CN107516870A CN201710948475.7A CN201710948475A CN107516870A CN 107516870 A CN107516870 A CN 107516870A CN 201710948475 A CN201710948475 A CN 201710948475A CN 107516870 A CN107516870 A CN 107516870A
Authority
CN
China
Prior art keywords
cable
mrow
short circuit
circuit current
automatic reclosing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710948475.7A
Other languages
Chinese (zh)
Other versions
CN107516870B (en
Inventor
刘健
赵艾萱
徐龙
张志华
赵学风
陈曦
李嘉明
邓军波
张冠军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Xian Jiaotong University
Electric Power Research Institute of State Grid Shaanxi Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
Xian Jiaotong University
Electric Power Research Institute of State Grid Shaanxi Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Xian Jiaotong University, Electric Power Research Institute of State Grid Shaanxi Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201710948475.7A priority Critical patent/CN107516870B/en
Publication of CN107516870A publication Critical patent/CN107516870A/en
Application granted granted Critical
Publication of CN107516870B publication Critical patent/CN107516870B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02HEMERGENCY PROTECTIVE CIRCUIT ARRANGEMENTS
    • H02H3/00Emergency protective circuit arrangements for automatic disconnection directly responsive to an undesired change from normal electric working condition with or without subsequent reconnection ; integrated protection
    • H02H3/02Details
    • H02H3/06Details with automatic reconnection
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02HEMERGENCY PROTECTIVE CIRCUIT ARRANGEMENTS
    • H02H3/00Emergency protective circuit arrangements for automatic disconnection directly responsive to an undesired change from normal electric working condition with or without subsequent reconnection ; integrated protection
    • H02H3/08Emergency protective circuit arrangements for automatic disconnection directly responsive to an undesired change from normal electric working condition with or without subsequent reconnection ; integrated protection responsive to excess current
    • H02H3/085Emergency protective circuit arrangements for automatic disconnection directly responsive to an undesired change from normal electric working condition with or without subsequent reconnection ; integrated protection responsive to excess current making use of a thermal sensor, e.g. thermistor, heated by the excess current

Landscapes

  • Laying Of Electric Cables Or Lines Outside (AREA)

Abstract

The present invention provides a kind of cable run automatic reclosing method based on short circuit current heat localization process, including:Obtain cable laying type, the operation time limit and ambient parameter;The geometrical structure parameter of cable is measured, reads the resistance parameter of the corresponding thermal capacitance of cable above layers, thermal resistance and metal part, wherein ambient parameter, thermal capacitance, thermal resistance and resistance parameter are as calculating parameter;According to the calculating parameter and the geometrical structure parameter of cable, establish the mathematical modeling of cable dynamic heat localization process under short circuit current effect, and automatic reclosing strategy is formulated according to the temperature change during the heat localization of gained cable and laying type, the operation time limit, include the delay time and number of automatic reclosing.Pin of the present invention has filled up the blank of existing cable automatic reclosing strategy application, can formulate automatic reclosing strategy according to the running status of different cables, greatly reduce the workload and power off time of artificial reclosing, improve the reliability of power supply conscientiously.

Description

A kind of cable run automatic reclosing method based on short circuit current heat localization process
Technical field
The present invention relates to high voltage and insulation technology field, and in particular to a kind of cable run automatic reclosing method.
Background technology
With Process of Urbanization Construction continuous quickening and to power supply reliability requirement raising, overhead transmission line change cable into For a kind of inevitable trend.For a long time, automatic reclosing technology is widely used in overhead transmission line, is effectively improved power supply Reliability, but whether automatic reclosing is used containing cable run for power distribution network, unified understanding is not yet formed at present.State's household electrical appliances Regulation cable run does not use automatic reclosing in net company current design criteria, mainly considers that cable run occurs in running Failure be generally permanent fault, reclosing operation will bring serious short-circuit impact and switching overvoltage, to cable and change The equipment belts such as depressor damage, and accident is further expanded.But from the point of view of operation department distribution line failure analysis result, full electricity The transient fault on cable road still occupies certain proportion, can if can effectively improve power supply to pure cable run input automatic reclosing By property.
However, reclosing is blindly carried out to the cable in different conditions, it is possible to cause cable on fire, blast serious Consequence, can not only give full play to automatic reclosing improve power supply reliability effect, also exist failure propagation, harm the person and The hidden danger of equipment safety.Therefore, it is badly in need of the actual conditions according to each cable run and reclosing is decided whether by scientific method.
The content of the invention
It is an object of the invention to provide a kind of cable run automatic reclosing side based on short circuit current heat localization process Method, to solve above-mentioned technical problem.The present invention only needs existing current monitoring system collection cable that short circuit occurs due to its input quantity The electric current of fault moment, therefore the hardware requirement applied is relatively low, it is easy to spread.The present invention can be based on existing current monitoring system Cable status can be scored with account information, to determine reclosing number and delay time.The present invention can be carried effectively The power supply reliability of high cable run, low-impedance earthed system is particularly switched to by high resistance ground in distribution network systems neutral grounding mode There is extremely important theory and practice to be worth under overall background.
To achieve these goals, the present invention adopts the following technical scheme that:
A kind of cable run automatic reclosing method based on short circuit current heat localization process, comprises the following steps:
Step 1: monitoring obtains ambient parameter corresponding to respective cable line cord laying type, including:Heat convection system Number а, soil near-bottom temperature Tsoil, soil thermal resistivity ρ and air real time temperature Tamb
Step 2: reading the geometric parameter of the construction of cable, and the corresponding thermal capacitance of each layer of cable, heat are solved according to geometric parameter Resistance and the resistance parameter of metal part;
Step 3: the limited element calculation model of short circuit current heat localization process is established, and according to the mode meter of iterative numerical Calculate cable temperature T (x, y, t) and time t under short circuit current effect variation relation;
Step 4: after obtaining temperature T (x, y, t) of each region of cable under short circuit current effect, by reading cable area Domain maximum temperature TmaxConfigure the automatic reclosing strategy of cable run.
Further, the geometric parameter of the construction of cable includes:Conductor diameter D1, conductor shielding thickness δ1, insulation thickness t1、 Insulation shielding thickness ti2, metallic shield thickness ts, sheath thickness t2, its thickness δ and outer jacket thickness t3
Further, the step 3 is specially:
Each layer thermal capacitance of cable, the thermal resistance calculated according to step 2, thermal conductivity factor D is calculated, and utilizes thermal capacitance storage energy Make every effort to solve thermal diffusivity K;Meanwhile according to short circuit current IFThe endogenous pyrogen heating of each core is tried to achieve with cable core resistance parameter Rate
qv=IF 2R/S0 (1)
Wherein, S0For cable core region area;R is the D.C. resistance of cable;
Cable domain S is established according to the geometrical structure parameter of each Rotating fields, where it on cable domain S a bit Coordinate x, y must conduct heat formula, as shown in formula (2):
Wherein T represents the temperature of cable core, and D is each region thermal conductivity factor, and K is each region thermal diffusivity, qvFor interior heat Source heat generation rate;
According to boundary condition of the ambient parameter that step 1 obtains as formula (2) domain S, in this, as basis to it Variation is carried out, is obtained shown in functional I such as formulas (3):
Wherein, L is region S border;
Functional I is divided into limited individual unit in the S of region, and by its discretization, obtains formula (4):
Wherein,For stiffness matrix,For heat source density matrix, NE is unit number, and the final extreme value for solving functional I is asked Obtain temperature T (x, y, t) and time t of each region of cable under short circuit current effect variation relation.
Further, according to temperature T (x, y, t) and the time t under short circuit current effect tried to achieve variation relation Scoring, system of laying scoring, run the time limit scoring, with reference to three's respective weights coefficient carry out calculate obtain overall score, Reclosing delay time and number are determined according to overall score.
Further, the ratio between weight coefficient corresponding to three is 40%:40%:20%.
Further, the variation relation of temperature T (x, y, t) and the time t under short circuit current effect, using desired Temperature T (x, y, t) and according to obtained temperature maximum T when delay time t solves the corresponding momentmaxThe corresponding scoring of inquiry:
TmaxTemperature range Scoring
(- ∞, 90 DEG C) 100
[90 DEG C, 135 DEG C) 80
[135 DEG C, 250 DEG C) 60
[250 DEG C ,+∞) 0
Further, scored accordingly according to different laying way of local type queries:
Further, according to the different corresponding scorings of operation time limit inquiry:
Run the time limit Scoring
Less than 5 years 100
More than 5 years, less than 15 years 80
More than 15 years, less than 25 years 60
More than 25 years 0
Further, delay time is voluntarily formulated according to relaying configuration strategy, and reclosing number, which is formulated, to be included:
Overall score Reclosing number
[90,100] 2
[80,90) 1
[0,80) Forbid to configure automatic reclosing
Relative to prior art, the invention has the advantages that:
The present invention gathers electric current when short trouble occurs for cable run by monitoring system, not only avoid additional monitoring Equipment belt comes cost and potential safety hazard, but also can effectively avoid traditional on-line monitoring from gathering weak current by outside The problem of interference.In the case where distribution network systems neutral grounding mode is changed to the overall background of low-impedance earthed system by high resistance ground, cable tripping operation Probability certainly will be greatly improved, and a line maintenance work efficiency and power supply reliability can be effectively improved using the present invention, existing each Do not related in class reclosing configuration strategy.
Brief description of the drawings
Fig. 1 is the schematic flow sheet of the configuration reclosing method of the invention based on short circuit current heat localization process;
Embodiment
Below in conjunction with the accompanying drawing in the present invention, the technical scheme in the present invention is clearly and completely described.
Reference picture 1, a kind of cable run automatic reclosing side based on short circuit current heat localization process of offer of the invention Method, comprise the following steps:
Step 1: monitoring obtains ambient parameter corresponding to respective cable laying type, including:Convection transfer rate а, soil Near-bottom temperature Tsoil, soil thermal resistivity ρ, air real time temperature Tamb
Step 2: read the geometric parameter of the construction of cable, and according to geometric parameter solve the corresponding thermal capacitance of each layer, thermal resistance with And the resistance parameter of metal part;
Step 3: the limited element calculation model of short circuit current heat localization process is established according to above-mentioned parameter, and according to numerical value The mode of iteration calculates cable temperature T (x, y, t) and time t under short circuit current effect variation relation;
Step 4: after temperature T (x, y, t) of each region of cable under short circuit current effect is obtained, by reading cable Region maximum temperature TmaxConfigure the automatic reclosing strategy of cable run.
In step 2, the geometric parameter of the construction of cable includes conductor diameter D1, conductor shielding thickness δ1, insulation thickness t1, absolutely Edge shielding thickness ti2, metallic shield thickness ts, sheath thickness t2, its thickness δ, outer jacket thickness t3
The step 3 is specially:
Each layer thermal capacitance of cable, the thermal resistance calculated according to step 2, thermal conductivity factor D is calculated, and utilizes thermal capacitance storage energy Make every effort to solve thermal diffusivity K.Meanwhile according to short circuit current IFThe endogenous pyrogen heating of each core is tried to achieve with cable core resistance parameter Rate
qv=IF 2R/S0 (1)
Wherein, S0For cable core region area;R is the D.C. resistance of cable.
Cable domain S is established according to the geometrical structure parameter of each Rotating fields, where it on cable domain S a bit Coordinate x, y must can conduct heat formula, as shown in formula (2):
Wherein T represents the temperature of cable core, and D is each region thermal conductivity factor, and K is each region thermal diffusivity, qvFor interior heat Source heat generation rate;
According to boundary condition of the ambient parameter that step 1 obtains as formula (2) domain S, in this, as basis to it Variation is carried out, is obtained shown in functional I such as formulas (3):
Wherein, L is region S border;
Functional I is divided into limited individual unit in the S of region, and by its discretization, obtains formula (4):
Wherein,For stiffness matrix,For heat source density matrix, NE is unit number, and final solution functional I extreme value is Temperature T (x, y, t) and time t of each region of cable under short circuit current effect variation relation can be tried to achieve.
Hereafter, according to the variation relation for being tried to achieve temperature T (x, y, t) and the time t under short circuit current effect and System of laying, the weight coefficient of the operation time limit are calculated, and determine that reclosing delay time and the ratio between number, the weight of three are 40%:40%:20%.
Specifically, the variation relation of temperature T (x, y, t) and the time t under short circuit current effect, is prolonged using desired When time t temperature T (x, y, t) and according to obtained temperature maximum T when solving the corresponding momentmaxThe corresponding scoring of inquiry.Its In, scoring includes:
Foregoing system of laying, scored accordingly according to different laying way of local type queries, including:
Lay type Scoring
Direct-burried/aerial 100
Comb 80
Groove 60
Tunnel 0
The foregoing operation time limit, according to the different corresponding scorings of operation time limit inquiry, including:
Run the time limit Scoring
Less than 5 years 100
More than 5 years, less than 15 years 80
More than 15 years, less than 25 years 60
More than 25 years 0
Foregoing reclosing delay time and number:Delay time is voluntarily formulated according to relaying configuration strategy, is overlapped Lock number, which is formulated, to be included:
Overall score Reclosing number
[90,100] 2
[80,90) 1
[0,80) Forbid to configure automatic reclosing
Corresponding weight is multiplied by the scoring of three, is then added and is obtained final scoring, and scoring is more than or equal to 90, overlaps Lock number is 2;Less than 90 and more than or equal to 80, reclosing number is 1;Less than 80, forbid to configure automatic reclosing.
The foregoing is only a specific embodiment of the invention, but protection scope of the present invention is not limited thereto, any Belong to those skilled in the art the invention discloses technical scope in, the change or replacement that can readily occur in, all should It is included within the scope of the present invention.Therefore, protection scope of the present invention should be defined by scope of the claims.

Claims (9)

  1. A kind of 1. cable run automatic reclosing method based on short circuit current heat localization process, it is characterised in that including as follows Step:
    Step 1: monitoring obtains ambient parameter corresponding to respective cable line cord laying type, including:Convection transfer rate а, Soil near-bottom temperature Tsoil, soil thermal resistivity ρ and air real time temperature Tamb
    Step 2: read the geometric parameter of the construction of cable, and according to geometric parameter solve the corresponding thermal capacitance of each layer of cable, thermal resistance with And the resistance parameter of metal part;
    Step 3: establishing the limited element calculation model of short circuit current heat localization process, and electricity is calculated according to the mode of iterative numerical Cable temperature T (x, y, t) and time t under short circuit current effect variation relation;
    Step 4: after obtaining temperature T (x, y, t) of each region of cable under short circuit current effect, by reading cable area most High-temperature TmaxConfigure the automatic reclosing strategy of cable run.
  2. 2. a kind of cable run automatic reclosing method based on short circuit current heat localization process according to claim 1, It is characterized in that:The geometric parameter of the construction of cable includes:Conductor diameter D1, conductor shielding thickness δ1, insulation thickness t1, insulation screen Cover thickness ti2, metallic shield thickness ts, sheath thickness t2, its thickness δ and outer jacket thickness t3
  3. 3. a kind of cable run automatic reclosing method based on short circuit current heat localization process according to claim 1, It is characterized in that:The step 3 is specially:
    Each layer thermal capacitance of cable, the thermal resistance calculated according to step 2, is calculated thermal conductivity factor D, and ask using thermal capacitance storage capacity Solve thermal diffusivity K;Meanwhile according to short circuit current IFThe endogenous pyrogen heat generation rate of each core is tried to achieve with cable core resistance parameter
    qv=IF 2R/S0 (1)
    Wherein, S0For cable core region area;R is the D.C. resistance of cable;
    Cable domain S is established according to the geometrical structure parameter of each Rotating fields, the seat of any on cable domain S where it X is marked, y must conduct heat formula, as shown in formula (2):
    <mrow> <mfrac> <mrow> <msup> <mo>&amp;part;</mo> <mn>2</mn> </msup> <mi>T</mi> </mrow> <mrow> <mo>&amp;part;</mo> <msup> <mi>x</mi> <mn>2</mn> </msup> </mrow> </mfrac> <mo>+</mo> <mfrac> <mrow> <msup> <mo>&amp;part;</mo> <mn>2</mn> </msup> <mi>T</mi> </mrow> <mrow> <mo>&amp;part;</mo> <msup> <mi>y</mi> <mn>2</mn> </msup> </mrow> </mfrac> <mo>+</mo> <mfrac> <msub> <mi>q</mi> <mi>v</mi> </msub> <mi>D</mi> </mfrac> <mo>=</mo> <mi>K</mi> <mfrac> <mrow> <mo>&amp;part;</mo> <mi>T</mi> </mrow> <mrow> <mo>&amp;part;</mo> <mi>t</mi> </mrow> </mfrac> <mo>-</mo> <mo>-</mo> <mo>-</mo> <mrow> <mo>(</mo> <mn>2</mn> <mo>)</mo> </mrow> </mrow>
    Wherein T represents the temperature of cable core, and D is each region thermal conductivity factor, and K is each region thermal diffusivity, qvGenerated heat for endogenous pyrogen Rate;
    According to boundary condition of the ambient parameter that step 1 obtains as formula (2) domain S, it is carried out in this, as basis Variation, obtain shown in functional I such as formulas (3):
    Wherein, L is region S border;
    Functional I is divided into limited individual unit in the S of region, and by its discretization, obtains formula (4):
    <mrow> <mi>I</mi> <mrow> <mo>(</mo> <mi>T</mi> <mo>)</mo> </mrow> <mo>=</mo> <munderover> <mo>&amp;Sigma;</mo> <mrow> <mi>e</mi> <mo>=</mo> <mn>1</mn> </mrow> <mrow> <mi>N</mi> <mi>E</mi> </mrow> </munderover> <msub> <mi>I</mi> <mi>e</mi> </msub> <mo>=</mo> <msup> <mover> <mi>T</mi> <mo>&amp;OverBar;</mo> </mover> <mi>T</mi> </msup> <mover> <mi>K</mi> <mo>&amp;OverBar;</mo> </mover> <mover> <mi>T</mi> <mo>&amp;OverBar;</mo> </mover> <mo>-</mo> <mn>2</mn> <msup> <mover> <mi>T</mi> <mo>&amp;OverBar;</mo> </mover> <mi>T</mi> </msup> <mover> <mi>P</mi> <mo>&amp;OverBar;</mo> </mover> <mo>-</mo> <mo>-</mo> <mo>-</mo> <mrow> <mo>(</mo> <mn>4</mn> <mo>)</mo> </mrow> </mrow>
    Wherein,For stiffness matrix,For heat source density matrix, NE is unit number, and the final extreme value for solving functional I tries to achieve electricity Temperature T (x, y, t) and time t of each region of cable under short circuit current effect variation relation.
  4. 4. a kind of cable run automatic reclosing method based on short circuit current heat localization process according to claim 3, It is characterized in that:According to the scoring for the variation relation for being tried to achieve temperature T (x, y, t) and the time t under short circuit current effect, The scoring of system of laying, the scoring for running the time limit, carry out calculating acquisition overall score with reference to three's respective weights coefficient, according to general comment Divide determination reclosing delay time and number.
  5. 5. a kind of cable run automatic reclosing method based on short circuit current heat localization process according to claim 4, It is characterized in that:The ratio between weight coefficient corresponding to three is 40%:40%:20%.
  6. 6. a kind of cable run automatic reclosing method based on short circuit current heat localization process according to claim 4, It is characterized in that:The variation relation of temperature T (x, y, t) and time t under short circuit current effect, during using desired delay Between t temperature T (x, y, t) and according to obtained temperature maximum T when solving the corresponding momentmaxThe corresponding scoring of inquiry:
    TmaxTemperature range Scoring (- ∞, 90 DEG C) 100 [90 DEG C, 135 DEG C) 80 [135 DEG C, 250 DEG C) 60 [250 DEG C ,+∞) 0
  7. 7. a kind of cable run automatic reclosing method based on short circuit current heat localization process according to claim 4, It is characterized in that:Scored accordingly according to different laying way of local type queries:
    Lay type Scoring Direct-burried/aerial 100 Comb 80 Groove 60 Tunnel 0
  8. 8. a kind of cable run automatic reclosing method based on short circuit current heat localization process according to claim 4, It is characterized in that:According to the different corresponding scorings of operation time limit inquiry:
    Run the time limit Scoring Less than 5 years 100 More than 5 years, less than 15 years 80 More than 15 years, less than 25 years 60 More than 25 years 0
  9. 9. a kind of cable run automatic reclosing method based on short circuit current heat localization process according to claim 4, It is characterized in that:Delay time is voluntarily formulated according to relaying configuration strategy, and reclosing number, which is formulated, to be included:
CN201710948475.7A 2017-10-12 2017-10-12 A kind of cable run automatic reclosing method based on short circuit current heat localization process Active CN107516870B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710948475.7A CN107516870B (en) 2017-10-12 2017-10-12 A kind of cable run automatic reclosing method based on short circuit current heat localization process

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710948475.7A CN107516870B (en) 2017-10-12 2017-10-12 A kind of cable run automatic reclosing method based on short circuit current heat localization process

Publications (2)

Publication Number Publication Date
CN107516870A true CN107516870A (en) 2017-12-26
CN107516870B CN107516870B (en) 2019-04-26

Family

ID=60727190

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710948475.7A Active CN107516870B (en) 2017-10-12 2017-10-12 A kind of cable run automatic reclosing method based on short circuit current heat localization process

Country Status (1)

Country Link
CN (1) CN107516870B (en)

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1780858A1 (en) * 2005-10-31 2007-05-02 ABB Technology AG Arrangement and method for protecting an electric power system
CN101789587A (en) * 2010-01-08 2010-07-28 黄震 Automatic reclosing method of A type overhead line- cable hybrid line
CN102749554A (en) * 2012-06-19 2012-10-24 张忠华 Electric power circuit fault detecting system

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1780858A1 (en) * 2005-10-31 2007-05-02 ABB Technology AG Arrangement and method for protecting an electric power system
CN101789587A (en) * 2010-01-08 2010-07-28 黄震 Automatic reclosing method of A type overhead line- cable hybrid line
CN102749554A (en) * 2012-06-19 2012-10-24 张忠华 Electric power circuit fault detecting system

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
杨军: ""高温超导电缆保护理论与技术研究"", 《中国优秀博士学位论文全文数据库》 *

Also Published As

Publication number Publication date
CN107516870B (en) 2019-04-26

Similar Documents

Publication Publication Date Title
Schneider et al. Analytic considerations and design basis for the IEEE distribution test feeders
Mokhtari et al. An improved circuit-based model of a grounding electrode by considering the current rate of rise and soil ionization factors
Pons et al. Impact of MV ground fault current distribution on global earthing systems
CN111123041B (en) Cable sheath fault positioning method based on temperature characteristic
Vita et al. The impact of distributed generation to the lightning protection of modern distribution lines
CN103412199A (en) Computing method of unbalancedness of multi-circuit power transmission lines on same tower
Li et al. Fault location algorithm in distribution networks considering distributed capacitive current
CN109167362B (en) Power distribution network load flow calculation method considering cable thermal characteristics
CN111048919A (en) Energy station grounding grid in high-soil-resistivity area and resistance reduction optimization method thereof
Cai et al. Optimal construction method and demonstration application of multi-in-one station grounding system
Bayramoğlu et al. The Development of Lightning Protection and Grounding Systems: A Survey
Li et al. Lightning transient characteristics of cable power collection system in wind power plants
CN107516870A (en) A kind of cable run automatic reclosing method based on short circuit current heat localization process
CN104021297A (en) Method for lowering step voltage
Lloyd et al. Real-time thermal rating and active control improved distribution network utilisation
CN109387742A (en) A kind of line fault recognition methods based on multiple spot active power monitoring and difference
CN104730388A (en) Method and device for evaluating influence of environment thermal resistance on three-core cable core temperature
Liang et al. Study on the calculation and suppression method of metal sheath circulating current of three-phase single-core cable
CN104698340A (en) Method for testing copper clad steel grounding grid design rationality
Hardi et al. Application Modeling of Substation Grounding Grid Design Using Matlab
CN107228994B (en) High-voltage alternating-current cable load cyclic heating method
Chen et al. Thermal grading around overhead transmission line under various environments and its influence to load capacity
CN108075380B (en) Converter station grounding grid design method capable of replacing direct current grounding electrode and grounding grid
Cao et al. New method for calculating ground resistance of grounding grids buried in horizon two-layer soil
Chen et al. A Study on the Cable Grounding Condition in Wind Turbines Under Direct Lightning

Legal Events

Date Code Title Description
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant