CN107658872A - A kind of electric network reconstruction method for optimizing the access of 35 kv substations - Google Patents

A kind of electric network reconstruction method for optimizing the access of 35 kv substations Download PDF

Info

Publication number
CN107658872A
CN107658872A CN201711002680.0A CN201711002680A CN107658872A CN 107658872 A CN107658872 A CN 107658872A CN 201711002680 A CN201711002680 A CN 201711002680A CN 107658872 A CN107658872 A CN 107658872A
Authority
CN
China
Prior art keywords
substations
kilovolts
substation
access
optimizing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201711002680.0A
Other languages
Chinese (zh)
Other versions
CN107658872B (en
Inventor
张雯
郑志杰
李凯
李昭
邓少治
倪媛媛
寇岩
吴奎华
于千千
杨慎全
杨波
冯亮
梁荣
杨扬
刘钊
崔灿
庞怡君
赵昕
王男
刘晓明
杨斌
杨思
曹相阳
高效海
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Economic and Technological Research Institute of State Grid Shandong Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
Economic and Technological Research Institute of State Grid Shandong Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Economic and Technological Research Institute of State Grid Shandong Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201711002680.0A priority Critical patent/CN107658872B/en
Publication of CN107658872A publication Critical patent/CN107658872A/en
Application granted granted Critical
Publication of CN107658872B publication Critical patent/CN107658872B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • H02J3/005
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • H02J3/04Circuit arrangements for ac mains or ac distribution networks for connecting networks of the same frequency but supplied from different sources
    • H02J3/06Controlling transfer of power between connected networks; Controlling sharing of load between connected networks
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J2203/00Indexing scheme relating to details of circuit arrangements for AC mains or AC distribution networks
    • H02J2203/20Simulating, e g planning, reliability check, modelling or computer assisted design [CAD]

Landscapes

  • Engineering & Computer Science (AREA)
  • Power Engineering (AREA)
  • Supply And Distribution Of Alternating Current (AREA)

Abstract

A kind of electric network reconstruction method of the kv substation of optimization 35 access of the present invention comprises the following steps:Step 1, the present situation and planning data of 35 kv substations access power network are collected;Step 2, judge whether 35 kv substations access power network meets transformation condition;Step 3,35 kv substations access power network is transformed.The characteristics of present invention is by studying and judging regional power grid structure, on the premise of not increasing or rationally increasing quantities, newly go out twice large-section leads from 220 kv substations to access on 35 kilovolts of buses of 110 kv substations, it is 35 kilovolts of switchyards by 35 kilovolts of side views of 110 kv substations, 110 kv substation, 35 kilovolts of side service entrance switch are opened, the kv substation load of periphery 35 is connected to 220 kv substations by 35 kilovolts of switchyards, so as to improve 110 kv substation, 10 kilovolts of side power supply capacities, reduce transformation level, reduce line loss, save track investment.

Description

A kind of electric network reconstruction method for optimizing the access of 35 kv substations
Technical field
The present invention relates to Power System Planning technical field, specifically a kind of electricity for optimizing the access of 35 kv substations Net remodeling method.
Background technology
In recent years, as the fast development of domestic economy, power grid construction grow continuously and fast, substation location quantity at different levels It is continuously increased, uncoordinated phenomenon, such as subregion especially 35 kilovolts of rural power grids region power transformation occur in some areas power networks at different levels Power supply of standing comes from 110 kv substations more, thus causes problems with:
1st, 110 kv substation power transformation capacities are occupied by 35 kilovolts of loads more, and 10 kilovolts of side power supply capacities are weaker, Wu Faman Sufficient Regional Economic Development demand, or 110 new kv substations of inappropriately high standard construction of having to, investment increase.
2nd, relative to 220/35 kilovolt decompression for, by 110/35 kilovolt decompression there are problems that repeatedly decompression, line loss compared with Greatly.
3rd, if newly going out line powering by 220 kv substations there is power supply in newly-built 35 kv substation (including subscriber station) Distance, circuit return the shortcomings of number is more, track investment is big, 35 kilovolts of outgoing line intervals occupancy of transformer station are more.
Therefore, in Electric Power Network Planning, take into full account that the reasonable kv substation of reconfiguration 35, reduction repeat be depressured, improve each electricity Press science, the economy of the operation of grade transformer substation main transformer significant for guarantee grid health, fast development.
The content of the invention
In view of the deficienciess of the prior art, the present invention proposes a kind of electric network reconstruction for optimizing the access of 35 kv substations Method, it can improve 35 kilovolts of sides of 220 kv substations, 110 kv substation, 10 kilovolts of side joint band abilities, optimize rack Structure, lifting region power supply capacity.
The present invention solves its technical problem and adopted the technical scheme that:
It is provided in an embodiment of the present invention it is a kind of optimize 35 kv substations access electric network reconstruction method, it can include with Lower step:
Step 1, the present situation and planning data of 35 kv substations access power network are collected;
Step 2, judge whether 35 kv substations access power network meets transformation condition;
Step 3,35 kv substations access power network is transformed.
As a kind of possible implementation of the present embodiment, the detailed process of the step 2 comprises the following steps:
Step 21, judge a certain 110kV transformer stations using 110/35/10 kilovoltage sequence at present or whether planning goes out Existing heavily loaded phenomenon, if yes then enter in next step, otherwise exit;
Step 22, judge whether 35 kilovolts of side loads of the 110kV transformer stations are larger, it is no if yes then enter next step Then exit;
Step 23, whether judge 220 kv substations on the 110kV transformer stations periphery has 35 kilovolts of standby outgoing line intervals, If it is 35 kv substations access power network is transformed, otherwise exited.
As a kind of possible implementation of the present embodiment, then judge when the load factor of 110kV transformer stations is more than 70% 35 kilovolts of side loads of the 110kV transformer stations are larger situation.
It is in step 3, described that 35 kv substations access power network is entered as a kind of possible implementation of the present embodiment The process of row transformation newly goes out 2 loop line roads to 110 kv substation for 220 kv substations from 110kV transformer stations periphery 35 kilovolts of buses.
As a kind of possible implementation of the present embodiment, the detailed process of the step 3 comprises the following steps:
Step 31,2 times heavy in section circuits are newly gone out to described 110 from 220 nearest kv substations of distance 110kV transformer stations 35 kilovolts of buses of kv substation, and be 35 kilovolts of switchyards by 35 kilovolts of side views of 110 kv substation
Step 32,35 kilovolts of side service entrance switch of 110 kv substations are opened, by the periphery 35 of 110 kv substations Kv substation load is connected to 220 kv substation by 35 kilovolts of switchyards.
It is further comprising the steps of as a kind of possible implementation of the present embodiment, the detailed process of the step 3:
Step 33, when the load factor of the kv substation of 110 kv substation higher level power supply point 220 is higher than 60%, Then newly-built 110 kv substation, and by its inlet wire reconfiguration to other 220 kv substations;If the region has formed 35 kilovolts Power network, then using 110/35/10 voltage change layer;
Step 34, the three-winding transformer of 110 kv substation is rotated to the newly-built change layer of use 110/35/10 110 kv substations, while use 110 kv substation instead two-winding transformer tape splicing 10 kilovolts of loads.
The technical scheme of the embodiment of the present invention can have the advantage that as follows:
The characteristics of technical scheme of the embodiment of the present invention is by studying and judging regional power grid structure, is not increasing or rationally increasing engineering On the premise of amount, newly go out twice large-section leads from 220 kv substations and access on 35 kilovolts of buses of 110 kv substations, It is 35 kilovolts of switchyards by 35 kilovolts of side views of 110 kv substations, by 110 kv substation, 35 kilovolts of side service entrance switch Open, kv substation (subscriber station) load of periphery 35 is connected to 220 kv substations by 35 kilovolts of switchyards, so as to improve 110 kv substation, 10 kilovolts of side power supply capacities, reduce transformation level, reduce line loss, save track investment, simultaneously The utilization ratio of 220 35 kilovolts of outgoing line intervals of kv substation can be improved.
Technical scheme of the embodiment of the present invention by double back large-section lead, (lead by model JL/G1A-300 and the aerial of the above Line) reconfiguration can improve 220 kv substation, 35 kilovolts of sides, the load tape splicing ability of 110 kv substation, 10 kilovolts of sides, rationally Tape splicing load, improve block supply ability;And calmodulin binding domain CaM grid structure, former three-winding transformer is rotated to newly-built power transformation Stand, avoid the wasting of resources.
Brief description of the drawings
Fig. 1 is a kind of electric network reconstruction method stream of the kv substation of optimization 35 access according to an exemplary embodiment Cheng Tu;
Fig. 2 is a kind of structural representation of 220/110/35 kilovolt of access way power network in certain region in the prior art;
Fig. 3 is to carry out improved structural representation to power network shown in Fig. 2 using technical scheme of the embodiment of the present invention.
Embodiment
For the technical characterstic for illustrating this programme can be understood, below by embodiment, and its accompanying drawing is combined, to this hair It is bright to be described in detail.Following disclosure provides many different embodiments or example is used for realizing the different knots of the present invention Structure.In order to simplify disclosure of the invention, hereinafter the part and setting of specific examples are described.In addition, the present invention can be with Repeat reference numerals and/or letter in different examples.This repetition is that for purposes of simplicity and clarity, itself is not indicated Relation between various embodiments are discussed and/or set.It should be noted that part illustrated in the accompanying drawings is not necessarily to scale Draw.Present invention omits the description to known assemblies and treatment technology and process to avoid being unnecessarily limiting the present invention.
Fig. 1 is a kind of electric network reconstruction method stream of the kv substation of optimization 35 access according to an exemplary embodiment Cheng Tu.As shown in figure 1, a kind of electric network reconstruction method for optimizing the access of 35 kv substations provided in an embodiment of the present invention, it can To comprise the following steps:
Step 1, the present situation and planning data of 35 kv substations access power network are collected;
Step 2, judge whether 35 kv substations access power network meets transformation condition;
Step 3,35 kv substations access power network is transformed.
In a kind of possible implementation, the detailed process of the step 2 comprises the following steps:
Step 21, judge a certain 110kV transformer stations using 110/35/10 kilovoltage sequence at present or whether planning goes out Existing heavily loaded phenomenon, if yes then enter in next step, otherwise exit;
Step 22, judge whether 35 kilovolts of side loads of the 110kV transformer stations are larger, it is no if yes then enter next step Then exit;
Step 23, whether judge 220 kv substations on the 110kV transformer stations periphery has 35 kilovolts of standby outgoing line intervals, If it is 35 kv substations access power network is transformed, otherwise exited.
In a kind of possible implementation, then judge that the 110kV becomes when the load factor of 110kV transformer stations is more than 70% 35 kilovolts of side loads in power station are larger situation.
It is in step 3, described that 35 kv substations are accessed with what power network was transformed in a kind of possible implementation Process newly goes out 2 loop line roads to 35 kilovolts of 110 kv substation for 220 kv substations from 110kV transformer stations periphery Bus.
In a kind of possible implementation, the detailed process of the step 3 comprises the following steps:Step 31, from distance 220 nearest kv substations of 110kV transformer stations newly go out 2 times heavy in section circuits to 35 kilovolts of mothers of 110 kv substation Line, and be 35 kilovolts of switchyards by 35 kilovolts of side views of 110 kv substation;
Step 32,35 kilovolts of side service entrance switch of 110 kv substations are opened, by the periphery 35 of 110 kv substations Kv substation load is connected to 220 kv substation by 35 kilovolts of switchyards.
In a kind of possible implementation, the detailed process of the step 3 is further comprising the steps of:
Step 33, when the load factor of the kv substation of 110 kv substation higher level power supply point 220 is higher than 60%, Then newly-built 110 kv substation, and by its inlet wire reconfiguration to other 220 kv substations;If the region has formed 35 kilovolts Power network, then using 110/35/10 voltage change layer;;
Step 34, the three-winding transformer of 110 kv substation is rotated to the newly-built change layer of use 110/35/10 110 kv substations, while use 110 kv substation instead two-winding transformer tape splicing 10 kilovolts of loads.
Fig. 2 is a kind of structural representation of 220/110/35 kilovolt of access way power network in certain region in the prior art;Fig. 3 It is that improved structural representation is carried out to power network shown in Fig. 2 using technical scheme of the embodiment of the present invention.As shown in Figures 2 and 3, The detailed process transformed using technical scheme of the embodiment of the present invention the existing power network shown in Fig. 2 is:Collect electricity shown in Fig. 2 The present situation and planning data of net, judging to use 110 kv substation A of 110/35/10 kilovoltage sequence current or plan is It is no heavily loaded phenomenon occur, if so, continuing to judge the 110kV transformer stations whether 35 kilovolts of side loads are larger;If judge periphery 220 Whether kv substation has 35 kilovolts of standby outgoing line intervals;If newly go out 2 times heavy in section circuits to 110 from 220 kv substations 35 kilovolts of buses of kv substation are transformed it.
As shown in Fig. 2 110 kv substation A and 220 kv substations I, apart from less than 3 kilometers, wave impedance is ignored. The public station of 35 kilovolts of the main tape splicings of 110 kv substation A and the load of subscriber station.When 110 kv substation A load factors exceed 70% and 220 load factors of kv substation I when being less than 40%, while 220 kv substations I must possess 35kV intervals or can expand 35kV intervals are built, now it is considered that possessing the condition transformed using technical scheme of the embodiment of the present invention it.Using this After inventive embodiments technical scheme is to power network is transformed shown in Fig. 2, with the continuous development of load, 220 kv substations I Load factor improves constantly, when higher than 60%, for the sub-load of its tape splicing is transferred into 220 kv substations II and 220,000 Transformer station III is lied prostrate, the kv substation D of planning construction 110, the load of 220 kv substations I is reduced by the adjustment of the method for operation Rate.Be present 35 kv grids for having had blank in 110 kv substation D regions, designed according to three-winding transformer.By 110 Kv substation A three-winding transformer is rotated to 110 kv substation D, and 110 kv substation A are become using double winding 10 kilovolts of loads of depressor tape splicing.
The characteristics of the present embodiment is by studying and judging regional power grid structure, on the premise of not increasing or rationally increasing quantities, Newly go out twice large-section leads from 220 kv substations to access on 35 kilovolts of buses of 110 kv substations, by 110 kilovolts of changes 35 kilovolts of side views in power station are 35 kilovolts of switchyards, 110 kv substation, 35 kilovolts of side service entrance switch are opened, by periphery 35 kv substations (subscriber station) load is connected to 220 kv substations by 35 kilovolts of switchyards, so as to improve 110 kilovolts of changes 10 kilovolts of power station side power supply capacity, reduce transformation level, reduce line loss, save track investment, while can improve The utilization ratio of 220 35 kilovolts of outgoing line intervals of kv substation.
The present embodiment can be carried by double back large-section lead (model JL/G1A-300 and the aerial condutor of the above) reconfiguration High 220 kv substation, 35 kilovolts of sides, the load tape splicing ability of 110 kv substation, 10 kilovolts of sides, reasonable tape splicing load, improve Block supply ability;And calmodulin binding domain CaM grid structure, former three-winding transformer is rotated to newly-built transformer station, avoids resource Waste.
Simply the preferred embodiment of the present invention described above, for those skilled in the art, Without departing from the principles of the invention, some improvements and modifications can also be made, these improvements and modifications are also regarded as this hair Bright protection domain.

Claims (6)

1. a kind of electric network reconstruction method for optimizing the access of 35 kv substations, it is characterized in that, comprise the following steps:
Step 1, the present situation and planning data of 35 kv substations access power network are collected;
Step 2, judge whether 35 kv substations access power network meets transformation condition;
Step 3,35 kv substations access power network is transformed.
2. a kind of electric network reconstruction method for optimizing the access of 35 kv substations as claimed in claim 1, it is characterized in that, the step Rapid 2 detailed process comprises the following steps:
Step 21, judge a certain 110kV transformer stations using 110/35/10 kilovoltage sequence at present or whether planning weight occurs Phenomenon is carried, if yes then enter in next step, is otherwise exited;
Step 22, judge whether 35 kilovolts of side loads of the 110kV transformer stations are larger, if yes then enter in next step, otherwise move back Go out;
Step 23, whether judge 220 kv substations on the 110kV transformer stations periphery has 35 kilovolts of standby outgoing line intervals, if It is that 35 kv substations access power network is transformed, otherwise exited.
3. a kind of electric network reconstruction method for optimizing the access of 35 kv substations as claimed in claim 2, it is characterized in that, when The load factor of 110kV transformer stations then judges that 35 kilovolts of side loads of the 110kV transformer stations are larger situation when being more than 70%.
4. a kind of electric network reconstruction method for optimizing the access of 35 kv substations as claimed in claim 2, it is characterized in that, in step In 3, described is 220 kilovolts of power transformations from 110kV transformer stations periphery to the process transformed of 35 kv substations access power network Stand and newly go out 2 loop line roads to 35 kilovolts of buses of 110 kv substation.
5. a kind of electric network reconstruction method for optimizing the access of 35 kv substations as claimed in claim 4, it is characterized in that, the step Rapid 3 detailed process comprises the following steps:
Step 31,2 times heavy in section circuits are newly gone out to described 110 kilovolts from 220 nearest kv substations of distance 110kV transformer stations 35 kilovolts of buses of transformer station, and be 35 kilovolts of switchyards by 35 kilovolts of side views of 110 kv substation;
Step 32,35 kilovolts of side service entrance switch of 110 kv substations are opened, by 35 kilovolts of the periphery of 110 kv substations Transformer station's load is connected to 220 kv substation by 35 kilovolts of switchyards.
6. a kind of electric network reconstruction method for optimizing the access of 35 kv substations as claimed in claim 5, it is characterized in that, the step Rapid 3 detailed process is further comprising the steps of:
Step 33, when the load factor of the kv substation of 110 kv substation higher level power supply point 220 is higher than 60%, then newly Build 110 kv substations, and by its inlet wire reconfiguration to other 220 kv substations;If the region has formed 35 kv grids, Then use 110/35/10 voltage change layer;
Step 34, the three-winding transformer of 110 kv substation is rotated to the newly-built change layer of use 110/35/10 110 kv substations, while use 110 kv substation instead two-winding transformer tape splicing 10 kilovolts of loads.
CN201711002680.0A 2017-10-24 2017-10-24 Power grid transformation method for optimizing 35KV substation access Active CN107658872B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711002680.0A CN107658872B (en) 2017-10-24 2017-10-24 Power grid transformation method for optimizing 35KV substation access

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711002680.0A CN107658872B (en) 2017-10-24 2017-10-24 Power grid transformation method for optimizing 35KV substation access

Publications (2)

Publication Number Publication Date
CN107658872A true CN107658872A (en) 2018-02-02
CN107658872B CN107658872B (en) 2021-04-06

Family

ID=61117886

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711002680.0A Active CN107658872B (en) 2017-10-24 2017-10-24 Power grid transformation method for optimizing 35KV substation access

Country Status (1)

Country Link
CN (1) CN107658872B (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP2461459A2 (en) * 2010-12-01 2012-06-06 Technische Universität Dortmund Control system
CN103855618A (en) * 2014-03-31 2014-06-11 国网上海市电力公司 10kV switching station
CN105354645A (en) * 2015-12-02 2016-02-24 国网山东省电力公司经济技术研究院 220kV transformer substation load transfer method
CN106451462A (en) * 2016-11-01 2017-02-22 国网上海市电力公司 Method for improving transfer supply capability of substation of power distribution network
CN106487012A (en) * 2016-11-30 2017-03-08 云南电网有限责任公司 A kind of system of selection of high voltage distribution network powering mode and system

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP2461459A2 (en) * 2010-12-01 2012-06-06 Technische Universität Dortmund Control system
CN103855618A (en) * 2014-03-31 2014-06-11 国网上海市电力公司 10kV switching station
CN105354645A (en) * 2015-12-02 2016-02-24 国网山东省电力公司经济技术研究院 220kV transformer substation load transfer method
CN106451462A (en) * 2016-11-01 2017-02-22 国网上海市电力公司 Method for improving transfer supply capability of substation of power distribution network
CN106487012A (en) * 2016-11-30 2017-03-08 云南电网有限责任公司 A kind of system of selection of high voltage distribution network powering mode and system

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
汪东: "220KV寿州变电站综合自动化改造", 《中国优秀硕士论文全文数据库 工程科技II辑》 *

Also Published As

Publication number Publication date
CN107658872B (en) 2021-04-06

Similar Documents

Publication Publication Date Title
CN107038530A (en) A kind of power distribution network overall planning method and system
CN109687496B (en) Method for calculating reliability of alternating current-direct current hybrid flexible power distribution network
CN109787224B (en) Method for generating regional power grid load transfer strategy for preventing cascading overload
CN104934972A (en) Active tide control power grid and control method of power exchange power node and medium-voltage distribution network
CN113689119B (en) Power distribution network power supply reliability evaluation method, equipment and medium based on digital twin
CN103839116B (en) A kind of substation capacity collocation method based on different power supply areas
CN110932258A (en) Diamond type distribution network
CN111009906B (en) Reactive compensation balancing method for full cable net rack
CN109768544B (en) Regional power grid load transfer method
CN108649578B (en) Method and device for adjusting grid structure and optimizing networking mode of high and medium voltage urban network
CN107176063A (en) A kind of electric railway external electrical network powered construction
CN203104104U (en) Optimized backbone transmission network system for electric power information communication
CN211351263U (en) 110kV transformer substation main wiring structure applying split transformer
CN107204624B (en) Power transmission system suitable for global energy Internet and control method thereof
CN107658872A (en) A kind of electric network reconstruction method for optimizing the access of 35 kv substations
CN204696685U (en) Power Exchange node and medium voltage distribution network initiatively power flowcontrol electrical network
CN115207919A (en) Grid frame system suitable for rural overhead power distribution network and grid frame construction method
CN111091307A (en) Power distribution network resource processing method, storage medium and processor
CN106356866A (en) Automatic voltage control substation device of intelligent substation and control method thereof
CN106099916B (en) A kind of method that 110kV substation load transfer scheme quickly determines
CN106130009B (en) A kind of method that 220kV substation load transfer scheme quickly determines
Büchner et al. Smart Grids in Germany: How much costs do distribution grids cause at planning time?
CN110011320B (en) Reactive voltage optimization control method and system for extra-high voltage alternating current transformer substation
CN113904326A (en) Urban distribution network wiring mode
Zhou et al. Mesh planning optimization for urban distribution network with high reliability

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant