CN107705013A - The delivery method and running scheduling platform of a kind of burning line rescue method - Google Patents

The delivery method and running scheduling platform of a kind of burning line rescue method Download PDF

Info

Publication number
CN107705013A
CN107705013A CN201710916982.2A CN201710916982A CN107705013A CN 107705013 A CN107705013 A CN 107705013A CN 201710916982 A CN201710916982 A CN 201710916982A CN 107705013 A CN107705013 A CN 107705013A
Authority
CN
China
Prior art keywords
mrow
msub
burning line
maintenance personnel
operation maintenance
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710916982.2A
Other languages
Chinese (zh)
Inventor
王丽山
简捷
李彬
李伟
郑涛
张伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
DONGGUAN XINAO GAS Co Ltd
Original Assignee
DONGGUAN XINAO GAS Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by DONGGUAN XINAO GAS Co Ltd filed Critical DONGGUAN XINAO GAS Co Ltd
Priority to CN201710916982.2A priority Critical patent/CN107705013A/en
Publication of CN107705013A publication Critical patent/CN107705013A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06311Scheduling, planning or task assignment for a person or group
    • G06Q10/063114Status monitoring or status determination for a person or group
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/20Administration of product repair or maintenance
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Economics (AREA)
  • Strategic Management (AREA)
  • Theoretical Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Marketing (AREA)
  • General Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • Tourism & Hospitality (AREA)
  • Quality & Reliability (AREA)
  • Health & Medical Sciences (AREA)
  • Operations Research (AREA)
  • Public Health (AREA)
  • Primary Health Care (AREA)
  • Water Supply & Treatment (AREA)
  • General Health & Medical Sciences (AREA)
  • Development Economics (AREA)
  • Educational Administration (AREA)
  • Game Theory and Decision Science (AREA)
  • Feeding And Controlling Fuel (AREA)

Abstract

The invention provides a kind of delivery method of burning line rescue method and running scheduling platform, this method to include:Obtain at least one failure burning line equipment;According to the fault type of each failure burning line equipment, rescue measure corresponding to the failure burning line equipment is determined;According to the quantity of the failure burning line equipment, and the quantity of the operation maintenance personnel corresponding to each failure burning line equipment needed for rescue measure is performed, determine the quantity of operation maintenance personnel;According to the rescue measure determined and the quantity of the operation maintenance personnel, rescue method corresponding to generation, and issue the rescue method.This programme can improve the treatment effeciency of burning line failure.

Description

The delivery method and running scheduling platform of a kind of burning line rescue method
Technical field
The present invention relates to field of computer technology, the delivery method of more particularly to a kind of burning line rescue method and operation Dispatching platform.
Background technology
Gas pipeline be by the combustion gas such as natural gas, manufactured gas, manufactured fuel gas, liquefied petroleum gas and biogas from exploitation ground or processing Factory is conveyed to urban gas center or the pipeline of user, ensures work and life of the normal work of gas pipeline to guarantee resident It is significant.
At present, gas pipeline administrative department would generally arrange operation maintenance personnel to carry out regular visit and maintenance to gas pipeline, In the process, because operation maintenance personnel is difficult to prejudge the fault type of burning line appearance, therefore phase can not be pre-established The maintenance measure answered, and corresponding maintenance tool is carried, so as to easily cause the troubleshooting to burning line not prompt enough.
The content of the invention
The embodiments of the invention provide a kind of delivery method of burning line rescue method and running scheduling platform, can improve The treatment effeciency of burning line failure.
In a first aspect, the embodiments of the invention provide a kind of delivery method of burning line rescue method, applied to operation Dispatching platform, including:
Obtain at least one failure burning line equipment;
According to the fault type of each failure burning line equipment, determine that the failure burning line equipment is corresponding Rescue measure;
According to the quantity of the failure burning line equipment, and perform corresponding to each failure burning line equipment The quantity of operation maintenance personnel needed for rescue measure, determine the quantity of operation maintenance personnel;
According to the rescue measure determined and the quantity of the operation maintenance personnel, rescue method corresponding to generation, and Issue the rescue method.
Preferably,
Further comprise:At least two monitoring nodes are determined on burning line to be managed, and in each monitoring Monitoring sensor is set on node;
At least one failure burning line equipment of acquisition, including:
Often pass through a monitoring cycle set in advance, saved using each each monitoring of monitoring sensor collection The running parameter of point;
For the adjacent monitoring node of any two at least two monitoring node, it is determined that adjacent positioned at two respectively The first monitoring sensor and the second monitoring sensor on monitoring node;
The first pipeline pressure value for being included according to the described first running parameter for collecting of monitoring sensor and the One fuel gas temperature value, and the second pipe pressure value that the running parameter that collects of the second monitoring sensor includes With the second fuel gas temperature value, the Gas Pipe between described two adjacent monitoring nodes is calculated by following first calculation formula The gas flow of line segment;
First calculation formula includes:
Wherein, the Q characterizes the gas flow of the Gas Pipe line segment between described two adjacent monitoring nodes, described D characterizes the internal diameter in the Gas Pipe line segment middle pipe road, and the L characterizes the length of the Gas Pipe line segment, and the λ characterizes the combustion The frictional resistant coefficient in tracheae line segment middle pipe road, the ρ characterize the density of combustion gas in normal conditions, the T0Combustion gas is characterized to exist Temperature under standard state, the P1Characterize the first pipeline pressure value, the P2Characterize the second pipe pressure value, institute State T1Characterize the first fuel gas temperature value, the T2Characterize the second fuel gas temperature value;
According to the gas flow positioned at each Gas Pipe line segment between the adjacent monitoring node, from described The failure burning line equipment is determined at least one burning line equipment that burning line to be managed includes.
Preferably,
It is described to issue the rescue method, including:
For failure burning line equipment each described, it is performed both by:
According to the positional information of the failure burning line equipment, alternative area is determined;Wherein, the failure burning line Equipment is the center of the alternative area;
At least one target operation maintenance personnel is determined from the alternative area;Wherein it is determined that the target O&M people gone out The quantity of member is identical with the quantity of the operation maintenance personnel needed for rescue measure corresponding to the failure burning line equipment;
The rescue method is handed down to each target operation maintenance personnel determined.
Preferably,
It is described to determine at least one target operation maintenance personnel from the alternative area, including:
At least one alternative operation maintenance personnel is determined in the alternative area, and determines each described alternative operation maintenance personnel Positional information;
Believed according to the position of the positional information of each alternative operation maintenance personnel and the failure burning line equipment Breath, determine each described alternative the distance between operation maintenance personnel and the failure burning line equipment;
According to each alternative the distance between the operation maintenance personnel and the failure burning line equipment, it is determined that it is described at least One target operation maintenance personnel.
Preferably,
It is described according to each described alternative positional information of operation maintenance personnel and the position of the failure burning line equipment Confidence ceases, and determines each described alternative the distance between operation maintenance personnel and the failure burning line equipment, including:
Determine the entry location information and exits location information of the failure burning line equipment;
According to the entry location information and exits location information determined, using following second calculation formula, calculate Each described alternative the distance between operation maintenance personnel and the failure burning line equipment:
Wherein, S characterizes alternative the distance between the operation maintenance personnel and the failure burning line equipment, the failure combustion The entry location information of gas pipeline equipment is (x1, y1, z1), the exits location information of the failure burning line equipment is (x2, y2, z2), the positional information of the alternative operation maintenance personnel is (x0, y0, z0)。
Second aspect, the embodiments of the invention provide a kind of running scheduling platform, including:Faulty equipment acquiring unit, really Order member and rescue method issuance unit;Wherein,
The faulty equipment acquiring unit, for obtaining at least one failure burning line equipment;
The determining unit, for the fault type according to each failure burning line equipment, determine the event Hinder rescue measure corresponding to burning line equipment, and according to the quantity of the failure burning line equipment, and perform each institute The quantity of the operation maintenance personnel corresponding to failure burning line equipment needed for rescue measure is stated, determines the quantity of operation maintenance personnel;
The rescue method issuance unit, for according to the rescue measure determined and the number of the operation maintenance personnel Amount, rescue method corresponding to generation, and issue the rescue method.
Preferably,
The faulty equipment acquiring unit, including collection subelement, sensor determination subelement, computation subunit and failure Equipment determination subelement;Wherein,
The collection subelement, for often passing through a monitoring cycle set in advance, adopted using each monitoring sensor Collect the running parameter of at least two monitoring nodes on burning line to be managed;Wherein, each described monitoring node is set State monitoring sensor;
The sensor determination subelement, for for the adjacent monitoring of any two at least two monitoring node Node, it is determined that the first monitoring sensor on two adjacent monitoring nodes and the second monitoring sensor respectively;
The computation subunit, what the running parameter for being collected according to the described first monitoring sensor included Wrapped in first pipeline pressure value and the first fuel gas temperature value, and the running parameter that collects of the second monitoring sensor The second pipe pressure value and the second fuel gas temperature value included, described two adjacent monitorings are calculated by following first calculation formula and saved The gas flow of the Gas Pipe line segment between point;
First calculation formula includes:
Wherein, the Q characterizes the gas flow of the Gas Pipe line segment between described two adjacent monitoring nodes, described D characterizes the internal diameter in the Gas Pipe line segment middle pipe road, and the L characterizes the length of the Gas Pipe line segment, and the λ characterizes the combustion The frictional resistant coefficient in tracheae line segment middle pipe road, the ρ characterize the density of combustion gas in normal conditions, the T0Combustion gas is characterized to exist Temperature under standard state, the P1Characterize the first pipeline pressure value, the P2Characterize the second pipe pressure value, institute State T1Characterize the first fuel gas temperature value, the T2Characterize the second fuel gas temperature value;
The faulty equipment determination subelement, it is located at each combustion gas between the adjacent monitoring node for basis The gas flow of line sections, determine at least one burning line equipment included from the burning line to be managed described in Failure burning line equipment.
Preferably,
The rescue method issuance unit, for for failure burning line equipment each described, being performed both by:According to institute The positional information of failure burning line equipment is stated, determines alternative area;Wherein, the failure burning line equipment is described alternative The center in region;At least one target operation maintenance personnel is determined from the alternative area;Wherein it is determined that the target O&M gone out The quantity of personnel is identical with the quantity of the operation maintenance personnel needed for rescue measure corresponding to the failure burning line equipment;By described in Rescue method is handed down to each target operation maintenance personnel determined.
Preferably,
The rescue method issuance unit, for determining at least one alternative operation maintenance personnel in the alternative area, and Determine the positional information of each alternative operation maintenance personnel;According to positional information of each alternative operation maintenance personnel and The positional information of the failure burning line equipment, determine that each described alternative operation maintenance personnel is set with the failure burning line It is the distance between standby;According to each alternative the distance between the operation maintenance personnel and the failure burning line equipment, institute is determined State at least one target operation maintenance personnel.
Preferably,
The rescue method issuance unit, for determining entry location information and the outlet of the failure burning line equipment Positional information;According to the entry location information and exits location information determined, using following second calculation formula, calculate Each described alternative the distance between operation maintenance personnel and the failure burning line equipment:
Wherein, S characterizes alternative the distance between the operation maintenance personnel and the failure burning line equipment, the failure combustion The entry location information of gas pipeline equipment is (x1, y1, z1), the exits location information of the failure burning line equipment is (x2, y2, z2), the positional information of the alternative operation maintenance personnel is (x0, y0, z0)。
The embodiments of the invention provide a kind of delivery method of burning line rescue method and running scheduling platform, according to obtaining In at least one failure burning line equipment got, the fault type of each failure burning line equipment, respectively determine with The corresponding rescue measure of each failure burning line equipment, and according to needed for performing each rescue measure operation maintenance personnel quantity And the total quantity of failure burning line equipment, it is determined that the quantity of required operation maintenance personnel, and according to determining rescue measure and fortune The quantity of dimension personnel, rescue measure corresponding to generation, and issue the rescue measure of generation.Thus, by actively generating rescue party Case, operation maintenance personnel can be made to have been recognized that corresponding rescue measure before fault in-situ is reached, be convenient for carrying corresponding maintenance workers Tool, consequently facilitating being safeguarded in time to failure burning line equipment, improve the treatment effeciency of burning line failure.
Brief description of the drawings
In order to illustrate more clearly about the embodiment of the present invention or technical scheme of the prior art, below will be to embodiment or existing There is the required accompanying drawing used in technology description to be briefly described, it should be apparent that, drawings in the following description are the present invention Some embodiments, for those of ordinary skill in the art, on the premise of not paying creative work, can also basis These accompanying drawings obtain other accompanying drawings.
Fig. 1 is a kind of flow chart of the delivery method for burning line rescue method that one embodiment of the invention provides;
Fig. 2 is a kind of flow chart of the delivery method for burning line rescue method that another embodiment of the present invention provides;
Fig. 3 is a kind of structural representation for running scheduling platform that one embodiment of the invention provides;
Fig. 4 is a kind of structural representation for running scheduling platform that another embodiment of the present invention provides.
Embodiment
To make the purpose, technical scheme and advantage of the embodiment of the present invention clearer, below in conjunction with the embodiment of the present invention In accompanying drawing, the technical scheme in the embodiment of the present invention is clearly and completely described, it is clear that described embodiment is Part of the embodiment of the present invention, rather than whole embodiments, based on the embodiment in the present invention, those of ordinary skill in the art The every other embodiment obtained on the premise of creative work is not made, belongs to the scope of protection of the invention.
As shown in figure 1, the embodiments of the invention provide a kind of delivery method of burning line rescue method, applied to operation Dispatching platform, this method may comprise steps of:
Step 101:Obtain at least one failure burning line equipment;
Step 102:According to the fault type of each failure burning line equipment, the failure burning line is determined Rescue measure corresponding to equipment;
Step 103:According to the quantity of the failure burning line equipment, and perform each failure burning line and set The quantity of operation maintenance personnel needed for standby corresponding rescue measure, determine the quantity of operation maintenance personnel;
Step 104:According to the rescue measure determined and the quantity of the operation maintenance personnel, corresponding rescue is generated Scheme, and issue the rescue method.
In above-described embodiment, according at least one failure burning line equipment got, each failure Gas Pipe The fault type of line equipment, the rescue measure corresponding with each failure burning line equipment is determined respectively, and it is every according to performing The total quantity of the quantity of operation maintenance personnel and failure burning line equipment needed for individual rescue measure, it is determined that the number of required operation maintenance personnel Amount, and according to the quantity for determining rescue measure and operation maintenance personnel, rescue measure corresponding to generation, and the rescue for issuing generation is arranged Apply.Thus, by actively generating rescue method, operation maintenance personnel can be made to have been recognized that corresponding rescue before fault in-situ is reached Measure, corresponding maintenance tool is convenient for carrying, consequently facilitating being safeguarded in time to failure burning line equipment, improves Gas Pipe The treatment effeciency of line failure.
In embodiments of the present invention, this method may further include:At least two are determined on burning line to be managed Monitoring node, and monitoring sensor is set on each described monitoring node;
The embodiment of step 101, it can include:
Often pass through a monitoring cycle set in advance, saved using each each monitoring of monitoring sensor collection The running parameter of point;
For the adjacent monitoring node of any two at least two monitoring node, it is determined that adjacent positioned at two respectively The first monitoring sensor and the second monitoring sensor on monitoring node;
The first pipeline pressure value for being included according to the described first running parameter for collecting of monitoring sensor and the One fuel gas temperature value, and the second pipe pressure value that the running parameter that collects of the second monitoring sensor includes With the second fuel gas temperature value, the Gas Pipe between described two adjacent monitoring nodes is calculated by following first calculation formula The gas flow of line segment;
First calculation formula includes:
Wherein, the Q characterizes the gas flow of the Gas Pipe line segment between described two adjacent monitoring nodes, described D characterizes the internal diameter in the Gas Pipe line segment middle pipe road, and the L characterizes the length of the Gas Pipe line segment, and the λ characterizes the combustion The frictional resistant coefficient in tracheae line segment middle pipe road, the ρ characterize the density of combustion gas in normal conditions, the T0Combustion gas is characterized to exist Temperature under standard state, the P1Characterize the first pipeline pressure value, the P2Characterize the second pipe pressure value, institute State T1Characterize the first fuel gas temperature value, the T2Characterize the second fuel gas temperature value;
According to the gas flow positioned at each Gas Pipe line segment between the adjacent monitoring node, from described The failure burning line equipment is determined at least one burning line equipment that burning line to be managed includes.
For example, a burning line to be managed is divided into five sections, then 6 monitoring sections is shared on this burning line Point, monitoring sensor is provided with each monitoring node, often by a monitoring cycle, for example, often passing through 1min, Ge Gejian Survey the running parameter that sensor gathers each node.For each section of Gas Pipe line segment on the burning line to be managed, it two The monitoring sensor at end is two adjacent monitoring sensors, and the two neighboring monitoring according to corresponding to every section of Gas Pipe line segment passes The pipeline pressure value and fuel gas temperature value that sensor collects respectively, the combustion gas of each Gas Pipe line segment is accurately calculated by formula Flow, then according to the gas flow of each Gas Pipe line segment calculated, it is determined that the burning line equipment that is out of order.
For example, five sections of Gas Pipe line segments on burning line to be managed are respectively A, B, C, D and E, wherein, combustion gas is from A to E Conveying, the gas flow of each section of Gas Pipe line segment calculated are respectively a, b, c, d and e, wherein, a and b meet default combustion gas Flow standard values, the difference between c and gas flow standard value is maximum, and d takes second place, the difference between e and gas flow standard value Minimum, it follows that the Gas Pipe line segment to break down should be in Gas Pipe line segment C, and Gas Pipe line segment D and E gas flow Difference is due to that Gas Pipe line segment C failure causes, therefore Gas Pipe line segment D and E gas flow difference are compared with Gas Pipe line segment C Difference it is small.It is determined that break down Gas Pipe line segment be Gas Pipe line segment C after, then can be from Gas Pipe line segment C Each burning line equipment in determine to be out of order burning line equipment, wherein, failure burning line equipment can be valve, mend Repay device, condenser cylinder, exhaust stack, force (forcing) pump or pipeline etc..
Thus, by each monitoring sensor automatic data collection running parameter being arranged on monitoring node, and without O&M Personnel carry out regular visit, so as to improve the efficiency for determining failure burning line equipment, determine the burning line that is out of order in time Equipment.Also, the gas flow of each Gas Pipe line segment is accurately calculated by calculation formula, further according to the combustion gas stream calculated Amount determines failure gas pipeline, is advantageous to accurately have and investigates failure burning line equipment, consequently facilitating corresponding to accurately making Rescue measure, further improve the treatment effeciency of burning line failure.
In one embodiment of the invention, the embodiment of step 104, it can include:For failure each described Burning line equipment, is performed both by:
According to the positional information of the failure burning line equipment, alternative area is determined;Wherein, the failure burning line Equipment is the center of the alternative area;
At least one target operation maintenance personnel is determined from the alternative area;Wherein it is determined that the target O&M people gone out The quantity of member is identical with the quantity of the operation maintenance personnel needed for rescue measure corresponding to the failure burning line equipment;
The rescue method is handed down to each target operation maintenance personnel determined.
For example, centered on failure burning line equipment, the border circular areas that radius is 10m is marked, as candidate area Domain, it then can determine to perform the target operation maintenance personnel needed for rescue method from the alternative area marked.Selection target O&M It during personnel, can randomly choose, can also be selected according to the distance between each operation maintenance personnel and failure burning line equipment, can also root Selected according to the professional ability of each operation maintenance personnel in alternative area.Thus, centered on failure burning line equipment, it is determined that Corresponding alternative area, then target operation maintenance personnel is determined from alternative area, it is easy to the selection to target O&M, so as to favourable In the execution of rescue method, to handle in time and preferably the failure of burning line.
It is described to determine at least one target operation maintenance personnel from the alternative area in one embodiment of the invention, including:
At least one alternative operation maintenance personnel is determined in the alternative area, and determines each described alternative operation maintenance personnel Positional information;
Believed according to the position of the positional information of each alternative operation maintenance personnel and the failure burning line equipment Breath, determine each described alternative the distance between operation maintenance personnel and the failure burning line equipment;
According to each alternative the distance between the operation maintenance personnel and the failure burning line equipment, it is determined that it is described at least One target operation maintenance personnel.
In the present embodiment, can be determined each according to the positional information of the alternative operation maintenance personnel of each in alternative area Individual alternative the distance between operation maintenance personnel and failure burning line equipment, then according to the distance calculated, chosen distance failure The nearest alternative operation maintenance personnel of burning line equipment is as the target operation maintenance personnel for performing rescue method.
In the process, in order to accurately determine it is each it is alternative between operation maintenance personnel and failure burning line equipment away from From can first determine that the entry location information and exits location information for the burning line equipment that is out of order, enter further according to what is determined Mouth positional information and exits location information, using formula is calculated as below, calculate each alternative operation maintenance personnel and failure Gas Pipe The distance between line equipment:
Wherein, S characterizes alternative the distance between the operation maintenance personnel and the failure burning line equipment, the failure combustion The entry location information of gas pipeline equipment is (x1, y1, z1), the exits location information of the failure burning line equipment is (x2, y2, z2), the positional information of the alternative operation maintenance personnel is (x0, y0, z0).Thus, selection and failure burning line equipment are apart from most Near operation maintenance personnel is advantageous to each target operation maintenance personnel and releases failure in time as the target operation maintenance personnel for performing rescue method The failure of burning line equipment, further improve the treatment effeciency of burning line failure.
As shown in Fig. 2 the embodiments of the invention provide a kind of delivery method of burning line rescue method, this method can be with Comprise the following steps:
Step 201:At least two monitoring nodes are determined on burning line to be managed, and in each monitoring node It is upper that monitoring sensor is set.
For example, a burning line to be managed is divided into five sections, then 6 monitoring nodes are shared on this burning line, Monitoring sensor is provided with each monitoring node.
Step 202:Often pass through a monitoring cycle set in advance, each institute is gathered using each monitoring sensor The running parameter of monitoring node is stated, for the adjacent monitoring node of any two at least two monitoring node, it is determined that point The first monitoring sensor and the second monitoring sensor that Wei Yu be on two adjacent monitoring nodes.
Step 203:The first pipeline pressure that the running parameter collected according to the described first monitoring sensor includes Force value and the first fuel gas temperature value, and the second pipe that the running parameter that collects of the second monitoring sensor includes Road pressure value and the second fuel gas temperature value, calculate the combustion gas stream of the Gas Pipe line segment between described two adjacent monitoring nodes Amount.
Herein, it is for each section of Gas Pipe line segment on burning line to be managed, the monitoring sensor at its both ends Two adjacent monitoring sensors, the pipe that the two neighboring monitoring sensor according to corresponding to every section of Gas Pipe line segment collects respectively Road pressure value, the gas flow of each Gas Pipe line segment is accurately calculated by formula, then according to each combustion gas calculated The gas flow of line sections, it is determined that the burning line equipment that is out of order.Specifically, each Gas Pipe can be calculated by below equation The gas flow of line segment,Wherein, between the described two adjacent monitoring nodes of the Q signs The Gas Pipe line segment gas flow, the d characterizes the internal diameter in the Gas Pipe line segment middle pipe road, described in the L is characterized The length of Gas Pipe line segment, the λ characterize the frictional resistant coefficient in the Gas Pipe line segment middle pipe road, and the ρ characterizes combustion gas and existed Density under standard state, the T0Characterize the temperature of combustion gas in normal conditions, the P1Characterize first pipeline pressure Value, the P2Characterize the second pipe pressure value, the T1Characterize the first fuel gas temperature value, the T2Characterize described Two fuel gas temperature values.
Step 204:According to the combustion gas stream positioned at each Gas Pipe line segment between the adjacent monitoring node Measure, the failure burning line equipment is determined at least one burning line equipment included from the burning line to be managed.
For example, five sections of Gas Pipe line segments on burning line to be managed are respectively A, B, C, D and E, wherein, combustion gas is from A to E Conveying, the gas flow of each section of Gas Pipe line segment calculated are respectively a, b, c, d and e, wherein, a and b meet default combustion gas Flow standard values, the difference between c and gas flow standard value is maximum, and d takes second place, the difference between e and gas flow standard value Minimum, it follows that the Gas Pipe line segment to break down should be in Gas Pipe line segment C, and Gas Pipe line segment D and E gas flow Difference is due to that Gas Pipe line segment C failure causes, therefore Gas Pipe line segment D and E gas flow difference are compared with Gas Pipe line segment C Difference it is small.It is determined that break down Gas Pipe line segment be Gas Pipe line segment C after, then can be from Gas Pipe line segment C Each burning line equipment in determine to be out of order burning line equipment, wherein, failure burning line equipment can be valve, mend Repay device, condenser cylinder, exhaust stack, force (forcing) pump or pipeline etc..
Step 205:According to the fault type of each failure burning line equipment, the failure burning line is determined Rescue measure corresponding to equipment, according to the quantity of the failure burning line equipment, and perform each failure Gas Pipe The quantity of operation maintenance personnel corresponding to line equipment needed for rescue measure, the quantity of operation maintenance personnel is determined, and according to the institute determined State the quantity of rescue measure and the operation maintenance personnel, rescue method corresponding to generation.
For example, the fault type of burning line equipment of determining to be out of order is pressure anomaly, then can speculate be probably valve or The equipment such as person's force (forcing) pump break down, if fault type is Traffic Anomaly, can speculate to be probably that the equipment such as pipeline break down, Specifically, Parameters variation corresponding to each fault type can be embodied by the failure summary sheet pre-set, actual true , can be by the failure summary sheet when determining failure burning line equipment., can be pre- for rescuing measure corresponding to each fault type First enumerated in measure statistical form is rescued, and rescue measure statistical form is stored, then when determining fault type, Corresponding rescue measure can be determined by rescuing measure statistical form.Determining that each failure burning line equipment is right respectively After the rescue measure answered, it may be determined that go out the operation maintenance personnel needed for each rescue measure, further according to the total of failure burning line equipment Amount, the total quantity of operation maintenance personnel can be calculated.Then arranged according to the total quantity of the operation maintenance personnel calculated and corresponding rescue Apply, corresponding rescue method can be generated.
Step 206:For failure burning line equipment each described, it is performed both by:Set according to the failure burning line Standby positional information, determines alternative area;Wherein, the failure burning line equipment is the center of the alternative area.
For example, centered on failure burning line equipment, the border circular areas that radius is 10m is marked, as candidate area Domain.
Step 207:At least one alternative operation maintenance personnel is determined in the alternative area, and determines that each is described alternative The positional information of operation maintenance personnel, set according to the positional information of each alternative operation maintenance personnel and the failure burning line Standby positional information, determine each described alternative the distance between operation maintenance personnel and the failure burning line equipment.
In order to accurately determine each alternative the distance between operation maintenance personnel and failure burning line equipment, can first determine that The entry location information and exits location information for the burning line equipment that is out of order, further according to the entry location information determined and go out Mouthful positional information, using formula is calculated as below, calculate between each alternative operation maintenance personnel and failure burning line equipment away from From:Wherein, S characterizes the alternative O&M The distance between personnel and the failure burning line equipment, the entry location information of the failure burning line equipment is (x1, y1, z1), the exits location information of the failure burning line equipment is (x2, y2, z2), the position letter of the alternative operation maintenance personnel Cease for (x0, y0, z0)。
Step 208:According to each alternative the distance between the operation maintenance personnel and the failure burning line equipment, it is determined that At least one target operation maintenance personnel, wherein it is determined that the quantity for the target operation maintenance personnel haveing is set with the failure burning line The quantity of operation maintenance personnel needed for standby corresponding rescue measure is identical.
Step 209:Rescue method is handed down to each the target operation maintenance personnel determined.
After distance between the alternative operation maintenance personnel of each in calculating alternative area and failure burning line equipment, The nearest alternative operation maintenance personnel of distance fault burning line equipment may be selected as the target operation maintenance personnel for performing rescue method, will Rescue method is handed down to these closest target operation maintenance personnels, is advantageous to each target operation maintenance personnel and releases failure combustion in time The failure of gas pipeline equipment.
As shown in figure 3, the embodiments of the invention provide a kind of running scheduling platform, including:Faulty equipment acquiring unit 301st, determining unit 302 and rescue method issuance unit 303;Wherein,
The faulty equipment acquiring unit 301, for obtaining at least one failure burning line equipment;
The determining unit 302, for the fault type according to each failure burning line equipment, it is determined that described Rescue measure corresponding to failure burning line equipment, and according to the quantity of the failure burning line equipment, and perform each The quantity of operation maintenance personnel corresponding to the failure burning line equipment needed for rescue measure, determine the quantity of operation maintenance personnel;
The rescue method issuance unit 303, for according to the rescue measure and the operation maintenance personnel determined Quantity, rescue method corresponding to generation, and issue the rescue method.
As shown in figure 4, in one embodiment of the invention, the faulty equipment acquiring unit 301, including collection subelement 3011st, sensor determination subelement 3012, computation subunit 3013 and faulty equipment determination subelement 3014;Wherein,
The collection subelement 3011, for often passing through a monitoring cycle set in advance, sensed using each monitoring Device gathers the running parameter of at least two monitoring nodes on burning line to be managed;Wherein, each described monitoring node is set There is the monitoring sensor;
The sensor determination subelement 3012, for adjacent for any two at least two monitoring node Monitoring node, it is determined that the first monitoring sensor on two adjacent monitoring nodes and the second monitoring sensor respectively;
The computation subunit 3013, for being wrapped according in the described first running parameter for collecting of monitoring sensor The the first pipeline pressure value and the first fuel gas temperature value included, and the running parameter that the second monitoring sensor collects The second pipe pressure value and the second fuel gas temperature value included, described two adjacent prisons are calculated by following first calculation formula The gas flow for the Gas Pipe line segment surveyed between node;
First calculation formula includes:
Wherein, the Q characterizes the gas flow of the Gas Pipe line segment between described two adjacent monitoring nodes, described D characterizes the internal diameter in the Gas Pipe line segment middle pipe road, and the L characterizes the length of the Gas Pipe line segment, and the λ characterizes the combustion The frictional resistant coefficient in tracheae line segment middle pipe road, the ρ characterize the density of combustion gas in normal conditions, the T0Combustion gas is characterized to exist Temperature under standard state, the P1Characterize the first pipeline pressure value, the P2Characterize the second pipe pressure value, institute State T1Characterize the first fuel gas temperature value, the T2Characterize the second fuel gas temperature value;
The faulty equipment determination subelement 3014, for according to positioned at each to described between the adjacent monitoring node The gas flow of Gas Pipe line segment, determine at least one burning line equipment included from the burning line to be managed The failure burning line equipment.
In one embodiment of the invention, the rescue method issuance unit 303, for for failure combustion gas each described Line equipment, it is performed both by:According to the positional information of the failure burning line equipment, alternative area is determined;Wherein, the failure Burning line equipment is the center of the alternative area;At least one target operation maintenance personnel is determined from the alternative area;Its In, the fortune needed for the quantity rescue measure corresponding with the failure burning line equipment for the target operation maintenance personnel determined The quantity of dimension personnel is identical;The rescue method is handed down to each target operation maintenance personnel determined.
In one embodiment of the invention, the rescue method issuance unit 303, for determined in the alternative area to A few alternative operation maintenance personnel, and determine the positional information of each alternative operation maintenance personnel;It is described alternative according to each The positional information of the positional information of operation maintenance personnel and the failure burning line equipment, determine each described alternative O&M people The distance between member and the failure burning line equipment;According to each alternative operation maintenance personnel and the failure burning line The distance between equipment, determine at least one target operation maintenance personnel.
In one embodiment of the invention, the rescue method issuance unit 303, for determining that the failure burning line is set Standby entry location information and exits location information;According to the entry location information and exits location information determined, profit With following second calculation formula, calculate each it is described it is alternative between operation maintenance personnel and the failure burning line equipment away from From:
Wherein, S characterizes alternative the distance between the operation maintenance personnel and the failure burning line equipment, the failure combustion The entry location information of gas pipeline equipment is (x1, y1, z1), the exits location information of the failure burning line equipment for (x2, Y2, z2), the positional information of the alternative operation maintenance personnel is (x0, y0, z0).
The contents such as the information exchange between each unit, implementation procedure in said apparatus, due to implementing with the inventive method Example is based on same design, and particular content can be found in the narration in the inventive method embodiment, and here is omitted.
The embodiment of the present invention additionally provides a kind of computer-readable recording medium, including execute instruction, when the processor of storage control is held During the row execute instruction, the storage control performs the method that any of the above-described embodiment of the present invention provides.
The embodiment of the present invention additionally provides a kind of storage control, including:Processor, memory and bus;The storage Device is used to store execute instruction, and the processor is connected with the memory by the bus, when the storage control is transported During row, the execute instruction of memory storage described in the computing device, so that the storage control performs the present invention The method that any of the above-described embodiment provides.
In summary, the more than present invention each embodiment at least has the advantages that:
1st, in embodiments of the present invention, according at least one failure burning line equipment got, each failure The fault type of burning line equipment, the determination rescue measure corresponding with each failure burning line equipment respectively, and according to The total quantity of the quantity of operation maintenance personnel and failure burning line equipment needed for each rescue measure is performed, it is determined that required O&M people The quantity of member, and according to the quantity for determining rescue measure and operation maintenance personnel, rescue measure corresponding to generation, and issue generation Rescue measure.Thus, by actively generating rescue method, operation maintenance personnel can be made before fault in-situ is reached, had been recognized that corresponding Rescue measure, be convenient for carrying corresponding maintenance tool, consequently facilitating safeguarded in time to failure burning line equipment, improve The treatment effeciency of burning line failure.
2nd, in embodiments of the present invention, at least two monitoring nodes are determined on burning line to be managed, and at each Monitoring sensor is set on monitoring node, it is then determined that the first monitoring sensor and the gone out on the adjacent monitoring node of any two Two monitoring sensors, the pipeline pressure value and fuel gas temperature value collected respectively using the two monitoring sensors determined, are led to The gas flow that formula accurately calculates each Gas Pipe line segment is crossed, then according to the combustion gas of each Gas Pipe line segment calculated Flow, it is determined that the burning line equipment that is out of order.Thus, each monitoring sensor automatic data collection by being arranged on monitoring node Running parameter, and regular visit is carried out without operation maintenance personnel, so as to improve the efficiency for determining failure burning line equipment, in time It is determined that the burning line equipment that is out of order.Also, the gas flow of each Gas Pipe line segment is accurately calculated by calculation formula, then Gas flow according to calculating determines failure gas pipeline, is advantageous to accurately have and investigates failure burning line equipment, so as to just In the treatment effeciency of rescue measure corresponding to accurate make, further raising burning line failure.
3rd, in embodiments of the present invention, according to the positional information of failure burning line equipment, determine with failure Gas Pipe Alternative area centered on line equipment, and determine the alternative operation maintenance personnel of each in alternative area and failure burning line equipment it Between distance, according to the distance determined, the nearest operation maintenance personnel of chosen distance failure burning line equipment is as performing rescue The target operation maintenance personnel of scheme, so as to be advantageous to the execution of rescue method, to handle in time and preferably the event of burning line Barrier, further improve the treatment effeciency of burning line failure.
It should be noted that herein, such as first and second etc relational terms are used merely to an entity Or operation makes a distinction with another entity or operation, and not necessarily require or imply and exist between these entities or operation Any this actual relation or order.Moreover, term " comprising ", "comprising" or its any other variant be intended to it is non- It is exclusive to include, so that process, method, article or equipment including a series of elements not only include those key elements, But also the other element including being not expressly set out, or also include solid by this process, method, article or equipment Some key elements.In the absence of more restrictions, the key element limited by sentence " including one ", is not arranged Except other identical factor in the process including the key element, method, article or equipment being also present.
One of ordinary skill in the art will appreciate that:Realizing all or part of step of above method embodiment can pass through Programmed instruction related hardware is completed, and foregoing program can be stored in computer-readable storage medium, the program Upon execution, the step of execution includes above method embodiment;And foregoing storage medium includes:ROM, RAM, magnetic disc or light Disk etc. is various can be with the medium of store program codes.
It is last it should be noted that:Presently preferred embodiments of the present invention is the foregoing is only, is merely to illustrate the skill of the present invention Art scheme, is not intended to limit the scope of the present invention.Any modification for being made within the spirit and principles of the invention, Equivalent substitution, improvement etc., are all contained in protection scope of the present invention.

Claims (10)

  1. A kind of 1. delivery method of burning line rescue method, it is characterised in that applied to running scheduling platform, including:
    Obtain at least one failure burning line equipment;
    According to the fault type of each failure burning line equipment, determine to rescue corresponding to the failure burning line equipment Help measure;
    According to the quantity of the failure burning line equipment, and perform and rescued corresponding to each failure burning line equipment The quantity of operation maintenance personnel needed for measure, determine the quantity of operation maintenance personnel;
    According to the rescue measure determined and the quantity of the operation maintenance personnel, rescue method corresponding to generation, and issue The rescue method.
  2. 2. according to the method described in right 1, it is characterised in that
    Further comprise:At least two monitoring nodes are determined on burning line to be managed, and in each monitoring node It is upper that monitoring sensor is set;
    At least one failure burning line equipment of acquisition, including:
    Often pass through a monitoring cycle set in advance, each monitoring node is gathered using each monitoring sensor Running parameter;
    For the adjacent monitoring node of any two at least two monitoring node, it is determined that being located at two adjacent monitorings respectively The first monitoring sensor and the second monitoring sensor on node;
    The the first pipeline pressure value and the first combustion that the running parameter collected according to the described first monitoring sensor includes Temperature value, and the second pipe pressure value that includes of the running parameter that collects of the second monitoring sensor and the Two fuel gas temperature values, the Gas Pipe line segment between described two adjacent monitoring nodes is calculated by following first calculation formula Gas flow;
    First calculation formula includes:
    <mrow> <mi>Q</mi> <mo>=</mo> <msqrt> <mrow> <mfrac> <mrow> <mrow> <mo>|</mo> <mrow> <msub> <mi>P</mi> <mn>1</mn> </msub> <mo>-</mo> <msub> <mi>P</mi> <mn>2</mn> </msub> </mrow> <mo>|</mo> </mrow> <mo>&amp;CenterDot;</mo> <msup> <mi>d</mi> <mn>5</mn> </msup> <mo>&amp;CenterDot;</mo> <msub> <mi>T</mi> <mn>0</mn> </msub> </mrow> <mrow> <mi>L</mi> <mo>&amp;CenterDot;</mo> <mi>&amp;lambda;</mi> <mo>&amp;CenterDot;</mo> <mi>&amp;rho;</mi> </mrow> </mfrac> <mo>&amp;CenterDot;</mo> <mfrac> <mn>2</mn> <mrow> <msub> <mi>T</mi> <mn>1</mn> </msub> <mo>+</mo> <msub> <mi>T</mi> <mn>2</mn> </msub> </mrow> </mfrac> </mrow> </msqrt> </mrow>
    Wherein, the Q characterizes the gas flow of the Gas Pipe line segment between described two adjacent monitoring nodes, the d tables The internal diameter in the Gas Pipe line segment middle pipe road is levied, the L characterizes the length of the Gas Pipe line segment, and the λ characterizes the combustion gas The frictional resistant coefficient of pipeline in line sections, the ρ characterize the density of combustion gas in normal conditions, the T0Combustion gas is characterized to mark Temperature under quasi- state, the P1Characterize the first pipeline pressure value, the P2The second pipe pressure value is characterized, it is described T1Characterize the first fuel gas temperature value, the T2Characterize the second fuel gas temperature value;
    According to the gas flow positioned at each Gas Pipe line segment between the adjacent monitoring node, pipe is treated from described The failure burning line equipment is determined at least one burning line equipment that reason burning line includes.
  3. 3. according to the method for claim 1, it is characterised in that
    It is described to issue the rescue method, including:
    For failure burning line equipment each described, it is performed both by:
    According to the positional information of the failure burning line equipment, alternative area is determined;Wherein, the failure burning line equipment For the center of the alternative area;
    At least one target operation maintenance personnel is determined from the alternative area;Wherein it is determined that the target operation maintenance personnel gone out Quantity is identical with the quantity of the operation maintenance personnel needed for rescue measure corresponding to the failure burning line equipment;
    The rescue method is handed down to each target operation maintenance personnel determined.
  4. 4. according to the method for claim 3, it is characterised in that
    It is described to determine at least one target operation maintenance personnel from the alternative area, including:
    At least one alternative operation maintenance personnel is determined in the alternative area, and determines the position of each alternative operation maintenance personnel Confidence ceases;
    According to each the alternative positional information of operation maintenance personnel and the positional information of the failure burning line equipment, really Fixed each described alternative the distance between operation maintenance personnel and the failure burning line equipment;
    According to each alternative the distance between the operation maintenance personnel and the failure burning line equipment, determine described at least one Target operation maintenance personnel.
  5. 5. according to the method for claim 4, it is characterised in that
    It is described to be believed according to the positional information of each alternative operation maintenance personnel and the position of the failure burning line equipment Breath, each described alternative the distance between operation maintenance personnel and the failure burning line equipment are determined, including:
    Determine the entry location information and exits location information of the failure burning line equipment;
    According to the entry location information and exits location information determined, using following second calculation formula, calculate each Individual alternative the distance between the operation maintenance personnel and the failure burning line equipment:
    <mrow> <mi>S</mi> <mo>=</mo> <msqrt> <mrow> <msup> <mrow> <mo>(</mo> <msub> <mi>x</mi> <mn>0</mn> </msub> <mo>-</mo> <mfrac> <mrow> <msub> <mi>x</mi> <mn>1</mn> </msub> <mo>+</mo> <msub> <mi>x</mi> <mn>2</mn> </msub> </mrow> <mn>2</mn> </mfrac> <mo>)</mo> </mrow> <mn>2</mn> </msup> <mo>+</mo> <msup> <mrow> <mo>(</mo> <msub> <mi>y</mi> <mn>0</mn> </msub> <mo>-</mo> <mfrac> <mrow> <msub> <mi>y</mi> <mn>1</mn> </msub> <mo>+</mo> <msub> <mi>y</mi> <mn>2</mn> </msub> </mrow> <mn>2</mn> </mfrac> <mo>)</mo> </mrow> <mn>2</mn> </msup> <mo>+</mo> <msup> <mrow> <mo>(</mo> <msub> <mi>z</mi> <mn>0</mn> </msub> <mo>-</mo> <mfrac> <mrow> <msub> <mi>z</mi> <mn>1</mn> </msub> <mo>+</mo> <msub> <mi>z</mi> <mn>2</mn> </msub> </mrow> <mn>2</mn> </mfrac> <mo>)</mo> </mrow> <mn>2</mn> </msup> </mrow> </msqrt> </mrow>
    Wherein, S characterizes alternative the distance between the operation maintenance personnel and the failure burning line equipment, the failure Gas Pipe The entry location information of line equipment is (x1, y1, z1), the exits location information of the failure burning line equipment is (x2, y2, z2), the positional information of the alternative operation maintenance personnel is (x0, y0, z0)。
  6. A kind of 6. running scheduling platform, it is characterised in that including:Under faulty equipment acquiring unit, determining unit and rescue method Bill member;Wherein,
    The faulty equipment acquiring unit, for obtaining at least one failure burning line equipment;
    The determining unit, for the fault type according to each failure burning line equipment, determine the failure combustion Rescue measure corresponding to gas pipeline equipment, and according to the quantity of the failure burning line equipment, and perform each event Hinder the quantity of the operation maintenance personnel corresponding to burning line equipment needed for rescue measure, determine the quantity of operation maintenance personnel;
    The rescue method issuance unit, the rescue measure determined for basis and the quantity of the operation maintenance personnel, Rescue method corresponding to generation, and issue the rescue method.
  7. 7. running scheduling platform according to claim 6, it is characterised in that
    The faulty equipment acquiring unit, including collection subelement, sensor determination subelement, computation subunit and faulty equipment Determination subelement;Wherein,
    The collection subelement, for often passing through a monitoring cycle set in advance, treated using each monitoring sensor collection Manage the running parameter of at least two monitoring nodes on burning line;Wherein, each described monitoring node is provided with the prison Survey sensor;
    The sensor determination subelement, for being saved for the adjacent monitoring of any two at least two monitoring node Point, it is determined that the first monitoring sensor on two adjacent monitoring nodes and the second monitoring sensor respectively;
    The computation subunit, for included according to the described first running parameter for collecting of monitoring sensor first Pipeline pressure value and the first fuel gas temperature value, and the running parameter that collects of the second monitoring sensor include Second pipe pressure value and the second fuel gas temperature value, by following first calculation formula calculate described two adjacent monitoring nodes it Between the Gas Pipe line segment gas flow;
    First calculation formula includes:
    <mrow> <mi>Q</mi> <mo>=</mo> <msqrt> <mrow> <mfrac> <mrow> <mrow> <mo>|</mo> <mrow> <msub> <mi>P</mi> <mn>1</mn> </msub> <mo>-</mo> <msub> <mi>P</mi> <mn>2</mn> </msub> </mrow> <mo>|</mo> </mrow> <mo>&amp;CenterDot;</mo> <msup> <mi>d</mi> <mn>5</mn> </msup> <mo>&amp;CenterDot;</mo> <msub> <mi>T</mi> <mn>0</mn> </msub> </mrow> <mrow> <mi>L</mi> <mo>&amp;CenterDot;</mo> <mi>&amp;lambda;</mi> <mo>&amp;CenterDot;</mo> <mi>&amp;rho;</mi> </mrow> </mfrac> <mo>&amp;CenterDot;</mo> <mfrac> <mn>2</mn> <mrow> <msub> <mi>T</mi> <mn>1</mn> </msub> <mo>+</mo> <msub> <mi>T</mi> <mn>2</mn> </msub> </mrow> </mfrac> </mrow> </msqrt> </mrow>
    Wherein, the Q characterizes the gas flow of the Gas Pipe line segment between described two adjacent monitoring nodes, the d tables The internal diameter in the Gas Pipe line segment middle pipe road is levied, the L characterizes the length of the Gas Pipe line segment, and the λ characterizes the combustion gas The frictional resistant coefficient of pipeline in line sections, the ρ characterize the density of combustion gas in normal conditions, the T0Combustion gas is characterized to mark Temperature under quasi- state, the P1Characterize the first pipeline pressure value, the P2The second pipe pressure value is characterized, it is described T1Characterize the first fuel gas temperature value, the T2Characterize the second fuel gas temperature value;
    The faulty equipment determination subelement, it is located at each burning line between the adjacent monitoring node for basis The gas flow of section, the failure is determined at least one burning line equipment included from the burning line to be managed Burning line equipment.
  8. 8. running scheduling platform according to claim 6, it is characterised in that
    The rescue method issuance unit, for for failure burning line equipment each described, being performed both by:According to the event Hinder the positional information of burning line equipment, determine alternative area;Wherein, the failure burning line equipment is the alternative area Center;At least one target operation maintenance personnel is determined from the alternative area;Wherein it is determined that the target operation maintenance personnel gone out Quantity it is identical with the quantity of the operation maintenance personnel needed for rescue measure corresponding to the failure burning line equipment;By the rescue Scheme is handed down to each target operation maintenance personnel determined.
  9. 9. running scheduling platform according to claim 8, it is characterised in that
    The rescue method issuance unit, for determining at least one alternative operation maintenance personnel in the alternative area, and determine The positional information of each alternative operation maintenance personnel;According to positional information of each alternative operation maintenance personnel and described The positional information of failure burning line equipment, determine each described alternative operation maintenance personnel and the failure burning line equipment it Between distance;According to each alternative the distance between the operation maintenance personnel and the failure burning line equipment, it is determined that it is described extremely A few target operation maintenance personnel.
  10. 10. running scheduling platform according to claim 9, it is characterised in that
    The rescue method issuance unit, for determining entry location information and the outlet port of the failure burning line equipment Information;According to the entry location information and exits location information determined, using following second calculation formula, calculate each Individual alternative the distance between the operation maintenance personnel and the failure burning line equipment:
    <mrow> <mi>S</mi> <mo>=</mo> <msqrt> <mrow> <msup> <mrow> <mo>(</mo> <msub> <mi>x</mi> <mn>0</mn> </msub> <mo>-</mo> <mfrac> <mrow> <msub> <mi>x</mi> <mn>1</mn> </msub> <mo>+</mo> <msub> <mi>x</mi> <mn>2</mn> </msub> </mrow> <mn>2</mn> </mfrac> <mo>)</mo> </mrow> <mn>2</mn> </msup> <mo>+</mo> <msup> <mrow> <mo>(</mo> <msub> <mi>y</mi> <mn>0</mn> </msub> <mo>-</mo> <mfrac> <mrow> <msub> <mi>y</mi> <mn>1</mn> </msub> <mo>+</mo> <msub> <mi>y</mi> <mn>2</mn> </msub> </mrow> <mn>2</mn> </mfrac> <mo>)</mo> </mrow> <mn>2</mn> </msup> <mo>+</mo> <msup> <mrow> <mo>(</mo> <msub> <mi>z</mi> <mn>0</mn> </msub> <mo>-</mo> <mfrac> <mrow> <msub> <mi>z</mi> <mn>1</mn> </msub> <mo>+</mo> <msub> <mi>z</mi> <mn>2</mn> </msub> </mrow> <mn>2</mn> </mfrac> <mo>)</mo> </mrow> <mn>2</mn> </msup> </mrow> </msqrt> </mrow>
    Wherein, S characterizes alternative the distance between the operation maintenance personnel and the failure burning line equipment, the failure Gas Pipe The entry location information of line equipment is (x1, y1, z1), the exits location information of the failure burning line equipment is (x2, y2, z2), the positional information of the alternative operation maintenance personnel is (x0, y0, z0)。
CN201710916982.2A 2017-09-30 2017-09-30 The delivery method and running scheduling platform of a kind of burning line rescue method Pending CN107705013A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710916982.2A CN107705013A (en) 2017-09-30 2017-09-30 The delivery method and running scheduling platform of a kind of burning line rescue method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710916982.2A CN107705013A (en) 2017-09-30 2017-09-30 The delivery method and running scheduling platform of a kind of burning line rescue method

Publications (1)

Publication Number Publication Date
CN107705013A true CN107705013A (en) 2018-02-16

Family

ID=61183987

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710916982.2A Pending CN107705013A (en) 2017-09-30 2017-09-30 The delivery method and running scheduling platform of a kind of burning line rescue method

Country Status (1)

Country Link
CN (1) CN107705013A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112381379A (en) * 2020-11-11 2021-02-19 深圳市元征科技股份有限公司 Traffic accident processing method and device and electronic equipment
CN112990883A (en) * 2021-04-22 2021-06-18 神彩科技股份有限公司 Waste liquid treatment method and device, electronic equipment and storage medium
CN115358432A (en) * 2022-10-14 2022-11-18 成都秦川物联网科技股份有限公司 Gas meter metering fault determination method for intelligent gas and Internet of things system

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106599201A (en) * 2016-12-15 2017-04-26 河海大学常州校区 Full life circle management method of gas transmission and distribution equipment
CN107067163A (en) * 2017-03-24 2017-08-18 青岛海信网络科技股份有限公司 A kind of breakdown maintenance work dispatching method and device
CN107101087A (en) * 2017-03-22 2017-08-29 北京航空航天大学 City gas pipeline system pipeline fault propagation impact evaluation method and system

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106599201A (en) * 2016-12-15 2017-04-26 河海大学常州校区 Full life circle management method of gas transmission and distribution equipment
CN107101087A (en) * 2017-03-22 2017-08-29 北京航空航天大学 City gas pipeline system pipeline fault propagation impact evaluation method and system
CN107067163A (en) * 2017-03-24 2017-08-18 青岛海信网络科技股份有限公司 A kind of breakdown maintenance work dispatching method and device

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
戴慎志: "《城市基础设施工程规划手册》", 29 February 2000 *
赵欧: "《燃气管网快速抢修技术的研发与应用》", 《低碳世界》 *
韩克顺等: "《燃气管网泄漏检测***的数值模拟》", 《煤气与热力》 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112381379A (en) * 2020-11-11 2021-02-19 深圳市元征科技股份有限公司 Traffic accident processing method and device and electronic equipment
CN112990883A (en) * 2021-04-22 2021-06-18 神彩科技股份有限公司 Waste liquid treatment method and device, electronic equipment and storage medium
CN115358432A (en) * 2022-10-14 2022-11-18 成都秦川物联网科技股份有限公司 Gas meter metering fault determination method for intelligent gas and Internet of things system
US11861567B2 (en) 2022-10-14 2024-01-02 Chengdu Qinchuan Iot Technology Co., Ltd. Method and internet of things system for determining gas meter measurement failure of smart gas

Similar Documents

Publication Publication Date Title
CN107705013A (en) The delivery method and running scheduling platform of a kind of burning line rescue method
CN104202329B (en) Ddos attack detection method and device
CN104808634B (en) A kind of thermal power plant&#39;s Visualized management system based on virtual reality
Shibano Assessing audit risk from errors and irregularities
CN102444885B (en) Method for avoiding overheat tube burst in tubular boiler of power station boiler
CN103635910B (en) For the automatic identification of the operating parameter in power plant
EP2520994A2 (en) Automated system and method for implementing statistical comparison of power plant operations
CN105205569B (en) State of fan gear box online evaluation method for establishing model and online evaluation method
CN107606489A (en) A kind of burning line management method, apparatus and system
US20140316737A1 (en) Method for monitoring inside-boiler dynamic wall temperature of power plant boiler high-temperature piping system
CN106249728A (en) A kind of thermal power generation unit on-line performance monitoring method based on characteristics of components
CN103080956A (en) Sensor system, computer, and instrument
CN106022710A (en) Insurance check method and apparatus
CN109242279A (en) A kind of appraisal procedure and server
CN108564284A (en) Gas detector addressing computational methods based on costs and benefits
CN108881326A (en) Determine method, system, medium and the equipment of exception of network traffic behavior
CN106198749A (en) A kind of data fusion method of multiple sensor based on Metal Crack monitoring
CN104408831B (en) Monitoring method and device for state of bank self-service equipment
CN111666652A (en) Steam heating network steam trap inspection emission operation scheduling method and operation scheduling system
WO2012120530A1 (en) A system and method for monitoring green house gas related data of an entity
CN107657764A (en) Finance self-help terminal and deposit, continuous deposit, withdraw the money, clear method
CN107357941A (en) A kind of system and method that watermark protocol data can be tested in real time
CN112508359A (en) Equipment management system and method
CN112489194A (en) Method and system for displaying account information and boiler four-tube information in three-dimensional scene
CN106224931B (en) The determination methods of the built-in waste heat boiler water leakage of sintering machine large flue

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20180216