CN107740708A - A kind of constructing structure and its construction method of tunnel arch wall pin anti-seep water - Google Patents

A kind of constructing structure and its construction method of tunnel arch wall pin anti-seep water Download PDF

Info

Publication number
CN107740708A
CN107740708A CN201710772437.0A CN201710772437A CN107740708A CN 107740708 A CN107740708 A CN 107740708A CN 201710772437 A CN201710772437 A CN 201710772437A CN 107740708 A CN107740708 A CN 107740708A
Authority
CN
China
Prior art keywords
arch wall
tunnel
rhone
arch
transverse drain
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710772437.0A
Other languages
Chinese (zh)
Other versions
CN107740708B (en
Inventor
杜兴学
邓成华
杜忠民
骆洪伟
黎洪安
陈超
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Fourth Bureau Fifth Construction Engineering Co Ltd
Original Assignee
China Construction Fourth Bureau Fifth Construction Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Fourth Bureau Fifth Construction Engineering Co Ltd filed Critical China Construction Fourth Bureau Fifth Construction Engineering Co Ltd
Priority to CN201710772437.0A priority Critical patent/CN107740708B/en
Publication of CN107740708A publication Critical patent/CN107740708A/en
Application granted granted Critical
Publication of CN107740708B publication Critical patent/CN107740708B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F16/00Drainage
    • E21F16/02Drainage of tunnels
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention discloses a kind of constructing structure and its construction method of tunnel arch wall pin anti-seep water, including secondary lining and arch wall, the secondary lining is arranged on arch wall, filled provided with inverted arch the top of the secondary lining, the corner opening position of the arch wall is longitudinally provided with rhone, rubble loaded filter is provided with the notch of the rhone, the upper surface of the rubble loaded filter is provided with geotextiles, the longitudinal multiple transverse drains in the upper surface of inverted arch filling, and transverse drain is located at the side of rhone, the upper surface of the transverse drain is provided with bottom plate, the upper surface of the geotextiles is provided with rear pouring concrete, and rear pouring concrete is set with bottom plate flush.The present invention is simple in construction, and easy to operate, workable, construction technology is simple, and spot effect is obvious, and antiseep effect is preferable, and two lining structures influence the characteristics of small, cost-effective, achieve huge economic and social benefit.

Description

A kind of constructing structure and its construction method of tunnel arch wall pin anti-seep water
Technical field
The present invention relates to tunneling technique field, more particularly to a kind of constructing structure of tunnel arch wall pin anti-seep water and its apply Work method.
Background technology
At present, it is mechanical, existing with continuous improvement of the sustainable development and people of social and economic level to quality of life demand The development of generation technique, highway in China, railway, subway etc. is built and continued to bring out in the form of Tunnel Engineering, the construction of Tunnel Engineering Development for traffic plays positive facilitation, has obtained quick development, in tunnel water handling splash guard laying construction In, the design the defects of and construct it is insufficient due to, cause the water of splash guard behind most of directly under two backings are backward It is discharged at arch wall pin and leaks out, percolating water scene generally existing at tunnel arch wall pin, not only exists to construction quality The problem of very big, and huge economic loss is caused, negative effect is also result in flat image, therefore, it is proposed that The constructing structure of tunnel arch wall pin anti-seep water a kind of and its construction method solve the above problems.
The content of the invention
The invention aims to solve percolating water scene generally existing at tunnel arch wall pin in the prior art, not only The problem of very big be present to construction quality, and cause huge economic loss, negative effect is also result in flat image Problem, and the constructing structure and its construction method of a kind of tunnel arch wall pin anti-seep water proposed.
To achieve these goals, present invention employs following technical scheme:
A kind of constructing structure of tunnel arch wall pin anti-seep water, including secondary lining and arch wall, the secondary lining are set On arch wall, the top of the secondary lining is filled provided with inverted arch, and the corner opening position of the arch wall is longitudinally provided with rhone, institute State and rubble loaded filter is provided with the notch of rhone, the upper surface of the rubble loaded filter is provided with geotextiles, the inverted arch filling Upper surface longitudinally multiple transverse drains, and transverse drain is located at the side of rhone, the upper table of the transverse drain Face is provided with bottom plate, and the upper surface of the geotextiles is provided with rear pouring concrete, and rear pouring concrete is set with bottom plate flush, described The top of pouring concrete is provided with multiple cable troughs afterwards, and per two neighboring cable trough between be provided with gutter, the gutter and Rhone connection is set, and the one end of the transverse drain away from rhone is provided with center gutter, and transverse drain is with The connection of heart gutter is set.
Preferably, the edge of the rhone is less than or equal to the edge of cable trough.
Preferably, the thickness of the rubble loaded filter is 10-20cm.
Preferably, the distance between described transverse drain is 20-30m, and between transverse drain and inverted arch filling Horizontal slope is 2%.
Preferably, the thickness of the rear pouring concrete is 20cm.
Its construction method comprises the following steps:
S1, construction inverted arch are filled to designed elevation;
S2, the transverse drain for being longitudinally 2% every 20-30m installation horizontal slopes in inverted arch filling, and in arch wall placement of foot Locate the longitudinal drainage groove that installation form reserves 0.5m or so width, draining groove edge is no more than the edge of cable trough;
S3, pour tunnel floor concrete;
S4, Tunnel Second Lining concrete is installed, longitudinal drainage groove is formed in arch wall placement of foot;
S5, in the thick rubble loaded filters of longitudinal drainage trench bottom laying 10-20cm, rubble loaded filter and transverse drain it Between ensure it is unobstructed;
S6, geotextiles are laid on rubble loaded filter, prevent rear pouring concrete from penetrating into rubble loaded filter;
S7, the thick rear pouring concretes of 20cm are poured in geotextiles, it is overall and equal with bottom plate to be connected to form one with bottom plate Together;
S8, constructed on rear pouring concrete longitudinal cable trough and longitudinal drainage ditch.
The present invention it is simple in construction, it is easy to operate, tunnel waterproof and water drainage system construct when, change construction technology, take " with row be It is main, supplemented by stifled " principle, longitudinal drainage groove is set at gutter and cable trough lower arch foundation, and draining well width is 0.5m Left and right, the interior setting thickness of notch are 10-20cm rubble loaded filters, set one layer of geotextiles on loaded filter, prevent from oozing under concrete Block longitudinal drainage groove, pour in geotextiles the thick concrete of 20cm and with bottom plate flush, every 20- between bottom plate and inverted arch The transverse drain that 30m sets horizontal slope to be 2% is connected with rubble loaded filter, and the present invention efficiently solves oozes at tunnel arch wall pin The situation of leak, the quality management of constructing tunnel is strengthened, reduce later stage infiltration blocking construction processing after the completion of construction, add Drainpipe draining is smooth, water is smoothly discharged to center gutter.
Brief description of the drawings
Fig. 1 is that a kind of constructing structure of tunnel arch wall pin anti-seep water proposed by the present invention and its structure of construction method are shown It is intended to;
Fig. 2 is the structural representation in gutter.
In figure:1 secondary lining, the filling of 2 inverted arch, 3 rhones, 4 rubble loaded filters, 5 transverse drains, 6 geotextiles, 7 bottoms Pouring concrete, 9 cable troughs, 10 gutters, 11 center gutters, 12 arch walls behind plate, 8.
Embodiment
Below in conjunction with the accompanying drawing in the embodiment of the present invention, the technical scheme in the embodiment of the present invention is carried out clear, complete Site preparation describes, it is clear that described embodiment is only part of the embodiment of the present invention, rather than whole embodiments.
Reference picture 1-2, a kind of constructing structure of tunnel arch wall pin anti-seep water, including secondary lining 1 and arch wall 12, it is secondary Lining cutting 1 is arranged on arch wall 12, and the top of secondary lining 1 is provided with inverted arch filling 2, and the corner opening position of arch wall 12 is longitudinally provided with row Tank 3, the edge of rhone 3 are less than or equal to the edge of cable trough 9, and the water being easy in cable trough 9 is discharged in rhone 3, is arranged Rubble loaded filter 4 is provided with the notch of tank 3, the thickness of rubble loaded filter 4 is 10-20cm, strengthens anti-filter effect, and rubble is anti- The upper surface of filtering layer 4 is provided with geotextiles 6, the longitudinal multiple transverse drains 5 in the upper surface of inverted arch filling 2, between transverse drain 5 Distance be 20-30m, and the horizontal slope between transverse drain 5 and inverted arch filling 2 is 2%, the water being easy in transverse drain 5 It is discharged in gutter 10, and transverse drain 5 is located at the side of rhone 3, the upper surface of transverse drain 5 is provided with bottom plate 7, The upper surface of geotextiles 6 is provided with rear pouring concrete 8, and the thickness of rear pouring concrete 8 is 20cm, increases intensity, and rear pouring concrete 8 Set with the flush of bottom plate 7, the top of rear pouring concrete 8 is provided with multiple cable troughs 9, and is set between every two neighboring cable trough 9 There is gutter 10, gutter 10 connects setting with rhone 3, and the one end of transverse drain 5 away from rhone 3 is provided with center draining Ditch 11, and transverse drain 5 connects setting with center gutter 11.
The present invention it is simple in construction, it is easy to operate, tunnel waterproof and water drainage system construct when, change construction technology, take " with row be It is main, supplemented by stifled " principle, longitudinal drainage groove 3, the width of rhone 3 are set at gutter 10 and the lower arch foundation of cable trough 9 For 0.5m or so, the interior setting thickness of notch is 10-20cm rubbles loaded filter 4, sets one layer of geotextiles 6 on loaded filter, prevents from mixing Oozed under solidifying soil and block longitudinal drainage groove 3, poured in geotextiles 6 the thick concrete of 20cm and with the flush of bottom plate 7, bottom plate 7 is with facing upward It is connected between arch every the 20-30m transverse drains 5 for setting horizontal slope to be 2% with rubble loaded filter 4, the present invention efficiently solves The situation of percolating water at tunnel arch wall pin, the quality management of constructing tunnel is strengthened, reduce later stage infiltration leak stopping after the completion of construction Construction processing, the draining of transverse drain 5 smoothness is added, water is smoothly discharged to center gutter 11.
The foregoing is only a preferred embodiment of the present invention, but protection scope of the present invention be not limited thereto, Any one skilled in the art the invention discloses technical scope in, technique according to the invention scheme and its Inventive concept is subject to equivalent substitution or change, should all be included within the scope of the present invention.

Claims (6)

1. a kind of constructing structure of tunnel arch wall pin anti-seep water, including secondary lining (1) and arch wall (12), it is characterised in that The secondary lining (1) is arranged on arch wall (12), and the top of the secondary lining (1) is provided with inverted arch filling (2), the arch wall (12) corner opening position is longitudinally provided with rhone (3), and rubble loaded filter (4) is provided with the notch of the rhone (3), described The upper surface of rubble loaded filter (4) is provided with geotextiles (6), the longitudinal multiple transverse drains in the upper surface of the inverted arch filling (2) (5), and transverse drain (5) is located at the side of rhone (3), and the upper surface of the transverse drain (5) is provided with bottom plate (7), The upper surface of the geotextiles (6) is provided with rear pouring concrete (8), and rear pouring concrete (8) is set with bottom plate (7) flush, institute The top for stating rear pouring concrete (8) is provided with multiple cable troughs (9), and is provided with gutter between every two neighboring cable trough (9) (10), the gutter (10) connects setting with rhone (3), and the one end of the transverse drain (5) away from rhone (3) is set There is center gutter (11), and transverse drain (5) connects setting with center gutter (11).
A kind of 2. constructing structure of tunnel arch wall pin anti-seep water according to claim 1, it is characterised in that the draining The edge of groove (3) is less than or equal to the edge of cable trough (9).
A kind of 3. constructing structure of tunnel arch wall pin anti-seep water according to claim 1, it is characterised in that the rubble The thickness of loaded filter (4) is 10-20cm.
A kind of 4. constructing structure of tunnel arch wall pin anti-seep water according to claim 1, it is characterised in that the transverse direction The distance between drainpipe (5) is 20-30m, and the horizontal slope between transverse drain (5) and inverted arch filling (2) is 2%.
5. the constructing structure of a kind of tunnel arch wall pin anti-seep water according to claim 1, it is characterised in that poured after described The thickness of concrete (8) is 20cm.
A kind of 6. construction party of the constructing structure of the tunnel arch wall pin anti-seep water in 1-5 such as claim as described in any one Method, it is characterised in that comprise the following steps:
S1, construction inverted arch are filled to designed elevation;
S2, the transverse drain for being longitudinally 2% every 20-30m installation horizontal slopes in inverted arch filling, and pacify at arch wall placement of foot Decking reserves the longitudinal drainage groove of 0.5m or so width, and draining groove edge is no more than the edge of cable trough;
S3, pour tunnel floor concrete;
S4, Tunnel Second Lining concrete is installed, longitudinal drainage groove is formed in arch wall placement of foot;
S5, in the thick rubble loaded filters of longitudinal drainage trench bottom laying 10-20cm, protected between rubble loaded filter and transverse drain Demonstrate,prove unobstructed;
S6, geotextiles are laid on rubble loaded filter, prevent rear pouring concrete from penetrating into rubble loaded filter;
S7, the thick rear pouring concretes of 20cm are poured in geotextiles, with bottom plate be connected to form one it is overall and with bottom plate flush;
S8, constructed on rear pouring concrete longitudinal cable trough and longitudinal drainage ditch.
CN201710772437.0A 2017-08-31 2017-08-31 Construction structure and construction method for preventing leakage of tunnel arch wall foot Active CN107740708B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710772437.0A CN107740708B (en) 2017-08-31 2017-08-31 Construction structure and construction method for preventing leakage of tunnel arch wall foot

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710772437.0A CN107740708B (en) 2017-08-31 2017-08-31 Construction structure and construction method for preventing leakage of tunnel arch wall foot

Publications (2)

Publication Number Publication Date
CN107740708A true CN107740708A (en) 2018-02-27
CN107740708B CN107740708B (en) 2023-07-25

Family

ID=61235561

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710772437.0A Active CN107740708B (en) 2017-08-31 2017-08-31 Construction structure and construction method for preventing leakage of tunnel arch wall foot

Country Status (1)

Country Link
CN (1) CN107740708B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109779682A (en) * 2019-03-08 2019-05-21 中铁十九局集团第三工程有限公司 A kind of water abundant ground vcehicular tunnel gutter structural system
CN114673528A (en) * 2022-03-28 2022-06-28 中国电建集团成都勘测设计研究院有限公司 Tunnel top cavity supporting method
CN115491939A (en) * 2022-10-11 2022-12-20 宁夏大学 Be applied to fender drainage facility of permafrost region road

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5510038A (en) * 1993-02-17 1996-04-23 Wegmueller; Marcel C. Process for preventing the formation of deposits in a construction drainage system
JP2008045399A (en) * 2007-11-30 2008-02-28 Kcon Kk Tunnel structure composed of watchman's passage and water channel for road surface drainage channel in automobile tunnel
CN102434175A (en) * 2012-01-12 2012-05-02 中国市政工程西北设计研究院有限公司 Tunnel lining self waterproof drainage system
CN105840210A (en) * 2016-06-12 2016-08-10 中铁二院工程集团有限责任公司 Box type tunnel-bottom composite arched tunnel lining structure with water drain function
CN106640189A (en) * 2017-02-22 2017-05-10 西南交通大学 Pressure bearing tunnel bottom structure drainage system and construction method thereof
CN206386150U (en) * 2016-12-16 2017-08-08 中铁二院工程集团有限责任公司 A kind of Underground Subway Station draining and examination and repair system

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5510038A (en) * 1993-02-17 1996-04-23 Wegmueller; Marcel C. Process for preventing the formation of deposits in a construction drainage system
JP2008045399A (en) * 2007-11-30 2008-02-28 Kcon Kk Tunnel structure composed of watchman's passage and water channel for road surface drainage channel in automobile tunnel
CN102434175A (en) * 2012-01-12 2012-05-02 中国市政工程西北设计研究院有限公司 Tunnel lining self waterproof drainage system
CN105840210A (en) * 2016-06-12 2016-08-10 中铁二院工程集团有限责任公司 Box type tunnel-bottom composite arched tunnel lining structure with water drain function
CN206386150U (en) * 2016-12-16 2017-08-08 中铁二院工程集团有限责任公司 A kind of Underground Subway Station draining and examination and repair system
CN106640189A (en) * 2017-02-22 2017-05-10 西南交通大学 Pressure bearing tunnel bottom structure drainage system and construction method thereof

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109779682A (en) * 2019-03-08 2019-05-21 中铁十九局集团第三工程有限公司 A kind of water abundant ground vcehicular tunnel gutter structural system
CN109779682B (en) * 2019-03-08 2020-04-14 中铁十九局集团第三工程有限公司 Water-rich section highway tunnel escape canal structure system
CN114673528A (en) * 2022-03-28 2022-06-28 中国电建集团成都勘测设计研究院有限公司 Tunnel top cavity supporting method
CN114673528B (en) * 2022-03-28 2023-04-28 中国电建集团成都勘测设计研究院有限公司 Tunnel top cavity supporting method
CN115491939A (en) * 2022-10-11 2022-12-20 宁夏大学 Be applied to fender drainage facility of permafrost region road

Also Published As

Publication number Publication date
CN107740708B (en) 2023-07-25

Similar Documents

Publication Publication Date Title
CN104514216B (en) A kind of canal on embankment frost heaving resistant leakage preventing structure and construction method
CN104878783B (en) A kind of Super-long Basement concrete floor deformation joint anti-seepage and method for treating seepage
CN204343339U (en) A kind of temporary support columns waterproof base plate
CN107740708A (en) A kind of constructing structure and its construction method of tunnel arch wall pin anti-seep water
CN110847327B (en) Water-proof and drainage construction method for large-area basement roof
CN206298900U (en) A kind of diaphram wall built-in type steel encloses purlin plug system
CN110004991A (en) Underground structure anti-floating system and construction method based on raised type tangs plate
CN105714849A (en) Reverse construction method for adjacent high and low floors (bays) of basement
CN108678029A (en) A kind of hills rich water area basement guarded drainage construction method near a river
CN112459116A (en) Construction method for rebuilding basement bottom plate of existing building
CN104234089B (en) The construction method that a kind of basement guarded drainage combines
CN105672443B (en) Structure integrating anchoring of anti-seepage film, flood interception and passing
CN110306591A (en) A kind of base pit engineering exempts to set the construction method of the underground structure of temporary support
CN207145004U (en) A kind of constructing structure of tunnel arch wall pin anti-seep water
CN105862662A (en) Curved-edge arched wave prevention dam
CN106436721B (en) The construction method of diaphram wall built-in type steel purlin plug system
CN108729927A (en) A kind of existing tunnel reorganization and expansion is the mid-board construction method of multiple-arch tunnel
CN208899507U (en) Integral type gutter structure
CN107419811B (en) The method and its structure of basement bottom board support pile and drain hole waterproofing and leakage-stopping
CN105862664A (en) Water retaining dam
CN110295630A (en) The late poured band structure of multilayer constraint antiseep
CN209412844U (en) A kind of assembled resin concrete drainage ditch
CN109555141A (en) Strong drainage system for ultra-large deep foundation pit and construction method
CN210621879U (en) Steel construction vestibule drainage structures system
JP4410572B2 (en) Construction method of revetment for landfill

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant