CN107558378A - A kind of Bridge Erector and its bridging method for being used to set up full precast beam - Google Patents

A kind of Bridge Erector and its bridging method for being used to set up full precast beam Download PDF

Info

Publication number
CN107558378A
CN107558378A CN201710858907.5A CN201710858907A CN107558378A CN 107558378 A CN107558378 A CN 107558378A CN 201710858907 A CN201710858907 A CN 201710858907A CN 107558378 A CN107558378 A CN 107558378A
Authority
CN
China
Prior art keywords
leg
supporting leg
bridge
dolly
horn
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710858907.5A
Other languages
Chinese (zh)
Other versions
CN107558378B (en
Inventor
张志华
贾力锋
陈德利
代宇
王琪
程波
陈媛媛
陈永久
牛青林
李军超
张俊艳
白康
宋飞
宋鲁竞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhengzhou New Dafang Heavy Industries and Technology Co Ltd
Original Assignee
Zhengzhou New Dafang Heavy Industries and Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhengzhou New Dafang Heavy Industries and Technology Co Ltd filed Critical Zhengzhou New Dafang Heavy Industries and Technology Co Ltd
Priority to CN201710858907.5A priority Critical patent/CN107558378B/en
Publication of CN107558378A publication Critical patent/CN107558378A/en
Application granted granted Critical
Publication of CN107558378B publication Critical patent/CN107558378B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The invention discloses a kind of Bridge Erector and its bridging method for being used to set up full precast beam, including the horn along the equal symmetric design of vertical and horizontal, affiliated horn is double box-beam structures, auxiliary leg before being provided with the front end of horn, it is provided with the rear end of horn and rises supporting leg, support supporting leg can be furnished with along the front leg strut and rear support leg longitudinally walked in the rear side of rear support leg by being provided with the middle part of horn;The bridging method carried out using above-mentioned Bridge Erector is highly suitable for surrounding city, and execution conditions are complicated, and the big place of construction environment traffic pressure carries out the fast erecting of the aerial part overpass such as urban road, urban light rail and subway line;Overhead highway in China, urban light rail, the construction of subway elevated bridge will be promoted to develop to greenization, batch production, standardized construction direction, its economical, societal benefits will be increasingly notable.

Description

A kind of Bridge Erector and its bridging method for being used to set up full precast beam
Technical field
The invention belongs to precast bridge technical field of construction, more particularly to a kind of Bridge Erector for being used to set up full precast beam and Its bridging method.
Background technology
With the quickening of Chinese Urbanization pace of construction, in order to economize the land resource, urban road, urban light rail and subway The aerial part overpass such as circuit is more and more.Its with conventional overpass except that, these elevated bridges mostly occur In surrounding city, execution conditions are complicated, and construction environment traffic pressure is big, and higher requirement is proposed to Bridge Erector adaptability.
Commonly used at this stage highway bridging machine construction technology is ripe and is widely used, but it the shortcomings that with work condition environment Development be also more obvious:
1st, existing highway bridge pier stud and bent cap typically take the colligation of on-site hoisting reinforcing bar to install, and in-site installation template, cast in situs is supported The mode of shield, constructs larger by natural environment influence, and quality control difficulties are serious to ambient contamination.
2nd, existing Bridge Erector generally itself can not realize reverse construction, be typically necessary the auxiliary dismounting of large tonnage crane, Even carrying out the dismounting of complete machine can realize;
3rd, it is many during existing Bridge Erector via traveling to require to lay vertical shift rail in beam face, not only to having built bridge beam stress not Profit, also influence efficiency of construction;
4th, it is not that wheel track bridge floor traveling is exactly to hang wheeled during each supporting leg via of existing Bridge Erector, former is applied in both modes Work bridge floor workload is big, and efficiency is low, and influences stress of having built bridge;Latter repeatedly occurs supporting leg during practical application and fallen Fall or traveling be not smooth, caused by loss it is very big.
It is more and more urgent to be consequently for overhead highway, urban light rail, the Bridge Erector demand of subway overpass.
The content of the invention
The present invention seeks to for solve above-mentioned technical problem propose it is a kind of be used to set up the Bridge Erector of full precast beam, for up to Adopted the technical scheme that to above-mentioned purpose:
It is a kind of to be used to set up the Bridge Erector of full precast beam, including the horn along the equal symmetric design of vertical and horizontal, affiliated horn are Double box-beam structures, auxiliary leg before being provided with the front end of horn, are provided with the rear end of horn and rise supporting leg, in horn Portion be provided with can be furnished with support supporting leg in the rear side of rear support leg along the front leg strut and rear support leg longitudinally walked, wherein, front leg strut, after Supporting leg, support supporting leg and rise supporting leg and be used to horn being supported on pier column or bridge piece, preceding auxiliary leg is used for horn Front support on the ground, dolly and rear lifting dolly, preceding lifting dolly and rear lifting dolly is lifted by crane on horn in abutment equipped with preceding Each independent lifting mechanism, walking mechanism and transverse-moving mechanism are equipped with, is equipped with the bottom of front leg strut and rear support leg traversing Roller, it is furnished with the cross moving track for being used for roller and laterally walking in the bottom of front leg strut and rear support leg;In preceding auxiliary leg, preceding branch Leg, rear support leg, support supporting leg and rise respective lifting body is equipped with supporting leg.
Preferably, the preceding auxiliary leg include connecting rod successively from top to bottom, draw money on credit strut and bottom supporting leg, connecting rod can Dismantling connection is detachably connected on the front end of horn, the lower end of connecting rod and the top for strut of drawing money on credit, the lower end for strut of drawing money on credit with Bottom supporting leg is detachably connected, and lifting body is arranged on the supporting leg of bottom;Lifting dolly is provided with rotating mechanism, the whirler before described The lifting mechanism of lifting dolly rotates in the horizontal plane before structure drives.
Preferably, the front leg strut, rear support leg, support supporting leg and rise supporting leg and be equipped with respective left column, right column So as to from middle transport bridge beam piece, pier column or bent cap.
A kind of construction method that full precast bridge is carried out using Bridge Erector as described above, Pn bridges are set along construction direction All Pn bridges pieces have been set up between pier stud and Pn+1 pier columns and have formed Pn section bridge floors, have then been entered using Bridge Erector Row following steps:
A:The Pn+3 pier columns of side are first set up, then set up the Pn+3 pier columns of opposite side;
B:During Pn+3 pier columns grouting etc. is strong, the Pn+1 bridges between Pn+1 pier columns and Pn+2 pier columns are installed Beam piece;
C:Set up in all Pn+1 bridges pieces and complete to be after formation Pn+1 saves bridge floor, in a structure of an essay for two Pn+3 pier columns If Pn+3 bent caps;
D:After reaching requirement Deng Pn+3 bent cap filling intensities, Bridge Erector via, to carry out the construction of Pn+4 pier columns;
E:Repeat step A to D, until final section bridge piece is installed.
Preferably, the step A comprises the following steps:
A1:The preceding auxiliary leg station of Bridge Erector is on the bracket by Pn+3 bridge pier bases, and front leg strut station is on Pn+2 pier columns On the track of Pn+2 bent caps, rear support leg and support supporting leg are stood on Pn section bridge floors;
A2:Front and rear two beam cars feed Pn+3 pier columns from Bridge Erector rear end;
A3:Preceding lifting dolly lifts the front end of Pn+3 pier columns, and then beam car moves ahead together, and beam car is before after During beam car, the rear rear end lifted by crane dolly and lift Pn+3 pier columns, preceding dolly and the rear lifting dolly of lifting by crane is by Pn+3 bridge piers Post transports to Pn+3 pier column installation site correct positions;
A4:Preceding lifting dolly remains stationary as, and rear lifting dolly is progressively close to preceding lifting dolly and while lower section Pn+3 pier columns Rear end, until Pn+3 pier columns are in vertical state;
A5:Dolly is lifted by crane afterwards and Pn+3 pier columns depart from, and preceding lifting dolly independently lifts Pn+3 pier columns and installed In corresponding position, the construction of side Pn+3 pier columns is completed;
A6:Transverse shifting Bridge Erector, repeat step A1 to A5 complete the construction of opposite side Pn+3 pier columns.
Preferably, the step B comprises the following steps:
B1:Preceding lifting dolly and rear lifting dolly take Pn+1 bridge pieces from beam car, and are transported to Pn+1 pier columns Between Pn+2 pier columns, erection installation is carried out;
B2:Transverse shifting Bridge Erector, repeat step B1 form Pn+1 until all Pn+1 bridges pieces are set up into installation Save bridge floor.
Preferably, the step C comprises the following steps:
C1:The region that lifting dolly can lift by crane before Pn+3 bent caps are transported to by beam car from the bridge floor of Bridge Erector rear end;
C2:Between slinging Pn+3 bent caps using preceding lifting dolly and be transported to Pn+3 pier columns, Pn+3 is then rotated Bent cap, by it across on two Pn+3 pier columns.
Preferably, the step D comprises the following steps:
D1:Bridge Erector is traversing to wire center, and preceding auxiliary leg station is preceding auxiliary leg, preceding on the bracket of Pn+3 bridge pier bases Supporting leg and support supporting leg support horn, rear support leg is hoisted on the Pn+1 section bridge floors at front leg strut rear simultaneously with preceding lifting dolly Horn is supported, then front leg strut is hoisted on the track of Pn+3 bent caps using preceding lifting dolly;
D2:Preceding dolly and the rear lifting dolly of lifting by crane is stepped back to above rear support leg, preceding auxiliary leg is packed up and rises supporting leg horn Advance a segment distance, and when rising supporting leg close to support supporting leg, horn halts, and rises supporting leg support horn, rear lifting Support supporting leg is hoisted to the rear of rear support leg by dolly;
D3:Above preceding lifting dolly and rear lifting carriage walking to rear support leg, before packing up auxiliary leg and rise supporting leg horn after Auxiliary leg is reached on the bracket of Pn+4 bridge pier bases before the continuous segment distance that advances progressively causes, at the same time preceding lifting dolly and Dolly is lifted by crane afterwards synchronously retreats the top for being maintained at rear support leg.
Preferably, the preceding auxiliary leg include connecting rod successively from top to bottom, draw money on credit strut and bottom supporting leg, connecting rod can Dismantling connection is detachably connected on the front end of horn, the lower end of connecting rod and the top for strut of drawing money on credit, the lower end for strut of drawing money on credit with Bottom supporting leg is detachably connected, and lifting body is arranged on the supporting leg of bottom.
Preferably, step F can also be carried out after step E, the step F comprises the following steps:
F1:The strut that will draw money on credit is disassembled from connecting rod and bottom supporting leg, and then bottom supporting leg is removably mounted in connecting rod Transition supporting leg is formed, transition supporting leg station is on minor details bridge floor or station is on the ground being connected with minor details bridge floor;
F2:Front leg strut, rear support leg are transported forward using preceding lifting dolly and rear lifting dolly;
F3:Transition supporting leg is exchanged into position installation with supporting leg is risen using preceding lifting dolly and rear lifting dolly;
F4:Front leg strut is arranged on by support supporting leg using preceding lifting dolly and rear lifting dolly;
F5:Support supporting leg is arranged on to the front of rear support leg using preceding lifting dolly and rear lifting dolly;
F6:Preceding lifting dolly and rear lifting dolly are exchanged into installation by crane;
F7:Bottom supporting leg is disassembled from connecting rod, the upper and lower side for strut of drawing money on credit is connected group with connecting rod, bottom supporting leg respectively Into preceding auxiliary leg;
F8:Electric hydraulic connection is adjusted, so as to possess the Summarized Account of Bridge Erection Construction of opposite direction.
The present invention has following beneficial effect compared with prior art:
(1)This construction method can not only complete the erection installation in whole hole, can also complete before precast pier post, bent cap across " one-stop " erection and installation, it is a kind of economy, efficiently form of construction work;
(2)This construction method when carrying out via step, without on bridge floor lay vertical shift rail, by it is preceding lifting dolly, after Lifting dolly, front leg strut, rear support leg, support supporting leg and rise the can of working in coordination of supporting leg and realize self-service via, carry significantly High efficiency of construction, shortens the engineering time;
(3)Simultaneously in via, the preceding lifting dolly and rear lifting dolly that are carried using Bridge Erector carry out Unwinding fortune, safety coefficient Height, greatly reduce the generation of accident;
(4)This construction method only needs in general crane to coordinate itself preceding again under conditions of no large tonnage crane auxiliary Hang dolly, afterwards lift by crane dolly, front leg strut, rear support leg, support supporting leg and rise supporting leg can be in less construction site rapidly Complete the action adjustment of opposite direction construction;
(5)This construction method full bridge structure, for example, pier column, bent cap, bridge piece etc. be factory shift to an earlier date it is prefabricated form, only need Transport to scene and carry out erection installation;Reduce requirement of the construction to site environment, production efficiency is high, and prefabricated production Quality is controlled, and the quality of bridge is high, integrated engineering low cost;
(6)This construction method is highly suitable for surrounding city, and execution conditions are complicated, the big place progress of construction environment traffic pressure The fast erecting of the aerial part overpass such as urban road, urban light rail and subway line;It will promote that highway in China is overhead, city City's light rail, the construction of subway elevated bridge develop to greenization, batch production, standardized construction direction, and its economical, societal benefits is by day It is beneficial notable.
Brief description of the drawings
Fig. 1 is the structural representation of Bridge Erector;
Fig. 2 is step A schematic diagrames;
Fig. 3 is step B schematic diagrames;
Fig. 4 is one of step C schematic diagrames;
Fig. 5 is the two of step C schematic diagrames;
Fig. 6 is one of step D schematic diagrames;
Fig. 7 is the two of step D schematic diagrames;
Fig. 8 is one of step F schematic diagrames;
Fig. 9 is the two of step F schematic diagrames.
Embodiment
The present invention is further described below in conjunction with the accompanying drawings.
As shown in figure 1, used Bridge Erector includes the horn 3 along the equal symmetric design of vertical and horizontal, affiliated horn 3 is Double box-beam structures, auxiliary leg 8 before being provided with the front end of horn 3, preceding auxiliary leg 8 include connecting rod successively from top to bottom 20th, draw money on credit strut 22 and bottom supporting leg 21, connecting rod 20 is detachably connected on the front end of horn 3, and the lower end of connecting rod 20 is with drawing money on credit The top of strut 22 is detachably connected, and lower end and the bottom supporting leg 21 of strut 22 of drawing money on credit are detachably connected, and are provided with bottom supporting leg 21 Lifting body, it is provided with the rear end of horn 3 and rises supporting leg 4, it can be construction direction walking along longitudinal direction to be provided with the middle part of horn 3 Front leg strut 7 and rear support leg 6, be furnished with support supporting leg 5 in the rear side of rear support leg 6, wherein, front leg strut 7, rear support leg 6, support supporting leg 5 are used to horn 3 being supported on pier column or bridge piece with supporting leg 4 is risen, and preceding auxiliary leg 8 is used for the front support of horn 3 In abutment on the ground, it is all provided with horn 3 equipped with preceding lifting dolly 2 and rear lifting dolly 1, preceding lifting dolly 2 and rear lifting dolly 1 There are each independent lifting mechanism, walking mechanism and transverse-moving mechanism, preceding lifting dolly 2 is provided with rotating mechanism, the rotating mechanism The lifting mechanism of lifting dolly rotates in the horizontal plane before driving;Traversing rolling is equipped with the bottom of front leg strut 7 and rear support leg 6 Wheel, it is furnished with the cross moving track for being used for roller and laterally walking in the bottom of front leg strut 7 and rear support leg 6, front leg strut 7, rear support leg 6, holds Support supporting leg 5 and rise supporting leg 4 and be equipped with respective left column, right column and crossbeam so as to from middle transport bridge beam piece, pier column Or bent cap;In preceding auxiliary leg 8, front leg strut 7, rear support leg 6, support supporting leg 5 and rise respective jack is equipped with supporting leg 4 Structure.
A kind of construction method of full precast bridge, Pn pier columns 13 and Pn are set for the ease of description along construction direction All Pn bridges pieces have been set up between+Bridge 1 pier stud 14 and have formed Pn section bridge floors 10, have then been carried out using above-mentioned Bridge Erector Following steps:
A:The Pn+3 pier columns of side are first set up, then set up the Pn+3 pier columns of opposite side;
B:During Pn+3 pier columns grouting etc. is strong, the Pn between installation Pn+1 pier columns 14 and Pn+2 pier columns 15 + Bridge 1 beam piece;
C:Set up in all Pn+1 bridges pieces and complete to be after formation Pn+1 saves bridge floor 16, between two Pn+3 pier columns Set up Pn+3 bent caps;
D:After reaching requirement Deng Pn+3 bent cap filling intensities, Bridge Erector via, the construction of Pn+4 pier columns is carried out;
E:Repeat step A to D, until final section bridge piece is installed.
After the completion of step E, step F can also be carried out:Carry out opposite direction construction.
As shown in Fig. 2 the step A specifically comprises the following steps:
A1:The station of preceding auxiliary leg 8 of Bridge Erector is on the bracket by Pn+3 bridge pier bases, and front leg strut station 7 is in Pn+2 pier columns On 15 on the track of Pn+2 bent caps 16, rear support leg 6 and support supporting leg 5 are stood on Pn section bridge floors 10;
A2:Front and rear two beam cars 9,12 feed Pn+3 pier columns 11 from Bridge Erector rear end;
A3:Preceding lifting dolly 2 lifts the front end of Pn+3 pier columns 11, and then beam car 9 moves ahead together, beam car 9 after During close to preceding beam car 12, the rear rear end lifted by crane dolly 1 and lift Pn+3 pier columns 11 is preceding to lift by crane dolly 2 and rear lifting dolly 1 Pn+3 pier columns 11 are transported into Pn+3 pier column installation site correct positions;
A4:Preceding lifting dolly 2 remains stationary as, and rear lifting dolly 1 is progressively close to preceding lifting dolly 2 and while lower section Pn+3 bridge piers The rear end of post 11, until Pn+3 pier columns 11 are in vertical state;
A5:Lifting dolly 1 departs from Pn+3 pier columns 11 afterwards, and preceding lifting dolly 2 independently lifts Pn+3 pier columns 11 and will It is arranged on corresponding position, completes the construction of side Pn+3 pier columns 11;
A6:Transverse shifting Bridge Erector, repeat step A1 to A5 complete the construction of opposite side Pn+3 pier columns 11.
As shown in figure 3, the step B comprises the following steps:
B1:Preceding lifting dolly 2 and rear lifting dolly 1 take Pn+1 bridge pieces from beam car, and are transported to Pn+1 bridge piers Between post 14 and Pn+2 pier columns 15, erection installation is carried out;
B2:Transverse shifting Bridge Erector, repeat step B1 form Pn+ until all Pn+1 bridges pieces are set up into installation 1 section bridge floor 17.
Such as Fig. 4, shown in Fig. 5, the step C comprises the following steps:
C1:The region that lifting dolly 2 can lift by crane before Pn+3 bent caps 18 are transported to by beam car from the bridge floor of Bridge Erector rear end;
C2:Between slinging Pn+3 bent caps 18 using preceding lifting dolly 2 and be transported to two Pn+3 pier columns, then rotate Pn+3 bent caps 18, by it across on two Pn+3 pier columns 11.
Such as Fig. 6, step D comprises the following steps described in Fig. 7:
D1:Bridge Erector is traversing to wire center, the preceding station of auxiliary leg 8 on the bracket of Pn+3 bridge pier bases, preceding auxiliary leg 8, Front leg strut 7 and support supporting leg 5 support horn 3, and the Pn+1 that rear support leg 6 is hoisted to the rear of front leg strut 7 with preceding lifting dolly 2 is saved On bridge floor 16 and horn 3 is supported, then front leg strut 7 is hoisted on the track of Pn+3 bent caps using preceding lifting dolly 2;
D2:Preceding dolly and the rear lifting dolly of lifting by crane is stepped back to the top of rear support leg 6, preceding auxiliary leg 8 is packed up and rises the machine of supporting leg 4 Arm one segment distance of advance, when rising supporting leg 4 close to support supporting leg 5, horn halts, and rises supporting leg 4 and support horn 3, Support supporting leg 5 is hoisted to the rear of rear support leg 6 by lifting dolly 1 afterwards;
D3:Preceding dolly 2 and the rear lifting dolly 1 of lifting by crane runs to the top of rear support leg 6, packs up preceding auxiliary leg 8 and rises supporting leg 4, Machine, 3, which move on auxiliary leg 8 before a segment distance progressively causes, reaches on the bracket of Pn+4 bridge pier bases, at the same time preceding Hang dolly 2 and the 1 synchronous retrogressing of rear lifting dolly is maintained at the top of rear support leg.
Such as Fig. 8, shown in Fig. 9, the step F comprises the following steps:
F1:The strut 22 that will draw money on credit disassembles from connecting rod 20 and bottom supporting leg 21, is then removably mounted at bottom supporting leg 21 Transition supporting leg is formed in connecting rod 20, transition supporting leg station is on minor details bridge floor or station is on the ground being connected with minor details bridge floor;
F2:Front leg strut 7, rear support leg 6 are transported forward using preceding lifting dolly 2 and rear lifting dolly 1;
F3:Transition supporting leg is exchanged into position installation with supporting leg 4 is risen using preceding lifting dolly 2 and rear lifting dolly 1;
F4:Front leg strut 7 is arranged on by support supporting leg 5 using preceding lifting dolly 2 and rear lifting dolly 1;
F5:Support supporting leg 5 is arranged on to the front of rear support leg 6 using preceding lifting dolly 2 and rear lifting dolly 1;
F6:Preceding lifting dolly 2 and rear lifting dolly 1 are exchanged into installation by crane;
F7:Bottom supporting leg 21 is disassembled from connecting rod 20, by the upper and lower side for strut 22 of drawing money on credit respectively with connecting rod 20, bottom branch Auxiliary leg before the connection composition of leg 21;
F8:Electric hydraulic connection is adjusted, so as to possess the Summarized Account of Bridge Erection Construction of opposite direction.
The present invention has following beneficial effect compared with prior art:
(1)This construction method can not only complete the erection installation in whole hole, can also complete before precast pier post, bent cap across " one-stop " erection and installation, it is a kind of economy, efficiently form of construction work;
(2)This construction method when carrying out via step, without on bridge floor lay vertical shift rail, by it is preceding lifting dolly, after Lifting dolly, front leg strut, rear support leg, support supporting leg and rise the can of working in coordination of supporting leg and realize self-service via, carry significantly High efficiency of construction, shortens the engineering time;
(3)Simultaneously in via, the preceding lifting dolly and rear lifting dolly that are carried using Bridge Erector carry out Unwinding fortune, safety coefficient Height, greatly reduce the generation of accident;
(4)This construction method only needs in general crane to coordinate itself preceding again under conditions of no large tonnage crane auxiliary Hang dolly, afterwards lift by crane dolly, front leg strut, rear support leg, support supporting leg and rise supporting leg can be in less construction site rapidly Complete the action adjustment of opposite direction construction;
(5)This construction method full bridge structure, for example, pier column, bent cap, bridge piece etc. be factory shift to an earlier date it is prefabricated form, only need Transport to scene and carry out erection installation;Reduce requirement of the construction to site environment, production efficiency is high, and prefabricated production Quality is controlled, and the quality of bridge is high, integrated engineering low cost;
(6)This construction method is highly suitable for surrounding city, and execution conditions are complicated, the big place progress of construction environment traffic pressure The fast erecting of the aerial part overpass such as urban road, urban light rail and subway line;It will promote that highway in China is overhead, city City's light rail, the construction of subway elevated bridge develop to greenization, batch production, standardized construction direction, and its economical, societal benefits is by day It is beneficial notable.
Finally it should be noted that:The above embodiments are merely illustrative of the technical solutions of the present invention, rather than its limitations;Although The present invention is described in detail with reference to the foregoing embodiments, it will be understood by those within the art that:It still may be used To be modified to the technical scheme described in foregoing embodiments, or equivalent substitution is carried out to which part technical characteristic, But these modification or replace, do not make appropriate technical solution essence depart from various embodiments of the present invention technical scheme spirit and Scope.

Claims (10)

1. a kind of Bridge Erector for being used to set up full precast beam, including the horn along the equal symmetric design of vertical and horizontal, affiliated horn For double box-beam structures, it is characterised in that auxiliary leg before being provided with the front end of horn, be provided with the rear end of horn and rise branch Leg, support supporting leg can be furnished with along the front leg strut and rear support leg longitudinally walked in the rear side of rear support leg by being provided with the middle part of horn, its In, front leg strut, rear support leg, support supporting leg and rise supporting leg and be used to horn being supported on pier column or bridge piece, preceding auxiliary branch Leg be used for by horn front support in abutment on the ground, equipped with preceding lifting dolly and rear lifting dolly, preceding lifting dolly on horn Each independent lifting mechanism, walking mechanism and transverse-moving mechanism are equipped with rear lifting dolly, at the bottom of front leg strut and rear support leg Portion is equipped with traversing roller, is furnished with the cross moving track for being used for roller and laterally walking in the bottom of front leg strut and rear support leg;Preceding auxiliary Help supporting leg, front leg strut, rear support leg, support supporting leg and rise respective lifting body is equipped with supporting leg.
2. the Bridge Erector according to claim 1 for being used to set up full precast beam, it is characterised in that the preceding auxiliary leg is certainly It is upper and under include connecting rod, draw money on credit strut and bottom supporting leg successively, connecting rod is detachably connected on the front end of horn, under connecting rod Hold and the draw money on credit top of strut is detachably connected, and lower end and the bottom supporting leg of strut of drawing money on credit are detachably connected, and lifting body is arranged on On the supporting leg of bottom;Lifting dolly is provided with rotating mechanism before described, and the lifting mechanism of lifting dolly is in water before the rotating mechanism drives Rotation with surface.
3. according to claim 1 or 2 be used to set up the Bridge Erector of full precast beam, it is characterised in that the front leg strut, after Supporting leg, support supporting leg and rise supporting leg be equipped with respective left column, right column so as to from middle transport bridge beam piece, pier column or Bent cap.
4. a kind of Bridge Erector using as described in any one of claims 1 to 3 carries out the construction method of full precast bridge, its feature It is, is set along construction direction and all Pn bridges pieces have been set up between Pn pier columns and Pn+1 pier columns form Pn saves bridge floor, then carries out following steps using Bridge Erector:
A:The Pn+3 pier columns of side are first set up, then set up the Pn+3 pier columns of opposite side;
B:During Pn+3 pier columns grouting etc. is strong, the Pn+1 bridges between Pn+1 pier columns and Pn+2 pier columns are installed Beam piece;
C:Set up in all Pn+1 bridges pieces and complete to be after formation Pn+1 saves bridge floor, in a structure of an essay for two Pn+3 pier columns If Pn+3 bent caps;
D:After reaching requirement Deng Pn+3 bent cap filling intensities, Bridge Erector via, to carry out the construction of Pn+4 pier columns;
E:Repeat step A to D, until final section bridge piece is installed.
5. the construction method of full precast bridge according to claim 4, it is characterised in that the step A includes following step Suddenly:
A1:The preceding auxiliary leg station of Bridge Erector is on the bracket by Pn+3 bridge pier bases, and front leg strut station is on Pn+2 pier columns On the track of Pn+2 bent caps, rear support leg and support supporting leg are stood on Pn section bridge floors;
A2:Front and rear two beam cars feed Pn+3 pier columns from Bridge Erector rear end;
A3:Preceding lifting dolly lifts the front end of Pn+3 pier columns, and then beam car moves ahead together, and beam car is before after During beam car, the rear rear end lifted by crane dolly and lift Pn+3 pier columns, preceding dolly and the rear lifting dolly of lifting by crane is by Pn+3 bridge piers Post transports to Pn+3 pier column installation site correct positions;
A4:Preceding lifting dolly remains stationary as, and rear lifting dolly is progressively close to preceding lifting dolly and while lower section Pn+3 pier columns Rear end, until Pn+3 pier columns are in vertical state;
A5:Dolly is lifted by crane afterwards and Pn+3 pier columns depart from, and preceding lifting dolly independently lifts Pn+3 pier columns and installed In corresponding position, the construction of side Pn+3 pier columns is completed;
A6:Transverse shifting Bridge Erector, repeat step A1 to A5 complete the construction of opposite side Pn+3 pier columns.
6. the construction method of full precast bridge according to claim 5, it is characterised in that the step B includes following step Suddenly:
B1:Preceding lifting dolly and rear lifting dolly take Pn+1 bridge pieces from beam car, and are transported to Pn+1 pier columns Between Pn+2 pier columns, erection installation is carried out;
B2:Transverse shifting Bridge Erector, repeat step B1 form Pn+1 until all Pn+1 bridges pieces are set up into installation Save bridge floor.
7. the construction method of full precast bridge according to claim 6, it is characterised in that the step C includes following step Suddenly:
C1:The region that lifting dolly can lift by crane before Pn+3 bent caps are transported to by beam car from the bridge floor of Bridge Erector rear end;
C2:Between slinging Pn+3 bent caps using preceding lifting dolly and be transported to Pn+3 pier columns, Pn+3 is then rotated Bent cap, by it across on two Pn+3 pier columns.
8. the construction method of full precast bridge according to claim 7, it is characterised in that the step D includes following step Suddenly:
D1:Bridge Erector is traversing to wire center, and preceding auxiliary leg station is preceding auxiliary leg, preceding on the bracket of Pn+3 bridge pier bases Supporting leg and support supporting leg support horn, rear support leg is hoisted on the Pn+1 section bridge floors at front leg strut rear simultaneously with preceding lifting dolly Horn is supported, then front leg strut is hoisted on the track of Pn+3 bent caps using preceding lifting dolly;
D2:Preceding dolly and the rear lifting dolly of lifting by crane is stepped back to above rear support leg, preceding auxiliary leg is packed up and rises supporting leg horn Advance a segment distance, and when rising supporting leg close to support supporting leg, horn halts, and rises supporting leg support horn, rear lifting Support supporting leg is hoisted to the rear of rear support leg by dolly;
D3:Above preceding lifting dolly and rear lifting carriage walking to rear support leg, before packing up auxiliary leg and rise supporting leg horn after Auxiliary leg is reached on the bracket of Pn+4 bridge pier bases before the continuous segment distance that advances progressively causes, at the same time preceding lifting dolly and Dolly is lifted by crane afterwards synchronously retreats the top for being maintained at rear support leg.
9. the construction method of the full precast bridge according to right wants 8, it is characterised in that the preceding auxiliary leg is from top to bottom Include connecting rod, draw money on credit strut and bottom supporting leg successively, connecting rod is detachably connected on the front end of horn, the lower end of connecting rod and length The top of support bar is detachably connected, and lower end and the bottom supporting leg of strut of drawing money on credit are detachably connected, and lifting body is arranged on bottom supporting leg On.
10. the construction method of the full precast bridge according to right wants 9, it is characterised in that can also be carried out after step E Step F, the step F comprise the following steps:
F1:The strut that will draw money on credit is disassembled from connecting rod and bottom supporting leg, and then bottom supporting leg is removably mounted in connecting rod Transition supporting leg is formed, transition supporting leg station is on minor details bridge floor or station is on the ground being connected with minor details bridge floor;
F2:Front leg strut, rear support leg are transported forward using preceding lifting dolly and rear lifting dolly;
F3:Transition supporting leg is exchanged into position installation with supporting leg is risen using preceding lifting dolly and rear lifting dolly;
F4:Front leg strut is arranged on by support supporting leg using preceding lifting dolly and rear lifting dolly;
F5:Support supporting leg is arranged on to the front of rear support leg using preceding lifting dolly and rear lifting dolly;
F6:Preceding lifting dolly and rear lifting dolly are exchanged into installation by crane;
F7:Bottom supporting leg is disassembled from connecting rod, the upper and lower side for strut of drawing money on credit is connected group with connecting rod, bottom supporting leg respectively Into preceding auxiliary leg;
F8:Electric hydraulic connection is adjusted, so as to possess the Summarized Account of Bridge Erection Construction of opposite direction.
CN201710858907.5A 2017-09-21 2017-09-21 Bridge girder erection machine for erecting full precast girder and bridge girder erection method thereof Active CN107558378B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710858907.5A CN107558378B (en) 2017-09-21 2017-09-21 Bridge girder erection machine for erecting full precast girder and bridge girder erection method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710858907.5A CN107558378B (en) 2017-09-21 2017-09-21 Bridge girder erection machine for erecting full precast girder and bridge girder erection method thereof

Publications (2)

Publication Number Publication Date
CN107558378A true CN107558378A (en) 2018-01-09
CN107558378B CN107558378B (en) 2023-06-23

Family

ID=60982435

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710858907.5A Active CN107558378B (en) 2017-09-21 2017-09-21 Bridge girder erection machine for erecting full precast girder and bridge girder erection method thereof

Country Status (1)

Country Link
CN (1) CN107558378B (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109024291A (en) * 2018-08-06 2018-12-18 江苏恩纳斯重工机械有限公司 A kind of integration Bridge Erector and its working method
CN110093863A (en) * 2019-05-31 2019-08-06 浙江省交通规划设计研究院有限公司 A kind of double face integration Bridge Erector being not provided with front leg strut
CN110748163A (en) * 2019-11-15 2020-02-04 河南省中冶起重机有限公司 Novel bridge girder erection machine
CN113373814A (en) * 2021-06-11 2021-09-10 中铁工程机械研究设计院有限公司 Highway bridge erecting method
CN114250711A (en) * 2021-12-31 2022-03-29 史托克(天津)工程技术有限公司 Highway bridge girder erection machine and hole passing method
CN114438901A (en) * 2022-03-22 2022-05-06 四川发展磁浮科技有限公司 Construction method for built-in magnetic suspension elevated line bridge girder erection machine
CN114808736A (en) * 2022-05-20 2022-07-29 中昕重工(宁波)有限公司 Bridge prefabricated part cross-inside transverse flat-turning hoisting device and hoisting process method

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11222819A (en) * 1998-02-10 1999-08-17 Kajima Corp Execution method of elevated structure using building girder
CN101144259A (en) * 2007-09-20 2008-03-19 中铁二局股份有限公司 Large tonnage whole opening box girder transmitting and construction method
US20130055512A1 (en) * 2010-05-19 2013-03-07 Beijing Wowjoint Machinery Co Transportation and erection integrated machine with displacement platforms and methods for erecting bridge using the same
CN202899044U (en) * 2012-07-26 2013-04-24 中铁六局集团有限公司 Vierendeel box-shaped double-girder bridge crane
CN104831630A (en) * 2014-10-22 2015-08-12 中铁十一局集团第六工程有限公司 Light small-curve segment assembling and bridging machine
CN105735142A (en) * 2016-05-06 2016-07-06 郑州新大方重工科技有限公司 Bridge girder erection machine for prestressed concrete bridge precast section span-by-span splicing construction
CN207775719U (en) * 2017-09-21 2018-08-28 郑州新大方重工科技有限公司 A kind of Bridge Erector for setting up full precast beam

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11222819A (en) * 1998-02-10 1999-08-17 Kajima Corp Execution method of elevated structure using building girder
CN101144259A (en) * 2007-09-20 2008-03-19 中铁二局股份有限公司 Large tonnage whole opening box girder transmitting and construction method
US20130055512A1 (en) * 2010-05-19 2013-03-07 Beijing Wowjoint Machinery Co Transportation and erection integrated machine with displacement platforms and methods for erecting bridge using the same
CN202899044U (en) * 2012-07-26 2013-04-24 中铁六局集团有限公司 Vierendeel box-shaped double-girder bridge crane
CN104831630A (en) * 2014-10-22 2015-08-12 中铁十一局集团第六工程有限公司 Light small-curve segment assembling and bridging machine
CN105735142A (en) * 2016-05-06 2016-07-06 郑州新大方重工科技有限公司 Bridge girder erection machine for prestressed concrete bridge precast section span-by-span splicing construction
CN207775719U (en) * 2017-09-21 2018-08-28 郑州新大方重工科技有限公司 A kind of Bridge Erector for setting up full precast beam

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109024291A (en) * 2018-08-06 2018-12-18 江苏恩纳斯重工机械有限公司 A kind of integration Bridge Erector and its working method
CN110093863A (en) * 2019-05-31 2019-08-06 浙江省交通规划设计研究院有限公司 A kind of double face integration Bridge Erector being not provided with front leg strut
CN110748163A (en) * 2019-11-15 2020-02-04 河南省中冶起重机有限公司 Novel bridge girder erection machine
CN113373814A (en) * 2021-06-11 2021-09-10 中铁工程机械研究设计院有限公司 Highway bridge erecting method
CN114250711A (en) * 2021-12-31 2022-03-29 史托克(天津)工程技术有限公司 Highway bridge girder erection machine and hole passing method
CN114250711B (en) * 2021-12-31 2024-06-04 史托克(天津)工程技术有限公司 Highway bridge girder erection machine and hole passing method
CN114438901A (en) * 2022-03-22 2022-05-06 四川发展磁浮科技有限公司 Construction method for built-in magnetic suspension elevated line bridge girder erection machine
CN114808736A (en) * 2022-05-20 2022-07-29 中昕重工(宁波)有限公司 Bridge prefabricated part cross-inside transverse flat-turning hoisting device and hoisting process method
CN114808736B (en) * 2022-05-20 2024-04-12 中昕重工(宁波)有限公司 Bridge prefabricated part inner-span transverse horizontal rotation hoisting device and hoisting process method

Also Published As

Publication number Publication date
CN107558378B (en) 2023-06-23

Similar Documents

Publication Publication Date Title
CN107558378A (en) A kind of Bridge Erector and its bridging method for being used to set up full precast beam
CN107740350B (en) The bridge pier column construction method and its passing method of full precast bridge Bridge Erector
CN102373671B (en) Steel trussed beam and flexible arch bridge construction method with vault pushing
CN101230785B (en) Construction method for large section and multiple sections tunnel lining
CN104499433B (en) One wears high ferro low clearance erecting beam construction method under acutangulating intersection
CN104594918B (en) Split integrated underground passage steel mold plate trolley and construction method thereof
CN100547225C (en) A kind of tunnel overhead arch mould plate trolley with floating type traffic under carriage
CN108677742B (en) Movable cantilever bridge girder erection machine for full-prefabricated bridge pier, bearing platform and girder body assembled construction
CN107460830A (en) The full precast bridge of Mid and minor spans is without sidewalk scheme of architecture
CN102979038A (en) Cast-in-place box beam mobile bracket with increased width
CN102134832A (en) Movable support and movable support assisted method for erecting steel box beams through non-variable amplitude frame beam crane
CN101324054B (en) Incremental launching positioning construction method of bridge subsection girder temporary pier
CN210561749U (en) Multi-frame juxtaposed double-cantilever bridge girder erection machine
CN201943004U (en) Double-girder transporting and erecting integrated bridge girder erecting machine capable of realizing girder erecting at zero distance from tunnel portal
CN207775719U (en) A kind of Bridge Erector for setting up full precast beam
CN110158486B (en) Bridge girder erection machine for erecting spliced wide beams and construction method
CN114808747A (en) Multifunctional bridge girder erection machine and bridge girder erection construction method
CN203248170U (en) Lining trolley for secondary lining construction of pedestrian crosswalk
CN110205948A (en) A kind of expanded letter Bridge Erector and its erection method
CN104110002A (en) Method for replacing bridge deck slabs of steel truss girder bridge
CN206035507U (en) Rectangle box culvert and for tunnel construction platform truck
CN202989781U (en) Width widened cast-in-place box beam moving support
CN110924310A (en) Adjustable movable lifting device on girder transporting bridge and opposite-pulling portal tunnel crossing construction method
CN111945572B (en) Multi-connected arch bridge erecting machine and multi-connected arch bridge erecting method
CN212925808U (en) Vertical and longitudinal connecting device for bridge erecting machine

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant