CN107611944B - A kind of intelligent substation secondary protection equipment safety quarantine measures automatic analysis method - Google Patents

A kind of intelligent substation secondary protection equipment safety quarantine measures automatic analysis method Download PDF

Info

Publication number
CN107611944B
CN107611944B CN201710856671.1A CN201710856671A CN107611944B CN 107611944 B CN107611944 B CN 107611944B CN 201710856671 A CN201710856671 A CN 201710856671A CN 107611944 B CN107611944 B CN 107611944B
Authority
CN
China
Prior art keywords
equipment
secondary device
isolated
circuit
goose
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201710856671.1A
Other languages
Chinese (zh)
Other versions
CN107611944A (en
Inventor
石光
韩伟
马伟东
孔圣立
张道杰
王广民
肖亮
慕宗君
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Electric Power Research Institute of State Grid Henan Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
Electric Power Research Institute of State Grid Henan Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Electric Power Research Institute of State Grid Henan Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201710856671.1A priority Critical patent/CN107611944B/en
Publication of CN107611944A publication Critical patent/CN107611944A/en
Application granted granted Critical
Publication of CN107611944B publication Critical patent/CN107611944B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Supply And Distribution Of Alternating Current (AREA)

Abstract

The invention discloses a kind of intelligent substation secondaries to protect equipment safety quarantine measures automatic analysis method, is based on SCD model, constructs empty path incidence model between first and second equipment correlation model and secondary device.For the primary equipment that needs have a power failure, associated secondary device is obtained automatically according to correlation model.The secondary device that needs are overhauled, the other secondary devices being associated are searched by Quadratic Imaginary circuit, had a power failure or the peace of power-off condition does not arrange principle according to secondary device, analyzing can make the peace be reliably isolated of secondary device of maintenance arrange operation, further it is efficient examine to pacify arranges operation order whether safe and reliable.

Description

A kind of intelligent substation secondary protection equipment safety quarantine measures automatic analysis method
Technical field
The present invention relates to technical field of electric power automation more particularly to a kind of intelligent substation secondary protection equipment safety every From measure automatic analysis method.
Background technique
Currently, the circuit form of the composition of relay protection device of intelligent substation and conventional stations have larger difference, secondary circuit The digital message composition being changed under IEC61850 specification, analog quantity sampling circuit use the SV message of IEC61850 9-2, protection The information such as tripping, input and output use the GOOSE message of IEC61850 8-1.Intelligent substation changes, extends and when turnaround of unit, The operation of secondary device safety measure mainly by breaker tripping and closing output clamping, maintenance pressing plate, GOOSE send to receive soft pressing plate etc. a variety of The features such as peace arranges technical combinations to form, and that there is pressing plate quantity is more, not intuitive, without " obvious electrical break point ", in operation It is easy to cause leakage to throw move back, miscarry and move back.Once there is leakage throwing, miscarrying will result in serious electric network fault.
The normal safety inspection of secondary device arranges operation order using the peace finished, carries out safety operation.But intelligence Energy substation is in enlarging, reconstruction and unconventional maintenance, it usually needs interim manual compiling safety operation ticket, so safety The quality of writing of operation order is also a problem place, and it is a urgent need solution that relevant secondary device, which how is isolated to high efficient and reliable, Certainly the problem of, how to carry out preoperative safety analysis to safety operation ticket is also to be difficult to solve the problems, such as.
Summary of the invention
The object of the present invention is to provide a kind of intelligent substation secondaries to protect equipment safety quarantine measures automatic analysis method, Must operating for secondary device security isolation can be analyzed, to be able to verify that peace arranges operation order whether safe and reliable.
The technical solution adopted by the present invention are as follows:
A kind of intelligent substation secondary protection equipment safety quarantine measures automatic analysis method, comprising the following steps:
A: it is based on SCD model, the empty path incidence model between the association of first and second equipment of building and secondary device: is utilized The information modelings such as the primary equipment configuration of SCD file, secondary device configuration, communication, pressing plate, the association of first and second equipment of building and Empty path incidence model between secondary device;
B: analysis, which obtains, needs the equipment collection be isolated: obtaining a secondary device to be isolated or deactivated once sets It is standby, if it is deactivated primary equipment is needed, then relevant secondary device is obtained automatically according to correlation model, relevant secondary Equipment is associated with secondary device collection to be isolated;If it is a secondary device to be isolated, then the secondary device with isolation The equipment collection that ontology is isolated as needs;
C: the secondary device investment maintenance pressing plate that the equipment be isolated of needs is concentrated, and successively judge to be isolated secondary set It is standby to concentrate whether secondary device is protected device, D is then entered step if not protected device, is set if it is by protection It is standby, then first protected secondary device is carried out entering back into step D after protection is exited;
D: the secondary device method of operation concentrated to the equipment that needs are isolated checks: not stopping if it is primary equipment Electricity then guarantees that primary equipment has double set protections and at least a set of protection operates normally, then carries out in next step, otherwise directly Binding beam;
E: in above-mentioned steps D primary equipment and/or secondary device successively according to secondary device have a power failure or do not have a power failure The safety measure principle of situation analyzes the safety measure operation that can make that the secondary device overhauled is needed reliably to be isolated, thus according to Security isolation is completed in safety measure operation accordingly.
Security isolation is carried out to each secondary device and/or primary equipment of secondary device to be isolated concentration in the step E Specifically comprise the following steps:
E1: all secondary circuits in each secondary device concentrated to secondary device to be isolated successively traverse, and obtain The equipment connected to the empty circuit other end, to judge that the empty circuit of each secondary circuit is to belong to the circuit GOOSE or SV Circuit, wherein the equipment and circuit to circuit both ends carry out isolated operation, if primary equipment does not have a power failure, must assure that has Double sets are protected and have a set of protection to operate normally, and otherwise isolated process exits;
E2: if the empty circuit of secondary device to be isolated belongs to the circuit GOOSE, to this relevant equipment to be isolated The circuit GOOSE and terminal device execute peace and arrange isolation: specifically including and exit equipment GOOSE output clamping, it is another to exit the circuit GOOSE The GOOSE of one end running equipment receives pressing plate, and wherein equipment is concentrated between secondary device to be isolated relevant to primary equipment GOOSE pressing plate does not move back;
E3: if the empty circuit of equipment to be isolated is to be not belonging to the circuit GS, equipment to be isolated is to belong to the circuit SV, to this The circuit SV of relevant equipment to be isolated and the other end execute peace and arrange isolation: specifically including: the protection equipment of the circuit the SV other end SV need to be exited and receive pressing plate, need to deactivate the protective device for receiving SV, device SV receives pressing plate and can not move back.
The present invention is based on SCD model, empty path incidence model between the association of first and second equipment and secondary device is constructed.It is right In the primary equipment that needs have a power failure, associated secondary device is obtained automatically according to correlation model.Two that needs are overhauled Secondary device searches the other secondary devices being associated by Quadratic Imaginary circuit, is having a power failure or is not having a power failure according to secondary device The peace of situation arranges principle, and the peace that analyzing can be such that the secondary device of maintenance is reliably isolated arranges operation, and further efficient examine is pacified Arrange operation order whether safe and reliable.
Detailed description of the invention
Fig. 1 is flow chart figure of the invention;
Fig. 2 is the flow chart of security isolation of the present invention.
Specific embodiment
As illustrated in fig. 1 and 2, the present invention includes that a kind of intelligent substation secondary protection equipment safety quarantine measures automatically analyze Method, comprising the following steps:
A: being based on SCD model, constructs the empty path incidence model between first and second equipment correlation model and secondary device: Using information modelings such as the primary equipment configuration of SCD file, secondary device configuration, communication, pressing plates, constructs first and second equipment and close Empty path incidence model between gang mould type and secondary device;
B: analysis, which obtains, needs the equipment collection be isolated: obtaining a secondary device to be isolated or deactivated once sets It is standby, if it is deactivated primary equipment is needed, then relevant secondary device is obtained automatically according to correlation model, to be deactivated one Secondary device and obtained relevant secondary devices all therewith are associated with the secondary device collection with isolation;It is to be isolated if it is one Secondary device, then using the secondary device ontology with isolation as needing the equipment collection be isolated;
C: the secondary device investment maintenance pressing plate that the equipment be isolated of needs is concentrated, and successively judge to be isolated secondary set It is standby to concentrate whether secondary device is protection equipment, D is then entered step if not protection equipment, if it is protection equipment, is then protected Shield enters back into step D after exiting;
D: the method for operation of secondary device and/or primary equipment that the equipment that needs are isolated is concentrated is checked: if it is Primary equipment does not have a power failure, then guarantees that primary equipment has double set protections and at least a set of protection operates normally, then carry out In next step, otherwise direct termination of security analysis process;
E: successively having a power failure or the safety of power-off condition is not arranged according to secondary device to the secondary device in above-mentioned steps D Principle is applied, the safety measure operation that can make that the secondary device overhauled is needed reliably to be isolated is analyzed, thus according to this safety measure Security isolation is completed in operation.Carrying out isolated operation to the equipment at circuit both ends and circuit in the present invention, (isolated operation refers to moving back The transmission in the circuit GOOSE and SV, reception pressing plate out, it is also possible to including operations such as protection the out of service of equipment, output clampings), If primary equipment does not have a power failure, must assure that, there are double sets to protect and have a set of protection to operate normally, otherwise isolated process It exits.
Each secondary device progress security isolation that secondary device to be isolated is concentrated is specifically included in the step E as follows Step:
E1: all secondary circuits in each secondary device concentrated to secondary device to be isolated successively traverse, and obtain The equipment connected to the empty circuit other end, to judge that the empty circuit of each secondary circuit is to belong to the circuit GOOSE or SV Circuit;Equipment and circuit to circuit both ends carry out isolated operation, and (isolated operation generally referred to as exits the circuit GOOSE and SV Send, receive pressing plate, it is also possible to including operations such as protection the out of service of equipment, output clampings), if primary equipment does not stop Electricity, then must assure that, there are double sets to protect and have a set of protection to operate normally, and otherwise isolated process exits;
E2: if the empty circuit of secondary device to be isolated belongs to the circuit GOOSE, to this relevant equipment to be isolated The circuit GOOSE and terminal device execute peace and arrange isolation: specifically including and exit equipment GOOSE output clamping, it is another to exit the circuit GOOSE The GOOSE of one end running equipment receives pressing plate, and wherein equipment is concentrated between secondary device to be isolated relevant to primary equipment GOOSE pressing plate does not move back;
E3: if the empty circuit of equipment to be isolated is to be not belonging to the circuit GS, equipment to be isolated is to belong to the circuit SV, to this The circuit SV of relevant equipment to be isolated and the other end execute peace and arrange isolation: specifically including: the protection equipment of the circuit the SV other end SV need to be exited and receive pressing plate, need to deactivate the protective device for receiving SV, device SV receives pressing plate and can not move back.
This patent constructs empty path incidence mould between the association of first and second equipment and secondary device based on new SCD model Type.For the primary equipment that needs have a power failure, associated secondary device is obtained automatically according to correlation model.For needing to overhaul Secondary device, other secondary devices for being associated are searched by Quadratic Imaginary circuit, are being had a power failure or not according to secondary device The peace of power-off condition arranges principle, and the peace that analyzing can be such that the secondary device of maintenance is reliably isolated arranges operation;
Peace arranges the main principle of isolation as follows: when the verification of 1 device or the field operations such as defect elimination, should be isolated sampling, tripping, Close a floodgate, open it is relevant to running equipment in failure circuit contact, and guarantee the normal operation of running equipment;2, single set equipment verifies Or when defect elimination, it should stop to use as a servant primary equipment;The secondary device of duplicate system retrofit, only single set equipment verification or when defect elimination can be with Do not stop to use as a servant primary equipment, but prevents primary equipment unprotect from running;3, there is the optical cable of soft pressing plate for sending side or receiving side, Optical fiber is not turned off as far as possible, guarantees that soft pressing plate has disconnected before disconnecting;4, when the security isolation of circuit, dual safety quarantine measures are taken. It is the transmission pressing plate of apparatus for examination and repair first, followed by the reception pressing plate of related running gear, also it is contemplated that the maintenance of apparatus for examination and repair Pressing plate.According to isolation principle, using following steps:
A, the secondary circuit of equipment is traversed, the equipment for obtaining empty circuit information and the connection of the circuit other end;
B, the method for operation of xegregating unit is checked, if primary equipment does not have a power failure, must assure that has double sets It protects and there is a set of protection to operate normally, otherwise isolated process exits.
C, peace is executed to the circuit GOOSE and terminal device and arranges isolation: exiting equipment GOOSE output clamping;GOOSE is exited to return The GOOSE of road other end running equipment receives pressing plate;GOOSE when deactivating primary equipment, between the secondary device of equipment concentration Pressing plate can not move back;
D, execute peace to the circuit SV of equipment and another both ends and arrange isolation: the protection equipment of the circuit the SV other end need to exit SV Receive pressing plate;When not deactivating primary equipment, need to deactivate the protective device for receiving SV, device SV receives pressing plate and can not move back.
The present invention is based on SCD model, empty path incidence model between the association of first and second equipment and secondary device is constructed.It is right In the primary equipment that needs have a power failure, associated secondary device is obtained automatically according to correlation model.Two that needs are overhauled Secondary device searches the other secondary devices being associated by Quadratic Imaginary circuit, is having a power failure or is not having a power failure according to secondary device The peace of situation arranges principle, and the peace that analyzing can be such that the secondary device of maintenance is reliably isolated arranges operation, and further efficient examine is pacified Arrange operation order whether safe and reliable.

Claims (2)

1. a kind of intelligent substation secondary protects equipment safety quarantine measures automatic analysis method, it is characterised in that: including following Step:
A: it is based on SCD model, the empty path incidence model between the association of first and second equipment of building and secondary device: utilizes SCD text Primary equipment configuration, the secondary device configuration, communication, pressing plate information modeling of part, the association of first and second equipment of building and secondary device Between empty path incidence model;
B: analysis obtains the equipment collection for needing to be isolated: obtaining a secondary device to be isolated or deactivated primary equipment, such as Fruit is to need deactivated primary equipment, then relevant secondary device is obtained automatically according to correlation model, relevant secondary device It is associated with secondary device collection to be isolated;If it is a secondary device to be isolated, then secondary device ontology to be isolated The equipment collection being isolated as needs;
C: the secondary device investment maintenance pressing plate that the equipment that needs are isolated is concentrated, and successively judge secondary device collection to be isolated Whether middle secondary device is protected device, then enters step D if not protected device, if it is protected device, then First protected secondary device is carried out to enter back into step D after protection is exited;
D: the secondary device method of operation concentrated to the equipment that needs are isolated checks: do not have a power failure if it is primary equipment, Guarantee that primary equipment has double set protections and at least a set of protection operates normally, then carries out in next step, otherwise directly tying Beam;
E: in above-mentioned steps D primary equipment and/or secondary device successively according to secondary device have a power failure or the feelings that do not have a power failure The safety measure principle of condition analyzes the safety measure operation that can make that the secondary device overhauled is needed reliably to be isolated, thus foundation Security isolation is completed in the operation of this safety measure.
2. a kind of intelligent substation secondary according to claim 1 protects equipment safety quarantine measures automatic analysis method, It is characterized in that, carrying out safety to each secondary device and/or primary equipment of secondary device to be isolated concentration in the step E Isolation specifically comprises the following steps:
E1: all secondary circuits in each secondary device concentrated to secondary device to be isolated successively traverse, and obtain void The equipment that the circuit other end is connected, thus judge that the empty circuit of each secondary circuit is to belong to the circuit GOOSE or the circuit SV, Wherein the equipment to circuit both ends and circuit carry out isolated operation, if primary equipment does not have a power failure, must assure that has double sets It protects and there is a set of protection to operate normally, otherwise isolated process exits;
E2: if the empty circuit of secondary device to be isolated belongs to the circuit GOOSE, to the GOOSE of this relevant equipment to be isolated Circuit and terminal device execute peace and arrange isolation: specifically including and exit equipment GOOSE output clamping, exit the circuit the GOOSE other end The GOOSE of running equipment receives pressing plate, and wherein equipment concentrates the GOOSE between secondary device to be isolated relevant to primary equipment Pressing plate does not move back;
E3: if the empty circuit of equipment to be isolated is to be not belonging to the circuit GOOSE, equipment to be isolated is to belong to the circuit SV, to this The circuit SV of relevant equipment to be isolated and the other end execute peace and arrange isolation: specifically including: the protection equipment of the circuit the SV other end SV need to be exited and receive pressing plate, need to deactivate the protective device for receiving SV, device SV receives pressing plate and do not move back.
CN201710856671.1A 2017-09-21 2017-09-21 A kind of intelligent substation secondary protection equipment safety quarantine measures automatic analysis method Active CN107611944B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710856671.1A CN107611944B (en) 2017-09-21 2017-09-21 A kind of intelligent substation secondary protection equipment safety quarantine measures automatic analysis method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710856671.1A CN107611944B (en) 2017-09-21 2017-09-21 A kind of intelligent substation secondary protection equipment safety quarantine measures automatic analysis method

Publications (2)

Publication Number Publication Date
CN107611944A CN107611944A (en) 2018-01-19
CN107611944B true CN107611944B (en) 2019-06-28

Family

ID=61061631

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710856671.1A Active CN107611944B (en) 2017-09-21 2017-09-21 A kind of intelligent substation secondary protection equipment safety quarantine measures automatic analysis method

Country Status (1)

Country Link
CN (1) CN107611944B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110070189B (en) * 2018-01-23 2023-05-23 福建永福数字能源技术有限公司 Intelligent substation protection system safety measure checking method

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103346497A (en) * 2013-07-09 2013-10-09 广东电网公司珠海供电局 Intelligent substation electrical virtual circuit isolation method and system
US8774975B2 (en) * 2011-02-08 2014-07-08 Avista Corporation Outage management algorithm
CN104617672A (en) * 2015-02-12 2015-05-13 上海毅昊自动化有限公司 Online monitoring system for modeling based on physical communication medium of process level
CN106159759A (en) * 2016-07-13 2016-11-23 国网四川省电力公司电力科学研究院 A kind of method automatically generating secondary system of intelligent substation maintenance safety measure
CN106384304A (en) * 2016-10-20 2017-02-08 许继集团有限公司 Intelligent substation secondary equipment safety measure bill automatic construction method and device
CN107147214A (en) * 2017-03-02 2017-09-08 许继集团有限公司 A kind of secondary peace suitable for intelligent substation arranges monitoring system

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US8774975B2 (en) * 2011-02-08 2014-07-08 Avista Corporation Outage management algorithm
CN103346497A (en) * 2013-07-09 2013-10-09 广东电网公司珠海供电局 Intelligent substation electrical virtual circuit isolation method and system
CN104617672A (en) * 2015-02-12 2015-05-13 上海毅昊自动化有限公司 Online monitoring system for modeling based on physical communication medium of process level
CN106159759A (en) * 2016-07-13 2016-11-23 国网四川省电力公司电力科学研究院 A kind of method automatically generating secondary system of intelligent substation maintenance safety measure
CN106159759B (en) * 2016-07-13 2018-03-20 国网四川省电力公司电力科学研究院 A kind of method for automatically generating secondary system of intelligent substation maintenance safety measure
CN106384304A (en) * 2016-10-20 2017-02-08 许继集团有限公司 Intelligent substation secondary equipment safety measure bill automatic construction method and device
CN107147214A (en) * 2017-03-02 2017-09-08 许继集团有限公司 A kind of secondary peace suitable for intelligent substation arranges monitoring system

Also Published As

Publication number Publication date
CN107611944A (en) 2018-01-19

Similar Documents

Publication Publication Date Title
CN104539043B (en) A kind of automatic switching device of standby power supply system haul oneself willingly into method
CN101673965B (en) Automatic switching control method for wide-area emergency power source of electric power system
CN106159759B (en) A kind of method for automatically generating secondary system of intelligent substation maintenance safety measure
CN106169740A (en) 110kV single-trunk segmental wiring incoming relay-protection locking prepared auto restart relay protecting method
CN103679350A (en) Power grid switching operation ticket automatic generating system and method
CN105069697A (en) Intelligent transformer station maintenance strategy automatic identification system and method
CN113364120B (en) Method, device and equipment for checking control process of intelligent substation and storage medium
CN104749487B (en) A kind of method in check protection device and its loop under circuit no cut-off condition
CN105470935B (en) A kind of intelligent substation relay protection device defect security isolation aid decision-making method
CN103872656A (en) Distributive bus fast protection realization method for intelligent transformer substation
CN103346497B (en) Intelligent substation electrical virtual circuit isolation method and system
CN105573283A (en) Transformer station equipment function association database establishing method and event association information group filtering method
CN201789272U (en) Relay protection circuit preventing transformer differential protection malfunction
CN102005819A (en) Fault isolation method of electric distribution network
CN107611944B (en) A kind of intelligent substation secondary protection equipment safety quarantine measures automatic analysis method
CN110619396A (en) Intelligent substation one-key type secondary safety measure generation method
CN108963841A (en) It is associated with the secondary device sequence method and system of primary equipment operating status
CN103887775B (en) Distribution network microcomputer protection system integrating distribution automation master station dynamic setting
CN101409443B (en) Line differential protection method capable of adapting by-path running status automatically
CN107947136A (en) A kind of Distribution Network Failure fast positioning cutting method and system based on fault vector
CN103701201B (en) Realize the system of locking prepared auto restart during stability control device action cutting load
CN207518284U (en) A kind of accident disconnection device of small power incorporating into power network
CN201860172U (en) Automatic looped network type distribution network based on reclosers
CN106684821A (en) Intelligent power distribution protection device with self-healing function and application thereof
CN106226687A (en) A kind of method for the checking of voltage-type on-load switch automation function

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant