CN107685835A - A kind of wind-powered electricity generation steel-pipe pile hoisting transportation technique - Google Patents
A kind of wind-powered electricity generation steel-pipe pile hoisting transportation technique Download PDFInfo
- Publication number
- CN107685835A CN107685835A CN201710169896.XA CN201710169896A CN107685835A CN 107685835 A CN107685835 A CN 107685835A CN 201710169896 A CN201710169896 A CN 201710169896A CN 107685835 A CN107685835 A CN 107685835A
- Authority
- CN
- China
- Prior art keywords
- steel
- pipe pile
- ship
- wire rope
- steel wire
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B63—SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
- B63B—SHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING
- B63B27/00—Arrangement of ship-based loading or unloading equipment for cargo or passengers
- B63B27/10—Arrangement of ship-based loading or unloading equipment for cargo or passengers of cranes
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B63—SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
- B63B—SHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING
- B63B25/00—Load-accommodating arrangements, e.g. stowing, trimming; Vessels characterised thereby
- B63B25/002—Load-accommodating arrangements, e.g. stowing, trimming; Vessels characterised thereby for goods other than bulk goods
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B63—SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
- B63B—SHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING
- B63B25/00—Load-accommodating arrangements, e.g. stowing, trimming; Vessels characterised thereby
- B63B25/24—Means for preventing unwanted cargo movement, e.g. dunnage
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B63—SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
- B63B—SHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING
- B63B39/00—Equipment to decrease pitch, roll, or like unwanted vessel movements; Apparatus for indicating vessel attitude
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B63—SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
- B63B—SHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING
- B63B2241/00—Design characteristics
- B63B2241/20—Designs or arrangements for particular purposes not otherwise provided for in this class
- B63B2241/24—Designs or arrangements for particular purposes not otherwise provided for in this class for facilitating transport, e.g. hull shape with limited dimensions
Landscapes
- Chemical & Material Sciences (AREA)
- Engineering & Computer Science (AREA)
- Combustion & Propulsion (AREA)
- Mechanical Engineering (AREA)
- Ocean & Marine Engineering (AREA)
- Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
- Load-Engaging Elements For Cranes (AREA)
Abstract
The invention discloses a kind of wind-powered electricity generation steel-pipe pile hoisting transportation technique, including selection crane barge ship and calculate the Hoisting Parameters of crane barge ship, the suspension centre for selecting steel-pipe pile, selection cargo ship, selection transport support, installation and transportation support, lifting steel-pipe pile, steel-pipe pile shipment, colligation steel-pipe pile, Accessory Members be installed.The advantage of the invention is that:Processing step smooth sequential, lifting is firm, colligation is firm, the position of hook device is closed by the selection and determination of two suspension centres, angle between two lifting steel wire ropes reduces the tension force between lifting steel wire rope no more than 45 °, avoids lifting steel wire rope from being broken, it is also prevented from lifting steel wire rope and sliding to the middle part of steel-pipe pile simultaneously causing one end to be laid particular stress on, ensures Hoisting Security;The load that the number of calculating transport support and single transport support are carried, ensure that wind-powered electricity generation steel-pipe pile will not produce destruction in transportation to cargo ship;Colligation steel-pipe pile firm stable, avoid cargo ship from occurring the phenomenon rocked in transportation, ensure transportation safety.
Description
Technical field
The invention belongs to marine transportation manufacturing field, and in particular to a kind of wind-powered electricity generation steel-pipe pile hoisting transportation technique.
Background technology
The project of operation on the sea is bulky, and center of gravity is high, general using manufacture, fragmented transport, segmentation installation is segmented, finally
The method of wind power plant general assembly at sea completes the installation of operation on the sea.Because offshore wind generating is typically using segmentation fortune
It is defeated, during shipping, in order to make full use of limited floor space to transport more steel-pipe piles and Accessory Members and subtract
The deformation of few pylon and steel-pipe pile, transport and the colligation of wind-driven generator steel-pipe pile and ship board are wind-driven generator steel
Pile tube most important link during sea-freight.
Now most steel-pipe pile in transport by the way of uprightly transporting, i.e., it is steel-pipe pile is upright above deck, due to steel
The stake of pile tube is long, and the mode uprightly transported increases steel-pipe pile and ship board transport and the difficulty of colligation, steel-pipe pile
During axial transport, easily appearance lifting is unstable in hoisting process, wire cable rupture, has a strong impact on Hoisting Security, is lifting
During colligation, because misoperation is easy to damage steel-pipe pile surface, some colligations are insecure, easily in transportation
Loosen, influence the normally travel of cargo ship.
The content of the invention
In view of the above-mentioned deficiencies in the prior art, it is an object of the present invention to now provide a kind of lifting is steady, avoid wire cable rupture,
Colligation is firm, ensures the wind-powered electricity generation steel-pipe pile hoisting transportation technique of transportation safety.
In order to solve the above technical problems, the technical solution adopted by the present invention is:A kind of wind-powered electricity generation steel-pipe pile hoisting transportation technique,
Wind-powered electricity generation steel-pipe pile includes pile body portion, flange portion and the connecting portion of connector drum portion and flange portion, and the interior circular diameter of flange portion is small
In the interior circular diameter of barrel, the weight of the steel-pipe pile is G, a diameter of D in pile body portion, a length of L stakes of stake, the distance of distance of centre of gravity flange
For L, including selection crane barge ship and calculate the Hoisting Parameters of crane barge ship, the suspension centre for selecting steel-pipe pile, selection cargo ship, selection transport
Support, installation and transportation support, lifting steel-pipe pile, steel-pipe pile shipment, colligation steel-pipe pile, installation Accessory Members;
Comprise the following steps that:
A, select crane barge ship and calculate the Hoisting Parameters of crane barge ship:The theoretical tonnage of crane barge ship is T, the steel pipe lifted by crane as needed
The parameter of stake, maximum hoisting weight Gmax=T × 3/L × 75% of crane barge ship is calculated, calculate the maximum sling height of crane barge ship
Hmax=H1+H2, wherein H1 are distance of the crane barge ship arm bar assembly pulley fixed pulley to arm lower axle, and H2 is arm lower axle to ground
The distance in face;
B, the suspension centre of steel-pipe pile is selected:Two right suspension centres of a first from left are selected on steel-pipe pile, according to the center of gravity of steel-pipe pile come really
Determine the position of suspension centre, two suspension centres in the first from left right side are equal with the distance of steel-pipe pile center of gravity, beaten at the hoisting point position on steel-pipe pile
Upper mark, while determine to close the position of hook device, close hook device and be connected with two suspension centres by lifting steel wire rope, while ensure two liftings
Angle between steel wire rope is less than or equal to 45 °;
C, cargo ship is selected:The overall length of cargo ship need to be more than the length of steel-pipe pile, and length difference carries in the scope of 3-10 rice, maximum
Goods amount is 1.8G;
D, transport support is selected:More steel-pipe pile weight of horizontal transport are G, and more steel-pipe piles of horizontal transport set n fortune
Defeated support, because cargo ship can have vertical acceleration during navigation, the vertical acceleration is 0.4G, calculates each transport
Load N=G that support is carried ×(1+0.4)/ n, verifies cargo ship《Ship Structure calculates》, find cargo ship transverse bulkhead position
The maximum load put, by maximum load value compared with the load N that each transport support carries, maximum load is more than each fortune
The load N that defeated support is carried could meet carriage requirement, if being unsatisfactory for requiring, increase the quantity of transport support;
E, installation and transportation support:N transport support is arranged in above the transverse bulkhead of cargo ship by welding manner, every steel pipe
The horizontal equidistant spread configuration of transport support that stake needs, n transport support determine transport support according to the quantity of steel-pipe pile
Row, setting is corresponding in turn between multiple rows of transport support, it is laterally solid that transport support both sides set two I-steel to carry out respectively
It is fixed;
F, steel-pipe pile is lifted:Crane barge ship lifts by crane steel-pipe pile, using hook device is closed, steel-pipe pile is rotated by 90 °, makes steel-pipe pile and harbour
It is parallel, using moving 50 meters after mooring cable and self power, by the barge with deck for loading steel-pipe pile advance to harbour and crane barge ship it
Between;
G, steel-pipe pile is loaded onto ship:Steel-pipe pile is fallen into by the suspension hook of crane barge ship in the transport support of a row, makes the flange portion of steel-pipe pile
Set close to carrier bow, by above-mentioned steps successively horizontal lifting steel-pipe pile;
H, colligation steel-pipe pile:Successively to steel-pipe pile progress colligation, oblique pull steel wire rope and along the outward flange of steel-pipe pile to steel-pipe pile
Colligation is carried out, oblique pull steel wire rope to next transport is propped up after one end of transport support of the one end of steel wire rope with being placed in stern be connected
Frame is simultaneously connected with the other end of the transport support, steel wire rope from the bottom to top or from top to bottom by stern-on bow direction successively
Colligation steel-pipe pile, finally steel wire rope is set to form twice pair on the surface of steel-pipe pile from bow to stern opposite direction successively colligation again
Claim shape arranged in a crossed manner.
Accessory Members are installed i,:First, crane barge ship lifts by crane Accessory Members, is lifted Accessory Members vertically using hook device is closed
To ship board, chosen between steel-pipe pile and bow it is multiple placement Accessory Members positions, and using the position of selection as
Circle is drawn in center above deck with the radius of Accessory Members bottom ring beam, chosen on the circumference several symmetrically arranged points and
Wood block filler is placed at the point;Secondly, Accessory Members are lifted at chosen position and making the collar tie beam of Accessory Members in headblock successively
The top of block;Again, the opening position positioned at wood block filler and the suit U-shaped card plate of the outer ring in Accessory Members bottom ring beam, and will be U-shaped
The both ends of clamp are fixed by welding on ship board, on the top of Accessory Members by being solid steel wire rope and cargo ship first
Plate connects.
Further, transport support includes the connecting portion that is vertically arranged, the upper surface of connecting portion for arc surface and along this
Arc surface is provided with an arc plate consistent with arc surface direction, and diameter of a circle where arc plate is identical with the diameter of steel-pipe pile, should
The upper surface of arc plate is provided with a foam pad, and the both sides of connecting portion are equipped with side plate and the bottom of connecting portion is provided with bottom plate, circle
Arc plate, side plate, the width of bottom plate are all higher than the thickness of connecting portion, while the outside of side plate is provided with the steel wire rope with colligation steel-pipe pile
The hanger a of connection, multiple be vertically arranged and positioned at the supporting plate of arc plate both sides, multiple supports is provided between arc plate and bottom plate
Plate is equally set, and the transverse bulkhead of bottom plate and cargo ship is bolted.
Further, in step i, Accessory Members include multiple collar tie beams, the multiple collar tie beams of connection being from top to bottom coaxially disposed
And the multiple support columns uniformly arranged in collar tie beam outer ring, the top of top ring beam are provided with operating platform, arranged in parallel and along branch
The axis of dagger is vertically provided with staircase and extends to operating platform by ship part, the upper end of the staircase, and its lower end extends to position
In the collar tie beam position of bottom, cable tube is vertically arranged with along the support column, the cable tube bottom extends to bottom ring beam position
Set outwardly for bell-mouth structure of air and opening;
Accessory Members are connected by the deck of the solid steel wire rope of six roots of sensation system and cargo ship, and this is upper end and the Accessory Members of solid steel wire rope
Collar tie beam connection, upper end is placed in the opening position of the upward 2-3 rice of Accessory Members center of gravity, is lower end and the ship board of solid steel wire rope
Connected by hanger b, hanger b is welded on the backing plate of ship board, and the backing plate is welded on ship board, while is solid
Steel wire rope and the angle on deck are 45 ° -60 °.
Further, in step b, rigging band is covered in the opening position of suspension centre, in lifting steel wire rope with steel-pipe pile close to lifting
One end of steel wire rope is fixed with the solid steel wire rope of a system, and this is that one end of solid steel wire rope is connected with lifting steel wire rope, the other end
It is connected with one end of steel-pipe pile.
Further, in step e, cotton-wadded quilt is laid on the transport support close to carrier bow.
Beneficial effects of the present invention are as follows:
1st, present invention process step smooth sequential, lifting is firm, and colligation is firm, and hook device is closed by the selection and determination of two suspension centres
Position, ensure that the angle between two lifting steel wire ropes no more than 45 °, reduces the tension force between lifting steel wire rope, avoids hanging
Steel loading cord is broken, while is also prevented from lifting steel wire rope and sliding to the middle part of steel-pipe pile causing one end to be laid particular stress on, and ensures lifting
Safety;The load that the number of calculating transport support and single transport support are carried, ensure wind-powered electricity generation steel-pipe pile in transportation
In will not to cargo ship produce destruction;Colligation steel-pipe pile firm stable, avoid what rocking occurred in transportation in cargo ship from showing
As ensureing transportation safety;The hoisting transportation of more set steel-pipe piles can be achieved, without repeatedly round transport, substantially increase work effect
Rate.
2nd, rigging band is covered in the opening position of suspension centre, prevents steel-pipe pile from the broken of steel-pipe pile surface paint occurring in hoisting process
It is bad, ensure the surface quality of steel-pipe pile;In lifting steel wire rope with steel-pipe pile close to one end of lifting steel wire rope solid steel wire of one system
Rope is fixed, and this is that one end of solid steel wire rope is connected with lifting steel wire rope, one end connection of the other end and steel-pipe pile, prevents from hanging
Steel loading cord is slided to center of gravity direction, causes the skewness of weight, ensures Hoisting Security.
3rd, Accessory Members are connected by the deck of the solid steel wire rope of six roots of sensation system and cargo ship, when cargo ship roll and pitch,
The solid steel wire rope of at least two root systems produces effective pulling force to Accessory Members, is that the lower end of solid steel wire rope and ship board pass through
Hanger b connections, hanger b are welded on the backing plate of ship board, and the backing plate is welded on ship board, and the setting of backing plate is prevented
Only cargo ship tears the deck of cargo ship under the state of rocking.
4th, cotton-wadded quilt is laid on the transport support close to carrier bow, because the diameter of the flange portion of steel-pipe pile compares pile body
The diameter in portion is small, and laying cotton-wadded quilt ensures that steel-pipe pile shipment is steady, while steel-pipe pile flange portion is protected, and prevents steel-pipe pile table
The destruction of face paint.
5th, transport support both sides set the I-steel of two to be laterallyd secure respectively, and cargo ship is deposited in transportation
In 30 ° of possibility of ship heel, I-steel is set in the both sides of transport support, the fastness of steel-pipe pile colligation can be ensured.
Brief description of the drawings
Fig. 1 is a kind of structural representation of single set steel-pipe pile transport of wind-powered electricity generation steel-pipe pile hoisting transportation technique of the present invention.
Fig. 2 is a kind of lifting schematic diagram of the steel-pipe pile of wind-powered electricity generation steel-pipe pile hoisting transportation technique of the present invention.
Fig. 3 is connection signal of the suspender belt with closing hook device in a kind of step b of wind-powered electricity generation steel-pipe pile hoisting transportation technique of the present invention
Figure.
Fig. 4 is that the barge with deck that steel-pipe pile is loaded in a kind of step f of wind-powered electricity generation steel-pipe pile hoisting transportation technique of the present invention is advanced
To the schematic diagram between harbour and crane barge.
Fig. 5 is the structural representation of transport support in a kind of step d of wind-powered electricity generation steel-pipe pile hoisting transportation technique of the present invention.
Fig. 6 is the side view of transport support in a kind of step d of wind-powered electricity generation steel-pipe pile hoisting transportation technique of the present invention.
Fig. 7 is the side that steel-pipe pile loads transport support in a kind of step g of wind-powered electricity generation steel-pipe pile hoisting transportation technique of the present invention
View.
Fig. 8 is the structural representation of Accessory Members in a kind of step i of wind-powered electricity generation steel-pipe pile hoisting transportation technique of the present invention.
Fig. 9 is the collar tie beam and U-shaped card plate of Accessory Members in a kind of step i of wind-powered electricity generation steel-pipe pile hoisting transportation technique of the present invention
Structural representation.
Figure 10 is is solid steel wire rope and ship board in a kind of step i of wind-powered electricity generation steel-pipe pile hoisting transportation technique of the present invention
The structural representation of connection.
Embodiment
Embodiments of the present invention are illustrated by particular specific embodiment below, those skilled in the art can be by this explanation
Content disclosed by book understands other advantages and effect of the present invention easily.
As shown in Fig. 1, a kind of wind-powered electricity generation steel-pipe pile hoisting transportation technique, wind-powered electricity generation steel-pipe pile include pile body portion, flange portion and
Connector drum portion and the connecting portion of flange portion, the interior circular diameter of flange portion are less than the interior circular diameter of barrel, the weight of the steel-pipe pile 6
Measure as G, a diameter of D in pile body portion, a length of L stakes of stake, the distance of distance of centre of gravity flange is L, including selection crane barge ship and calculates crane barge ship
Hoisting Parameters, select steel-pipe pile suspension centre, selection cargo ship, selection transport support, installation and transportation support, lifting steel-pipe pile,
Steel-pipe pile shipment, colligation steel-pipe pile, installation Accessory Members;
Comprise the following steps that:
A, select crane barge ship 1 and calculate the Hoisting Parameters of crane barge ship 1:The theoretical tonnage of crane barge ship 1 is T, is lifted by crane as needed
The parameter of steel-pipe pile 6, maximum hoisting weight Gmax=T × 3/L × 75% of crane barge ship 1 is calculated, calculate the maximum lifting of crane barge ship 1
Height Hmax=H1+H2, wherein H1 be the arm bar assembly pulley fixed pulley of crane barge ship 1 to the distance of arm lower axle, H2 is arm lower axle
To the distance on ground;
B, the suspension centre of steel-pipe pile 6 is selected:As shown in Figure 2 and Figure 3, two right suspension centres of a first from left are selected on steel-pipe pile 6, according to
The center of gravity of steel-pipe pile 6 determines the position of suspension centre, and two suspension centres in the first from left right side are equal with the distance of the center of gravity of steel-pipe pile 6, in steel pipe
Marked at hoisting point position in stake 6, while determine to close the position of hook device 4, closed at hook device 4 and two suspension centres by lifting steel wire
The connection of rope 5, while ensure that the angle between two lifting steel wire ropes 5 is less than or equal to 45 °;Rigging band 3 is covered in the opening position of suspension centre, is prevented
Only the destruction of the surface of steel-pipe pile 6 paint occurs in hoisting process for steel-pipe pile 6, ensures the surface quality of steel-pipe pile 6;In lifting steel
Cord 5 is fixed with steel-pipe pile 6 close to one end of lifting steel wire rope 5 with the solid steel wire rope 8 of a system, and this is the one of solid steel wire rope 8
End is connected with lifting steel wire rope 5, and the other end is connected with one end of steel-pipe pile 6, prevents that lift steel wire rope 5 slides to center of gravity direction
It is dynamic, cause the skewness of weight, ensure Hoisting Security;
C, cargo ship 11 is selected:The overall length of cargo ship 11 need to be more than the length of steel-pipe pile 6, and length difference is in the scope of 3-10 rice,
Maximum cargo dead-weight is 1.8G;
D, transport support is selected:As shown in Figure 5, Figure 6, transport support 12 includes the connecting portion 13 being vertically arranged, connecting portion 13
Upper surface is provided with an arc plate 14 consistent with arc surface direction for arc surface and along the arc surface, circle where arc plate 14
Diameter is identical with the diameter of steel-pipe pile 6, and the upper surface of the arc plate 14 is provided with a foam pad, and the both sides of connecting portion 13 are equipped with side
The bottom of plate 15 and connecting portion 13 is provided with bottom plate 16, and arc plate 14, side plate 15, the width of bottom plate 16 are all higher than connecting portion 13
Thickness, while the outside of side plate 15 is provided with the hanger a17 being connected with the steel wire rope of colligation steel-pipe pile 6, arc plate 14 and bottom plate 16
Between be provided with multiple be vertically arranged and positioned at the supporting plates 18 of arc plate both sides, multiple supporting plates 18 equally set, bottom plate
16 are bolted with the transverse bulkhead of cargo ship 11;
More steel-pipe pile weight of horizontal transport are G, if more steel-pipe piles of horizontal transport set n transport support, due to fortune
Defeated ship 11 can have vertical acceleration during navigation, and the vertical acceleration is 0.4G, calculate each transport support and carried
Load N=G ×(1+0.4)/ n, verify cargo ship 11《Ship Structure calculates》, find the transverse bulkhead position of cargo ship 11 most
Big load, by maximum load value compared with the load N that each transport support 12 carries, maximum load is more than each transport branch
The load N that frame 12 is carried could meet carriage requirement, if being unsatisfactory for requiring, increase the quantity of transport support 12;
E, installation and transportation support 12:N transport support 12 is arranged in above the transverse bulkhead of cargo ship 11 by welding manner, often
The horizontal equidistant spread configuration of transport support 12 that root steel-pipe pile 6 needs, n transport support 12 according to the quantity of steel-pipe pile 6 come
The row of transport support 12 is determined, is corresponding in turn to setting between multiple rows of transport support 12, the both sides of transport support 12 set two respectively
Root I-steel 19 is laterallyd secure, and cargo ship 11 there is a possibility that 30 ° of ship heel in transportation, in transport branch
The both sides of frame 12 set I-steel 19, can ensure the fastness of the colligation of steel-pipe pile 6, in the transport branch close to the bow of cargo ship 11
Cotton-wadded quilt is laid on frame 12, because the diameter of the flange portion of steel-pipe pile 6 is smaller than the diameter in pile body portion, laying cotton-wadded quilt ensures steel-pipe pile 6
Shipment is steady, while the flange portion of steel-pipe pile 6 is protected, the destruction for preventing the surface of steel-pipe pile 6 from painting;
F, steel-pipe pile 6 is lifted:As shown in figure 4, crane barge ship 1 lifts by crane steel-pipe pile 6, using hook device 4 is closed, steel-pipe pile 6 is rotated
90 °, make steel-pipe pile 6 parallel with harbour 10, using moving 50 meters after mooring cable 7 and self power, the deck of steel-pipe pile 6 will be loaded
9 are refuted to advance between harbour 10 and crane barge ship 1;
G, steel-pipe pile 6 is loaded onto ship:As shown in fig. 7, steel-pipe pile 6 is fallen into the transport support 12 of a row by the suspension hook 2 of crane barge ship 1,
The flange portion of steel-pipe pile 6 is set to be set close to the bow of cargo ship 11, by above-mentioned steps successively horizontal lifting steel-pipe pile 6;
H, colligation steel-pipe pile 6:Successively to the progress colligation of steel-pipe pile 6, oblique pull steel wire rope and along the outward flange of steel-pipe pile 6 to steel pipe
Stake 6 carries out colligations, and oblique pull steel wire rope is to next after one end of transport support 12 of the one end of steel wire rope with being placed in stern is connected
Transport support 12 is simultaneously connected with the other end of the transport support 12, and steel wire rope is from the bottom to top or from top to bottom by stern-on bow
Direction colligation steel-pipe pile 6 successively, finally make steel wire rope in the table of steel-pipe pile 6 from bow to stern opposite direction successively colligation again
Face forms the shape that twice symmetrical chiasma is set.
Accessory Members are installed i,:
As shown in figure 8, multiple collar tie beams 20, multiple collar tie beams 20 of connection and in collar tie beam that Accessory Members include from top to bottom being coaxially disposed
Multiple support columns 21 that 20 outer rings are uniformly arranged, the top of top ring beam 20 are provided with operating platform 22, arranged in parallel and along branch
The axis of dagger 21 is vertically provided with staircase 23 and extends to operating platform 22 by ship part 24, the upper end of the staircase 23, under it
End is extended to positioned at the position of collar tie beam 20 of bottom, and cable tube 25 is vertically arranged with along support column 21, the bottom of cable tube 25 extension
To the position of bottom ring beam 20 be bell-mouth structure of air and opening is set outwardly;
As first, crane barge ship 1 lifts by crane Accessory Members, is lifted Accessory Members to ship board vertically using hook device 4 is closed,
The position of multiple placement Accessory Members is chosen between steel-pipe pile 6 and bow, and with Accessory Members centered on the position of selection
The radius of bottom ring beam 20 draws circle above deck, and several symmetrically arranged points are chosen on the circumference and place wood at this point
Cushion block 26;Secondly, Accessory Members are lifted at chosen position and making the collar tie beam 20 of Accessory Members in the upper of wood block filler 26 successively
Side;Again, the opening position positioned at wood block filler 26 and the suit U-shaped card plate of the outer ring in Accessory Members bottom ring beam 20 27, and will be U-shaped
The both ends of clamp 27 are fixed by welding on the deck of cargo ship 11, pass through steel wire rope and cargo ship 11 on the top of Accessory Members
Deck connects.
The annexation of Accessory Members and ship board:As shown in Figure 9, Figure 10, Accessory Members pass through the solid steel of six roots of sensation system
Cord 28 is connected with the deck of cargo ship 11, and this is that the upper end a of solid steel wire rope 28 and the collar tie beam 20 of Accessory Members connect, and upper end is put
It is that the lower end b of solid steel wire rope 28 and the deck of cargo ship 11 pass through hanger b29 in the opening position of the upward 2-3 rice of Accessory Members center of gravity
Connection, hanger b29 are welded on the backing plate 30 of ship board, and the backing plate 30 is welded on the deck of cargo ship 11, while are solid
Steel wire rope 28 and the angle on deck are 45 ° -60 °.
The weight for such as lifting by crane the steel-pipe pile of transport is 840 tons, a diameter of 6800 millimeters of pile body portion, a length of 84 meters of stake, center of gravity
When distance away from flange is 41.16 meters, maximum hoisting weight Gmax=T × 3/ of crane barge ship 1 is calculated when transporting the wind-powered electricity generation steel-pipe pile
L × 75% draws about 1300 tons, calculates maximum sling height Hmax=H1+H2 of crane barge ship 1 and must locate 71.2 meters;
After the suspension centre of step b selection steel-pipe piles 6, the intensity of steel-pipe pile 6 and deflection are analyzed:The structure for drawing steel-pipe pile 6 should
Power distribution map, the maximum internal stress that steel-pipe pile 6 is calculated are 254N/mm2, the steel material that steel-pipe pile 6 uses for Q345C,
Yield strength is 355 N/mm2, and analysis show that the self-strength of steel-pipe pile 6 can meet lifting requirements;Steel-pipe pile 6 is drawn to lift
The Aberration nephogram of journey, the maximum amount of hanging down in the range of 30 meters of free end of steel-pipe pile 6 be 26.8mm, analyzes and show that the deformation belongs to bullet
Be not in deformation in property deformation range;
The length that the overall length of step c selection cargo ships 11 need to be more than steel-pipe pile 6 is 88 meters, 22 meters of molded breadth, 6.1 meters of moldeed depth, loading
77.5 meters of bosun, 18 meters of cargo deck effective width, maximum 1500 tons of cargo dead-weight;
Step d selects transport support, and the weight of steel-pipe pile 6 is 840 tons, 5 transport supports 12 is set, because cargo ship 11 is navigating
There can be vertical acceleration during row, the vertical acceleration is 0.4G, calculates load N=G that each transport support 12 is carried
×(1+0.4)/ n, draw N=840 ×(1+0.4)/ 5=235.2 tons, verify cargo ship 11《Ship Structure calculates》, find fortune
The maximum load of the defeated transverse bulkhead position of ship 11 is 346.5 tons, and 346.5 tons of maximum load value is carried with each transport support 12
235.2 tons of load is compared, and meets this carriage requirement;
Structural strength of the transport support 12 in transportation is checked after step f lifting steel-pipe piles:Draw answering for transport support 12
Power distribution map and Aberration nephogram, the maximum stress that transport support 12 is calculated is 34.2N/mm2, strong much smaller than the surrender of material
Degree the fair of 355N/mm2 uses stress, and therefore, transport support 12 is in a safe condition, and then enters next process steps.
Above-described embodiment is presently preferred embodiments of the present invention, is not the limitation to technical solution of the present invention, as long as
The technical scheme that can be realized on the basis of above-described embodiment without creative work, it is regarded as falling into patent of the present invention
Rights protection scope in.
Claims (5)
1. a kind of wind-powered electricity generation steel-pipe pile hoisting transportation technique, the wind-powered electricity generation steel-pipe pile includes pile body portion, flange portion and connector drum
Portion and the connecting portion of flange portion, the interior circular diameter of the flange portion are less than the interior circular diameter of barrel, and the weight of the steel-pipe pile is
G, a diameter of D in pile body portion, a length of L stakes of stake, the distance of distance of centre of gravity flange is L, it is characterised in that:Including selection crane barge ship and calculate
The Hoisting Parameters of crane barge ship, the suspension centre for selecting steel-pipe pile, selection cargo ship, selection transport support, installation and transportation support, lifting steel
Pile tube, steel-pipe pile shipment, colligation steel-pipe pile, installation Accessory Members;
Comprise the following steps that:
A, select crane barge ship and calculate the Hoisting Parameters of crane barge ship:The theoretical tonnage of crane barge ship is T, the steel pipe lifted by crane as needed
The parameter of stake, maximum hoisting weight Gmax=T × 3/L × 75% of crane barge ship is calculated, calculate the maximum sling height of crane barge ship
Hmax=H1+H2, wherein H1 are distance of the crane barge ship arm bar assembly pulley fixed pulley to arm lower axle, and H2 is arm lower axle to ground
The distance in face;
B, the suspension centre of steel-pipe pile is selected:Two right suspension centres of a first from left are selected on steel-pipe pile, according to the center of gravity of steel-pipe pile come really
Determine the position of suspension centre, two suspension centres in the first from left right side are equal with the distance of steel-pipe pile center of gravity, beaten at the hoisting point position on steel-pipe pile
Upper mark, while determine to close the position of hook device, close hook device and be connected with two suspension centres by lifting steel wire rope, while ensure two liftings
Angle between steel wire rope is less than or equal to 45 °;
C, cargo ship is selected:The overall length of cargo ship need to be more than the length of steel-pipe pile, and length difference carries in the scope of 3-10 rice, maximum
Goods amount is 1.8G;
D, transport support is selected:More steel-pipe pile weight of horizontal transport are G, and more steel-pipe piles of horizontal transport set n fortune
Defeated support, because cargo ship can have vertical acceleration during navigation, the vertical acceleration is 0.4G, calculates each transport
Load N=G that support is carried ×(1+0.4)/ n, verifies cargo ship《Ship Structure calculates》, find cargo ship transverse bulkhead position
The maximum load put, by maximum load value compared with the load N that each transport support carries, maximum load is more than each fortune
The load N that defeated support is carried could meet carriage requirement, if being unsatisfactory for requiring, increase the quantity of transport support;
E, installation and transportation support:N transport support is arranged in above the transverse bulkhead of cargo ship by welding manner, every steel pipe
The horizontal equidistant spread configuration of transport support that stake needs, n transport support determine transport support according to the quantity of steel-pipe pile
Row, setting is corresponding in turn between multiple rows of transport support, it is laterally solid that transport support both sides set two I-steel to carry out respectively
It is fixed;
F, steel-pipe pile is lifted:Crane barge ship lifts by crane steel-pipe pile, using hook device is closed, steel-pipe pile is rotated by 90 °, makes steel-pipe pile and harbour
It is parallel, using moving 50 meters after mooring cable and self power, by the barge with deck for loading steel-pipe pile advance to harbour and crane barge ship it
Between;
G, steel-pipe pile is loaded onto ship:Steel-pipe pile is fallen into by the suspension hook of crane barge ship in the transport support of a row, makes the flange portion of steel-pipe pile
Set close to carrier bow, by above-mentioned steps successively horizontal lifting steel-pipe pile;
H, colligation steel-pipe pile:Successively to steel-pipe pile progress colligation, oblique pull steel wire rope and along the outward flange of steel-pipe pile to steel-pipe pile
Colligation is carried out, oblique pull steel wire rope to next transport is propped up after one end of transport support of the one end of steel wire rope with being placed in stern be connected
Frame is simultaneously connected with the other end of the transport support, steel wire rope from the bottom to top or from top to bottom by stern-on bow direction successively
Colligation steel-pipe pile, finally steel wire rope is set to form twice pair on the surface of steel-pipe pile from bow to stern opposite direction successively colligation again
Claim shape arranged in a crossed manner;
Accessory Members are installed i,:First, crane barge ship lifts by crane Accessory Members, is lifted Accessory Members to fortune vertically using hook device is closed
On defeated boat deck, the position of multiple placement Accessory Members is chosen between steel-pipe pile and bow, and centered on the position of selection
Circle is drawn with the radius of Accessory Members bottom ring beam above deck, several symmetrically arranged points are chosen on the circumference and in the point
Place wood block filler in place;Secondly, Accessory Members are lifted at chosen position and making the collar tie beam of Accessory Members in wood block filler successively
Top;Again, the opening position positioned at wood block filler and the suit U-shaped card plate of the outer ring in Accessory Members bottom ring beam, and by U-shaped card plate
Both ends be fixed by welding on ship board, on the top of Accessory Members by being solid steel wire rope and ship board connects
Connect.
A kind of 2. wind-powered electricity generation steel-pipe pile hoisting transportation technique according to claim 1, it is characterised in that:The transport support includes
The connecting portion being vertically arranged, the upper surface of the connecting portion are provided with one and arc surface direction one for arc surface and along the arc surface
The arc plate of cause, diameter of a circle where arc plate is identical with the diameter of steel-pipe pile, and the upper surface of the arc plate is provided with a foam pad,
The both sides of the connecting portion are equipped with side plate and the bottom of connecting portion is provided with bottom plate, the arc plate, side plate, the width of bottom plate
The thickness of connecting portion is all higher than, while the outside of side plate is provided with the hanger a being connected with the steel wire rope of colligation steel-pipe pile, the circular arc
Multiple supporting plates for being vertically arranged and being located at arc plate both sides are provided between plate and bottom plate, multiple supporting plates are equally set,
The transverse bulkhead of the bottom plate and cargo ship is bolted.
A kind of 3. wind-powered electricity generation steel-pipe pile hoisting transportation technique according to claim 1, it is characterised in that:It is described in the step i
Multiple collar tie beams that Accessory Members include from top to bottom being coaxially disposed, the multiple collar tie beams of connection and uniformly arranged in collar tie beam outer ring multiple
Support column, the top of the top ring beam are provided with operating platform, the arranged in parallel and axis along support column is vertically provided with and helped
Ladder and operating platform is extended to by ship part, the upper end of the staircase, its lower end is extended to positioned at the collar tie beam position of bottom, along described
Support column is vertically arranged with cable tube, and the cable tube bottom extends to bottom ring beam position as bell-mouth structure of air and is open towards peripheral hardware
Put;
The Accessory Members are connected by the deck of the solid steel wire rope of six roots of sensation system and cargo ship, this be solid steel wire rope upper end with it is attached
The collar tie beam connection of component, upper end is placed in the opening position of the upward 2-3 rice of Accessory Members center of gravity, is lower end and the cargo ship of solid steel wire rope
Deck is connected by hanger b, and the hanger b is welded on the backing plate of ship board, and the backing plate is welded on ship board,
The angle for being simultaneously solid steel wire rope and deck is 45 ° -60 °.
A kind of 4. wind-powered electricity generation steel-pipe pile hoisting transportation technique according to claim 1, it is characterised in that:In the step b, in institute
The opening position set rigging band of suspension centre is stated, in lifting steel wire rope with steel-pipe pile close to one end of lifting steel wire rope solid steel wire rope of one system
It is fixed, this is that one end of solid steel wire rope is connected with lifting steel wire rope, one end connection of the other end and steel-pipe pile.
A kind of 5. wind-powered electricity generation steel-pipe pile hoisting transportation technique according to claim 1, it is characterised in that:In the step e, by
Cotton-wadded quilt is laid on the transport support of nearly carrier bow.
Priority Applications (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710169896.XA CN107685835A (en) | 2017-03-21 | 2017-03-21 | A kind of wind-powered electricity generation steel-pipe pile hoisting transportation technique |
PCT/CN2017/119666 WO2018171284A1 (en) | 2017-03-21 | 2017-12-29 | Wind power steel pipe pile lifting transportation process |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710169896.XA CN107685835A (en) | 2017-03-21 | 2017-03-21 | A kind of wind-powered electricity generation steel-pipe pile hoisting transportation technique |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107685835A true CN107685835A (en) | 2018-02-13 |
Family
ID=61152358
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710169896.XA Pending CN107685835A (en) | 2017-03-21 | 2017-03-21 | A kind of wind-powered electricity generation steel-pipe pile hoisting transportation technique |
Country Status (2)
Country | Link |
---|---|
CN (1) | CN107685835A (en) |
WO (1) | WO2018171284A1 (en) |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108407707A (en) * | 2018-04-05 | 2018-08-17 | 南京高传机电自动控制设备有限公司 | Cushioning supportive mechanism when a kind of wind-driven generator blade transport |
CN109052169A (en) * | 2018-09-03 | 2018-12-21 | 江苏长风海洋装备制造有限公司 | A kind of hoisting transportation technique for offshore wind farm jacket |
CN111017590A (en) * | 2019-12-24 | 2020-04-17 | 南通泰胜蓝岛海洋工程有限公司 | Shipping method and support frame of conduit frame assembly |
CN111889956A (en) * | 2020-06-23 | 2020-11-06 | 广州文冲船舶修造有限公司 | Large-area replacing and repairing process for top plate of cabin cover |
CN113120173A (en) * | 2021-05-27 | 2021-07-16 | 广船国际有限公司 | Hose hanger bracket and oil tanker |
CN114455025A (en) * | 2022-03-11 | 2022-05-10 | 中交一航局第三工程有限公司 | Method for realizing water transport tank car by landing boat |
CN114506417A (en) * | 2022-04-21 | 2022-05-17 | 江苏道达风电设备科技有限公司 | Roll-on and roll-off boarding method for thin-wall steel cylinder |
CN115258056A (en) * | 2022-09-19 | 2022-11-01 | 南通泰胜蓝岛海洋工程有限公司 | Integrated transportation overturning process for offshore steel pipe pile |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112850488B (en) * | 2020-12-31 | 2024-03-26 | 保利长大工程有限公司 | Method for overturning steel pipe pile by fixed arm frame crane ship |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101879932A (en) * | 2009-05-08 | 2010-11-10 | 中国海洋石油总公司 | Method for lengthening and lading steel piles of large deepwater jacket |
CN103803024A (en) * | 2014-01-31 | 2014-05-21 | 中交一航局第二工程有限公司 | Semi-floating offshore wind power unit overall transportation and installation one-in-all ship and construction method |
WO2015034351A1 (en) * | 2013-09-05 | 2015-03-12 | Jumbo Maritime B.V. | Method for arranging a pile on a vessel |
CN104989875A (en) * | 2015-05-19 | 2015-10-21 | 中国海洋石油总公司 | Submarine pipeline flange underwater abutting joint installation method |
Family Cites Families (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US6422795B2 (en) * | 1998-01-16 | 2002-07-23 | Anthony J. Holt | Cargo lash to bar |
CN101417693B (en) * | 2008-11-14 | 2012-10-10 | 大连船舶重工集团有限公司 | Oceanography engineering module integral hoisting method |
CN201756173U (en) * | 2010-08-13 | 2011-03-09 | 广东冠粤路桥有限公司 | Water surface hoisting construction ship with buoyant boxes |
CN202358280U (en) * | 2011-11-25 | 2012-08-01 | 天津港航工程有限公司 | Special ship for transporting large-diameter steel pipe piles and assisting in pile hoisting construction |
CN102425167B (en) * | 2011-11-25 | 2013-10-30 | 天津港航工程有限公司 | Pile sinking method for driving large-diameter steel pipe pile in intertidal zone |
CN105329765A (en) * | 2015-11-06 | 2016-02-17 | 天津港第二港埠有限公司 | Method for steel pipe winding and pocket hoisting work through steel wire rope buckles |
-
2017
- 2017-03-21 CN CN201710169896.XA patent/CN107685835A/en active Pending
- 2017-12-29 WO PCT/CN2017/119666 patent/WO2018171284A1/en active Application Filing
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101879932A (en) * | 2009-05-08 | 2010-11-10 | 中国海洋石油总公司 | Method for lengthening and lading steel piles of large deepwater jacket |
WO2015034351A1 (en) * | 2013-09-05 | 2015-03-12 | Jumbo Maritime B.V. | Method for arranging a pile on a vessel |
CN103803024A (en) * | 2014-01-31 | 2014-05-21 | 中交一航局第二工程有限公司 | Semi-floating offshore wind power unit overall transportation and installation one-in-all ship and construction method |
CN104989875A (en) * | 2015-05-19 | 2015-10-21 | 中国海洋石油总公司 | Submarine pipeline flange underwater abutting joint installation method |
Cited By (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108407707A (en) * | 2018-04-05 | 2018-08-17 | 南京高传机电自动控制设备有限公司 | Cushioning supportive mechanism when a kind of wind-driven generator blade transport |
CN109052169A (en) * | 2018-09-03 | 2018-12-21 | 江苏长风海洋装备制造有限公司 | A kind of hoisting transportation technique for offshore wind farm jacket |
CN109052169B (en) * | 2018-09-03 | 2019-09-24 | 江苏长风海洋装备制造有限公司 | A kind of hoisting transportation technique for offshore wind farm jacket |
CN111017590A (en) * | 2019-12-24 | 2020-04-17 | 南通泰胜蓝岛海洋工程有限公司 | Shipping method and support frame of conduit frame assembly |
CN111017590B (en) * | 2019-12-24 | 2022-02-25 | 南通泰胜蓝岛海洋工程有限公司 | Shipping method and support frame of conduit frame assembly |
CN111889956A (en) * | 2020-06-23 | 2020-11-06 | 广州文冲船舶修造有限公司 | Large-area replacing and repairing process for top plate of cabin cover |
CN113120173A (en) * | 2021-05-27 | 2021-07-16 | 广船国际有限公司 | Hose hanger bracket and oil tanker |
CN114455025A (en) * | 2022-03-11 | 2022-05-10 | 中交一航局第三工程有限公司 | Method for realizing water transport tank car by landing boat |
CN114455025B (en) * | 2022-03-11 | 2023-06-20 | 中交一航局第三工程有限公司 | Method for realizing water transport tank car by landing boat |
CN114506417A (en) * | 2022-04-21 | 2022-05-17 | 江苏道达风电设备科技有限公司 | Roll-on and roll-off boarding method for thin-wall steel cylinder |
CN115258056A (en) * | 2022-09-19 | 2022-11-01 | 南通泰胜蓝岛海洋工程有限公司 | Integrated transportation overturning process for offshore steel pipe pile |
Also Published As
Publication number | Publication date |
---|---|
WO2018171284A1 (en) | 2018-09-27 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107685835A (en) | A kind of wind-powered electricity generation steel-pipe pile hoisting transportation technique | |
US10894701B2 (en) | Crane, vessel comprising such a crane, and a method for up-ending a longitudinal structure | |
CN100537348C (en) | Offshore platform integral constructing and hoisting method and special-purpose hoisting machine for the same | |
CN100340470C (en) | Sectional hoisting method | |
CN110217698B (en) | Offshore wind power large-diameter single pile overturning tool and overturning method | |
CN107244382A (en) | The assemble method of lashing bridge and container ship | |
CN108455451B (en) | A kind of 600 tons of gantry cranes hold the method for hanging installation superelevation flare tower | |
CN103057672A (en) | Platform for transportation and installation of offshore fan unit complete machine | |
CN210973614U (en) | Marine wind power major diameter single pile upset frock | |
KR100940795B1 (en) | Method for launching and transporting heavy weight structures using air bags | |
US20230399206A1 (en) | Offshore wind turbine assembly vessel | |
CN105523477A (en) | Method for carrying out pile leg connection by utilizing 3000t floating crane | |
US8967930B2 (en) | Transport system for large items | |
CN206142022U (en) | Steel tray is used in submarine cable transportation | |
CN105947910B (en) | The hoisting of FPSO crane superstructures | |
CN109665445B (en) | Loading, transporting and conveying process for torch tower crane | |
CN111152899B (en) | Method for leveling 3000-ton floating crane main arm frame by using semi-submersible barge and floating crane | |
CN106115044B (en) | A kind of submarine cable transport teel pallet | |
CN105129622A (en) | Segmental hoisting process method | |
CN201228192Y (en) | Hanging arrangement equipment | |
CN112079270A (en) | Water surface hoisting equipment | |
JP2001226073A (en) | Method of installing portal crane | |
CN203855334U (en) | Hoisting device in complex sea conditions | |
KR101566522B1 (en) | Method for loading large block of ship | |
CN215361767U (en) | Offshore wind power transportation device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20180213 |
|
RJ01 | Rejection of invention patent application after publication |