CN107700336A - A kind of determination method of Main Girder of Concrete Cable-stayed Bridge construction stage Shear Lag - Google Patents

A kind of determination method of Main Girder of Concrete Cable-stayed Bridge construction stage Shear Lag Download PDF

Info

Publication number
CN107700336A
CN107700336A CN201710993245.2A CN201710993245A CN107700336A CN 107700336 A CN107700336 A CN 107700336A CN 201710993245 A CN201710993245 A CN 201710993245A CN 107700336 A CN107700336 A CN 107700336A
Authority
CN
China
Prior art keywords
shear lag
point
force application
beam section
cable
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710993245.2A
Other languages
Chinese (zh)
Inventor
李艳凤
姜满宏
于欢
全伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenyang Jianzhu University
Original Assignee
Shenyang Jianzhu University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenyang Jianzhu University filed Critical Shenyang Jianzhu University
Priority to CN201710993245.2A priority Critical patent/CN107700336A/en
Publication of CN107700336A publication Critical patent/CN107700336A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D11/00Suspension or cable-stayed bridges
    • E01D11/04Cable-stayed bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • E01D21/10Cantilevered erection
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/10Geometric CAD
    • G06F30/13Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Geometry (AREA)
  • General Physics & Mathematics (AREA)
  • Computer Hardware Design (AREA)
  • Theoretical Computer Science (AREA)
  • Computational Mathematics (AREA)
  • Mathematical Analysis (AREA)
  • Mathematical Optimization (AREA)
  • Pure & Applied Mathematics (AREA)
  • Evolutionary Computation (AREA)
  • General Engineering & Computer Science (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The present invention provides a kind of determination method of Main Girder of Concrete Cable-stayed Bridge construction stage Shear Lag, is related to technical field of bridge engineering.A kind of determination method of Main Girder of Concrete Cable-stayed Bridge construction stage Shear Lag, at cantilever end rope point of force application, with the shear lag coefficient λ of axle power effectNReflect the actual loading situation of the point;Beam section between Suo Li, at rope point of force application, reflect the actual loading situation of the point than the shear lag coefficient λ of determination according to moment of flexure axle power;The beam section of span centre between rope point of force application, with the shear lag coefficient λ of MomentMReflect the actual loading situation of the point, the beam section between rope point of force application and span centre, the stagnant coefficient of section shear is tried to achieve using linear interpolation.The determination method of Main Girder of Concrete Cable-stayed Bridge construction stage Shear Lag provided by the invention, the problem of being difficult to accurate description Cable-Stayed Bridge Structure loading characteristic because of the single effective flange width definition of code requirement is avoided, has further ensured the safety of stayed-cable bridge structure system.

Description

A kind of determination method of Main Girder of Concrete Cable-stayed Bridge construction stage Shear Lag
Technical field
The present invention relates to technical field of bridge engineering, more particularly to a kind of Main Girder of Concrete Cable-stayed Bridge construction stage Shear Lag Determination method.
Background technology
Main Girder of Concrete Cable-stayed Bridge refers mainly to box section, in bridge structure design, due to the shearing of web plates of box girders Flange plate transfer lag is flowed to, so that there is shear lageffect for flange plate.Stress inhomogeneous caused by shear lageffect Design work that can be to box beam brings adverse effect, if not accounting for the effect of Shear Lag, it is possible to it is irretrievable to occur some Consequence.Especially for this complicated structural system of cable-stayed bridge, with the propulsion of construction stage, structure in work progress System constantly changes, after the completion of folding structures and suspension cable whole tensioning, the geometry linear of cable-stayed bridge bridge completion state and Internal force situation is changed.
The structural internal force of cable-stayed bridge is a complicated space problem, in the case of uneven loading, torsion, abnormal be present The effects such as change so that force analysis is more complicated, and carrying out analysis with general box beam computational theory has certain difficulty.At present The method of edge of a wing developed width is replaced to consider influence of the Shear Lag to box beam, Bridges in Our Country specification rule using effective width in engineering Determine the computational methods clause to the specific structure effective width such as simply supported beam, continuous beam and cantilever beam, but not clearly to oblique pull The regulation of bridge design.It is also no to be applied to cable-stayed bridge although external specification has detailed regulation to Flange Effective Distribution Width The provision of girder.
The content of the invention
The defects of for prior art, the present invention provide a kind of determination of Main Girder of Concrete Cable-stayed Bridge construction stage Shear Lag Method, determine the shear lag coefficient that Main Girder of Concrete Cable-stayed Bridge construction stage diverse location should be taken.
A kind of determination method of Main Girder of Concrete Cable-stayed Bridge construction stage Shear Lag, comprises the following steps:
Step 1, determine Shear Lag at two cantilever end rope points of force application of cable-stayed bridge;
The shear lag coefficient λ acted at two cantilever end rope points of force application of cable-stayed bridge with axle powerNReflect the reality of the point Stressing conditions and Shear Lag, the computational methods of Shear Lag as caused by axle power are shown below at this:
Wherein, λNFor shear lag coefficient, σ caused by axle power at stayed-cable bridge cantilever end cable force application pointNFor stayed-cable bridge cantilever end Actual direct stress caused by axle power at rope point of force application,For name caused by axle power at stayed-cable bridge cantilever end cable force application point just Stress;
Step 2, the Shear Lag for determining beam section between Suo Li;
Step 2.1:Determine the Shear Lag at the rope point of force application of beam section between Suo Li;
Reflect the reality of the point between Suo Li at the rope point of force application of beam section than the shear lag coefficient λ of determination with moment of flexure and axle power The Shear Lag of border stressing conditions and the point, the computational methods of Shear Lag are shown below at the point:
Wherein, shear lag coefficients of the λ between Suo Li at the rope point of force application of beam section, the Suo Li of σ beam sections between Suo Li Actual stress at application point,Nominal stress between Suo Li at the rope point of force application of beam section, actual stress σ should with name PowerIt is the superposition of corresponding direct stress caused by moment of flexure and axle power, λN′Axle power is produced at beam section rope point of force application between Suo Li Raw shear lag coefficient, λM′Shear lag coefficient caused by moment of flexure, M, N are respectively beam section at beam section rope point of force application between Suo Li Moment of flexure and axle power suffered by section,Wherein, y be the girder section centre of form to the distance of upper lower edge, A is girder section face Product, I is girder section the moment of inertia;
Step 2.2:Determine the Shear Lag of span centre beam section at half between rope point of force application;
The span centre beam section at half between rope point of force application, with the shear lag coefficient λ of MomentMReflect the point Actual loading situation and Shear Lag, the computational methods of Shear Lag are as follows at the point:
Wherein, λMShear lag coefficient, σ caused by the moment of flexure of span centre beam section at half between rope point of force applicationMFor rope Actual direct stress caused by the moment of flexure of span centre beam section at half between point of force application,Two points between rope point of force application One of nominal direct stress caused by the moment of flexure of place's span centre beam section;
Step 2.3:Determine the Shear Lag between rope point of force application and span centre beam section;
Shear Lag between rope point of force application and span centre beam section, by the Shear Lag of the rope point of force application of beam section between Suo Li Between coefficient lambda and rope point of force application at half span centre beam section shear lag coefficient λMBetween using linear interpolation try to achieve should The shear lag coefficient reflection in beam section section.
As shown from the above technical solution, the beneficial effects of the present invention are:A kind of concrete deck cable stayed bridge provided by the invention The determination method of main girder construction stage Shear Lag, in single cable plane P C Cable-Stayed Bridges, difference is taken in different positions Shear lag coefficient carry out plane finite bar elements analysis, avoid the single effective flange width of code requirement and define Shear Lag Coefficient, the loading characteristic of Cable-Stayed Bridge Structure is accurately described, make stayed-cable bridge structure system safe.
Brief description of the drawings
Fig. 1 is the elevation of cable-stayed bridge provided in an embodiment of the present invention;
Fig. 2 is the cross-sectional view of cable-stayed bridge main-beam provided in an embodiment of the present invention;
Fig. 3 is stayed-cable bridge cantilever provided in an embodiment of the present invention construction schematic diagram;
Fig. 4 is the bending moment diagram of girder at No. 4 bridge piers of cable-stayed bridge provided in an embodiment of the present invention;
Fig. 5 is the axial force diagram of girder at No. 4 bridge piers of cable-stayed bridge provided in an embodiment of the present invention.
In figure:1st, suspension cable;2nd, bridge king-tower;3rd, girder;4th, No. 4 bridge piers;5th, No. 5 bridge piers;6th, middle room;7th, side room;8th, hang Arm plate;9th, median ventral plate;10th, side web;11st, middle room upper limb;12nd, middle room lower edge.
Embodiment
With reference to the accompanying drawings and examples, the embodiment of the present invention is described in further detail.Implement below Example is used to illustrate the present invention, but is not limited to the scope of the present invention.
The embodiment of the present invention describes the construction stage by taking certain single plane cable stayed bridge prestressed concrete box shape girder bridge as an example The determination method of bridge diverse location Shear Lag.The main bridge of certain bridge is single cable plane prestressed concrete oblique pull used by the present embodiment Bridge, as shown in figure 1, suspension cable 1 uses zinc coated high strength steel silk, 15 pairs are arranged on each king-tower, full-bridge totally 120.Bridge king-tower 2 is adopted To be poured into a mould with C50 concrete, box section, bridge floor above tower height 67.5m, king-tower knuckle is located at bridge floor above 33.9m, wherein under Duan Tashen is 75 ° with horizontal plane angle, and epimere tower body and hypomere tower body angle are 7.5 °.The main a length of 420m of bridge, span setting are 89m+242m+89m.Girder 3 is single Room of case three, deck-molding 3.414m.Rope is away from being arranged as mid-span rope away from for 14 × 7.4m on girder 3; End bay rope away from except pygochord area be 1.5m+1.5m+5.75m+7.0m in addition to, remaining is 10 × 6.3m.At No. 4 bridge piers 4 for tower, beam, The affixed system of pier, for tower beam is affixed, beam pier separation system at No. 5 bridge piers 5.Mid-span and the structure of end bay as shown in Fig. 2 its In, mid-span each several part size is:Both sides room 7 upper limb thickness 25cm, the middle upper limb thickness 40cm of room 6, lower edge thickness 30cm, side web 10 are thick 25cm, 9 thick 40cm of median ventral plate, the length of cantilever slab 8 are 5m;End bay each several part size is:The upper limb thickness 40cm of both sides room 7, on middle room 6 Edge thickness 50cm, lower edge thickness 40cm, 9 thick 50cm of median ventral plate, 10 thick 30cm of side web, the length of cantilever slab 8 are 5m.
When the present embodiment uses cantilever construction as shown in Figure 3 under typical condition, girder section upper limb shear lag coefficient edge is vertical To the distribution situation of total length, carry out the shear lageffect in labor Construction of Cable-Stayed Bridges middle girder section.
A kind of determination method of Main Girder of Concrete Cable-stayed Bridge construction stage Shear Lag, specifically includes herein below:
Step 1, determine Shear Lag at two cantilever end rope points of force application of cable-stayed bridge;
The shear lag coefficient λ acted at two cantilever end rope points of force application of cable-stayed bridge with axle powerNReflect the reality of the point Stressing conditions and Shear Lag, the computational methods of Shear Lag as caused by axle power are shown below at this:
Wherein, λNFor shear lag coefficient, σ caused by axle power at stayed-cable bridge cantilever end cable force application pointNFor stayed-cable bridge cantilever end Actual direct stress caused by axle power at rope point of force application,For name caused by axle power at stayed-cable bridge cantilever end cable force application point just Stress;
In the present embodiment, according to《Highway reinforced concrete and prestressed concrete bridge contain design specification》4.2.3 take girder Section top flange top plate effective width is 4.00m, and lower flange bottom plate tunneling boring participates in calculating, and obtains stayed-cable bridge cantilever end cable force work With at actual direct stress caused by axle powerWith axle at stayed-cable bridge cantilever end cable force application point Nominal direct stress caused by powerWherein N be Suo Li axial thrust load, AEffectivelyFor cable-stayed bridge main-beam Effective cross-sectional area, AEntirelyFor cable-stayed bridge main-beam area of section.Two cantilever end rope point of force application C4 of cable-stayed bridge finally are calculated Shear lag coefficient with C4 ' places is
Step 2, the Shear Lag for determining beam section between Suo Li;
Step 2.1:Determine the Shear Lag at the rope point of force application of beam section between Suo Li;
Reflect the reality of the point between Suo Li at the rope point of force application of beam section than the shear lag coefficient λ of determination with moment of flexure and axle power The Shear Lag of border stressing conditions and the point, the computational methods of Shear Lag are shown below at the point:
Wherein, shear lag coefficients of the λ between Suo Li at the rope point of force application of beam section, the Suo Li of σ beam sections between Suo Li Actual stress at application point,Nominal stress between Suo Li at the rope point of force application of beam section, actual stress σ should with name PowerIt is the superposition of direct stress caused by moment of flexure and axle power;
Shear lag coefficient caused by moment of flexure is λ at beam section rope point of force application between definition Suo LiM′, Shear Lag caused by axle power Coefficient is λN′, the shear lag coefficient after superposition is λ, then has:
Wherein,WithNominal direct stress, σ caused by axle power and moment of flexure respectively at rope point of force applicationN′And σM′Respectively For actual direct stress caused by axle power at rope point of force application and moment of flexure, the shear lag coefficient of nominal direct stress corresponding thereto is multiplied Product be actual direct stress;
Above formula right-hand member molecule denominator simultaneously divided byThen
Wherein,Then:
OrderThen
Wherein, y is the girder section centre of form to the distance of upper lower edge, and A is girder section area, and I is girder section the moment of inertia, M, N is respectively the moment of flexure and axle power suffered by beam section section.
In the present embodiment, the distance y=1.09 of the girder section centre of form to upper limb, girder section area A=22.9, girder are cut Face the moment of inertia I=26.5,According to《Highway reinforced concrete and prestressed concrete bridge contain design specification》 4.2.3, calculate at rope point of force application caused by axle power during shear lag coefficient, girder section top flange top plate effective width is 4.00m, lower flange bottom plate tunneling boring participate in calculating, and obtain actual direct stress caused by axle power and name at rope point of force application and just should Power is respectivelyWherein, N ' is rope point of force application Locate Suo Li axial thrust load, AEffectivelyFor girder effective cross-sectional area, AEntirelyFor girder section area, axle power at rope point of force application is obtained Caused shear lag coefficient λN′=2.62.Caused by calculated bending moment during shear lag coefficient, top flange top plate effective width is 24m, is obtained Actual direct stress caused by moment of flexure and nominal direct stress are respectively at rope point of force application Wherein, M ' be rope point of force application at moment of flexure, WEffectivelyFor the effective bending resistant section mould of girder Amount, WEntirelyFor girder module of anti-bending section, shear lag coefficient λ caused by moment of flexure at rope point of force application is obtainedM′=1.17.
The present embodiment uses the full-bridge plane bar mechanism model that finite element software is established, the moment of flexure and axle of operating mode lower girder of constructing The internal force diagram of power, the internal force diagram result difference of 4# bridge piers and 5# bridge pier girders is smaller, only extracts the internal force diagram of girder at 4# bridge piers, 4# bridge pier axial force diagrams shown in the bending moment diagram and Fig. 5 of 4# bridge piers as shown in Figure 4.According to Suo Lisuo points of force application in Fig. 4 and Fig. 5 The axle power and moment of flexure at place obtain, rope point of force application C3 '~C1 ' places girder section moment of flexure axle power ratioRespectively:1.49、1.59、 1.64, substitute into formula
It is respectively 1.77,1.75,1.74 to obtain girder section upper limb shear lag coefficient λ at C3 '~C1 ' Suo Li;
Girder section moment of flexure axle power ratio at rope point of force application C3~C1Respectively:1.47、1.81、2.03;Substitute into formula
It is respectively 1.78,1.71,1.67 to obtain girder section upper limb shear lag coefficient λ at C3~C1 Suo Li.
Step 2.2:Determine the Shear Lag of span centre beam section at half between rope point of force application;
The span centre beam section at half between rope point of force application, with the shear lag coefficient λ of MomentMReflect the point Actual loading situation and Shear Lag, the computational methods of Shear Lag are as follows at the point:
Wherein,The nominal direct stress caused by the moment of flexure of span centre beam section at half between rope point of force application;σMFor Actual direct stress, λ caused by the moment of flexure of span centre beam section at half between rope point of force applicationMTwo points between rope point of force application One of shear lag coefficient caused by the moment of flexure of place's span centre beam section.
In the present embodiment, the shearing of the span centre beam section of rope point of force application C3 '~between C1 ' and C3~C1 at half It is stagnant, with the shear lag coefficient λ of MomentMReflect the actual loading situation of the point, λ is calculatedM=1.17;
Step 2.3:Determine the Shear Lag between rope point of force application and span centre beam section;
Shear Lag between rope point of force application and span centre beam section, by the Shear Lag of the rope point of force application of beam section between Suo Li Between coefficient lambda and rope point of force application at half span centre beam section shear lag coefficient λMBetween using linear interpolation try to achieve should The shear lag coefficient reflection in beam section section.
In the present embodiment, C3 ' arrive C3 '~C2 ' half span centres between beam section Shear Lag, should 1.77 and 1.17 it Between tried to achieve using linear interpolation;C2 ' arrive C2 '~C1 ' half span centres between beam section Shear Lag, should 1.75 and 1.17 it Between tried to achieve using linear interpolation;The Shear Lag of beam section between C3 to C3~C2 half span centres, should be between 1.78 and 1.17 Tried to achieve using linear interpolation;The Shear Lag of beam section, should be adopted between 1.71 and 1.17 between C2 to C2~C1 half span centres Tried to achieve with linear interpolation.As C3 points shear lag coefficient be 1.77, C3~C2 half span centres at Shear Lag 1.17, distance C3 points The shear lag coefficient linear interpolation of beam section is 1.61 at 1 meter.
Finally it should be noted that:The above embodiments are merely illustrative of the technical solutions of the present invention, rather than its limitations;Although The present invention is described in detail with reference to the foregoing embodiments, it will be understood by those within the art that:It still may be used To be modified to the technical scheme described in previous embodiment, either which part or all technical characteristic are equal Replace;And these modifications or replacement, the essence of appropriate technical solution is departed from the model that the claims in the present invention are limited Enclose.

Claims (4)

  1. A kind of 1. determination method of Main Girder of Concrete Cable-stayed Bridge construction stage Shear Lag, it is characterised in that:Comprise the following steps:
    Step 1, determine Shear Lag at two cantilever end rope points of force application of cable-stayed bridge;
    Step 2, the Shear Lag for determining beam section between Suo Li;
    Step 2.1:Determine the Shear Lag at the rope point of force application of beam section between Suo Li;
    Step 2.2:Determine the Shear Lag of span centre beam section at half between rope point of force application;
    Step 2.3:Determine the Shear Lag between rope point of force application and span centre beam section;
    Shear Lag between rope point of force application and span centre beam section, by the shear lag coefficient of the rope point of force application of beam section between Suo Li Between λ and rope point of force application at half span centre beam section shear lag coefficient λMBetween the beam section tried to achieve using linear interpolation The shear lag coefficient reflection in section.
  2. 2. a kind of determination method of Main Girder of Concrete Cable-stayed Bridge construction stage Shear Lag according to claim 1, its feature It is:The Shear Lag that Shear Lag at two cantilever end rope points of force application of cable-stayed bridge described in step 1 is acted on axle power at the point Coefficient lambdaNReflect, the computational methods of Shear Lag as caused by axle power are shown below at this:
    <mrow> <msub> <mi>&amp;lambda;</mi> <mi>N</mi> </msub> <mo>=</mo> <mfrac> <msub> <mi>&amp;sigma;</mi> <mi>N</mi> </msub> <msub> <mover> <mi>&amp;sigma;</mi> <mo>&amp;OverBar;</mo> </mover> <mi>N</mi> </msub> </mfrac> </mrow>
    Wherein, λNFor shear lag coefficient, σ caused by axle power at stayed-cable bridge cantilever end cable force application pointNFor stayed-cable bridge cantilever end cable force Actual direct stress caused by axle power at application point,Just should for name caused by axle power at stayed-cable bridge cantilever end cable force application point Power.
  3. 3. a kind of determination method of Main Girder of Concrete Cable-stayed Bridge construction stage Shear Lag according to claim 1, its feature It is:Shear Lag between Suo Li described in step 2.1 at the rope point of force application of beam section is with moment of flexure at the point and axle power than determination Shear lag coefficient λ reflects that the computational methods of Shear Lag are shown below at the point:
    <mrow> <mi>&amp;lambda;</mi> <mo>=</mo> <mfrac> <mi>&amp;sigma;</mi> <mover> <mi>&amp;sigma;</mi> <mo>&amp;OverBar;</mo> </mover> </mfrac> <mo>=</mo> <mfrac> <mrow> <msub> <mi>&amp;lambda;</mi> <msup> <mi>N</mi> <mo>&amp;prime;</mo> </msup> </msub> <mo>+</mo> <msub> <mi>C&amp;lambda;</mi> <msup> <mi>M</mi> <mo>&amp;prime;</mo> </msup> </msub> <mfrac> <mi>M</mi> <mi>N</mi> </mfrac> </mrow> <mrow> <mn>1</mn> <mo>+</mo> <mi>C</mi> <mfrac> <mi>M</mi> <mi>N</mi> </mfrac> </mrow> </mfrac> </mrow>
    Wherein, shear lag coefficients of the λ between Suo Li at the rope point of force application of beam section, the Suo Li effects of σ beam sections between Suo Li Actual stress at point,Nominal stress between Suo Li at the rope point of force application of beam section, actual stress σ and nominal stress The even superposition for corresponding direct stress caused by moment of flexure and axle power, λN′Between Suo Li at beam section rope point of force application caused by axle power Shear lag coefficient, λM′Shear lag coefficient caused by moment of flexure at beam section rope point of force application, M, N are respectively beam section section between Suo Li Suffered moment of flexure and axle power,Wherein, y is distance of the girder section centre of form to upper lower edge, and A is girder section area, I For girder section the moment of inertia.
  4. 4. a kind of determination method of Main Girder of Concrete Cable-stayed Bridge construction stage Shear Lag according to claim 1, its feature It is:The Shear Lag of span centre beam section is cut with Moment at the point at half between rope point of force application described in step 2.2 The stagnant coefficient lambda of powerMReflect, the computational methods of Shear Lag are as follows at the point:
    <mrow> <msub> <mi>&amp;lambda;</mi> <mi>M</mi> </msub> <mo>=</mo> <mfrac> <msub> <mi>&amp;sigma;</mi> <mi>M</mi> </msub> <msub> <mover> <mi>&amp;sigma;</mi> <mo>&amp;OverBar;</mo> </mover> <mi>M</mi> </msub> </mfrac> </mrow>
    Wherein, λMShear lag coefficient, σ caused by the moment of flexure of span centre beam section at half between rope point of force applicationMFor Suo Lizuo With actual direct stress caused by the moment of flexure of span centre beam section at half between point,The half between rope point of force application Locate nominal direct stress caused by the moment of flexure of span centre beam section.
CN201710993245.2A 2017-10-23 2017-10-23 A kind of determination method of Main Girder of Concrete Cable-stayed Bridge construction stage Shear Lag Pending CN107700336A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710993245.2A CN107700336A (en) 2017-10-23 2017-10-23 A kind of determination method of Main Girder of Concrete Cable-stayed Bridge construction stage Shear Lag

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710993245.2A CN107700336A (en) 2017-10-23 2017-10-23 A kind of determination method of Main Girder of Concrete Cable-stayed Bridge construction stage Shear Lag

Publications (1)

Publication Number Publication Date
CN107700336A true CN107700336A (en) 2018-02-16

Family

ID=61182770

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710993245.2A Pending CN107700336A (en) 2017-10-23 2017-10-23 A kind of determination method of Main Girder of Concrete Cable-stayed Bridge construction stage Shear Lag

Country Status (1)

Country Link
CN (1) CN107700336A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111881613A (en) * 2020-08-05 2020-11-03 武汉市政工程设计研究院有限责任公司 Inversion method and system for three-dimensional stress field with different weights of normal stress and shear stress
CN112832114A (en) * 2020-12-10 2021-05-25 中铁第四勘察设计院集团有限公司 Stay cable bridge and anchoring optimization method thereof

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105243236A (en) * 2015-11-05 2016-01-13 盐城工学院 Box girder bridge section design optimization method
CN106894328A (en) * 2017-02-20 2017-06-27 重庆大学 A kind of processing method of Π shapes bondbeam Shear Lag

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105243236A (en) * 2015-11-05 2016-01-13 盐城工学院 Box girder bridge section design optimization method
CN106894328A (en) * 2017-02-20 2017-06-27 重庆大学 A kind of processing method of Π shapes bondbeam Shear Lag

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
李艳凤等: ""预应力混凝土斜拉桥箱梁剪力滞规律"", 《沈阳工业大学学报》 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111881613A (en) * 2020-08-05 2020-11-03 武汉市政工程设计研究院有限责任公司 Inversion method and system for three-dimensional stress field with different weights of normal stress and shear stress
CN112832114A (en) * 2020-12-10 2021-05-25 中铁第四勘察设计院集团有限公司 Stay cable bridge and anchoring optimization method thereof

Similar Documents

Publication Publication Date Title
Rosignoli PRESTRESSED CONCRETE BOX GIRDER BRIDGES WITH FOLDED STEEL PLATE WEBS.
CN110032829A (en) The calculation method for stress of steel-concrete composite beam
Cluley et al. Analysis of concrete cable-stayed bridges for creep, shrinkage and relaxation effects
CN110795785A (en) Model building system of concrete continuous box girder bridge
CN107700336A (en) A kind of determination method of Main Girder of Concrete Cable-stayed Bridge construction stage Shear Lag
CN111611642A (en) Method for calculating bending rigidity of concrete composite beam wrapped with corrugated side plate
CN112252188B (en) Steel box arch rib hoisting construction method for balancing horizontal thrust by using temporary tie bar
CN113849888B (en) Calculation method for hole-by-hole erection of continuous steel truss girder closure rod piece matching and cutting amount
CN116240819A (en) Linear control method for cantilever pouring bridge construction
Zhang et al. Experimental and theoretical study of the torsional mechanism of a hybrid FRP-aluminum triangular deck-truss structure
CN110175389B (en) Main span and side span constant load configuration method for cable-stayed bridge
White Steel bridge design handbook: Structural behavior of steel
Plos et al. Evaluation of shear capacity of a prestressed concrete box girder bridge using non-linear FEM
Iles Design guide for composite box girder bridges
Cai et al. Study on Reinforcement of Transverse Prestressed Carbon Fiber Slab for Assembled Skew Hollow Slab Bridge
CN213625180U (en) Arch pier connecting device for connecting steel box arch rib and flexible pier
Zhou et al. Comparison and analysis of the results of grillage method and single beam method to continuous box girder with variable width
CN114753265A (en) Midspan closure method of large-span composite beam cable-stayed bridge
Cai et al. Shear force distribution mechanism of perfobond leiste connectors in joint between corrugated steel web and concrete top slab
Strasky Viaducts with progressively erected decks
Asghar Bhatti et al. Preliminary optimal design of cable-stayed bridges
Huang Flutter analysis of long-span suspension bridges: the case-study of the Messina Strait project
Icke et al. The benefits and use of FE modelling in bridge assessment and design
CN118345689A (en) Steel-concrete combined cross-sea high-speed railway cable-stayed bridge and construction method thereof
Sun Research on Construction Monitoring and Numerical Analysis of Walking Pushing Method Steel Arch Bridge

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20180216

WD01 Invention patent application deemed withdrawn after publication