CN107558612A - A kind of curved space pipe truss installation method - Google Patents
A kind of curved space pipe truss installation method Download PDFInfo
- Publication number
- CN107558612A CN107558612A CN201710583761.8A CN201710583761A CN107558612A CN 107558612 A CN107558612 A CN 107558612A CN 201710583761 A CN201710583761 A CN 201710583761A CN 107558612 A CN107558612 A CN 107558612A
- Authority
- CN
- China
- Prior art keywords
- truss
- installation
- sections
- lifting
- checked
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The invention discloses a kind of curved space pipe truss installation method, comprise the following steps:Preparative work before construction, including:Prepare field operation condition;Basis is checked and accepted;Drawing prepares, and component is checked and checked;Lifting includes:Determine lifting sequence;50 tons of cranes are provided from suspender;The installation of rectangle A section roofing truss;The installation of fan-shaped B sections roofing truss;The installation of C sections roofing truss before sector.The curved space pipe truss installation method of the present invention has ground assembling roofing truss, the method for whole section of lifting, have construction it is succinct, conveniently, short time limit and construction quality easily ensure, save the advantages of heavy mechanical equipment, reduction operating expenses.
Description
Technical field
The present invention relates to a kind of truss installation method, and in particular to a kind of curved space pipe truss installation method.
Background technology
In recent years, space truss architecture because of it from heavy and light, span is big, short construction period, variation in moulding complexity U.S.A are refuted
The features such as bank, is rapidly developed, and is used widely in the Big Space Public Architectures such as gymnasium, exhibition pipe, airport.
Run in early stage International airport administration building main-inlet employs curved space truss structure, by outer layer batter post, column
And roofing truss collectively constitutes fan truss structure, single Pin roofing truss most weight is 2.8 tons, main-inlet truss overall length
60m, beam overall 57m, always weigh about 137 tons.Main-inlet truss Steel Structure makes at home, and each part is through preassembling passed examination
Afterwards, transported by sea by container to erecting bed, building site assembling and lifting are carried out by an Indian Company, production unit provides installation
Scheme is to instruct site operation.Each transport section of truss Steel Structure need to meet the built-in size sea-freight of container and require, but can not be complete
Portion splits into single part delivery, to reduce steel construction Assembling workload.
Both ends hold-down support installation method known to roofing truss use can day and night difference variation be produced greatly because of Middle East
Raw stress causes truss structure modification to destroy, and after the batter post lifting in truss Steel Structure and before roofing truss installation, batter post
Stability be also a construction Difficulties.
The content of the invention
Goal of the invention:The present invention is directed to deficiency of the prior art, proposes a kind of curved space pipe truss installation method, has
Have ground assembling roofing truss, the method for whole section of lifting, have construction it is succinct, conveniently, short time limit and construction quality easily ensure, save
About heavy mechanical equipment, reduce operating expenses the advantages of.
Technical scheme:A kind of curved space pipe truss installation method of the present invention, comprises the following steps:
A, preparative work before construction, comprise the following steps:
(1)Prepare field operation condition
Job site possesses " three supplies and one leveling ";Relevant basic terrace project is basically completed, and its concrete strength is not lower than
75% ;The coordinate and absolute altitude at each measurement control point are accurately clear, and each basic center line and level measurement finish;Each passage, building
Ladder, railing possess execution conditions, each hole, and hole and Buddhist monk in progress have open position to have the reliable precautionary measures;It is furnished with
The fire-fighting equipment of enough acceptance(check)s;Each professional teams and groups possess work box, and have the special shelf for stacking parts;
(2)Basis is checked and accepted
Basis concrete cast before civil engineering unit should together with installation unit by net of control points total powerstation to all kinds of lower margins
Bolt, the coordinate of built-in fitting, absolute altitude are checked, are just in the milk after meeting code requirement, should be checked after grouting;Fill
Check need to be done easy to remember after checking and be in the milk before slurry;Surface of base should be marked and clearly indulged, horizontal center line, elevation line;
(3)Drawing prepares, and component is checked and checked
Whether the packing list of inspection steel construction delivery, installation diagram, component diagram are correct;Component inspection checks work by management list
Position is taken the lead, represented with manufactory based on, kind, can be advised with total Bao Fang, unit in charge of construction the number of components as packing slip listed by jointly
Lattice, inspection is checked, should made a record, check whether component apparent size is consistent with drawing according to component diagram, if problematic, through each
Fang, which is represented, confirms visa, and is negotiated by Zong Bao directions manufactory, and solves in time;The parts checked through unpacking, Ying Youshi
It is responsible for keeping in work order position;
B, lift, comprise the following steps:
(1)Determine lifting sequence
Rectangle A section roofing truss, fan-shaped B sections roofing truss and C before sector are included according to curved space tube truss structure
Section roofing truss, is lifted since A sections, after with B sections, is finally terminated to the lifting of C sections;Each truss is often across by outer framework
Formed with inner frame, often across outer framework maximum weight is 28 tons, and lifting sequence is first integral hoisting outer framework, then again with list
Part installs inner frame;One end hold-down support is used in the jointing of each truss, the other end uses slotted eye type of attachment
Sliding support, so that day and night difference variation is big adjusting Middle East produces stress, a small amount of installation deviation by sliding, and
During across the civil engineering expansion joint of large-scale truss, the stress concentration that the later stage causes malformation to bring because of foundation of civil work sedimentation, increase are reduced
The security of structure;
(2)50 tons of cranes are provided from suspender;
(3)The installation of rectangle A section roofing truss
1)The lifting for being arranged on A sections and carrying out column of A section columns, is carried out windproof before not installing truss and forming stable frame
Measure, prevent column from toppling over;
2)First on ground by installation diagram assembling truss before the installation lifting of A section truss, truss bolt of lower base hole horizontal and right is measured
Linea angulata distance meets design requirement, prevents from doing over again because pitch-row deviation is big in lifting;
Truss base is fixed with column top using high-strength bolt, and verticality of stand column, horizontal range, truss top should be checked after lifting
Hold levelness deviation otherwise should adjust to meeting the requirements whether in regulating scope, continue to construct, until two crosses of A sections
Type truss installa-tion is completed;
(4)The installation of fan-shaped B sections roofing truss
1)The lifting for being arranged on B sections and carrying out column of B section columns, is carried out windproof before not installing truss and forming stable frame
Measure, prevent column from toppling over;
2)First on ground by installation diagram assembling truss before the installation lifting of B section truss, truss bolt of lower base hole horizontal and right is measured
Linea angulata distance meets design requirement, prevents from doing over again because pitch-row deviation is big in lifting;Truss base uses with column top
Whether high-strength bolt is fixed, should check verticality of stand column, horizontal range, truss upper horizontal degree deviation in regulating scope after lifting
It is interior, it otherwise should adjust to meeting the requirements, continue to construct, until B sections truss installa-tion is completed;
(5)The installation of C sections roofing truss before sector
1)The lifting for being arranged on C sections and carrying out column of c section columns, is carried out windproof before not installing truss and forming stable frame
Measure, prevent column from toppling over;Batter post is held in the very useful chain block of lifting rear pillar, by pulling chain block chain conveniently to adjust
Horizontal level at the top of whole batter post, after batter post top horizontal distance reaches requirement, tighten the nut of batter post foundation bolt;
2)The installation of C section truss among the C sections truss is installed, after truss element forms rock-steady structure, start to adjust
Whether the locus of truss meets drawing requirement, otherwise should adjust in time;Continue that truss is installed to both sides, in all truss
After installation, check whether the integral installation size of truss meets the requirements, fasten all bolts and related welding, polishing,
Application subsequent job, complete whole curved space tube truss structure installation.
Further, the gradient on the batter post of the C sections truss and ground is 65 degree.
Further, batter post capital absolute altitude >=14m of the C sections truss, batter post suspension column absolute altitude are zero m.
Further, the batter post of the C sections truss is Φ 406*25mm steel pipes.
Further, the column in A sections truss and B the section truss is H350*350*14*22mm shaped steel.
Beneficial effect:The curved space pipe truss installation method of the present invention, there is ground assembling roofing truss, whole section of lifting
Method, have construction it is succinct, conveniently, short time limit and construction quality easily ensure, save heavy mechanical equipment, reduction operating expenses
The advantages of.
Embodiment
With reference to specific embodiment, the invention will be further described:
Embodiment 1
A kind of curved space pipe truss installation method, comprises the following steps:
A, preparative work before construction, comprise the following steps:
(1)Prepare field operation condition
Job site possesses " three supplies and one leveling ";Relevant basic terrace project is basically completed, and its concrete strength is not lower than
75% ;The coordinate and absolute altitude at each measurement control point are accurately clear, and each basic center line and level measurement finish;Each passage, building
Ladder, railing possess execution conditions, each hole, and hole and Buddhist monk in progress have open position to have the reliable precautionary measures;It is furnished with
The fire-fighting equipment of enough acceptance(check)s;Each professional teams and groups possess work box, and have the special shelf for stacking parts;
(2)Basis is checked and accepted
Basis concrete cast before civil engineering unit should together with installation unit by net of control points total powerstation to all kinds of lower margins
Bolt, the coordinate of built-in fitting, absolute altitude are checked, are just in the milk after meeting code requirement, should be checked after grouting;Fill
Check need to be done easy to remember after checking and be in the milk before slurry;Surface of base should be marked and clearly indulged, horizontal center line, elevation line;
(3)Drawing prepares, and component is checked and checked
Whether the packing list of inspection steel construction delivery, installation diagram, component diagram are correct;Component inspection checks work by management list
Position is taken the lead, represented with manufactory based on, kind, can be advised with total Bao Fang, unit in charge of construction the number of components as packing slip listed by jointly
Lattice, inspection is checked, should made a record, check whether component apparent size is consistent with drawing according to component diagram, if problematic, through each
Fang, which is represented, confirms visa, and is negotiated by Zong Bao directions manufactory, and solves in time;The parts checked through unpacking, Ying Youshi
It is responsible for keeping in work order position;
B, lift, comprise the following steps:
(1)Determine lifting sequence
Rectangle A section roofing truss, fan-shaped B sections roofing truss and C before sector are included according to curved space tube truss structure
Section roofing truss, is lifted since A sections, after with B sections, is finally terminated to the lifting of C sections;Each truss is often across by outer framework
Formed with inner frame, often across outer framework maximum weight is 28 tons, and lifting sequence is first integral hoisting outer framework, then again with list
Part installs inner frame;One end hold-down support is used in the jointing of each truss, the other end uses slotted eye type of attachment
Sliding support, so that day and night difference variation is big adjusting Middle East produces stress, a small amount of installation deviation by sliding, and
During across the civil engineering expansion joint of large-scale truss, the stress concentration that the later stage causes malformation to bring because of foundation of civil work sedimentation, increase are reduced
The security of structure;
(2)50 tons of cranes are provided from suspender;
(3)The installation of rectangle A section roofing truss
1)The lifting for being arranged on A sections and carrying out column of A section columns, is carried out windproof before not installing truss and forming stable frame
Measure, prevent column from toppling over;
2)First on ground by installation diagram assembling truss before the installation lifting of A section truss, truss bolt of lower base hole horizontal and right is measured
Linea angulata distance meets design requirement, prevents from doing over again because pitch-row deviation is big in lifting;
Truss base is fixed with column top using high-strength bolt, and verticality of stand column, horizontal range, truss top should be checked after lifting
Hold levelness deviation otherwise should adjust to meeting the requirements whether in regulating scope, continue to construct, until two crosses of A sections
Type truss installa-tion is completed;
(4)The installation of fan-shaped B sections roofing truss
1)The lifting for being arranged on B sections and carrying out column of B section columns, is carried out windproof before not installing truss and forming stable frame
Measure, prevent column from toppling over;
2)First on ground by installation diagram assembling truss before the installation lifting of B section truss, truss bolt of lower base hole horizontal and right is measured
Linea angulata distance meets design requirement, prevents from doing over again because pitch-row deviation is big in lifting;Truss base uses with column top
Whether high-strength bolt is fixed, should check verticality of stand column, horizontal range, truss upper horizontal degree deviation in regulating scope after lifting
It is interior, it otherwise should adjust to meeting the requirements, continue to construct, until B sections truss installa-tion is completed;
(5)The installation of C sections roofing truss before sector
1)The lifting for being arranged on C sections and carrying out column of c section columns, is carried out windproof before not installing truss and forming stable frame
Measure, prevent column from toppling over;Batter post is held in the very useful chain block of lifting rear pillar, by pulling chain block chain conveniently to adjust
Horizontal level at the top of whole batter post, after batter post top horizontal distance reaches requirement, tighten the nut of batter post foundation bolt;
2)The installation of C section truss among the C sections truss is installed, after truss element forms rock-steady structure, start to adjust
Whether the locus of truss meets drawing requirement, otherwise should adjust in time;Continue that truss is installed to both sides, in all truss
After installation, check whether the integral installation size of truss meets the requirements, fasten all bolts and related welding, polishing,
Application subsequent job, complete whole curved space tube truss structure installation.
The batter post of the C sections truss and the gradient on ground are 65 degree.The batter post capital absolute altitude of the C sections truss >=
14m, batter post suspension column absolute altitude are zero m.The batter post of the C sections truss is Φ 406*25mm steel pipes.The A sections truss and B sections purlin
Column in frame is H350*350*14*22mm shaped steel.
The curved space pipe truss installation method of the present invention, there is ground assembling roofing truss, the whole section of method lifted, tool
Have construction it is succinct, conveniently, short time limit and construction quality easily ensure, save the advantages of heavy mechanical equipment, reduction operating expenses.
The above described is only a preferred embodiment of the present invention, any formal limitation not is made to the present invention, though
So the present invention is disclosed above with preferred embodiment, but is not limited to the present invention, any to be familiar with this professional technology people
Member, without departing from the scope of the present invention, when the technology contents using the disclosure above make a little change or modification
For the equivalent embodiment of equivalent variations, as long as being the content without departing from technical solution of the present invention, the technical spirit according to the present invention
Any simple modification, equivalent change and modification made to above example, in the range of still falling within technical solution of the present invention.
Claims (5)
- A kind of 1. curved space pipe truss installation method, it is characterised in that:Comprise the following steps:A, preparative work before construction, comprise the following steps:(1)Prepare field operation conditionJob site possesses " three supplies and one leveling ";Relevant basic terrace project is basically completed, and its concrete strength is not lower than 75% ;The coordinate and absolute altitude at each measurement control point are accurately clear, and each basic center line and level measurement finish;Each passage, building Ladder, railing possess execution conditions, each hole, and hole and Buddhist monk in progress have open position to have the reliable precautionary measures;It is furnished with The fire-fighting equipment of enough acceptance(check)s;Each professional teams and groups possess work box, and have the special shelf for stacking parts;(2)Basis is checked and acceptedBasis concrete cast before civil engineering unit should together with installation unit by net of control points total powerstation to all kinds of lower margins Bolt, the coordinate of built-in fitting, absolute altitude are checked, are just in the milk after meeting code requirement, should be checked after grouting;Fill Check need to be done easy to remember after checking and be in the milk before slurry;Surface of base should be marked and clearly indulged, horizontal center line, elevation line;(3)Drawing prepares, and component is checked and checkedWhether the packing list of inspection steel construction delivery, installation diagram, component diagram are correct;Component inspection checks work by management list Position is taken the lead, represented with manufactory based on, kind, can be advised with total Bao Fang, unit in charge of construction the number of components as packing slip listed by jointly Lattice, inspection is checked, should made a record, check whether component apparent size is consistent with drawing according to component diagram, if problematic, through each Fang, which is represented, confirms visa, and is negotiated by Zong Bao directions manufactory, and solves in time;The parts checked through unpacking, Ying Youshi It is responsible for keeping in work order position;B, lift, comprise the following steps:(1)Determine lifting sequenceRectangle A section roofing truss, fan-shaped B sections roofing truss and C before sector are included according to curved space tube truss structure Section roofing truss, is lifted since A sections, after with B sections, is finally terminated to the lifting of C sections;Each truss is often across by outer framework Formed with inner frame, often across outer framework maximum weight is 28 tons, and lifting sequence is first integral hoisting outer framework, then again with list Part installs inner frame;One end hold-down support is used in the jointing of each truss, the other end uses slotted eye type of attachment Sliding support, so that day and night difference variation is big adjusting Middle East produces stress, a small amount of installation deviation by sliding, and During across the civil engineering expansion joint of large-scale truss, the stress concentration that the later stage causes malformation to bring because of foundation of civil work sedimentation, increase are reduced The security of structure;(2)50 tons of cranes are provided from suspender;(3)The installation of rectangle A section roofing truss1)The lifting for being arranged on A sections and carrying out column of A section columns, is carried out windproof before not installing truss and forming stable frame Measure, prevent column from toppling over;2)First on ground by installation diagram assembling truss before the installation lifting of A section truss, truss bolt of lower base hole horizontal and right is measured Linea angulata distance meets design requirement, prevents from doing over again because pitch-row deviation is big in lifting;Truss base is fixed with column top using high-strength bolt, and verticality of stand column, horizontal range, truss top should be checked after lifting Hold levelness deviation otherwise should adjust to meeting the requirements whether in regulating scope, continue to construct, until two crosses of A sections Type truss installa-tion is completed;(4)The installation of fan-shaped B sections roofing truss1)The lifting for being arranged on B sections and carrying out column of B section columns, is carried out windproof before not installing truss and forming stable frame Measure, prevent column from toppling over;2)First on ground by installation diagram assembling truss before the installation lifting of B section truss, truss bolt of lower base hole horizontal and right is measured Linea angulata distance meets design requirement, prevents from doing over again because pitch-row deviation is big in lifting;Truss base uses with column top Whether high-strength bolt is fixed, should check verticality of stand column, horizontal range, truss upper horizontal degree deviation in regulating scope after lifting It is interior, it otherwise should adjust to meeting the requirements, continue to construct, until B sections truss installa-tion is completed;(5)The installation of C sections roofing truss before sector1)The lifting for being arranged on C sections and carrying out column of c section columns, is carried out windproof before not installing truss and forming stable frame Measure, prevent column from toppling over;Batter post is held in the very useful chain block of lifting rear pillar, by pulling chain block chain conveniently to adjust Horizontal level at the top of whole batter post, after batter post top horizontal distance reaches requirement, tighten the nut of batter post foundation bolt;2)The installation of C section truss among the C sections truss is installed, after truss element forms rock-steady structure, start to adjust Whether the locus of truss meets drawing requirement, otherwise should adjust in time;Continue that truss is installed to both sides, in all truss After installation, check whether the integral installation size of truss meets the requirements, fasten all bolts and related welding, polishing, Application subsequent job, complete whole curved space tube truss structure installation.
- A kind of 2. curved space pipe truss installation method according to claim 1, it is characterised in that:The C sections truss The gradient on batter post and ground is 65 degree.
- A kind of 3. curved space pipe truss installation method according to claim 1, it is characterised in that:The C sections truss Batter post capital absolute altitude >=14m, batter post suspension column absolute altitude are zero m.
- A kind of 4. curved space pipe truss installation method according to claim 1, it is characterised in that:The C sections truss Batter post is Φ 406*25mm steel pipes.
- A kind of 5. curved space pipe truss installation method according to claim 1, it is characterised in that:The A sections truss and B Column in section truss is H350*350*14*22mm shaped steel.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710583761.8A CN107558612A (en) | 2017-07-18 | 2017-07-18 | A kind of curved space pipe truss installation method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710583761.8A CN107558612A (en) | 2017-07-18 | 2017-07-18 | A kind of curved space pipe truss installation method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107558612A true CN107558612A (en) | 2018-01-09 |
Family
ID=60973567
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710583761.8A Pending CN107558612A (en) | 2017-07-18 | 2017-07-18 | A kind of curved space pipe truss installation method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107558612A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108644469A (en) * | 2018-05-22 | 2018-10-12 | 山西省工业设备安装集团有限公司 | The construction technology of main steam system pipeline in a kind of Steam Turbine |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102777047A (en) * | 2012-08-22 | 2012-11-14 | 河北二十冶工程技术有限公司 | Assembling and splicing installation method of large-span tube-truss roof beam |
CN104727564A (en) * | 2015-04-17 | 2015-06-24 | 中亿丰建设集团股份有限公司 | Method for installation construction of roof free-form surface single-layer latticed shell structure of super high-rise building |
CN105133841A (en) * | 2015-07-29 | 2015-12-09 | 五洋建设集团股份有限公司 | Spatial curved surface steel structure pipe truss roof installation construction method |
CN105780995A (en) * | 2014-12-22 | 2016-07-20 | 五冶集团上海有限公司 | Curved surface space pipe truss structure and mounting method thereof |
CN106703419A (en) * | 2017-01-22 | 2017-05-24 | 中国十七冶集团有限公司 | Large-span roof truss high-altitude assembly sliding control method |
-
2017
- 2017-07-18 CN CN201710583761.8A patent/CN107558612A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102777047A (en) * | 2012-08-22 | 2012-11-14 | 河北二十冶工程技术有限公司 | Assembling and splicing installation method of large-span tube-truss roof beam |
CN105780995A (en) * | 2014-12-22 | 2016-07-20 | 五冶集团上海有限公司 | Curved surface space pipe truss structure and mounting method thereof |
CN104727564A (en) * | 2015-04-17 | 2015-06-24 | 中亿丰建设集团股份有限公司 | Method for installation construction of roof free-form surface single-layer latticed shell structure of super high-rise building |
CN105133841A (en) * | 2015-07-29 | 2015-12-09 | 五洋建设集团股份有限公司 | Spatial curved surface steel structure pipe truss roof installation construction method |
CN106703419A (en) * | 2017-01-22 | 2017-05-24 | 中国十七冶集团有限公司 | Large-span roof truss high-altitude assembly sliding control method |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108644469A (en) * | 2018-05-22 | 2018-10-12 | 山西省工业设备安装集团有限公司 | The construction technology of main steam system pipeline in a kind of Steam Turbine |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105780995B (en) | A kind of curved space tube truss structure and its installation method | |
CN110886423B (en) | BIM technology-based steel structure tension beam roof construction method | |
CN107012949B (en) | A kind of method for improving of large-span steel vestibule | |
CN104141383B (en) | A kind of Bailey beam pendent form support system and construction thereof | |
CN1978801B (en) | Super-span steel skew arch construction method | |
CN103774854A (en) | Construction method for hoisting heavy type ultrahigh steel member | |
CN101538936B (en) | Hydraulic slip-and-lift construction method for water tower | |
CN203947771U (en) | A kind of Bailey beam pendent form support system | |
CN102535845A (en) | Construction method of bearing frame of corridor structure | |
CN109853394A (en) | Arch bridge cable hoisting tower button integrated construction engineering method | |
CN102787560B (en) | Integrated construction method of support of large cantilevered capping beam and vertical column | |
CN105586833B (en) | Stiff skeleton steel reinforcement cage global formation large-scale cast-in-place tall pier and thin wall construction method | |
CN104674665B (en) | Large-spatial structures vestibule bridge installation method | |
CN106192758A (en) | A kind of construction method utilizing the cantilever form large-scale high pier stud of construction | |
CN114232805B (en) | Construction method of ultrahigh-height large-span steel concrete beam hanging structure | |
CN115419277B (en) | Construction method of heavy steel box type diagonal column | |
CN103216103A (en) | Pre-deformation construction method for mounting oblique-arc-shaped combined steel-structured column of annular roof | |
CN108411790A (en) | A kind of adjustable installing bracket of prefabricated assembled segmentation bent cap | |
CN104929047B (en) | A kind of V-type pier outer support construction method | |
CN115467421A (en) | Hoisting construction method for complex large-span steel roof | |
CN106639147B (en) | Super high-rise building enhancement layer steel construction semi-girder truss construction method | |
CN102777044B (en) | Hoisting method of steel-structured spraying layer of urea prilling tower | |
CN109457814B (en) | Construction method for top cover of high-rise and large-diameter building based on Bailey truss structure | |
CN107558612A (en) | A kind of curved space pipe truss installation method | |
CN102635061B (en) | Mountain stream river-crossing cable-stayed chain trestle and hoisting method thereof |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20180109 |
|
WD01 | Invention patent application deemed withdrawn after publication |