 and indirect cool tower triangle The cant beam of frame is fixed, the other end with connect welded tube spot welding;One end of the adhering bar part is fixed with tower crane, and the other end passes through Support lug is fixed with welded tube is connect.
5. the double tower according to claim 4 for indirect cool tower installation hangs the installation method of adhering bar part, feature It is, is fixedly installed with vertical ladder channel on horizontal welded tube FG2.
6. the double tower according to claim 5 for indirect cool tower installation hangs the installation method of adhering bar part, feature It is, the connection welded tube is fixedly installed with a root post far from one end of horizontal welded tube FG2, and a peace is fixed on the column The one end restricted entirely, the other end of safety rope and the cant beam of indirect cool tower tripod are fixed.
CN201711082431.7A 2017-11-07 2017-11-07 A kind of double tower for indirect cool tower installation hangs the installation method of adhering bar part Active CN107826989B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711082431.7A CN107826989B (en) 2017-11-07 2017-11-07 A kind of double tower for indirect cool tower installation hangs the installation method of adhering bar part

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711082431.7A CN107826989B (en) 2017-11-07 2017-11-07 A kind of double tower for indirect cool tower installation hangs the installation method of adhering bar part

Publications (2)

Publication Number Publication Date
CN107826989A CN107826989A (en) 2018-03-23
CN107826989B true CN107826989B (en) 2019-04-19

Family

ID=61653760

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711082431.7A Active CN107826989B (en) 2017-11-07 2017-11-07 A kind of double tower for indirect cool tower installation hangs the installation method of adhering bar part

Country Status (1)

Country Link
CN (1) CN107826989B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110424784B (en) * 2019-08-07 2021-02-23 上海市机械施工集团有限公司 Tower crane construction method of steel structure indirect cooling tower

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000303695A (en) * 1999-04-16 2000-10-31 Kumagai Gumi Co Ltd Tower crane for construction of base isolated building and method for installation thereof
CN101286624A (en) * 2008-03-07 2008-10-15 福建省厦门电业局 Safety distance extending method for live operation with earth electric potential of tension resistant tower crossarm
JP2009091123A (en) * 2007-10-10 2009-04-30 Hitachi Constr Mach Co Ltd Crane for steel tower
CN201896319U (en) * 2010-11-24 2011-07-13 浙江中成建工集团有限公司 Conversion platform for connecting tower crane basic section with steel lattice piles
CN205575425U (en) * 2016-04-01 2016-09-14 江苏庞源机械工程有限公司 High strength tower crane attachment structure
CN106495026A (en) * 2017-01-09 2017-03-15 山东华邦建设集团有限公司 Attachment built temporarily by construction tower crane
CN206328068U (en) * 2016-12-17 2017-07-14 开封大学 A kind of both arms loop wheel machine for construction

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000303695A (en) * 1999-04-16 2000-10-31 Kumagai Gumi Co Ltd Tower crane for construction of base isolated building and method for installation thereof
JP2009091123A (en) * 2007-10-10 2009-04-30 Hitachi Constr Mach Co Ltd Crane for steel tower
CN101286624A (en) * 2008-03-07 2008-10-15 福建省厦门电业局 Safety distance extending method for live operation with earth electric potential of tension resistant tower crossarm
CN201896319U (en) * 2010-11-24 2011-07-13 浙江中成建工集团有限公司 Conversion platform for connecting tower crane basic section with steel lattice piles
CN205575425U (en) * 2016-04-01 2016-09-14 江苏庞源机械工程有限公司 High strength tower crane attachment structure
CN206328068U (en) * 2016-12-17 2017-07-14 开封大学 A kind of both arms loop wheel machine for construction
CN106495026A (en) * 2017-01-09 2017-03-15 山东华邦建设集团有限公司 Attachment built temporarily by construction tower crane

Also Published As

Publication number Publication date
CN107826989A (en) 2018-03-23

Similar Documents

Publication Publication Date Title
CN203201562U (en) Shield tunneling machine initial counter-force frame convenient to detach, install and transport
CN105970819A (en) Installation construction method for steel anchor beams
CN209457425U (en) A kind of ancient architecture wall recovery support
CN107826989B (en) A kind of double tower for indirect cool tower installation hangs the installation method of adhering bar part
CN105781210A (en) Taper tower rack and tool section auxiliary cross-core type integral lifting construction method thereof
CN108775081A (en) A kind of hydraulic lifting inverted structure and its application method
CN205653706U (en) T roof beam vaulting pole that stabilizes
CN105040591A (en) Positioning device for waveform steel web and positioning method thereof
CN103663302A (en) L-type portal installation frame
CN204940861U (en) Adjustable case beam side steel bracket
CN109629812A (en) The fast assembling-disassembling method of super high-rise steel pipe column operating platform
CN106368322B (en) A kind of installation method for the bi-directional symmetrical inclination steel column between super high-rise building conversion layer
CN104310234B (en) Outer outstanding climbing tower crane support system
CN104192579B (en) Method for replacing material taking machine jackstay and material taking machine jackstay used for method
CN215593700U (en) Construction platform for welding steel box girder support by using method
CN102259794B (en) Method for installing overall combined type crane beam
CN103754908A (en) Large-scale seed precipitation tank body mounting construction method
CN203347024U (en) Continuous purline installation connecting structure in steel structure integral hoisting method
CN209288575U (en) A kind of tooled joint welding trolley suitable for the installation of penstock curved segment
CN102900023B (en) A kind of combined type working platform
CN206232343U (en) A kind of special-shaped C-type beam for tower crane
CN106285017B (en) Thermal control boiler steel vertical shaft installation method
CN109629420A (en) A kind of king-tower transverse brace structure and its installation method
CN205014326U (en) Big plate -girder stoplog installation device
CN110205947A (en) A kind of overline bridge steel box girder construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information

Address after: 230000 East Fozhang Road and North Tingyun Road Office Building, Hefei Economic and Technological Development Zone, Anhui Province

Applicant after: China National Chemical Engineering Third Construction Co., Ltd.

Address before: 232038 No. 98 Dongshan Road, Tianjiaan District, Huainan City, Anhui Province

Applicant before: China National Chemical Engineering Third Construction Co., Ltd.

CB02 Change of applicant information
GR01 Patent grant
GR01 Patent grant