CN107609794A - A kind of technology maturity evaluation information processing unit - Google Patents

A kind of technology maturity evaluation information processing unit Download PDF

Info

Publication number
CN107609794A
CN107609794A CN201710933643.5A CN201710933643A CN107609794A CN 107609794 A CN107609794 A CN 107609794A CN 201710933643 A CN201710933643 A CN 201710933643A CN 107609794 A CN107609794 A CN 107609794A
Authority
CN
China
Prior art keywords
evaluation
technology
layer
data
grade
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710933643.5A
Other languages
Chinese (zh)
Inventor
陈青
邱新媛
王广金
李朋州
周天
高志虎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nuclear Power Institute of China
Original Assignee
Nuclear Power Institute of China
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nuclear Power Institute of China filed Critical Nuclear Power Institute of China
Priority to CN201710933643.5A priority Critical patent/CN107609794A/en
Publication of CN107609794A publication Critical patent/CN107609794A/en
Pending legal-status Critical Current

Links

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses a kind of technology maturity evaluation information processing unit, including access layer, infrastructure service layer, core layer, data Layer and hardware layer;Infrastructure service layer, controlled for technology maturity evaluation rubric and data caused by evaluation rubric are analyzed and handled, including:Evaluate Whole Course Management module, technical information management module, document management module.The present invention has the characteristics such as the working specification guide of procedure, efficient information processing manner, the report template output of standardization.The evaluation information processing unit can be used in nuclear power and nuclear power field, also can be widely used to the new high-tech industry such as space flight and aviation, ship, petrochemical industry field.

Description

A kind of technology maturity evaluation information processing unit
Technical field
The present invention relates to technology maturity to evaluate field, and in particular to a kind of technology maturity evaluation information processing unit.
Background technology
Technology maturity evaluation is that a kind of developed based on technology develops rule with project, and grade is measured to skill using standardization Set of system standard, the methods and procedures that art maturity is evaluated.From mid-term American National space flight the 1970s Since office Sadin proposes technology maturity concept first, tend to be ripe the 1990s substantially, it is beautiful afterwards into 21 century The mechanisms such as Ministry of National Defence of state, audit in U.S.A. administration, European Space Agency or tissue are widely used, and it is reducing equipment preparation technical risk and solution The problems such as equipment preparation " degree of being dragged into, drop index, rise expense ", aspect played important function, especially had exploration to some Technology, funds and the risk of management can be effectively reduced with the project of novelty, technical specialist and manager is lived in research and development management Combined well in dynamic.
Nuclear power and nuclear power projects have the characteristics of investment is big, the cycle is long, technology is new, especially China's nuclear power at this stage And the exploitation of nuclear power model is digested and assimilated by the technology transfer of early stage, has enter into the integrated innovation stage.This technology path Transformation, add the uncertainty of model research and development.In great nuclear power and nuclear power development project, evaluated using technology maturity Research Management can be instructed to formulate practicable science and technology development planning and risk management and control, held for technical staff in project development Row order section provides transition number, the scientific basis of upper engineering.Technology maturity appraisal at present is mainly commented by technology maturity Valency Research Management organizes, and evaluates scientific research personnel first and fills in assessment item essential information, collects CTE (key technologies Element) various data messages of the identification needed for TRL (technology maturity grade) judgements, carry out technology maturity self-evaluation and life Reported into self-evaluation, then submit assessment item application to management level, last organizes expert is commented technology maturity report Examine.Evaluating that overall process is substantially lower online to be carried out, its personnel is related to numerous, and evaluation rubric is more complicated, expends more time and energy, Assessment item is caused effectively to be managed and flow monitoring.Can not be convenient simultaneously for the project evaluated Its evaluation procedure is inquired about and traces, its evaluation durability for relevant item is low.
Therefore, it is necessary to the method for informationization is incorporated into nuclear power and the management of nuclear power technology maturity assessment, with reference to The Project-developing feature of nuclear power and nuclear power field, invention is a kind of to be evaluated suitable for nuclear power and the technology maturity of nuclear power field Information processor.
The research to evaluation method is concentrated mainly on to technology maturity evaluation both at home and abroad at present, lacked at evaluation information The exploitation of device is managed, existing evaluating apparatus again more is directed to space flight and aviation and weaponry field, and directly set moves used in core by it Power and nuclear power field lack of targeted, while its operability is not strong.As the A of Chinese patent CN 103226743 are announced《It is based on TRL aircraft equipment technology maturity assesses information processing method》Mainly illustrate be assess information handling process, its scope Primarily directed to aircraft equipment, it is not suitable for nuclear power and nuclear power field, commenting based on Template Manager client and project in patent It is cumbersome to estimate two kinds of information processing manners of client, not easy to operate, it, which assesses Template Information, needs voluntarily to make according to disparity items It is fixed, without unified Template Information.The function division that each user implements to operate in evaluation tissue is indefinite, and experts' evaluation is not to commenting Valency task is divided the work, and it is big that it directly carries out evaluating whole project work amount, while it is to experts' evaluation function in tissue-estimating Module elaboration is not general comprehensive, and its estimation flow only identifies key technology element and assesses key technology element maturity, not by force Adjust Project decomposition structure evaluation functional block.The information processing manner lacks the statistical analysis to evaluation result, the intuitive of information It is not strong, it is unfavorable for global control and the coordinated management of entry of the management level to project key technology, while lack expert's depositary management The tackling problems in key technologies functional module managed module and implemented for influenceing subsequent project.The U of national patent CN 202838345《Base Information processor is assessed in TRL aircraft equipment technology maturity》Though the hardware structure supplemented with device, it is not specific In detail, the effect of client, application server, communication network and database server is only simply described, is lacked to each composition The elaboration of middle key function module, it can not learn how to complete whole evaluation rubric using each composition of hardware structure.In addition such as What the A of Chinese patent CN 103391317 were announced《A kind of system technology maturity appraisal procedure and device》The appraisal procedure and dress It is put it is emphasised that the operation of keeper and the role of expert two to technology maturity apparatus for evaluating, and not offline version this should With scene, technology maturity evaluation rubric control and data caused by evaluation rubric are analyzed and processing module on, close The basis of design of key technology item is excessively simple, technology maturity can be caused to judge not rigorous enough, adaptive surface is not wide.
A kind of technology maturity evaluation information processing unit for being applied to nuclear power and nuclear power field, utilizes information-based hand Section, the existing achievements in research such as evaluation method, evaluation rubric, job specification, opinion rating condition, result treatment are integrated, its Can completing technology maturity assessment on line overall process, including formulate Project decomposition structure, key technology elemental recognition, technology The appraisals such as the judgement of maturity grade, tackling problems in key technologies, realize that appraisal report automatically generates, evaluation information variation shows Show, assessment item can the function such as tracing management.
The content of the invention
Present invention aims at a kind of technology maturity evaluation information processing unit is provided, the present invention has the behaviour of procedure Make the characteristics such as Practice guidelines, efficient information processing manner, the report template output of standardization.The evaluation information processing unit energy Nuclear power and nuclear power field are enough in, also can be widely used to the new high-tech industry such as space flight and aviation, ship, petrochemical industry field.
The present invention is achieved through the following technical solutions:
A kind of technology maturity evaluation information processing unit, including access layer, infrastructure service layer, core layer, data Layer and Hardware layer;
Access layer, progress technology maturity evaluation is logged in for providing user;
Data Layer, for the process data and relevant documentation data submitted during memory technology maturity assessment;
Core layer, for building distribution role-security module, building evaluation automatic flow module and building evaluation number According to analysis and processing unit;
Hardware layer, for realizing that access layer, infrastructure service layer, core layer, data Layer build basis;
Infrastructure service layer, for technology maturity evaluation rubric control and to data caused by evaluation rubric carry out analysis and Processing, including:
Whole Course Management module is evaluated, for the control to evaluation procedure, evaluation Whole Course Management module includes:Project knot Structure resolving cell, for establishing the multi-layer architecture of project using technology resolving cell as terminal node;Key technology identifies Unit, for carrying out key problem in technology degree identification to technology resolving cell;Software and hardware technology grade preliminary judgement unit, carry out soft The preliminary grade of part key technology grade or hardware key technology grade judges;Key Software grade sentences unit and hardware in detail Key technology grade sentences unit in detail, for carrying out final grade judgement to Key Software or hardware key technology;System Maturity computing unit, utilize short slab method and the more CTE of calculated with weighted average method system maturation degree;
Technical information management module, the grade result of determination of project-based multiple technology items, with short slab method and weighting The method of average carries out statistical analysis to the data of result of determination:Evaluate integrated information output, TRL visualization contrast, decomposition texture can Depending on changing contrast and CTE statistic of classifications;
Document management module, for generating accordingly report and the management to relevant documentation in evaluation rubric after the completion of evaluation.
Access layer includes technology maturity evaluation management for being responsible for user based on access of the client to data Layer, user Layer, evaluation executing agency, expert group, the side of being evaluated, the client of login is PC, and user is realized different by web browser Data syn-chronization between user.
Technical information management module includes evaluation integrated information statistic unit, TRL visualizations comparison unit, decomposition texture can Depending on changing comparison unit and CTE statistic of classification units, the system of support disparity items different phase and different CTE TRL are visual Change contrast, decomposition texture carries out images outputting contrast and closed according to TRL grades or CTE technology in all previous evaluation of specific project Stroke degree classification carries out the corresponding CTE of statistic of classification quantity, be easy to unified management of the manager to entry, resource allocation and The global control of key technology to project of interest.
Infrastructure service layer also includes experts' evaluation module, and expert is commented technology maturity in tissue-estimating on line Examine.
Data Layer specifically includes demographic data's layer in evaluation personnel storehouse, assessment item data Layer, evaluation rubric data Layer, commented Valency criteria data layer and relevant documentation data, wherein interpretational criteria data Layer include again:Technical significance classification chart, technical risk Property classification chart, key technology recognition matrix tables of data, hardware technology factor change-technology maturity grade detail list, software skill Art factor change-technology maturity grade detail list, hardware key technology grade judge that detail list, Key Software grade are sentenced Determine detail list.
Demographic data's layer in evaluation personnel storehouse:Evaluation management layer, the side of being evaluated, expert group and evaluation executing agency everyone Basic document;Assessment item data Layer:That is the essential information of assessment item, the formulation of appraisal plan and Working Group on Evaluation Foundation;Evaluation rubric data Layer:The final inventory of Project decomposition structure, CTE, CTE and system TRL decision statistics analysis knot Fruit and experts' evaluation opinion.
Evaluating Whole Course Management module also includes tackling key problem planning unit, for for CTE to be tackled key problems, according to current TRL With the tackling key problem TRL to be reached, the TRL lists for needing to tackle key problems are automatically generated, by loading evaluation all-purpose grade condition and having completed Evaluation result, compare all entries in selected TRL, be made whether the verification met, corresponding bar is carried out according to verification result Purpose is planned, and finally automatically generates tackling problems in key technologies planning report according to planning result.
Experts database is individually managed and safeguarded by system manager in the demographic data of evaluation personnel storehouse, unified to personnel storehouse role Authority is configured, and support is docked with system OA storehouses and adds expert outside storehouse manually, is entered according to not commensurate, different majors condition Row refined queries, it is easy to the evaluation of disparity items technology maturity to carry out the selection of expert according to project art.
Evaluation rubric data Layer stored to caused data in evaluation information handling process, retrieved, inquired about, is multiplexed, Change and liter version.
Interpretational criteria data Layer enters row information storage, change based on technology maturity evaluation criterion specification and safeguarded.
Relevant documentation data in data Layer also includes the detailed Tips in evaluation system interface, for each in advisory visit layer User implements technology maturity related work, and comprising technology maturity assessment guidelines, relevant criterion and with informative The learning database of appraisal report example.
The function of access layer is implemented to be completed by infrastructure service layer and data Layer, be mainly used in evaluation rubric business control and The preservation of related data.
Project structure breakdown unit creates decomposition texture tree structure, project structure export by the addition or deletion of node By selection node position or the export of node position level in the form of three kinds of tree-like, form and intermediate file, while intermediate file can be led Enter project structure breakdown unit, the Project decomposition structure of similar or identical evaluation can be also mutually multiplexed.
The application scenarios of the present invention are divided into two kinds of offline version and the network edition, and system uses B/S frameworks.
Offline its server of version evaluation information processing unit and storage device are integrated in access layer client, access layer Middle user directly carries out evaluation information processing on the client, after it completes self-evaluation work on line, is evaluated using offline version Information processor can carry out on-the-spot demonstration, record expert opinion and online modification self-evaluation report generation in experts' evaluation Latest report, its is applied widely, is not limited by region and personnel's authority.It can back up evaluation procedure and file data simultaneously, prop up Its system of synchronizing network version evaluation information processing unit timely with network edition evaluation information processing unit data is held using centralization Database deployment architecture, server and storage device are disposed in central machine room, only one need to be installed in the client of access layer Individual browser, you can be connected by communication network with server and storage device, carry out data interaction.
Network edition evaluation information processing unit is carried out on line except self-evaluation, and evaluation application and expert opinion flow also exist Carried out on line, by the pattern of task management, each user of access layer can log in client, check personal pending business, done and appointed Task situation is engaged in and finishes, from specially:Its self-evaluation, evaluation application and expert opinion are carried out on line, can be by appointing The pattern of business management, realize that each user of access layer checks personal pending business, done task and finish task feelings in client Condition, complete the switching of different role and different task in evaluation procedure, evaluation executing agency as evaluation rubric progress monitoring end, Multi-expert can be initiated by way of task distribution to evaluate, each expert can be examined being evaluated project simultaneously, evaluation result Evaluation executing agency is automatically fed to, and is carried out by it collecting arrangement.Such as expert opinion Lothrus apterus, then evaluation result is returned to The side of being evaluated, such as there is the inconsistent situation of expert opinion, by evaluating executing agency by initiating to comment again to inconsistent place Careful task coordinate unifies expert each side opinion, finally draws evaluation result.This operation can greatly improve evaluation efficiency, also allow for commenting Real-time tracking and tracing management of the Jia Ge establishment officers to evaluation rubric.
Offline version evaluation information processing unit due to being used in meeting examination scene more, and it evaluates application and evaluation is implemented to lead to Often do not carry out on line, but the concrete operations flow directly by being completed to expert's on-the-spot demonstration.At network edition evaluation information Device is managed except completion evaluation prepares and self-evaluation implementing procedure, it is also necessary to complete to submit being automatically generated to management level on line by system Evaluation application paper, and thus start experts' evaluation functional module, this module mainly complete expert on line to decompose tie The evaluation that structure, CTE inventories and CTE and system TRL judge, ultimately generates experts' evaluation opinion and is stored in data Layer.Two kinds The various reports generated under application scenarios support secondary editor, and can export as the file of WINDOWS operating systems identification, can User is facilitated to make the modification of adaptability according to actual conditions.
Project structure breakdown unit in device basic service layer by the addition of node, delete that to complete decomposition texture tree-like The establishment of structure, the coupling of STRUCTURE DECOMPOSITION and sub-project and top layer project for ease of the identical assessment item of phase Sihe, it is propped up Hold the multiplexing of decomposition texture and import and export, export mode, which is divided into, to be exported by node position and exported by node position level, supports tree Three kinds of shape, form and intermediate file (xml forms) forms, lead-in mode support xml formatted files.
Tackling problems in key technologies planning in device basic service layer is according to current TRL and tackling key problem for CTE to be tackled key problems The TRL to be reached is planned, and it can be supported step by step or across level tackling key problem, and device is by loading evaluation all-purpose grade condition and complete Into evaluation structure, one by one contrast tackling key problem rank all entries, the verification whether met, for being unsatisfactory for and not judging Entry, it is necessary to do corresponding research of technique, it is final utilize it is crucial corresponding to the tackling key problem report template generation stored in data Layer Research of technique planning report.
Statistical analysis of the technical information management module to evaluation result, can be screened by filter condition, can carry out different item The system TRL and different CTE of mesh different phase TRL visualization contrasts, the decomposition texture figure of all previous evaluation of specific project are defeated Go out contrast and count corresponding CTE quantity according to TRL grades or CTE key problem in technology degree category classification.This function can have Help manager's Amulti-project management and to key technology the overall situation grasp, be easy to project funds, human and material resources resource it is reasonable Distribution.
Overall process data and relevant documentation data are evaluated, supports the more CTE retrieval and inquisitions of entry.It can be different according to project Stage multiplexing change, it is convenient to rise version in time, including assessment item essential information, opinion rating condition and decomposition texture etc. are carried out Multiplexing change, rise version.Interpretational criteria data Layer and template document data, by the system maintenance personnel of information processor according to mark The change of quasi- specification carries out unified maintenance of information, while it is unified to personnel storehouse angle for network edition evaluation information processing unit Color authority is configured, and ensures the real-time of evaluation information renewal and the efficiently and accurately of evaluation on line.Expert in personnel storehouse Personnel expert outside the storehouse that storehouse is added manually comprising the expert in system OA storehouses and system maintenance personnel, it can guarantee that the complete of experts database Whole property, also inquiry can be finely divided according to conditions such as not commensurate, different majors, be easy to disparity items technology maturity to evaluate root The selection of expert is carried out according to project art.
The present invention compared with prior art, has the following advantages and advantages:
1st, the interpretational criteria of fully integrated science, the evaluation rubric of specification and tissue is clearly evaluated, is related to evaluation each Human roles can carry out the operation of each functional module according to system flow guide scientific and efficiently, cover the side's of being evaluated self-evaluation, Overall process is signed in management level examination & verification evaluation application, experts' evaluation to final appraisal results, and it can improve the normalization of evaluation, be easy to The unified management of evaluation procedure.
2nd, application scenarios of the invention are divided into offline version and the network edition, it is ensured that on-line off-line types of applications field is completely covered Scape.
3rd, its specific Project decomposition structure function module of the evaluation information processing unit, the not only increasing of supporting node Delete, also the multiplexing imported and exported between disparity items of supporting node tree;CTE identification functions module can be according to importance and wind The selection of dangerous two key element carries out matrix computations automatically, and technology is classified, finally identifies CTE;Technology maturity grade Decision-making function module can load automatically just to be sentenced three elements table and sentences each rating conditions in detail, and completion is just sentenced, sentenced in detail, iterative function, meter Individual event CTE technology maturity grade is calculated, and is based ultimately upon short slab method and calculated with weighted average method goes out the technology maturation of system Spend grade;Tackling problems in key technologies function also compares technology maturity rating conditions using completed evaluation result and carried out accordingly The planning tackling key problem of grade.
4th, the present invention can automatically save all kinds of pictures and form involved in evaluation procedure, while using file service Standard report template is deposited in device, self-evaluation report, evaluation application paper, tackling key problem planning report are automatically generated, for identical entry Mesh different phase or similar terms, device support the multiplexing of evaluation procedure data, can greatly reduce the work of appraisal personnel Amount, lift operating efficiency.
5th, the present invention can carry out statistical analysis to evaluation result, make the intuitive of evaluation result stronger, be easy to manager to enter Row all events management, tracking technique research and development, makes overall plans and coordinate each resource.Support the system of disparity items different phase and CTE TRL Contrast, by the graphic correlation of project decomposition texture in the CTE quantity statisticses and all previous evaluation of grade or CTE technology category.
6th, the present invention has the expert opinion module of high efficiency, is initiated by evaluating executing agency by way of task distribution Multi-expert is evaluated, and an expert need not carry out complete evaluation rubric, and each expert can be examined being evaluated project simultaneously, Evaluation result is automatically fed to evaluation executing agency, collects arrangement by it, is easy to being uniformly coordinated for expert opinion.
7th, the present invention is uniformly managed maintenance by system manager, it is ensured that all kinds of Template Informations upgrade in time, institute The file format uniformity of generation, it is ensured that the normalization and high efficiency of evaluation management.
Brief description of the drawings
Accompanying drawing described herein is used for providing further understanding the embodiment of the present invention, forms one of the application Point, do not form the restriction to the embodiment of the present invention.In the accompanying drawings:
Fig. 1 is schematic structural view of the invention.
Fig. 2 is the flow chart of the present invention.
Embodiment
For the object, technical solutions and advantages of the present invention are more clearly understood, with reference to embodiment and accompanying drawing, to this Invention is described in further detail, and exemplary embodiment of the invention and its explanation are only used for explaining the present invention, do not make For limitation of the invention.
Embodiment 1
As shown in figure 1, a kind of technology maturity evaluation information processing unit, including access layer, infrastructure service layer, core Layer, data Layer and hardware layer;
Access layer, progress technology maturity evaluation is logged in for providing user;
Data Layer, for the process data and relevant documentation data submitted during memory technology maturity assessment;
Core layer, for building distribution role-security module, building evaluation automatic flow module and building evaluation number According to analysis and processing unit;
Hardware layer, for realizing that access layer, infrastructure service layer, core layer, data Layer build basis;
Infrastructure service layer, for technology maturity evaluation rubric control and to data caused by evaluation rubric carry out analysis and Processing, including:
Whole Course Management module is evaluated, for the control to evaluation procedure, evaluation Whole Course Management module includes:Project knot Structure resolving cell, for establishing the multi-layer architecture of project using technology resolving cell as terminal node;Key technology identifies Unit, for carrying out key problem in technology degree identification to technology resolving cell;Software and hardware technology grade preliminary judgement unit, carry out soft The preliminary grade of part key technology grade or hardware key technology grade judges;Key Software grade sentences unit and hardware in detail Key technology grade sentences unit in detail, for carrying out final grade judgement to Key Software or hardware key technology;System Maturity computing unit, utilize short slab method and the more CTE of calculated with weighted average method system maturation degree;
Technical information management module, the grade result of determination of project-based multiple technology items, with short slab method and weighting The method of average carries out statistical analysis to the data of result of determination:Evaluate integrated information output, TRL visualization contrast, decomposition texture can Depending on changing contrast and CTE statistic of classifications;
Document management module, for generating accordingly report and the management to relevant documentation in evaluation rubric after the completion of evaluation.
When the application of embodiment 2 is offline version
As shown in Fig. 2 evaluation preparation is carried out, including assessment item essential information, appraisal plan, tissue-estimating work Group
The side of being evaluated carries out self-evaluation implementation, based on infrastructure service layer, carries out Project decomposition structure, CTE identifications, CTE TRL judges (to carry out becoming based on hardware technology factor change-technology maturity grade detail list or software engineering key element first Key technology is carried out the preliminary of Key Software grade or hardware key technology grade by change-technology maturity grade detail list Judge;Judge that detail list and hardware key technology grade judge detail list to software key skill based on Key Software grade again Art or hardware key technology carry out grade judgement), again on the basis of technical information management module, carry out system maturation degree meter Calculation is the grade result of determination of project-based multiple technology items, the data progress statistical analysis to result of determination, finally in text The output that result is carried out on the basis of part management module forms self-evaluation report.
Specially:Infrastructure service layer and data Layer complete evaluation Whole Process Control and data preserve, and the side of being evaluated is based on base The evaluation Whole Course Management module of plinth service layer according to process wizard using data Layer interpretational criteria data Layer (including technology into It is ripe degree evaluation in CTE identification used in Assessment of Important table, risk assessment table, technology maturity tier definition intension table with And evaluation all-purpose grade condition table etc.) evaluation preparation, self-evaluation implementation, evaluation application and evaluation implementation are completed on the client, Implement interface and be respectively provided with corresponding Tips, it is basic for aiding in the specific evaluation operation of each user's progress to fill in assessment item first Information, formulate appraisal plan, set up appraisal group, then carry out project structure breakdown successively, according to importance and The selection of the key element of risk two carries out matrix computations and technology is classified automatically, finally identifies CTE, and automatic loading just sentences three Key element table and each rating conditions are sentenced in detail, complete just to sentence, in detail sentence, iterative function, the TRL for calculating individual event CTE judges, and final base Go out the technology maturity grade of system in short slab method and calculated with weighted average method, can also judge to tie according to CTE TRL if needed Fruit carries out tackling problems in key technologies planning.Device carries out statistical using technical information management module to evaluation result after the completion of evaluation Analysis, TRL and decomposition texture visualization contrast and CTE statistic of classifications can be carried out, finally utilizes the evaluation for being stored in data Layer Project data layer (including assessment item essential information, appraisal plan and appraisal group), evaluation rubric data Layer (bag Include the final inventory of Project decomposition structure, CTE, CTE and system TRL result of determination) and normative document template, by file management mould Block automatically generates self-evaluation report.
The above-mentioned CTE technology maturity evaluation methods that refer to are specially:
(1), establishing techniques maturity assessment framework;
(2) framework establishing techniques maturity assessment general rule, is evaluated according to technology maturity;
(3) general rule, is evaluated according to technology maturity and is iterated judgement, obtains final appraisal results.
Establishing techniques maturity assessment framework includes technology maturity connotative definition in step (1) and technology maturity is evaluated Definition, technology maturity connotative definition are:Project is divided into hardware technology and the major class of software engineering two, re-defined in hardware technology Appearance and software engineering content, are respectively obtained based on factor change-technology maturation according to hardware technology content and software engineering content Spend tier definition Tables 1 and 2;
The hardware technology factor change of table 1-technology maturity grade
The software engineering factor change of table 2-technology maturity grade
Technology maturity evaluation definition includes the definition of hardware technology maturity assessment and the definition of software engineering maturity assessment Respectively such as table 3 and as shown in table 4,
Table 3
Table 4
The technology maturity evaluation general rule includes just sentencing and in detail sentencing;It is to be based on technology maturity connotative definition to sentence at the beginning of described The CTE is subjected to technology maturity grade and is just judged to N levels, N takes 1~9 grade;It is described in detail sentence be by technology maturity evaluation definition in Rank under be divided into n must be fulfilled for entry contents N` and it is nonessential meet entry contents O, just sentence after obtaining preliminary grade, base The grade of table 3 or the corresponding preliminary grade of table 4 in technology maturity evaluation definition, carries out N` the and O item grade bars under the grade The statistics of part Service Efficiency, the respective Service Efficiency of N` and O items is calculated, obtains the current TRL of the CTE.
If the Service Efficiency that the Service Efficiency for meeting N` items is 100%, O items be 85% and more than, then this it is first sentence grade for CTE work as Preceding TRL is the preliminary grade, is unsatisfactory for, then the TRL current CTE is that the preliminary grade subtracts one-level.
Iteration judges to refer to according to technology maturity evaluation general rule result, the CTE is continued according into technology maturity and evaluated General rule carries out the evaluation of N+1 levels technology maturity or the evaluation of N-1 levels technology maturity, until the CTE technology maturities judge energy Untill enough meeting certain grade and being unsatisfactory for higher one-level.Specially:When sentencing result in detail to meet N level technology maturity grades, Carry out the evaluation of N+1 levels technology maturity;When sentencing result in detail to be unsatisfactory for N level technology maturity grades, then N-1 level technologies are carried out Maturity assessment.
A kind of Project Technical maturity assessment method, comprises the following steps:
(1) key problem in technology degree identification, is carried out first to each CTE in project;
(2) technology maturity grade evaluation, is carried out according to preceding described CTE technology maturities evaluation method, is obtained each CTE technology maturity grade point;
(3), according to each CTE technology maturity grade point be based on weighted mean method and short slab method computing system technology into Ripe degree.
Key technology Elements C TE is identified:Skill element in project is divided into seven classes according to criticality:A classes For key technology, B classes, C1Class is emphasis key technology, C2Class is general key technology, C3~C5Class is other technologies, fortune Importance is carried out to the skill element of project with synthetic evaluation matrix and risk rank judges, carries out the criticality class of technology Other matrix computations, synthetic evaluation matrix such as table 5 below, define A classes, B classes, C1、C2Class is CTE, C3~C5The non-CTE of class,
Table 5
Specifically it is calculated as:First pass through short slab method and obtain the technology maturity grade for multiple CTE that key problem in technology degree is A classes It is worth minimum value, is designated as TRL1, then by weighted mean method to key problem in technology degree be B classes, C1Class, C2Multiple CTE of class technology Maturity grade point, is designated as TRL2, then:
W in formulaiFor the CTE technology maturity weighted values of i-th of project, TRLiFor the CTE technology maturities of i-th of project Grade, n are B classes, C1、C2The CTE of class total quantity, final system technology maturity grade
=min { TRL1,TRL2, and round numerical value.
It is to meet equation W according to the CTE weight assignments of weighted mean methodi*np1+0.75*Wi*np2+0.5*Wi*np3=1, np1For the number of B class CTE projects, np2For C1The number of class CTE projects, np3For C2The number of class CTE projects, can try to achieve Wi.This CTE weight ratios, which are set, in evaluation method is divided into two kinds, and a kind of is the CTE weight assignment recommendation tables of weighted mean method, for the present invention Recommendation assignment method, as shown in table 6;Another kind is self-defined weight ratio, is conferred and determined by evaluation tissue according to project characteristic.
Table 6
, it is necessary to carry out the establishment of Project decomposition structure before step (1) is carried out, the Project decomposition structure is to work point Based on solution structure WBS, combination technology decomposition texture TBS, the multi-layer project using technology resolving cell as terminal node is established Architecture, the way of output of Project decomposition structure are tree-like and two kinds of form, for associated item and its project not same order Section can integrate, be multiplexed existing Project decomposition structure.
If necessary to carry out tackling problems in key technologies planning, for CTE to be tackled key problems, to be reached according to current TRL and tackling key problem TRL, automatically generating needs the TRL lists tackled key problems, by loading evaluation all-purpose grade condition and completed evaluation result, than To selecting all entries in TRL, the verification met is made whether, the planning of respective entries is carried out according to verification result, according to Planning result automatically generates tackling problems in key technologies planning report.
When the application of embodiment 3 is the network edition
As shown in Fig. 2 on the basis of embodiment 2, evaluation application is carried out based on access layer by internet online, carried Hand over evaluation application paper, access layer management level examination & verification evaluation application paper after, based on core layer set up evaluation executing agency and Expert group;Evaluate executing agency and appraisal is started based on access layer, expert group's system in the database set up based on core layer Determine expert, evaluated by expert, i.e., Project decomposition structure, the final inventories of CTE, CTE and system are carried out based on infrastructure service layer TRL judges evaluation, finally obtains the generation that result carries out appraisal report.Each expert can simultaneously examine being evaluated project, Evaluation result is automatically fed to evaluation executing agency, and is carried out by it collecting arrangement.Such as expert opinion Lothrus apterus, then evaluation is tied Fruit returns to the side of being evaluated, and the inconsistent situation of expert opinion such as occurs, by evaluating executing agency by sending out inconsistent place Play evaluation task coordinate again and unify expert each side opinion, finally draw evaluation result.This operation can greatly improve evaluation efficiency, Also allow for evaluating real-time tracking and tracing management of each establishment officer to evaluation rubric.
Above-described embodiment, the purpose of the present invention, technical scheme and beneficial effect are carried out further Describe in detail, should be understood that the embodiment that the foregoing is only the present invention, be not intended to limit the present invention Protection domain, within the spirit and principles of the invention, any modification, equivalent substitution and improvements done etc., all should include Within protection scope of the present invention.

Claims (12)

  1. A kind of 1. technology maturity evaluation information processing unit, it is characterised in that including access layer, infrastructure service layer, core layer, Data Layer and hardware layer;
    Access layer, progress technology maturity evaluation is logged in for providing user;
    Data Layer, for the process data and relevant documentation data submitted during memory technology maturity assessment;
    Core layer, for building distribution role-security module, building evaluation automatic flow module and building evaluating data point Analyse processing unit;
    Hardware layer, for realizing that access layer, infrastructure service layer, core layer, data Layer build basis;
    Infrastructure service layer, controlled for technology maturity evaluation rubric and data caused by evaluation rubric are analyzed and located Reason, including:
    Whole Course Management module is evaluated, for the control to evaluation procedure, evaluation Whole Course Management module includes:Project structure point Unit is solved, for establishing the multi-layer architecture of project using technology resolving cell as terminal node;Key technology recognition unit, For carrying out key problem in technology degree identification to technology resolving cell;Software and hardware technology grade preliminary judgement unit, carry out software pass The preliminary grade of key technology grade or hardware key technology grade judges;Key Software grade sentences unit in detail and hardware is crucial Industrial grade sentences unit in detail, for carrying out final grade judgement to Key Software or hardware key technology;System maturation Computing unit is spent, utilizes short slab method and the more CTE of calculated with weighted average method system maturation degree;
    Technical information management module, the grade result of determination of project-based multiple technology items, with short slab method and weighted average Method carries out statistical analysis to the data of result of determination:Evaluate integrated information output, TRL visualizations contrast, decomposition texture visualization Contrast and CTE statistic of classifications;
    Document management module, for generating accordingly report and the management to relevant documentation in evaluation rubric after the completion of evaluation.
  2. 2. a kind of technology maturity evaluation information processing unit according to claim 1, it is characterised in that access layer is used for It is responsible for user based on access of the client to data Layer, user includes technology maturity evaluation management layer, evaluates executing agency, be special Family's group, the side of being evaluated, the client of login is PC, and user realizes the data syn-chronization between different user by web browser.
  3. A kind of 3. technology maturity evaluation information processing unit according to claim 1, it is characterised in that technical information pipe Manage module and include evaluation integrated information unit, TRL visualizations comparison unit, decomposition texture visualization comparison unit and CTE points Class statistic unit, for supporting the system of disparity items different phase and different CTE TRL to visualize contrast, specific project is gone through Decomposition texture carries out images outputting contrast and divided according to TRL grades or CTE key problem in technology degree classification in secondary evaluation Class counts corresponding CTE quantity, is easy to unified management, resource allocation and pass to of interest project of the manager to entry Key technology is global to be controlled.
  4. A kind of 4. technology maturity evaluation information processing unit according to claim 1, it is characterised in that infrastructure service layer Also include experts' evaluation module, evaluation of the expert to technology maturity in tissue-estimating on line.
  5. 5. a kind of technology maturity evaluation information processing unit according to claim 1, it is characterised in that data Layer is specific Demographic data's layer, assessment item data Layer, evaluation rubric data Layer, interpretational criteria data Layer and correlation including evaluation personnel storehouse Document information, wherein interpretational criteria data Layer include again:Technical significance classification chart, technical risk classification chart, key technology Recognition matrix tables of data, hardware technology factor change-technology maturity grade detail list, software engineering factor change-technology into Ripe degree grade detail list, hardware key technology grade judge that detail list, Key Software grade judge detail list.
  6. A kind of 6. technology maturity evaluation information processing unit according to claim 5, it is characterised in that evaluation personnel storehouse Demographic data's layer be used for store evaluation management layer, the side of being evaluated, expert group and evaluate executing agency everyone basic document; Assessment item data Layer is used for essential information, the formulation of appraisal plan and the foundation of Working Group on Evaluation of assessment item;Comment Valency flow data layer is used to carry out the final inventory of stored items decomposition texture, CTE, CTE and the analysis of system TRL decision statistics And experts' evaluation opinion as a result.
  7. A kind of 7. technology maturity evaluation information processing unit according to claim 5, it is characterised in that evaluation personnel storehouse Demographic data's layer in experts database individually managed and safeguarded by system manager, for being configured to personnel storehouse role-security, Expert outside storehouse is docked and added with system OA storehouses, inquiry is finely divided according to not commensurate, different majors condition, is easy to different item The evaluation of mesh technology maturity carries out the selection of expert according to project art.
  8. A kind of 8. technology maturity evaluation information processing unit according to claim 5, it is characterised in that evaluation rubric number According to layer version is stored, is retrieved, is inquired about, is multiplexed, is changed and is risen to caused data in evaluation information handling process.
  9. A kind of 9. technology maturity evaluation information processing unit according to claim 5, it is characterised in that interpretational criteria number Row information storage, change are entered based on technology maturity evaluation criterion specification according to layer and safeguarded.
  10. A kind of 10. technology maturity evaluation information processing unit according to claim 1, it is characterised in that project structure Resolving cell creates decomposition texture tree structure by the addition or deletion of node, and project structure is with tree-like, form and centre text Three kinds of forms of part by selection node position or node position level export, while intermediate file can lead-in item STRUCTURE DECOMPOSITION unit, The Project decomposition structure of similar or identical evaluation can be mutually multiplexed.
  11. 11. a kind of technology maturity evaluation information processing unit according to claim 1, it is characterised in that evaluate full mistake Thread management module also includes tackling key problem planning unit, for for CTE to be tackled key problems, to be reached according to current TRL and tackling key problem TRL, the TRL lists for needing to tackle key problems are automatically generated, by loading evaluation all-purpose grade condition and completed evaluation result, compared All entries in selected TRL, the verification met is made whether, the planning of respective entries, last root are carried out according to verification result Tackling problems in key technologies planning report is automatically generated according to planning result.
  12. 12. a kind of technology maturity evaluation information processing unit according to claim 1, it is characterised in that in data Layer Relevant documentation data also include the detailed Tips in evaluation system interface, implement technology maturation for each user in advisory visit layer Related work is spent, and includes technology maturity assessment guidelines, relevant criterion and with informative appraisal report example Practise storehouse.
CN201710933643.5A 2017-10-10 2017-10-10 A kind of technology maturity evaluation information processing unit Pending CN107609794A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710933643.5A CN107609794A (en) 2017-10-10 2017-10-10 A kind of technology maturity evaluation information processing unit

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710933643.5A CN107609794A (en) 2017-10-10 2017-10-10 A kind of technology maturity evaluation information processing unit

Publications (1)

Publication Number Publication Date
CN107609794A true CN107609794A (en) 2018-01-19

Family

ID=61068462

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710933643.5A Pending CN107609794A (en) 2017-10-10 2017-10-10 A kind of technology maturity evaluation information processing unit

Country Status (1)

Country Link
CN (1) CN107609794A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110851460A (en) * 2019-10-24 2020-02-28 华中科技大学 Graphic query method for product research progress and application thereof
CN112465392A (en) * 2020-12-10 2021-03-09 浙江大学 Life cycle evaluation system and method based on cloud service mode
CN112764794A (en) * 2021-01-08 2021-05-07 世纪龙信息网络有限责任公司 Open source software information management system and method
CN113033956A (en) * 2021-02-26 2021-06-25 中国人民解放军军事科学院国防科技创新研究院 Scientific and technological achievement evaluation system based on technical maturity
CN113313395A (en) * 2021-06-03 2021-08-27 中国电子科技集团公司第二十九研究所 Quantitative evaluation method for manufacturing maturity of electronic equipment
CN113673914A (en) * 2021-10-21 2021-11-19 国家电网有限公司 Technical grade determination method and device and electronic equipment

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102890753A (en) * 2012-10-24 2013-01-23 北京信息控制研究所 Technology readiness level (TRL) determination method based on technology readiness attribute
CN103226743A (en) * 2012-09-12 2013-07-31 中国人民解放军92728部队 TRL-based technical maturity assessment information processing method for aeronautic equipment
CN104899143A (en) * 2015-06-15 2015-09-09 中国航空无线电电子研究所 Software peer review system realizing device for providing DM (Data Mining)
CN106600096A (en) * 2016-10-19 2017-04-26 国网上海市电力公司 Distributed S&T (science and technology) accomplishment evaluation system

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103226743A (en) * 2012-09-12 2013-07-31 中国人民解放军92728部队 TRL-based technical maturity assessment information processing method for aeronautic equipment
CN102890753A (en) * 2012-10-24 2013-01-23 北京信息控制研究所 Technology readiness level (TRL) determination method based on technology readiness attribute
CN104899143A (en) * 2015-06-15 2015-09-09 中国航空无线电电子研究所 Software peer review system realizing device for providing DM (Data Mining)
CN106600096A (en) * 2016-10-19 2017-04-26 国网上海市电力公司 Distributed S&T (science and technology) accomplishment evaluation system

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
张慧 等: "《基于技术成熟度的航空科研管理平台研究》", 《2013年中国航空学会管理科学分会学术会议论文集》 *

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110851460A (en) * 2019-10-24 2020-02-28 华中科技大学 Graphic query method for product research progress and application thereof
CN112465392A (en) * 2020-12-10 2021-03-09 浙江大学 Life cycle evaluation system and method based on cloud service mode
CN112764794A (en) * 2021-01-08 2021-05-07 世纪龙信息网络有限责任公司 Open source software information management system and method
CN113033956A (en) * 2021-02-26 2021-06-25 中国人民解放军军事科学院国防科技创新研究院 Scientific and technological achievement evaluation system based on technical maturity
CN113313395A (en) * 2021-06-03 2021-08-27 中国电子科技集团公司第二十九研究所 Quantitative evaluation method for manufacturing maturity of electronic equipment
CN113673914A (en) * 2021-10-21 2021-11-19 国家电网有限公司 Technical grade determination method and device and electronic equipment

Similar Documents

Publication Publication Date Title
CN107609794A (en) A kind of technology maturity evaluation information processing unit
KR102184182B1 (en) Project/Task Intelligent Goal Management Method and Platform based on Super Tree
CN107256443B (en) Line loss real-time computing technique based on business and data integration
CN105574652B (en) Intelligent power distribution network planning big data management and control system and method
CN110493025B (en) Fault root cause diagnosis method and device based on multilayer digraphs
Hu et al. Research and application of capability maturity model for Chinese intelligent manufacturing
CN103902816A (en) Electrification detection data processing method based on data mining technology
CN107784397A (en) A kind of power network material requirements forecasting system and its Forecasting Methodology
CN103970887A (en) Information stream display system and method based on GIS distribution network graphs
CN102932419A (en) Data storage system for industrial and mining enterprise oriented safety production cloud service platform
CN109933934A (en) A kind of equipment maintenance and management method and system, computer readable storage medium
Gohar et al. Identifying and evaluating risks of construction projects in fuzzy environment: a case study in Iranian construction industry
CN103226743A (en) TRL-based technical maturity assessment information processing method for aeronautic equipment
CN102917032A (en) Safety production cloud service platform for industrial and mining enterprises
CN113872813B (en) Full life cycle management method and system for carrier communication equipment
Feng et al. [Retracted] Design and Simulation of Human Resource Allocation Model Based on Double‐Cycle Neural Network
CN109412155B (en) Power distribution network power supply capacity evaluation method based on graph calculation
CN107194533A (en) A kind of power distribution network full information model building method and system
CN110489749A (en) Intelligent Office-Automation System Work Flow Optimizing
CN115271648B (en) Project visual supervision system, method, equipment and storage medium
CN109242248A (en) Cigarette machine multidimensional data comprehensive analysis platform and method
CN107369003A (en) A kind of intelligent laboratory management system method and system
CN115689415A (en) Digital twin-based logistics monitoring and simulation system
El‐Ghandour et al. Survey of information technology applications in construction
CN109447466A (en) A kind of overall process visualization managing and control system based on Distribution Network Communication network construction

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination