CN107762017A - The connection method of curtain skeleton and the pre-buried anchor slab of major structure of construction - Google Patents

The connection method of curtain skeleton and the pre-buried anchor slab of major structure of construction Download PDF

Info

Publication number
CN107762017A
CN107762017A CN201610664559.3A CN201610664559A CN107762017A CN 107762017 A CN107762017 A CN 107762017A CN 201610664559 A CN201610664559 A CN 201610664559A CN 107762017 A CN107762017 A CN 107762017A
Authority
CN
China
Prior art keywords
construction
major structure
anchor slab
buried anchor
steel plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN201610664559.3A
Other languages
Chinese (zh)
Inventor
张睿
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC20 Group Corp Ltd
Original Assignee
China MCC20 Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC20 Group Corp Ltd filed Critical China MCC20 Group Corp Ltd
Priority to CN201610664559.3A priority Critical patent/CN107762017A/en
Publication of CN107762017A publication Critical patent/CN107762017A/en
Withdrawn legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/88Curtain walls
    • E04B2/96Curtain walls comprising panels attached to the structure through mullions or transoms

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Load-Bearing And Curtain Walls (AREA)

Abstract

The invention discloses the connection method of a kind of curtain skeleton and the pre-buried anchor slab of major structure of construction, this method carries out screening property partial cut to the major structure of construction wall for building shaping by laying bricks or stones first, and cutting part is corresponding with the pre-buried anchor slab of major structure of construction;Then penetrate cutting part using some square steel tube levels to be connected with the pre-buried anchor slab full weld of major structure of construction, some square steel tube head end full welds connect the parallel steel plate parallel with major structure of construction wall, and the facade of some parallel steel plates is located at same vertical line;Some parallel steel plate end faces full weld connects steel plate vertical with major structure of construction wall body vertical, and vertical steel plate forms the adaptor with curtain skeleton, realizes the connection of curtain skeleton and the pre-buried anchor slab of major structure of construction.This method overcomes the defects of conventional curtain wall construction, avoids the position deviation of pre-buried anchor slab and curtain skeleton connector, it is ensured that the normal construction operation of curtain wall, reduces construction cost, improves efficiency of construction.

Description

The connection method of curtain skeleton and the pre-buried anchor slab of major structure of construction
Technical field
The present invention relates to the connection method of a kind of curtain skeleton and the pre-buried anchor slab of major structure of construction.
Background technology
With the rapid development of building trade, alien invasion decorative engineering also progressively tends to be ripe.Glass curtain wall, aluminium sheet curtain Effective connection of the ornament materials such as wall, dry-hang stone curtain wall and major structure of construction is more and more in widespread attention.But general In building construction process, typically not commensurate is individually designed, therefore often occur with main building design for alien invasion Decoration Design The connector of the pre-buried anchor slab of major structure of construction alien invasion and curtain skeleton not at grade, pre-buried anchor slab and curtain skeleton There is deviation in connector position, it is impossible to effectively realize connection, have a strong impact on the construction operation of curtain wall.To overcome drawbacks described above, lead to The wall that shaping need to often have been built by laying bricks or stones to major structure of construction alien invasion is largely removed, changes the global shape that alien invasion is decorated.Such as This causes the artificial, significant wastage of material, and secondary operating expenses occurs, and has a strong impact on construction period, reduces efficiency of construction.
The content of the invention
The technical problems to be solved by the invention are to provide the company of a kind of curtain skeleton and the pre-buried anchor slab of major structure of construction Method is connect, this method overcomes the defects of conventional curtain wall is constructed, and avoids the position deviation of pre-buried anchor slab and curtain skeleton connector, Ensure the normal construction operation of curtain wall, reduce construction cost, improve efficiency of construction.
In order to solve the above technical problems, the connection method of curtain skeleton of the present invention and the pre-buried anchor slab of major structure of construction includes Following steps:
Step 1: screening property partial cut, cutting part and building body are carried out to the major structure of construction wall for building shaping by laying bricks or stones The pre-buried anchor slab of structure is corresponding;
Step 2: penetrate cutting part and square steel tube tail end and the pre-buried anchor slab of major structure of construction using some square steel tube levels Full weld connects, and some square steel tube head end full welds connect the parallel steel plate parallel with major structure of construction wall, some parallel steel plates Facade be located at same vertical line;
Step 3: some parallel steel plate end faces full weld connects steel plate vertical with major structure of construction wall body vertical, vertical steel plate The adaptor with curtain skeleton is formed, realizes the connection of curtain skeleton and the pre-buried anchor slab of major structure of construction.
Further, the size of the square steel tube is 100 × 50 × 4mm.
Further, the thickness of the parallel steel plate and vertical steel plate is respectively 8mm and 6mm.
Because the connection method of curtain skeleton of the present invention and the pre-buried anchor slab of major structure of construction employs above-mentioned technical proposal, i.e., originally Method carries out screening property partial cut, cutting part and major structure of construction to the major structure of construction wall for building shaping by laying bricks or stones first Pre-buried anchor slab is corresponding;Then cutting part is penetrated using some square steel tube levels with the pre-buried anchor slab full weld of major structure of construction to connect Connect, some square steel tube head end full welds connect the parallel steel plate parallel with major structure of construction wall, the facade of some parallel steel plates Positioned at same vertical line;Some parallel steel plate end faces full weld connects steel plate vertical with major structure of construction wall body vertical, vertical steel Plate forms the adaptor with curtain skeleton, realizes the connection of curtain skeleton and the pre-buried anchor slab of major structure of construction.This method overcomes The defects of conventional curtain wall construction, avoid the position deviation of pre-buried anchor slab and curtain skeleton connector, it is ensured that curtain wall is normally applied Work industry, reduces construction cost, improves efficiency of construction.
Brief description of the drawings
The present invention is described in further detail with embodiment below in conjunction with the accompanying drawings:
Fig. 1 is the structural representation that curtain skeleton is connected with the pre-buried anchor slab of major structure of construction in this method.
Embodiment
Embodiment is as shown in figure 1, the connection method of curtain skeleton of the present invention and the pre-buried anchor slab of major structure of construction is included such as Lower step:
Step 1: screening property partial cut, cutting part and building body are carried out to the major structure of construction wall 1 for building shaping by laying bricks or stones The pre-buried correspondence of anchor slab 2 of structure;
Step 2: penetrate cutting part and the tail end of square steel tube 3 and the pre-buried anchor of major structure of construction using some levels of square steel tube 3 The full weld of plate 2 connects, and some head end full welds of square steel tube 3 connect the parallel steel plate 4, Ruo Ganping parallel with major structure of construction wall 1 The facade of row steel plate 4 is located at same vertical line;
Step 3: some end face full welds of parallel steel plate 4 connect the vertical steel plate 5 vertical with major structure of construction wall 1, vertical steel Plate 5 forms the adaptor with curtain skeleton 6, realizes the connection of curtain skeleton 6 and the pre-buried anchor slab 2 of major structure of construction.
Preferably, the size of the square steel tube 3 is 100 × 50 × 4mm.
Preferably, the thickness of the parallel steel plate 4 and vertical steel plate 5 is respectively 8mm and 6mm.
This method is entered before partial cut is carried out to major structure of construction wall by the infrared measurement machine to pre-buried anchor slab Row measurement, it is some parallel because adaptor length is by compound afterwards according to the accurate blanking of data other side's length of steel pipe of measurement The facade of steel plate is located at same vertical line, so that it is guaranteed that the perpendicularity of curtain wall facade, improves installation quality.
This method easy construction, good engineering quality, engineering efficiency high, cost payout are low;And connection member used Directly spelled according to live entity and make and connect shaping, site operation is directly welded to connect, and can be improved construction precision, be kept away The cost increase exempted from live secondary operation and occurred, solving alien invasion curtain skeleton can not be connected and cause with concrete structured beam The problem of curtain wall can not be fixed.

Claims (3)

1. the connection method of a kind of curtain skeleton and the pre-buried anchor slab of major structure of construction, it is characterised in that this method includes following step Suddenly:
Step 1: screening property partial cut, cutting part and building body are carried out to the major structure of construction wall for building shaping by laying bricks or stones The pre-buried anchor slab of structure is corresponding;
Step 2: penetrate cutting part and square steel tube tail end and the pre-buried anchor slab of major structure of construction using some square steel tube levels Full weld connects, and some square steel tube head end full welds connect the parallel steel plate parallel with major structure of construction wall, some parallel steel plates Facade be located at same vertical line;
Step 3: some parallel steel plate end faces full weld connects steel plate vertical with major structure of construction wall body vertical, vertical steel plate The adaptor with curtain skeleton is formed, realizes the connection of curtain skeleton and the pre-buried anchor slab of major structure of construction.
2. the connection method of curtain skeleton according to claim 1 and the pre-buried anchor slab of major structure of construction, it is characterised in that: The size of the square steel tube is 100 × 50 × 4mm.
3. the connection method of curtain skeleton according to claim 1 and the pre-buried anchor slab of major structure of construction, it is characterised in that: The thickness of the parallel steel plate and vertical steel plate is respectively 8mm and 6mm.
CN201610664559.3A 2016-08-15 2016-08-15 The connection method of curtain skeleton and the pre-buried anchor slab of major structure of construction Withdrawn CN107762017A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610664559.3A CN107762017A (en) 2016-08-15 2016-08-15 The connection method of curtain skeleton and the pre-buried anchor slab of major structure of construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610664559.3A CN107762017A (en) 2016-08-15 2016-08-15 The connection method of curtain skeleton and the pre-buried anchor slab of major structure of construction

Publications (1)

Publication Number Publication Date
CN107762017A true CN107762017A (en) 2018-03-06

Family

ID=61259677

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610664559.3A Withdrawn CN107762017A (en) 2016-08-15 2016-08-15 The connection method of curtain skeleton and the pre-buried anchor slab of major structure of construction

Country Status (1)

Country Link
CN (1) CN107762017A (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2678659A1 (en) * 1991-07-01 1993-01-08 Sogea Method for protection and cladding of a building facade, and corresponding building
FR2743101A1 (en) * 1995-12-28 1997-07-04 Spie Citra Method of making cavity wall
CN103758265A (en) * 2014-01-22 2014-04-30 合肥建工集团有限公司 Rack type GRC curtain wall with irregular vertical face and mounting method thereof
CN104110125A (en) * 2014-07-18 2014-10-22 浙江万华建设有限公司 Scaffold wall-connecting device and waterproof method after dismantling of scaffold wall-connecting device
CN205224362U (en) * 2015-12-07 2016-05-11 南京三惠建设工程有限公司 Open type aluminum plate curtain wall

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2678659A1 (en) * 1991-07-01 1993-01-08 Sogea Method for protection and cladding of a building facade, and corresponding building
FR2743101A1 (en) * 1995-12-28 1997-07-04 Spie Citra Method of making cavity wall
CN103758265A (en) * 2014-01-22 2014-04-30 合肥建工集团有限公司 Rack type GRC curtain wall with irregular vertical face and mounting method thereof
CN104110125A (en) * 2014-07-18 2014-10-22 浙江万华建设有限公司 Scaffold wall-connecting device and waterproof method after dismantling of scaffold wall-connecting device
CN205224362U (en) * 2015-12-07 2016-05-11 南京三惠建设工程有限公司 Open type aluminum plate curtain wall

Similar Documents

Publication Publication Date Title
CN204475716U (en) A kind of Protective angle for stairs structure
CN204225388U (en) A kind of Protective angle for stairs structure
CN103934693B (en) The processing technology of box-structure post/beam shaping
CN101664847A (en) Method for producing box beam/column with steel structure
CN110984446A (en) Efficient curtain wall installation method
CN103122696B (en) Cast-in-place concrete floor gage controller and method thereof
CN108894488A (en) A kind of construction method of Novel section steel keel steel and wood composite template
CN104343239A (en) Electric threading pipe dark laying construction technology for aerated concrete filler wall punching
CN204356970U (en) Based on the single-layer lattice shell steel house plane system of concrete construction
CN206957185U (en) External corner shear wall set buries screw rod and fixes suspension scaffold shaped steel connector
CN103418994A (en) Method for equal-strength butt joint of steel tubes
KR20180052802A (en) The welding structure of steel pipe
CN109898776A (en) A kind of more curved surface aluminium sheet construction methods of assembled
CN107762017A (en) The connection method of curtain skeleton and the pre-buried anchor slab of major structure of construction
CN109208821A (en) A kind of built-in steel pipe Constructional Col-umn Construction method of ALC building block
CN104989107A (en) Curved ribbed beam processing and assembling construction process
CN106401276A (en) Construction method for wall column binding bars of frame type building block enclosing wall
CN103981909A (en) Rapid repair method and structure for broken foundation bolt
CN116427743A (en) Large-span door opening construction method
CN202214939U (en) Marble closing-in wall facade including embedded part
CN107447975A (en) Exterior wall scaffold tapered cup nut wall-connecting piece
CN215716065U (en) Connecting structure of precast concrete exterior wall cladding and building steel beam
CN213573060U (en) Light-duty automatic nuclear position ware of reinforcement
CN211172608U (en) Keel of cold-bending glass curtain wall
CN108381128B (en) Manufacturing method of I-shaped weather-resistant steel edge girder with lifting point penetrating out

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WW01 Invention patent application withdrawn after publication
WW01 Invention patent application withdrawn after publication

Application publication date: 20180306