CN107558378A - A kind of Bridge Erector and its bridging method for being used to set up full precast beam - Google Patents
A kind of Bridge Erector and its bridging method for being used to set up full precast beam Download PDFInfo
- Publication number
- CN107558378A CN107558378A CN201710858907.5A CN201710858907A CN107558378A CN 107558378 A CN107558378 A CN 107558378A CN 201710858907 A CN201710858907 A CN 201710858907A CN 107558378 A CN107558378 A CN 107558378A
- Authority
- CN
- China
- Prior art keywords
- leg
- supporting leg
- bridge
- dolly
- horn
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
The invention discloses a kind of Bridge Erector and its bridging method for being used to set up full precast beam, including the horn along the equal symmetric design of vertical and horizontal, affiliated horn is double box-beam structures, auxiliary leg before being provided with the front end of horn, it is provided with the rear end of horn and rises supporting leg, support supporting leg can be furnished with along the front leg strut and rear support leg longitudinally walked in the rear side of rear support leg by being provided with the middle part of horn;The bridging method carried out using above-mentioned Bridge Erector is highly suitable for surrounding city, and execution conditions are complicated, and the big place of construction environment traffic pressure carries out the fast erecting of the aerial part overpass such as urban road, urban light rail and subway line;Overhead highway in China, urban light rail, the construction of subway elevated bridge will be promoted to develop to greenization, batch production, standardized construction direction, its economical, societal benefits will be increasingly notable.
Description
Technical field
The invention belongs to precast bridge technical field of construction, more particularly to a kind of Bridge Erector for being used to set up full precast beam and
Its bridging method.
Background technology
With the quickening of Chinese Urbanization pace of construction, in order to economize the land resource, urban road, urban light rail and subway
The aerial part overpass such as circuit is more and more.Its with conventional overpass except that, these elevated bridges mostly occur
In surrounding city, execution conditions are complicated, and construction environment traffic pressure is big, and higher requirement is proposed to Bridge Erector adaptability.
Commonly used at this stage highway bridging machine construction technology is ripe and is widely used, but it the shortcomings that with work condition environment
Development be also more obvious:
1st, existing highway bridge pier stud and bent cap typically take the colligation of on-site hoisting reinforcing bar to install, and in-site installation template, cast in situs is supported
The mode of shield, constructs larger by natural environment influence, and quality control difficulties are serious to ambient contamination.
2nd, existing Bridge Erector generally itself can not realize reverse construction, be typically necessary the auxiliary dismounting of large tonnage crane,
Even carrying out the dismounting of complete machine can realize;
3rd, it is many during existing Bridge Erector via traveling to require to lay vertical shift rail in beam face, not only to having built bridge beam stress not
Profit, also influence efficiency of construction;
4th, it is not that wheel track bridge floor traveling is exactly to hang wheeled during each supporting leg via of existing Bridge Erector, former is applied in both modes
Work bridge floor workload is big, and efficiency is low, and influences stress of having built bridge;Latter repeatedly occurs supporting leg during practical application and fallen
Fall or traveling be not smooth, caused by loss it is very big.
It is more and more urgent to be consequently for overhead highway, urban light rail, the Bridge Erector demand of subway overpass.
The content of the invention
The present invention seeks to for solve above-mentioned technical problem propose it is a kind of be used to set up the Bridge Erector of full precast beam, for up to
Adopted the technical scheme that to above-mentioned purpose:
It is a kind of to be used to set up the Bridge Erector of full precast beam, including the horn along the equal symmetric design of vertical and horizontal, affiliated horn are
Double box-beam structures, auxiliary leg before being provided with the front end of horn, are provided with the rear end of horn and rise supporting leg, in horn
Portion be provided with can be furnished with support supporting leg in the rear side of rear support leg along the front leg strut and rear support leg longitudinally walked, wherein, front leg strut, after
Supporting leg, support supporting leg and rise supporting leg and be used to horn being supported on pier column or bridge piece, preceding auxiliary leg is used for horn
Front support on the ground, dolly and rear lifting dolly, preceding lifting dolly and rear lifting dolly is lifted by crane on horn in abutment equipped with preceding
Each independent lifting mechanism, walking mechanism and transverse-moving mechanism are equipped with, is equipped with the bottom of front leg strut and rear support leg traversing
Roller, it is furnished with the cross moving track for being used for roller and laterally walking in the bottom of front leg strut and rear support leg;In preceding auxiliary leg, preceding branch
Leg, rear support leg, support supporting leg and rise respective lifting body is equipped with supporting leg.
Preferably, the preceding auxiliary leg include connecting rod successively from top to bottom, draw money on credit strut and bottom supporting leg, connecting rod can
Dismantling connection is detachably connected on the front end of horn, the lower end of connecting rod and the top for strut of drawing money on credit, the lower end for strut of drawing money on credit with
Bottom supporting leg is detachably connected, and lifting body is arranged on the supporting leg of bottom;Lifting dolly is provided with rotating mechanism, the whirler before described
The lifting mechanism of lifting dolly rotates in the horizontal plane before structure drives.
Preferably, the front leg strut, rear support leg, support supporting leg and rise supporting leg and be equipped with respective left column, right column
So as to from middle transport bridge beam piece, pier column or bent cap.
A kind of construction method that full precast bridge is carried out using Bridge Erector as described above, Pn bridges are set along construction direction
All Pn bridges pieces have been set up between pier stud and Pn+1 pier columns and have formed Pn section bridge floors, have then been entered using Bridge Erector
Row following steps:
A:The Pn+3 pier columns of side are first set up, then set up the Pn+3 pier columns of opposite side;
B:During Pn+3 pier columns grouting etc. is strong, the Pn+1 bridges between Pn+1 pier columns and Pn+2 pier columns are installed
Beam piece;
C:Set up in all Pn+1 bridges pieces and complete to be after formation Pn+1 saves bridge floor, in a structure of an essay for two Pn+3 pier columns
If Pn+3 bent caps;
D:After reaching requirement Deng Pn+3 bent cap filling intensities, Bridge Erector via, to carry out the construction of Pn+4 pier columns;
E:Repeat step A to D, until final section bridge piece is installed.
Preferably, the step A comprises the following steps:
A1:The preceding auxiliary leg station of Bridge Erector is on the bracket by Pn+3 bridge pier bases, and front leg strut station is on Pn+2 pier columns
On the track of Pn+2 bent caps, rear support leg and support supporting leg are stood on Pn section bridge floors;
A2:Front and rear two beam cars feed Pn+3 pier columns from Bridge Erector rear end;
A3:Preceding lifting dolly lifts the front end of Pn+3 pier columns, and then beam car moves ahead together, and beam car is before after
During beam car, the rear rear end lifted by crane dolly and lift Pn+3 pier columns, preceding dolly and the rear lifting dolly of lifting by crane is by Pn+3 bridge piers
Post transports to Pn+3 pier column installation site correct positions;
A4:Preceding lifting dolly remains stationary as, and rear lifting dolly is progressively close to preceding lifting dolly and while lower section Pn+3 pier columns
Rear end, until Pn+3 pier columns are in vertical state;
A5:Dolly is lifted by crane afterwards and Pn+3 pier columns depart from, and preceding lifting dolly independently lifts Pn+3 pier columns and installed
In corresponding position, the construction of side Pn+3 pier columns is completed;
A6:Transverse shifting Bridge Erector, repeat step A1 to A5 complete the construction of opposite side Pn+3 pier columns.
Preferably, the step B comprises the following steps:
B1:Preceding lifting dolly and rear lifting dolly take Pn+1 bridge pieces from beam car, and are transported to Pn+1 pier columns
Between Pn+2 pier columns, erection installation is carried out;
B2:Transverse shifting Bridge Erector, repeat step B1 form Pn+1 until all Pn+1 bridges pieces are set up into installation
Save bridge floor.
Preferably, the step C comprises the following steps:
C1:The region that lifting dolly can lift by crane before Pn+3 bent caps are transported to by beam car from the bridge floor of Bridge Erector rear end;
C2:Between slinging Pn+3 bent caps using preceding lifting dolly and be transported to Pn+3 pier columns, Pn+3 is then rotated
Bent cap, by it across on two Pn+3 pier columns.
Preferably, the step D comprises the following steps:
D1:Bridge Erector is traversing to wire center, and preceding auxiliary leg station is preceding auxiliary leg, preceding on the bracket of Pn+3 bridge pier bases
Supporting leg and support supporting leg support horn, rear support leg is hoisted on the Pn+1 section bridge floors at front leg strut rear simultaneously with preceding lifting dolly
Horn is supported, then front leg strut is hoisted on the track of Pn+3 bent caps using preceding lifting dolly;
D2:Preceding dolly and the rear lifting dolly of lifting by crane is stepped back to above rear support leg, preceding auxiliary leg is packed up and rises supporting leg horn
Advance a segment distance, and when rising supporting leg close to support supporting leg, horn halts, and rises supporting leg support horn, rear lifting
Support supporting leg is hoisted to the rear of rear support leg by dolly;
D3:Above preceding lifting dolly and rear lifting carriage walking to rear support leg, before packing up auxiliary leg and rise supporting leg horn after
Auxiliary leg is reached on the bracket of Pn+4 bridge pier bases before the continuous segment distance that advances progressively causes, at the same time preceding lifting dolly and
Dolly is lifted by crane afterwards synchronously retreats the top for being maintained at rear support leg.
Preferably, the preceding auxiliary leg include connecting rod successively from top to bottom, draw money on credit strut and bottom supporting leg, connecting rod can
Dismantling connection is detachably connected on the front end of horn, the lower end of connecting rod and the top for strut of drawing money on credit, the lower end for strut of drawing money on credit with
Bottom supporting leg is detachably connected, and lifting body is arranged on the supporting leg of bottom.
Preferably, step F can also be carried out after step E, the step F comprises the following steps:
F1:The strut that will draw money on credit is disassembled from connecting rod and bottom supporting leg, and then bottom supporting leg is removably mounted in connecting rod
Transition supporting leg is formed, transition supporting leg station is on minor details bridge floor or station is on the ground being connected with minor details bridge floor;
F2:Front leg strut, rear support leg are transported forward using preceding lifting dolly and rear lifting dolly;
F3:Transition supporting leg is exchanged into position installation with supporting leg is risen using preceding lifting dolly and rear lifting dolly;
F4:Front leg strut is arranged on by support supporting leg using preceding lifting dolly and rear lifting dolly;
F5:Support supporting leg is arranged on to the front of rear support leg using preceding lifting dolly and rear lifting dolly;
F6:Preceding lifting dolly and rear lifting dolly are exchanged into installation by crane;
F7:Bottom supporting leg is disassembled from connecting rod, the upper and lower side for strut of drawing money on credit is connected group with connecting rod, bottom supporting leg respectively
Into preceding auxiliary leg;
F8:Electric hydraulic connection is adjusted, so as to possess the Summarized Account of Bridge Erection Construction of opposite direction.
The present invention has following beneficial effect compared with prior art:
(1)This construction method can not only complete the erection installation in whole hole, can also complete before precast pier post, bent cap across
" one-stop " erection and installation, it is a kind of economy, efficiently form of construction work;
(2)This construction method when carrying out via step, without on bridge floor lay vertical shift rail, by it is preceding lifting dolly, after
Lifting dolly, front leg strut, rear support leg, support supporting leg and rise the can of working in coordination of supporting leg and realize self-service via, carry significantly
High efficiency of construction, shortens the engineering time;
(3)Simultaneously in via, the preceding lifting dolly and rear lifting dolly that are carried using Bridge Erector carry out Unwinding fortune, safety coefficient
Height, greatly reduce the generation of accident;
(4)This construction method only needs in general crane to coordinate itself preceding again under conditions of no large tonnage crane auxiliary
Hang dolly, afterwards lift by crane dolly, front leg strut, rear support leg, support supporting leg and rise supporting leg can be in less construction site rapidly
Complete the action adjustment of opposite direction construction;
(5)This construction method full bridge structure, for example, pier column, bent cap, bridge piece etc. be factory shift to an earlier date it is prefabricated form, only need
Transport to scene and carry out erection installation;Reduce requirement of the construction to site environment, production efficiency is high, and prefabricated production
Quality is controlled, and the quality of bridge is high, integrated engineering low cost;
(6)This construction method is highly suitable for surrounding city, and execution conditions are complicated, the big place progress of construction environment traffic pressure
The fast erecting of the aerial part overpass such as urban road, urban light rail and subway line;It will promote that highway in China is overhead, city
City's light rail, the construction of subway elevated bridge develop to greenization, batch production, standardized construction direction, and its economical, societal benefits is by day
It is beneficial notable.
Brief description of the drawings
Fig. 1 is the structural representation of Bridge Erector;
Fig. 2 is step A schematic diagrames;
Fig. 3 is step B schematic diagrames;
Fig. 4 is one of step C schematic diagrames;
Fig. 5 is the two of step C schematic diagrames;
Fig. 6 is one of step D schematic diagrames;
Fig. 7 is the two of step D schematic diagrames;
Fig. 8 is one of step F schematic diagrames;
Fig. 9 is the two of step F schematic diagrames.
Embodiment
The present invention is further described below in conjunction with the accompanying drawings.
As shown in figure 1, used Bridge Erector includes the horn 3 along the equal symmetric design of vertical and horizontal, affiliated horn 3 is
Double box-beam structures, auxiliary leg 8 before being provided with the front end of horn 3, preceding auxiliary leg 8 include connecting rod successively from top to bottom
20th, draw money on credit strut 22 and bottom supporting leg 21, connecting rod 20 is detachably connected on the front end of horn 3, and the lower end of connecting rod 20 is with drawing money on credit
The top of strut 22 is detachably connected, and lower end and the bottom supporting leg 21 of strut 22 of drawing money on credit are detachably connected, and are provided with bottom supporting leg 21
Lifting body, it is provided with the rear end of horn 3 and rises supporting leg 4, it can be construction direction walking along longitudinal direction to be provided with the middle part of horn 3
Front leg strut 7 and rear support leg 6, be furnished with support supporting leg 5 in the rear side of rear support leg 6, wherein, front leg strut 7, rear support leg 6, support supporting leg
5 are used to horn 3 being supported on pier column or bridge piece with supporting leg 4 is risen, and preceding auxiliary leg 8 is used for the front support of horn 3
In abutment on the ground, it is all provided with horn 3 equipped with preceding lifting dolly 2 and rear lifting dolly 1, preceding lifting dolly 2 and rear lifting dolly 1
There are each independent lifting mechanism, walking mechanism and transverse-moving mechanism, preceding lifting dolly 2 is provided with rotating mechanism, the rotating mechanism
The lifting mechanism of lifting dolly rotates in the horizontal plane before driving;Traversing rolling is equipped with the bottom of front leg strut 7 and rear support leg 6
Wheel, it is furnished with the cross moving track for being used for roller and laterally walking in the bottom of front leg strut 7 and rear support leg 6, front leg strut 7, rear support leg 6, holds
Support supporting leg 5 and rise supporting leg 4 and be equipped with respective left column, right column and crossbeam so as to from middle transport bridge beam piece, pier column
Or bent cap;In preceding auxiliary leg 8, front leg strut 7, rear support leg 6, support supporting leg 5 and rise respective jack is equipped with supporting leg 4
Structure.
A kind of construction method of full precast bridge, Pn pier columns 13 and Pn are set for the ease of description along construction direction
All Pn bridges pieces have been set up between+Bridge 1 pier stud 14 and have formed Pn section bridge floors 10, have then been carried out using above-mentioned Bridge Erector
Following steps:
A:The Pn+3 pier columns of side are first set up, then set up the Pn+3 pier columns of opposite side;
B:During Pn+3 pier columns grouting etc. is strong, the Pn between installation Pn+1 pier columns 14 and Pn+2 pier columns 15
+ Bridge 1 beam piece;
C:Set up in all Pn+1 bridges pieces and complete to be after formation Pn+1 saves bridge floor 16, between two Pn+3 pier columns
Set up Pn+3 bent caps;
D:After reaching requirement Deng Pn+3 bent cap filling intensities, Bridge Erector via, the construction of Pn+4 pier columns is carried out;
E:Repeat step A to D, until final section bridge piece is installed.
After the completion of step E, step F can also be carried out:Carry out opposite direction construction.
As shown in Fig. 2 the step A specifically comprises the following steps:
A1:The station of preceding auxiliary leg 8 of Bridge Erector is on the bracket by Pn+3 bridge pier bases, and front leg strut station 7 is in Pn+2 pier columns
On 15 on the track of Pn+2 bent caps 16, rear support leg 6 and support supporting leg 5 are stood on Pn section bridge floors 10;
A2:Front and rear two beam cars 9,12 feed Pn+3 pier columns 11 from Bridge Erector rear end;
A3:Preceding lifting dolly 2 lifts the front end of Pn+3 pier columns 11, and then beam car 9 moves ahead together, beam car 9 after
During close to preceding beam car 12, the rear rear end lifted by crane dolly 1 and lift Pn+3 pier columns 11 is preceding to lift by crane dolly 2 and rear lifting dolly 1
Pn+3 pier columns 11 are transported into Pn+3 pier column installation site correct positions;
A4:Preceding lifting dolly 2 remains stationary as, and rear lifting dolly 1 is progressively close to preceding lifting dolly 2 and while lower section Pn+3 bridge piers
The rear end of post 11, until Pn+3 pier columns 11 are in vertical state;
A5:Lifting dolly 1 departs from Pn+3 pier columns 11 afterwards, and preceding lifting dolly 2 independently lifts Pn+3 pier columns 11 and will
It is arranged on corresponding position, completes the construction of side Pn+3 pier columns 11;
A6:Transverse shifting Bridge Erector, repeat step A1 to A5 complete the construction of opposite side Pn+3 pier columns 11.
As shown in figure 3, the step B comprises the following steps:
B1:Preceding lifting dolly 2 and rear lifting dolly 1 take Pn+1 bridge pieces from beam car, and are transported to Pn+1 bridge piers
Between post 14 and Pn+2 pier columns 15, erection installation is carried out;
B2:Transverse shifting Bridge Erector, repeat step B1 form Pn+ until all Pn+1 bridges pieces are set up into installation
1 section bridge floor 17.
Such as Fig. 4, shown in Fig. 5, the step C comprises the following steps:
C1:The region that lifting dolly 2 can lift by crane before Pn+3 bent caps 18 are transported to by beam car from the bridge floor of Bridge Erector rear end;
C2:Between slinging Pn+3 bent caps 18 using preceding lifting dolly 2 and be transported to two Pn+3 pier columns, then rotate
Pn+3 bent caps 18, by it across on two Pn+3 pier columns 11.
Such as Fig. 6, step D comprises the following steps described in Fig. 7:
D1:Bridge Erector is traversing to wire center, the preceding station of auxiliary leg 8 on the bracket of Pn+3 bridge pier bases, preceding auxiliary leg 8,
Front leg strut 7 and support supporting leg 5 support horn 3, and the Pn+1 that rear support leg 6 is hoisted to the rear of front leg strut 7 with preceding lifting dolly 2 is saved
On bridge floor 16 and horn 3 is supported, then front leg strut 7 is hoisted on the track of Pn+3 bent caps using preceding lifting dolly 2;
D2:Preceding dolly and the rear lifting dolly of lifting by crane is stepped back to the top of rear support leg 6, preceding auxiliary leg 8 is packed up and rises the machine of supporting leg 4
Arm one segment distance of advance, when rising supporting leg 4 close to support supporting leg 5, horn halts, and rises supporting leg 4 and support horn 3,
Support supporting leg 5 is hoisted to the rear of rear support leg 6 by lifting dolly 1 afterwards;
D3:Preceding dolly 2 and the rear lifting dolly 1 of lifting by crane runs to the top of rear support leg 6, packs up preceding auxiliary leg 8 and rises supporting leg 4,
Machine, 3, which move on auxiliary leg 8 before a segment distance progressively causes, reaches on the bracket of Pn+4 bridge pier bases, at the same time preceding
Hang dolly 2 and the 1 synchronous retrogressing of rear lifting dolly is maintained at the top of rear support leg.
Such as Fig. 8, shown in Fig. 9, the step F comprises the following steps:
F1:The strut 22 that will draw money on credit disassembles from connecting rod 20 and bottom supporting leg 21, is then removably mounted at bottom supporting leg 21
Transition supporting leg is formed in connecting rod 20, transition supporting leg station is on minor details bridge floor or station is on the ground being connected with minor details bridge floor;
F2:Front leg strut 7, rear support leg 6 are transported forward using preceding lifting dolly 2 and rear lifting dolly 1;
F3:Transition supporting leg is exchanged into position installation with supporting leg 4 is risen using preceding lifting dolly 2 and rear lifting dolly 1;
F4:Front leg strut 7 is arranged on by support supporting leg 5 using preceding lifting dolly 2 and rear lifting dolly 1;
F5:Support supporting leg 5 is arranged on to the front of rear support leg 6 using preceding lifting dolly 2 and rear lifting dolly 1;
F6:Preceding lifting dolly 2 and rear lifting dolly 1 are exchanged into installation by crane;
F7:Bottom supporting leg 21 is disassembled from connecting rod 20, by the upper and lower side for strut 22 of drawing money on credit respectively with connecting rod 20, bottom branch
Auxiliary leg before the connection composition of leg 21;
F8:Electric hydraulic connection is adjusted, so as to possess the Summarized Account of Bridge Erection Construction of opposite direction.
The present invention has following beneficial effect compared with prior art:
(1)This construction method can not only complete the erection installation in whole hole, can also complete before precast pier post, bent cap across
" one-stop " erection and installation, it is a kind of economy, efficiently form of construction work;
(2)This construction method when carrying out via step, without on bridge floor lay vertical shift rail, by it is preceding lifting dolly, after
Lifting dolly, front leg strut, rear support leg, support supporting leg and rise the can of working in coordination of supporting leg and realize self-service via, carry significantly
High efficiency of construction, shortens the engineering time;
(3)Simultaneously in via, the preceding lifting dolly and rear lifting dolly that are carried using Bridge Erector carry out Unwinding fortune, safety coefficient
Height, greatly reduce the generation of accident;
(4)This construction method only needs in general crane to coordinate itself preceding again under conditions of no large tonnage crane auxiliary
Hang dolly, afterwards lift by crane dolly, front leg strut, rear support leg, support supporting leg and rise supporting leg can be in less construction site rapidly
Complete the action adjustment of opposite direction construction;
(5)This construction method full bridge structure, for example, pier column, bent cap, bridge piece etc. be factory shift to an earlier date it is prefabricated form, only need
Transport to scene and carry out erection installation;Reduce requirement of the construction to site environment, production efficiency is high, and prefabricated production
Quality is controlled, and the quality of bridge is high, integrated engineering low cost;
(6)This construction method is highly suitable for surrounding city, and execution conditions are complicated, the big place progress of construction environment traffic pressure
The fast erecting of the aerial part overpass such as urban road, urban light rail and subway line;It will promote that highway in China is overhead, city
City's light rail, the construction of subway elevated bridge develop to greenization, batch production, standardized construction direction, and its economical, societal benefits is by day
It is beneficial notable.
Finally it should be noted that:The above embodiments are merely illustrative of the technical solutions of the present invention, rather than its limitations;Although
The present invention is described in detail with reference to the foregoing embodiments, it will be understood by those within the art that:It still may be used
To be modified to the technical scheme described in foregoing embodiments, or equivalent substitution is carried out to which part technical characteristic,
But these modification or replace, do not make appropriate technical solution essence depart from various embodiments of the present invention technical scheme spirit and
Scope.
Claims (10)
1. a kind of Bridge Erector for being used to set up full precast beam, including the horn along the equal symmetric design of vertical and horizontal, affiliated horn
For double box-beam structures, it is characterised in that auxiliary leg before being provided with the front end of horn, be provided with the rear end of horn and rise branch
Leg, support supporting leg can be furnished with along the front leg strut and rear support leg longitudinally walked in the rear side of rear support leg by being provided with the middle part of horn, its
In, front leg strut, rear support leg, support supporting leg and rise supporting leg and be used to horn being supported on pier column or bridge piece, preceding auxiliary branch
Leg be used for by horn front support in abutment on the ground, equipped with preceding lifting dolly and rear lifting dolly, preceding lifting dolly on horn
Each independent lifting mechanism, walking mechanism and transverse-moving mechanism are equipped with rear lifting dolly, at the bottom of front leg strut and rear support leg
Portion is equipped with traversing roller, is furnished with the cross moving track for being used for roller and laterally walking in the bottom of front leg strut and rear support leg;Preceding auxiliary
Help supporting leg, front leg strut, rear support leg, support supporting leg and rise respective lifting body is equipped with supporting leg.
2. the Bridge Erector according to claim 1 for being used to set up full precast beam, it is characterised in that the preceding auxiliary leg is certainly
It is upper and under include connecting rod, draw money on credit strut and bottom supporting leg successively, connecting rod is detachably connected on the front end of horn, under connecting rod
Hold and the draw money on credit top of strut is detachably connected, and lower end and the bottom supporting leg of strut of drawing money on credit are detachably connected, and lifting body is arranged on
On the supporting leg of bottom;Lifting dolly is provided with rotating mechanism before described, and the lifting mechanism of lifting dolly is in water before the rotating mechanism drives
Rotation with surface.
3. according to claim 1 or 2 be used to set up the Bridge Erector of full precast beam, it is characterised in that the front leg strut, after
Supporting leg, support supporting leg and rise supporting leg be equipped with respective left column, right column so as to from middle transport bridge beam piece, pier column or
Bent cap.
4. a kind of Bridge Erector using as described in any one of claims 1 to 3 carries out the construction method of full precast bridge, its feature
It is, is set along construction direction and all Pn bridges pieces have been set up between Pn pier columns and Pn+1 pier columns form
Pn saves bridge floor, then carries out following steps using Bridge Erector:
A:The Pn+3 pier columns of side are first set up, then set up the Pn+3 pier columns of opposite side;
B:During Pn+3 pier columns grouting etc. is strong, the Pn+1 bridges between Pn+1 pier columns and Pn+2 pier columns are installed
Beam piece;
C:Set up in all Pn+1 bridges pieces and complete to be after formation Pn+1 saves bridge floor, in a structure of an essay for two Pn+3 pier columns
If Pn+3 bent caps;
D:After reaching requirement Deng Pn+3 bent cap filling intensities, Bridge Erector via, to carry out the construction of Pn+4 pier columns;
E:Repeat step A to D, until final section bridge piece is installed.
5. the construction method of full precast bridge according to claim 4, it is characterised in that the step A includes following step
Suddenly:
A1:The preceding auxiliary leg station of Bridge Erector is on the bracket by Pn+3 bridge pier bases, and front leg strut station is on Pn+2 pier columns
On the track of Pn+2 bent caps, rear support leg and support supporting leg are stood on Pn section bridge floors;
A2:Front and rear two beam cars feed Pn+3 pier columns from Bridge Erector rear end;
A3:Preceding lifting dolly lifts the front end of Pn+3 pier columns, and then beam car moves ahead together, and beam car is before after
During beam car, the rear rear end lifted by crane dolly and lift Pn+3 pier columns, preceding dolly and the rear lifting dolly of lifting by crane is by Pn+3 bridge piers
Post transports to Pn+3 pier column installation site correct positions;
A4:Preceding lifting dolly remains stationary as, and rear lifting dolly is progressively close to preceding lifting dolly and while lower section Pn+3 pier columns
Rear end, until Pn+3 pier columns are in vertical state;
A5:Dolly is lifted by crane afterwards and Pn+3 pier columns depart from, and preceding lifting dolly independently lifts Pn+3 pier columns and installed
In corresponding position, the construction of side Pn+3 pier columns is completed;
A6:Transverse shifting Bridge Erector, repeat step A1 to A5 complete the construction of opposite side Pn+3 pier columns.
6. the construction method of full precast bridge according to claim 5, it is characterised in that the step B includes following step
Suddenly:
B1:Preceding lifting dolly and rear lifting dolly take Pn+1 bridge pieces from beam car, and are transported to Pn+1 pier columns
Between Pn+2 pier columns, erection installation is carried out;
B2:Transverse shifting Bridge Erector, repeat step B1 form Pn+1 until all Pn+1 bridges pieces are set up into installation
Save bridge floor.
7. the construction method of full precast bridge according to claim 6, it is characterised in that the step C includes following step
Suddenly:
C1:The region that lifting dolly can lift by crane before Pn+3 bent caps are transported to by beam car from the bridge floor of Bridge Erector rear end;
C2:Between slinging Pn+3 bent caps using preceding lifting dolly and be transported to Pn+3 pier columns, Pn+3 is then rotated
Bent cap, by it across on two Pn+3 pier columns.
8. the construction method of full precast bridge according to claim 7, it is characterised in that the step D includes following step
Suddenly:
D1:Bridge Erector is traversing to wire center, and preceding auxiliary leg station is preceding auxiliary leg, preceding on the bracket of Pn+3 bridge pier bases
Supporting leg and support supporting leg support horn, rear support leg is hoisted on the Pn+1 section bridge floors at front leg strut rear simultaneously with preceding lifting dolly
Horn is supported, then front leg strut is hoisted on the track of Pn+3 bent caps using preceding lifting dolly;
D2:Preceding dolly and the rear lifting dolly of lifting by crane is stepped back to above rear support leg, preceding auxiliary leg is packed up and rises supporting leg horn
Advance a segment distance, and when rising supporting leg close to support supporting leg, horn halts, and rises supporting leg support horn, rear lifting
Support supporting leg is hoisted to the rear of rear support leg by dolly;
D3:Above preceding lifting dolly and rear lifting carriage walking to rear support leg, before packing up auxiliary leg and rise supporting leg horn after
Auxiliary leg is reached on the bracket of Pn+4 bridge pier bases before the continuous segment distance that advances progressively causes, at the same time preceding lifting dolly and
Dolly is lifted by crane afterwards synchronously retreats the top for being maintained at rear support leg.
9. the construction method of the full precast bridge according to right wants 8, it is characterised in that the preceding auxiliary leg is from top to bottom
Include connecting rod, draw money on credit strut and bottom supporting leg successively, connecting rod is detachably connected on the front end of horn, the lower end of connecting rod and length
The top of support bar is detachably connected, and lower end and the bottom supporting leg of strut of drawing money on credit are detachably connected, and lifting body is arranged on bottom supporting leg
On.
10. the construction method of the full precast bridge according to right wants 9, it is characterised in that can also be carried out after step E
Step F, the step F comprise the following steps:
F1:The strut that will draw money on credit is disassembled from connecting rod and bottom supporting leg, and then bottom supporting leg is removably mounted in connecting rod
Transition supporting leg is formed, transition supporting leg station is on minor details bridge floor or station is on the ground being connected with minor details bridge floor;
F2:Front leg strut, rear support leg are transported forward using preceding lifting dolly and rear lifting dolly;
F3:Transition supporting leg is exchanged into position installation with supporting leg is risen using preceding lifting dolly and rear lifting dolly;
F4:Front leg strut is arranged on by support supporting leg using preceding lifting dolly and rear lifting dolly;
F5:Support supporting leg is arranged on to the front of rear support leg using preceding lifting dolly and rear lifting dolly;
F6:Preceding lifting dolly and rear lifting dolly are exchanged into installation by crane;
F7:Bottom supporting leg is disassembled from connecting rod, the upper and lower side for strut of drawing money on credit is connected group with connecting rod, bottom supporting leg respectively
Into preceding auxiliary leg;
F8:Electric hydraulic connection is adjusted, so as to possess the Summarized Account of Bridge Erection Construction of opposite direction.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710858907.5A CN107558378B (en) | 2017-09-21 | 2017-09-21 | Bridge girder erection machine for erecting full precast girder and bridge girder erection method thereof |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710858907.5A CN107558378B (en) | 2017-09-21 | 2017-09-21 | Bridge girder erection machine for erecting full precast girder and bridge girder erection method thereof |
Publications (2)
Publication Number | Publication Date |
---|---|
CN107558378A true CN107558378A (en) | 2018-01-09 |
CN107558378B CN107558378B (en) | 2023-06-23 |
Family
ID=60982435
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710858907.5A Active CN107558378B (en) | 2017-09-21 | 2017-09-21 | Bridge girder erection machine for erecting full precast girder and bridge girder erection method thereof |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107558378B (en) |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109024291A (en) * | 2018-08-06 | 2018-12-18 | 江苏恩纳斯重工机械有限公司 | A kind of integration Bridge Erector and its working method |
CN110093863A (en) * | 2019-05-31 | 2019-08-06 | 浙江省交通规划设计研究院有限公司 | A kind of double face integration Bridge Erector being not provided with front leg strut |
CN110748163A (en) * | 2019-11-15 | 2020-02-04 | 河南省中冶起重机有限公司 | Novel bridge girder erection machine |
CN113373814A (en) * | 2021-06-11 | 2021-09-10 | 中铁工程机械研究设计院有限公司 | Highway bridge erecting method |
CN114250711A (en) * | 2021-12-31 | 2022-03-29 | 史托克(天津)工程技术有限公司 | Highway bridge girder erection machine and hole passing method |
CN114438901A (en) * | 2022-03-22 | 2022-05-06 | 四川发展磁浮科技有限公司 | Construction method for built-in magnetic suspension elevated line bridge girder erection machine |
CN114808736A (en) * | 2022-05-20 | 2022-07-29 | 中昕重工(宁波)有限公司 | Bridge prefabricated part cross-inside transverse flat-turning hoisting device and hoisting process method |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH11222819A (en) * | 1998-02-10 | 1999-08-17 | Kajima Corp | Execution method of elevated structure using building girder |
CN101144259A (en) * | 2007-09-20 | 2008-03-19 | 中铁二局股份有限公司 | Large tonnage whole opening box girder transmitting and construction method |
US20130055512A1 (en) * | 2010-05-19 | 2013-03-07 | Beijing Wowjoint Machinery Co | Transportation and erection integrated machine with displacement platforms and methods for erecting bridge using the same |
CN202899044U (en) * | 2012-07-26 | 2013-04-24 | 中铁六局集团有限公司 | Vierendeel box-shaped double-girder bridge crane |
CN104831630A (en) * | 2014-10-22 | 2015-08-12 | 中铁十一局集团第六工程有限公司 | Light small-curve segment assembling and bridging machine |
CN105735142A (en) * | 2016-05-06 | 2016-07-06 | 郑州新大方重工科技有限公司 | Bridge girder erection machine for prestressed concrete bridge precast section span-by-span splicing construction |
CN207775719U (en) * | 2017-09-21 | 2018-08-28 | 郑州新大方重工科技有限公司 | A kind of Bridge Erector for setting up full precast beam |
-
2017
- 2017-09-21 CN CN201710858907.5A patent/CN107558378B/en active Active
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH11222819A (en) * | 1998-02-10 | 1999-08-17 | Kajima Corp | Execution method of elevated structure using building girder |
CN101144259A (en) * | 2007-09-20 | 2008-03-19 | 中铁二局股份有限公司 | Large tonnage whole opening box girder transmitting and construction method |
US20130055512A1 (en) * | 2010-05-19 | 2013-03-07 | Beijing Wowjoint Machinery Co | Transportation and erection integrated machine with displacement platforms and methods for erecting bridge using the same |
CN202899044U (en) * | 2012-07-26 | 2013-04-24 | 中铁六局集团有限公司 | Vierendeel box-shaped double-girder bridge crane |
CN104831630A (en) * | 2014-10-22 | 2015-08-12 | 中铁十一局集团第六工程有限公司 | Light small-curve segment assembling and bridging machine |
CN105735142A (en) * | 2016-05-06 | 2016-07-06 | 郑州新大方重工科技有限公司 | Bridge girder erection machine for prestressed concrete bridge precast section span-by-span splicing construction |
CN207775719U (en) * | 2017-09-21 | 2018-08-28 | 郑州新大方重工科技有限公司 | A kind of Bridge Erector for setting up full precast beam |
Cited By (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109024291A (en) * | 2018-08-06 | 2018-12-18 | 江苏恩纳斯重工机械有限公司 | A kind of integration Bridge Erector and its working method |
CN110093863A (en) * | 2019-05-31 | 2019-08-06 | 浙江省交通规划设计研究院有限公司 | A kind of double face integration Bridge Erector being not provided with front leg strut |
CN110748163A (en) * | 2019-11-15 | 2020-02-04 | 河南省中冶起重机有限公司 | Novel bridge girder erection machine |
CN113373814A (en) * | 2021-06-11 | 2021-09-10 | 中铁工程机械研究设计院有限公司 | Highway bridge erecting method |
CN114250711A (en) * | 2021-12-31 | 2022-03-29 | 史托克(天津)工程技术有限公司 | Highway bridge girder erection machine and hole passing method |
CN114250711B (en) * | 2021-12-31 | 2024-06-04 | 史托克(天津)工程技术有限公司 | Highway bridge girder erection machine and hole passing method |
CN114438901A (en) * | 2022-03-22 | 2022-05-06 | 四川发展磁浮科技有限公司 | Construction method for built-in magnetic suspension elevated line bridge girder erection machine |
CN114808736A (en) * | 2022-05-20 | 2022-07-29 | 中昕重工(宁波)有限公司 | Bridge prefabricated part cross-inside transverse flat-turning hoisting device and hoisting process method |
CN114808736B (en) * | 2022-05-20 | 2024-04-12 | 中昕重工(宁波)有限公司 | Bridge prefabricated part inner-span transverse horizontal rotation hoisting device and hoisting process method |
Also Published As
Publication number | Publication date |
---|---|
CN107558378B (en) | 2023-06-23 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107558378A (en) | A kind of Bridge Erector and its bridging method for being used to set up full precast beam | |
CN107740350B (en) | The bridge pier column construction method and its passing method of full precast bridge Bridge Erector | |
CN102373671B (en) | Steel trussed beam and flexible arch bridge construction method with vault pushing | |
CN101230785B (en) | Construction method for large section and multiple sections tunnel lining | |
CN104499433B (en) | One wears high ferro low clearance erecting beam construction method under acutangulating intersection | |
CN104594918B (en) | Split integrated underground passage steel mold plate trolley and construction method thereof | |
CN100547225C (en) | A kind of tunnel overhead arch mould plate trolley with floating type traffic under carriage | |
CN108677742B (en) | Movable cantilever bridge girder erection machine for full-prefabricated bridge pier, bearing platform and girder body assembled construction | |
CN107460830A (en) | The full precast bridge of Mid and minor spans is without sidewalk scheme of architecture | |
CN102979038A (en) | Cast-in-place box beam mobile bracket with increased width | |
CN102134832A (en) | Movable support and movable support assisted method for erecting steel box beams through non-variable amplitude frame beam crane | |
CN101324054B (en) | Incremental launching positioning construction method of bridge subsection girder temporary pier | |
CN210561749U (en) | Multi-frame juxtaposed double-cantilever bridge girder erection machine | |
CN201943004U (en) | Double-girder transporting and erecting integrated bridge girder erecting machine capable of realizing girder erecting at zero distance from tunnel portal | |
CN207775719U (en) | A kind of Bridge Erector for setting up full precast beam | |
CN110158486B (en) | Bridge girder erection machine for erecting spliced wide beams and construction method | |
CN114808747A (en) | Multifunctional bridge girder erection machine and bridge girder erection construction method | |
CN203248170U (en) | Lining trolley for secondary lining construction of pedestrian crosswalk | |
CN110205948A (en) | A kind of expanded letter Bridge Erector and its erection method | |
CN104110002A (en) | Method for replacing bridge deck slabs of steel truss girder bridge | |
CN206035507U (en) | Rectangle box culvert and for tunnel construction platform truck | |
CN202989781U (en) | Width widened cast-in-place box beam moving support | |
CN110924310A (en) | Adjustable movable lifting device on girder transporting bridge and opposite-pulling portal tunnel crossing construction method | |
CN111945572B (en) | Multi-connected arch bridge erecting machine and multi-connected arch bridge erecting method | |
CN212925808U (en) | Vertical and longitudinal connecting device for bridge erecting machine |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |