CN107489447A - Temporary track fixed system and its construction in a kind of tunnel - Google Patents

Temporary track fixed system and its construction in a kind of tunnel Download PDF

Info

Publication number
CN107489447A
CN107489447A CN201710655314.9A CN201710655314A CN107489447A CN 107489447 A CN107489447 A CN 107489447A CN 201710655314 A CN201710655314 A CN 201710655314A CN 107489447 A CN107489447 A CN 107489447A
Authority
CN
China
Prior art keywords
sleeper
battery truck
chassis
tunnel
track
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710655314.9A
Other languages
Chinese (zh)
Other versions
CN107489447B (en
Inventor
王成
张凯
黄胜
任彦顺
胡卫国
吕军鹏
梁东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Stecol Corp
PowerChina Railway Construction Co Ltd
Original Assignee
PowerChina Railway Construction Co Ltd
Sinohydro Tianjin Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Railway Construction Co Ltd, Sinohydro Tianjin Engineering Co Ltd filed Critical PowerChina Railway Construction Co Ltd
Priority to CN201710655314.9A priority Critical patent/CN107489447B/en
Publication of CN107489447A publication Critical patent/CN107489447A/en
Application granted granted Critical
Publication of CN107489447B publication Critical patent/CN107489447B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F13/00Transport specially adapted to underground conditions
    • E21F13/006Equipment transport systems
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/40Devices or apparatus specially adapted for handling or placing units of linings or supporting units for tunnels or galleries
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/06Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Geology (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Mechanical Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Arrangement Or Mounting Of Propulsion Units For Vehicles (AREA)
  • Body Structure For Vehicles (AREA)

Abstract

The invention discloses temporary track fixed system in a kind of tunnel, including the battery truck sleeper located at tunnel wall bottom and the chassis sleeper located at battery truck sleeper both sides, battery truck sleeper is connected with chassis sleeper, battery truck sleeper and chassis sleeper are connected with tunnel wall respectively, battery truck track is provided with above battery truck sleeper both ends, two battery truck tracks are connected with battery truck sleeper respectively, and battery truck track presses close to tunnel wall, chassis sleeper is provided with trolley track, and trolley track is connected with chassis sleeper.Present invention also offers a kind of construction of temporary track fixed system in tunnel.The present invention is calculated using the chord length of circle and determines physical dimension, battery truck track is pressed close to tunnel wall, be highly shortened the distance between battery truck track and tunnel wall, reduces the height of battery truck rail level, so that battery truck operation becomes more steady.

Description

Temporary track fixed system and its construction in a kind of tunnel
Technical field
The present invention relates to temporary track fixed system and its construction in a kind of tunnel.
Background technology
At present during shield-tunneling construction, most of arcs being combined using battery truck sleeper with bogie wheels sleeper Sleeper, as shield-tunneling construction promotes, the sleeper that will be disengaged from chassis removes left and right wheel sleeper in pairs, and place mat is before shield-tunneling construction Enter direction and make the follow-up chassis support of new shield, and remainder is then used as battery truck sleeper after removing.This type sleeper is present Following shortcoming:Single weight is big, wastes raw material, and integral reinforcing is difficult.Battery truck sleeper and chassis sleeper are using 10mm Steel plate is processed for former material, and single battery truck sleeper weight reaches 11.6kg, on the one hand made up to 30kg, bogie wheels sleeper Into the waste of former material, another aspect 30kg weight is in tunnel, it is necessary to which two people cooperate in the short environment in shield body bottom It could carry and be in place, cause the waste of personnel;Rail level is too high, causes battery truck operation unstable.After arc sleeper laying Rail level is caused to raise so that battery truck rail level lifting 114mm, rail level is unstable, easily slides down, has in battery truck running Potential safety hazard.Rail level is raised rear shield machine trolley distance from top tunnel edge distance and furthered, and easily collide friction, to construction Quality brings hidden danger.
Above deficiency, it is to be improved.
The content of the invention
In order to overcome the shortcomings of existing technology, the present invention provides temporary track fixed system in a kind of tunnel and its applied Work engineering method.
Technical solution of the present invention is as described below:
Temporary track fixed system in a kind of tunnel, including battery truck sleeper located at tunnel wall bottom and located at the battery truck The chassis sleeper of sleeper both sides, the battery truck sleeper are connected with the chassis sleeper, the battery truck sleeper and the chassis Sleeper is connected with the tunnel wall respectively, and battery truck track, two battery trucks are provided with above the battery truck sleeper both ends Track is connected with the battery truck sleeper respectively, and the battery truck track presses close to the tunnel wall, is set on the chassis sleeper There is trolley track, the trolley track is connected with the chassis sleeper.
Further, the battery truck sleeper includes the end sleeper at interlude sleeper and both ends, the end sleeper with Battery truck track neck is provided between the interlude sleeper, the battery truck track is located in the battery truck track neck, The battery truck track is connected with the battery truck sleeper.
Further, the bottom of the chassis sleeper is provided with the connector being connected with the battery truck sleeper, the connection Part is connected with the chassis sleeper, and the connector is connected with the end sleeper.
Further, the horizontal segment on the top of the chassis sleeper is provided with two fixtures, the fixture with described Track pillow connects, and is provided with trolley track neck between two fixtures, the trolley track is located at the trolley track card In groove, the trolley track is connected with the chassis sleeper.
Further, the both sides of the battery truck sleeper are provided with that reinforcing bar is vertical to be connected, and the reinforcing bar is vertical even and the storage battery track The end of pillow is by being welded to connect.
Further, the reinforcing bar is vertical even at interval of band iron is provided with 20m~30m, and the band iron is indulged with the reinforcing bar to be connected By being welded to connect, the band iron is connected by segment bolt with the tunnel wall.
Further, the battery truck sleeper and the chassis sleeper are multiple.
It is another object of the present invention to provide a kind of construction of temporary track fixed system in tunnel, including:
S1:Measure the distance between battery truck wheel;
S2:Height of the battery truck sleeper apart from tunnel wall is calculated using round chord length;
S3:Measure the distance between bogie wheels;
S4:Measure the height of chassis;
S5:The height in tunnel is calculated according to design drawing;
S6:Under the precondition that chassis does not collide tunnel wall, chassis sleeper is calculated apart from tunnel wall using diameter of a circle Highly;
S7:Chassis sleeper is calculated apart from the height and chassis sleeper of tunnel wall apart from the height of tunnel wall according to battery truck sleeper With the relative position of battery truck sleeper;
S8:Trolley rail pillow and battery truck sleeper are installed.
Further, in S2, the length of battery truck tie, battery truck are calculated according to the distance between battery truck wheel The length of sleeper is longer than the distance between battery truck wheel, the length of battery truck sleeper and the difference of the distance between battery truck wheel For fixed value, you can the length of battery truck sleeper is calculated, because the distance at tunnel center to tunnel wall is round radius, you can Tunnel center is calculated to the height of battery truck sleeper, then by round radius and the height phase at tunnel center to battery truck sleeper Subtract, you can calculate battery truck sleeper to the height of tunnel wall, you can calculate height of the battery truck sleeper apart from tunnel wall.
Further, in S6, due to the distance between bogie wheels it has been determined that the height of chassis is it has been determined that work as chassis Height when being contacted just with tunnel wall, the line between the end of the top of chassis and the chassis sleeper of opposite side is by circle The heart, you can calculate the air line distance of both sides chassis sleeper, then utilize the radius of circle, you can calculate tunnel center to chassis Sleeper height, round radius is subtracted each other with tunnel center to the height of chassis sleeper, that is, calculated chassis sleeper apart from tunnel The height of road wall.
According to the present invention of such scheme, its advantage is, the present invention is calculated using the chord length of circle and determines structure chi It is very little, battery truck track is pressed close to tunnel wall, highly shortened the distance between battery truck track and tunnel wall, reduce storage battery The height in track face, so that battery truck operation becomes more steady.
Brief description of the drawings
Fig. 1 is the structural representation of the present invention.
Fig. 2 is the plan of the present invention.
The battery truck sleeper both sides that Fig. 3 is the present invention set the vertical even structural representation of reinforcing bar.
Fig. 4 is the construction flow chart of the present invention.
Fig. 5 is the installation trolley rail pillow and battery truck sleeper flow chart of the present invention.
In figure, reference is as follows:
1- tunnel walls;
2- battery truck sleepers;21st, interlude sleeper;22nd, battery truck track neck;23rd, end sleeper;
3- chassis sleepers;31st, connector;32nd, fixture;33rd, chassis sleeper neck;
4- reinforcing bars are vertical to be connected;
5- battery truck tracks;
6- trolley tracks.
Embodiment
Below in conjunction with the accompanying drawings and the present invention is further described embodiment:
As shown in Figure 1 to Figure 2, temporary track fixed system in a kind of tunnel, including the battery truck sleeper located at the bottom of tunnel wall 1 2 and the chassis sleeper 3 located at the both sides of battery truck sleeper 2, battery truck sleeper 2 be connected with chassis sleeper 3, battery truck sleeper 2 and platform Track pillow 3 is connected with tunnel wall 1 respectively, is provided with battery truck track 5 above the both ends of battery truck sleeper 2, two battery truck tracks 5 divide It is not connected with battery truck sleeper 2, and battery truck track 5 presses close to tunnel wall 1, chassis sleeper 3 is provided with trolley track 6, trolley rail Road 6 is connected with chassis sleeper 3.
The beneficial effect so set is that the present invention is calculated using the chord length of circle and determines physical dimension, makes storage battery track Tunnel wall 1 is pressed close in road 5, be highly shortened the distance between battery truck track 5 and tunnel wall 1, is reduced battery truck rail level Highly, so that battery truck operation becomes more steady.
The effect of chassis sleeper 3 is entered in face of mainly meeting shield machine when tunneling forward in orbit, when chassis sleeper 3 After departing from chassis, then disassemble and reinstall to foremost, chassis sleeper 3 may be reused.
The effect of battery truck sleeper 2 is mainly to provide shield machine battery truck construction transport routes in tunneling process, mainly The mortar for transport section of jurisdiction, slagging tap and pick synchronous grouting needs.Battery truck sleeper 2 just needs to install before shield machine is gone into the well.
In the present embodiment, the distance between battery truck track 5 and tunnel wall 1 are 30mm, and traditional arc sleeper phase Than highly shortened the distance between battery truck track 5 and tunnel wall 1.
Battery truck sleeper 2 includes interlude sleeper 21 and the end sleeper 23 at both ends, end sleeper 23 and interlude sleeper Battery truck track neck 22 is provided between 21, battery truck track 5 is in battery truck track neck 22, battery truck track 5 and electricity The connection of bottle track pillow 2.
The bottom of chassis sleeper 3 is provided with the connector 31 being connected with battery truck sleeper 2, and connector 31 connects with chassis sleeper 3 Connect, connector 31 is connected with end sleeper 23.In the end insertion connector 31 of end sleeper 23, the connector 31 at both ends is by end Portion's sleeper 23 is fixed.
The length of battery truck sleeper 2 is slightly larger than the distance between battery truck wheel, and the length of battery truck sleeper 2 is slightly larger than electricity The part of bottle car wheel is end sleeper 23, and end sleeper 23 is used to be connected with connector 31.
The horizontal segment on the top of chassis sleeper 3 is provided with two fixtures 32, and fixture 32 is connected with chassis sleeper 3, two Trolley track neck 33 is provided between fixture 32, trolley track 3 is in trolley track neck 33, trolley track 6 and chassis Sleeper 3 connects.
Battery truck sleeper 2 and chassis sleeper 3 are multiple.Battery truck sleeper 2 and chassis sleeper 3 are spread according to certain spacing If until Tunnel leads to, so that battery truck and chassis can smoothly be run.
As shown in figure 3, after chassis sleeper 3 is removed, the both sides of battery truck sleeper 2, which are provided with reinforcing bar and indulged, connects 4, and reinforcing bar is vertical to connect 4 End with battery truck sleeper 2 is by being welded to connect.Reinforcing bar is vertical even 4 at interval of being provided with band iron, band iron and reinforcing bar at 20m~30m Vertical to connect 4 by being welded to connect, band iron is fixedly connected by segment bolt with tunnel wall 1.This setting can improve battery truck sleeper 2 Stability, when battery truck by when, the stress of battery truck sleeper 2 is without departing from section of jurisdiction.The laying structure of battery truck sleeper 2 is simple, The same in the very big the inside conveying track spacing of tunnel wall 1 of the gradient, battery truck can smoothly be run.
In the present embodiment, it even 4 be one-level steel that reinforcing bar is vertical, reinforcing bar it is vertical even 4 a diameter of 18mm~22mm, so as to more preferable Reinforcing battery truck sleeper 2 is vertical to link system.
In the present embodiment, battery truck sleeper 2 is channel-section steel, and further, channel-section steel is No. 10 channel-section steels so that single battery truck The weight of sleeper 2 only has 12kg, and traditional battery truck sleeper is processed for former material by 10mm steel plates and formed, its single storage battery track Pillow weight has reached 30kg, therefore the weight of the single battery truck sleeper 2 of the present embodiment offer is than the weight of traditional battery truck sleeper Amount alleviates 18kg, reduces the weight of single battery truck sleeper, considerably reduces the use to former material, the mitigation of weight is same When reduce labour cost, reduce cost, and assemble, remove convenient, improve efficiency of construction.
In the present embodiment, the material of chassis sleeper 3 is steel, and further, chassis sleeper 3 is processed by 10mm steel Form.
Present invention employs the side that battery truck sleeper 2 is combined using No. 10 channel-section steels with chassis sleeper 3 using 10mm steel plates Formula, cost is reduced, improve operating efficiency.
As shown in figure 4, the present embodiment additionally provides a kind of construction of temporary track fixed system in tunnel, including:
S1:Measure the distance between battery truck wheel;
S2:Height of the battery truck sleeper 2 apart from tunnel wall 1 is calculated using round chord length;
S3:Measure the distance between bogie wheels;
S4:Measure the height of chassis;
S5:The height in tunnel is calculated according to design drawing;
S6:Under the precondition that chassis does not collide tunnel wall 1, chassis sleeper 3 is calculated apart from tunnel wall 1 according to diameter of a circle Height;
S7:Chassis is calculated apart from the height and chassis sleeper 3 of tunnel wall 1 apart from the height of tunnel wall 1 according to battery truck sleeper 2 The relative position of sleeper 3 and battery truck sleeper 2;
S8:Trolley rail pillow 3 and battery truck sleeper 2 are installed.
Further, in S2, the length of battery truck tie 2, storage battery are calculated according to the distance between battery truck wheel The length of track pillow 2 is longer than the distance between battery truck wheel, the distance between the length of battery truck sleeper 2 and battery truck wheel Difference be fixed value, you can the length of battery truck sleeper 2 is calculated, because the distance at tunnel center to tunnel wall 1 is the half of circle Footpath, you can tunnel center is calculated to the height of battery truck sleeper 2, then by round radius and tunnel center to battery truck sleeper 2 height is subtracted each other, you can calculates height of the battery truck sleeper 2 apart from tunnel wall 1.
Further, in S6, due to the distance between bogie wheels it has been determined that the height of chassis is it has been determined that work as chassis Height when being contacted just with tunnel wall 1, the line between the end of the top of chassis and the chassis sleeper 3 of opposite side is by circle The heart, you can calculate the air line distance of both sides chassis sleeper 3, then utilize the radius of circle, you can calculate tunnel center to platform Track pillow 3 height, round radius is subtracted each other with tunnel center to the height of chassis sleeper 3, that is, calculated chassis sleeper 3 away from From the height of tunnel wall 1.
As shown in figure 5, in S8, S81:Placing storage battery track pillow 2 is with placing trolley rail pillow 3, specially:Electricity is placed first Bottle track pillow 2, then places trolley rail pillow 3, by the end of battery truck sleeper 2 and the end of chassis sleeper 3 in the both sides of battery truck sleeper 2 The connector 31 in portion connects.
S82:Placing storage battery track road 5 is specially with placing trolley track 6:Battery truck track 5 is placed on storage battery track The both ends of pillow 2, trolley track 6 is placed on chassis sleeper 3.
S83:Place reinforcing bar and indulge and connect 4, be specially:After chassis sleeper 3 is removed, steel is placed in the both sides of battery truck sleeper 2 Flaccidity of tendon and muscle connects 4, and reinforcing bar is vertical even 4 to be fixedly connected with battery truck sleeper 2;At interval of 20~30m, in reinforcing bar, vertical company 4 passes through band iron and tunnel Road wall 1 is fixedly connected.
It should be appreciated that for those of ordinary skills, can according to the above description be improved or converted, And all these modifications and variations should all belong to the protection domain of appended claims of the present invention.
Exemplary description has been carried out to patent of the present invention above in conjunction with accompanying drawing, it is clear that the realization of patent of the present invention not by The limitation of aforesaid way, if the various improvement that the methodology of patent of the present invention and technical scheme are carried out are employed, or without Improve and the design of patent of the present invention and technical scheme are directly applied into other occasions, within the scope of the present invention.

Claims (10)

  1. A kind of 1. temporary track fixed system in tunnel, it is characterised in that including the battery truck sleeper located at tunnel wall bottom and Chassis sleeper located at the battery truck sleeper both sides, the battery truck sleeper are connected with the chassis sleeper, the battery truck Sleeper and the chassis sleeper are connected with the tunnel wall respectively, and battery truck track is provided with above the battery truck sleeper both ends, Two the battery truck track is connected with the battery truck sleeper respectively, and the battery truck track presses close to the tunnel wall, institute State chassis sleeper and be provided with trolley track, the trolley track is connected with the chassis sleeper.
  2. 2. temporary track fixed system in tunnel according to claim 1, it is characterised in that the battery truck sleeper includes Interlude sleeper and the end sleeper at both ends, battery truck track card is provided between the end sleeper and the interlude sleeper Groove, in the battery truck track neck, the battery truck track is connected the battery truck track with the battery truck sleeper.
  3. 3. temporary track fixed system in tunnel according to claim 2, it is characterised in that the bottom of the chassis sleeper Provided with the connector being connected with the battery truck sleeper, the connector is connected with the chassis sleeper, the connector and institute State end sleeper connection.
  4. 4. temporary track fixed system in tunnel according to claim 1, it is characterised in that the top of the chassis sleeper Horizontal segment be provided with two fixtures, the fixture is connected with the chassis sleeper, and platform is provided between two fixtures Track road neck, in the trolley track neck, the trolley track is connected the trolley track with the chassis sleeper.
  5. 5. temporary track fixed system in tunnel according to claim 1, it is characterised in that the two of the battery truck sleeper Side is provided with the vertical company of reinforcing bar, and the vertical even end with the battery truck sleeper of the reinforcing bar is by being welded to connect.
  6. 6. temporary track fixed system in tunnel according to claim 5, it is characterised in that the reinforcing bar it is vertical even at interval of Be provided with band iron at 20m~30m, the band iron was welded to connect with vertical connected of the reinforcing bar, the band iron by segment bolt with The tunnel wall connection.
  7. 7. temporary track fixed system in tunnel according to claim 1, it is characterised in that the battery truck sleeper and institute It is multiple to state chassis sleeper.
  8. A kind of 8. construction of temporary track fixed system in tunnel:It is characterised in that it includes:
    S1:Measure the distance between battery truck wheel;
    S2:Height of the battery truck sleeper apart from tunnel wall is calculated using round chord length;
    S3:Measure the distance between bogie wheels;
    S4:Measure the height of chassis;
    S5:The height in tunnel is calculated according to design drawing;
    S6:Under the precondition that chassis does not collide tunnel wall, chassis sleeper is calculated apart from tunnel wall using diameter of a circle Highly;
    S7:Chassis sleeper is calculated apart from the height and chassis sleeper of tunnel wall apart from the height of tunnel wall according to battery truck sleeper With the relative position of battery truck sleeper;
    S8:Trolley rail pillow and battery truck sleeper are installed.
  9. 9. the construction of temporary track fixed system in tunnel according to claim 8, it is characterised in that in S2, Calculate the length of battery truck tie according to the distance between battery truck wheel, the length of battery truck sleeper than battery truck wheel it Between distance, the length of battery truck sleeper and the difference of the distance between battery truck wheel are fixed value, you can calculate storage battery The length of track pillow, because the distance at tunnel center to tunnel wall is round radius, you can calculate tunnel center to battery truck The height of sleeper, then round radius is subtracted each other with tunnel center to the height of battery truck sleeper, you can calculate storage battery track Rest the head on the height of tunnel wall, you can calculate height of the battery truck sleeper apart from tunnel wall.
  10. 10. the construction of temporary track fixed system in tunnel according to claim 8, it is characterised in that in S6, Due to the distance between bogie wheels it has been determined that the height of chassis is it has been determined that when the height of chassis contacts with tunnel wall just, Line between the top of chassis and the end of the chassis sleeper of opposite side is by the center of circle, you can calculates both sides chassis sleeper Air line distance, then utilize the radius of circle, you can tunnel center is calculated to trolley rail pillow height degree, by round radius and tunnel The height of the heart to chassis sleeper is subtracted each other, that is, has calculated the height apart from tunnel wall of chassis sleeper.
CN201710655314.9A 2017-08-03 2017-08-03 Temporary track fixing system in tunnel and construction method thereof Active CN107489447B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710655314.9A CN107489447B (en) 2017-08-03 2017-08-03 Temporary track fixing system in tunnel and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710655314.9A CN107489447B (en) 2017-08-03 2017-08-03 Temporary track fixing system in tunnel and construction method thereof

Publications (2)

Publication Number Publication Date
CN107489447A true CN107489447A (en) 2017-12-19
CN107489447B CN107489447B (en) 2024-05-10

Family

ID=60644172

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710655314.9A Active CN107489447B (en) 2017-08-03 2017-08-03 Temporary track fixing system in tunnel and construction method thereof

Country Status (1)

Country Link
CN (1) CN107489447B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112144322A (en) * 2020-09-29 2020-12-29 广西壮族自治区建筑科学研究设计院 Green construction method for track

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10331104A (en) * 1997-06-02 1998-12-15 Izumi:Kk Sleeper for tunnel construction works
CN103061213A (en) * 2012-12-28 2013-04-24 中铁二十四局集团上海铁建工程有限公司 Independent shield trolley sleeper and construction method thereof
CN203947375U (en) * 2014-06-30 2014-11-19 葛洲坝集团基础工程有限公司 A kind of shield machine chassis and battery truck composite sleeper
CN204475070U (en) * 2015-01-29 2015-07-15 中铁十九局集团轨道交通工程有限公司 Portable combined shield machine sleeper
CN105133443A (en) * 2015-07-30 2015-12-09 中铁二十四局集团有限公司 Universal shield trolley sleeper installation structure and construction method for same
CN105369699A (en) * 2015-09-30 2016-03-02 龚金京 Construction method for dividing sleeper of portable novel shielding tunneling machine backup trailer and accumulator car system
CN205443816U (en) * 2015-12-31 2016-08-10 中交一公局第三工程有限公司 Assembled single shield sleeper for TBM
CN205676737U (en) * 2016-05-27 2016-11-09 中国电建集团铁路建设有限公司 A kind of shield-tunneling construction train sleeper
CN206015442U (en) * 2015-07-30 2017-03-15 中国建筑第六工程局有限公司 A kind of removable compound shield-tunneling construction sleeper
CN207212401U (en) * 2017-08-03 2018-04-10 中国电建集团铁路建设有限公司 Temporary track fixed system in a kind of tunnel

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10331104A (en) * 1997-06-02 1998-12-15 Izumi:Kk Sleeper for tunnel construction works
CN103061213A (en) * 2012-12-28 2013-04-24 中铁二十四局集团上海铁建工程有限公司 Independent shield trolley sleeper and construction method thereof
CN203947375U (en) * 2014-06-30 2014-11-19 葛洲坝集团基础工程有限公司 A kind of shield machine chassis and battery truck composite sleeper
CN204475070U (en) * 2015-01-29 2015-07-15 中铁十九局集团轨道交通工程有限公司 Portable combined shield machine sleeper
CN105133443A (en) * 2015-07-30 2015-12-09 中铁二十四局集团有限公司 Universal shield trolley sleeper installation structure and construction method for same
CN206015442U (en) * 2015-07-30 2017-03-15 中国建筑第六工程局有限公司 A kind of removable compound shield-tunneling construction sleeper
CN105369699A (en) * 2015-09-30 2016-03-02 龚金京 Construction method for dividing sleeper of portable novel shielding tunneling machine backup trailer and accumulator car system
CN205443816U (en) * 2015-12-31 2016-08-10 中交一公局第三工程有限公司 Assembled single shield sleeper for TBM
CN205676737U (en) * 2016-05-27 2016-11-09 中国电建集团铁路建设有限公司 A kind of shield-tunneling construction train sleeper
CN207212401U (en) * 2017-08-03 2018-04-10 中国电建集团铁路建设有限公司 Temporary track fixed system in a kind of tunnel

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112144322A (en) * 2020-09-29 2020-12-29 广西壮族自治区建筑科学研究设计院 Green construction method for track
CN112144322B (en) * 2020-09-29 2022-03-08 广西壮族自治区建筑科学研究设计院 Green construction method for track

Also Published As

Publication number Publication date
CN107489447B (en) 2024-05-10

Similar Documents

Publication Publication Date Title
CN104775825B (en) Single-well integral starting construction method of shield tunneling machine
CN207363606U (en) A kind of drilling machine sliding system
CN205638490U (en) A portable platform truck that is used for subway station tread wind channel to pour
CN206752216U (en) A kind of shield machine trolley and electric locomotive pin-connected panel sleeper with lower arcuate surface
CN104294715A (en) Safe and rapid combined shield tunneling light sleeper
CN207212401U (en) Temporary track fixed system in a kind of tunnel
CN105369699A (en) Construction method for dividing sleeper of portable novel shielding tunneling machine backup trailer and accumulator car system
CN107489447A (en) Temporary track fixed system and its construction in a kind of tunnel
CN204475070U (en) Portable combined shield machine sleeper
CN104562870B (en) Portable combined shield machine sleeper
CN202117689U (en) Light-duty trolley which is matched with shield station-passing for structure formwork
CN201933423U (en) Movable type protecting canopy frame
CN206553835U (en) A kind of track guard
CN104164838A (en) Light combined type beam moving trolley
CN210310336U (en) Power station rock anchor beam track pouring travelling bogie
CN207847035U (en) A kind of device constructed and transported for section
CN207943794U (en) Pipeline fast dismounting device in a kind of tunnel
CN206707719U (en) The bracket of supporting chassis translation after a kind of constructing tunnel auxiliary TBM
CN110626733A (en) Special device for transporting ultra-large-diameter pipeline in narrow space
CN202577067U (en) Simple and practical trolley sleeper for shield tunnel
CN106544934B (en) A kind of railway shunting hump line reinforced construction method
CN204959505U (en) Single line roof beam security platform
CN205474623U (en) Sloping between tracks connection device goes up and down
CN207554104U (en) A kind of multifunction railway is passed a bridge
CN214295931U (en) Ballastless track template transport trolley suitable for high-speed railway bridge

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant