CN107489258A - The prefabricated pit of elevator hoistways, elevator hoistways pit method of construction and installation elevator - Google Patents

The prefabricated pit of elevator hoistways, elevator hoistways pit method of construction and installation elevator Download PDF

Info

Publication number
CN107489258A
CN107489258A CN201710689794.0A CN201710689794A CN107489258A CN 107489258 A CN107489258 A CN 107489258A CN 201710689794 A CN201710689794 A CN 201710689794A CN 107489258 A CN107489258 A CN 107489258A
Authority
CN
China
Prior art keywords
pit
side wall
bottom plate
elevator
waterproof
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710689794.0A
Other languages
Chinese (zh)
Inventor
秦健聪
王森华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Dongnan Elevator Co Ltd
Original Assignee
Dongnan Elevator Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Dongnan Elevator Co Ltd filed Critical Dongnan Elevator Co Ltd
Priority to CN201710689794.0A priority Critical patent/CN107489258A/en
Publication of CN107489258A publication Critical patent/CN107489258A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F17/00Vertical ducts; Channels, e.g. for drainage
    • E04F17/005Lift shafts
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • Lift-Guide Devices, And Elevator Ropes And Cables (AREA)

Abstract

The invention discloses a kind of prefabricated pit of elevator hoistways, elevator hoistways pit method of construction and installation elevator, installing elevator additional includes prefabricated pit, the prefabricated pit it include bottom plate, pour in column on bottom plate and positioned at four corners, side wall between column, bed course below bottom plate, the lower waterproof layer and side waterproof layer being respectively arranged on around the bottom base plate and side wall, the lower waterproof layer includes the waterproof mortar dry batch being layed between the bottom plate and the bed course, coated on the waterproof coating layer on the bottom plate, the side waterproof layer is included coated on the waterproof coating layer on the side wall lateral surface, protective layer located at the waterproof coating layer periphery.The present invention completes prefabricated pit and built inside, and waterproof layer is completed in the lump, greatly shortens the construction period, prevents farm labourer is interim from being caused construction quality to reduce by bad weather.

Description

The prefabricated pit of elevator hoistways, elevator hoistways pit method of construction and installation elevator
Technical field
The invention belongs to hoist and traction apparatus field, the prefabricated pit of more particularly to a kind of elevator hoistways, elevator hoistways pit Method of construction and installation elevator.
Background technology
Hoistway must first be arranged complete that in a pre-installation the construction of pit is most important ring in hoistway arrangement again by elevator Section, traditional pit construction process cycle must mainly include the following steps that for more than 29 days:Civil engineering is excavated(2 days);Rammed earth (0.5 day);Molding-C15 plain concrete cushion layer pouring constructions(0.5 day);Steel reinforcement cage construction-molding-elevator built-in fitting is put into(2 My god);C30 or C35 concretings(0.5 day);Shaping(3 days);Form removal(0.5 day);Maintenance(More than 20 days);Last ability Hoistway is marched into the arena construction.Therefore construction time limit for length, if period runs into the bad weathers such as rainwater, not only can extend the duration, can also influence The performance qualities such as hoistway waterproof.There is a kind of hoistway arrangement of prefabricated pit at present, its Publication No. CN202519693U, but It does not pre-set waterproof layer, therefore also needs after prefabricated pit is marched into the arena to do waterproof construction, and the duration of waterproof construction with Traditional molding duration is close, therefore is still not reaching to the purpose for shortening the duration.
The content of the invention
It is an object of the invention to provide a kind of short time limit and the high prefabricated pit of elevator hoistways of water resistance.
In order to solve the above technical problems, the present invention adopts the following technical scheme that:A kind of prefabricated pit of elevator hoistways, it includes Bottom plate, pour on the bottom plate and column positioned at four corners, the side wall between column, be respectively arranged on the bottom plate bottom Lower waterproof layer and side waterproof layer around portion and side wall, the lower waterproof layer include being layed in the waterproof below the bottom plate Mortar dry batch, coated on the waterproof coating layer on the bottom plate lower surface, the side waterproof layer includes being coated on the side wall Waterproof coating layer on lateral surface, the protective layer located at the waterproof coating layer periphery.
Optimization, coated on the waterproof coating layer on the bottom plate successively include elastomer asphalt waterproofing paint layer and Dry to spread cement-based capillary crystalline waterproof coating layer, the elastomer asphalt waterproofing paint layer is close on the bottom surface of the bottom plate.
Optimization, be elastomer asphalt waterproofing paint layer coated on the waterproof coating layer on the side wall lateral surface.
Optimization, the bottom plate includes bottom reinforcement bars structure and the concrete being coated on bar construction, the side wall bag Sidepiece bar construction and the concrete being coated on bar construction are included, the bottom reinforcement bars structure includes prolonging to bottom plate peripheral direction The bottom lapping plate stretched, the sidepiece bar construction include the side lapping plate extended downwards, the bottom lapping plate with it is described Side lapping plate is interlockingly connected.
Optimization, the bottom plate and the side wall form pit body, the pit body by decile four part pits Monomer composition, the prefabricated pit also include the connector being connected between the pit monomer, the connector across Connecting plate, it is provided with the connecting key and keyway that match with the side wall that the pit monomer splices.
Optimization, the side wall forms side wall body with the column, and the side wall body is by multiple sides being coaxially disposed Wall monomer is socketed to be formed successively, and the lower surface of each monomer is provided with set access slot and upper surface is provided with Coupling.
Optimization, the protective layer is plastic foamboard, and its thickness is not less than 20mm.
Present invention also offers a kind of elevator hoistways pit method of construction, it comprises the following steps,
One, civil engineerings are excavated;
Two, rammed earths
Three, moldings;
Four, casting concrete cushion constructions on the element soil of compacting;
The prefabricated pits of five, are marched into the arena on fixed and concrete cushion;
Six, hoistways are marched into the arena construction,
The prefabricated pit is any of the above-described prefabricated pit of elevator hoistways, and the prefabricated pit of elevator hoistways is completed inside Construction.
Present invention also offers one kind to install elevator additional, and it includes hoistway, the elevator body being installed in the hoistway, described Hoistway includes pit, and the pit is any of the above-described prefabricated pit of elevator hoistways.
The beneficial effects of the present invention are:The present invention completes prefabricated pit and built inside, and waterproof layer is complete in the lump Into greatly shortening the construction period, prevent farm labourer is interim from being caused construction quality to reduce by bad weather.
Brief description of the drawings
Accompanying drawing 1 is the structural representation of the prefabricated pit of elevator hoistways in the present invention;
Accompanying drawing 2 is the structural representation of pit in embodiment one;
Accompanying drawing 3 is the sectional view A-A of accompanying drawing 2;
Accompanying drawing 4 is the sectional view B-B of accompanying drawing 2;
Accompanying drawing 5 is the structural representation of pit in embodiment two;
Accompanying drawing 6 is the bottom plate of embodiment two or the attachment structure schematic diagram of side wall and connector;
Accompanying drawing 7 is the structural representation of pit in embodiment three.
Embodiment
Shown embodiment is described in detail below to the present invention below in conjunction with the accompanying drawings:
As shown in figure 1, the prefabricated pit of elevator hoistways is on the concrete cushion 4, it includes bottom plate 1, pour on bottom plate 1 and Column 2 positioned at four corners, the side wall 3 between column 2, it is respectively arranged on around the bottom of bottom plate 1 and side wall 3 Lower waterproof layer 5 and side waterproof layer 6, the lower waterproof layer 5 include being layed between the bottom plate 1 and the concrete cushion 4 Waterproof mortar dry batch 51, coated on the waterproof coating layer on the bottom plate 1, the side waterproof layer 6 is included coated on described Waterproof coating layer on the lateral surface of side wall 3, the protective layer 61 located at the waterproof coating layer periphery.
Include elastomer asphalt waterproofing paint layer 52 successively coated on the waterproof coating layer on the bottom plate 1 and dry spread Cement-based capillary crystalline waterproof coating layer 53, the elastomer asphalt waterproofing paint layer 52 are close on the bottom surface of the bottom plate 1. It is elastomer asphalt waterproofing paint layer 52 coated on the waterproof coating layer on the lateral surface of side wall 3.The elastomer drip The thickness of blue or green waterproof coating layer 52 is not less than 1mm.The thickness of the waterproof mortar dry batch 51 is not less than 10mm.It is dry to spread cement base Capillary crystalline waterproof coating material layer 53 is not less than 0.5kg per square meter.The protective layer 61 is plastic foamboard, and its thickness is not less than 20mm.The elastomer asphalt waterproofing paint layer 52 of lower waterproof layer 5, the dry cement-based capillary crystalline waterproof coating layer 53 and anti-of spreading Water sand slurry dry batch 51 extends into the lower section of side waterproof layer 6.
Bottom plate 1 and side wall 3 can be that following four form is formed:
Embodiment one, in the present embodiment, side wall and column and bottom plate are molded by concrete formed by integrally casting, inside concrete tool Have to form the bar construction of the integral type of side wall and column and bottom plate.In the case that hanging device allows at the construction field (site), greatly Use this kind of mode, its intensity, sealing highest more.But in the case that job site hanging device or transporting equipment are limited, Then need to use the several ways in following examples.
Embodiment two, as shown in Figure 2,3, 4, the bottom plate 1 include bottom reinforcement bars structure and are coated on bar construction Concrete seven, the side wall 3 include sidepiece bar construction and the concrete seven being coated on bar construction, the bottom reinforcement bars structure Bottom lapping plate 84, the sidepiece bar construction including extending to the peripheral direction of bottom plate 1 include the side overlap joint extended downwards Plate 85, the bottom lapping plate 84 into door shape, the side lapping plate 85 into two L-shaped, the bottom lapping plate 84 with it is described Side lapping plate 85 is interlockingly connected.So connection can not only improve waterproof effect, moreover it is possible to be greatly enhanced the connection of bottom plate 1 and side wall 3 Intensity.
Embodiment three, as shown in Figure 5,6, the bottom plate 1 and the side wall 3 form pit body, the pit body by Four part pit monomers 91 of decile form, and the prefabricated pit also includes the connector being connected between the pit monomer 91 92, the connector 92 is in cross connecting plate-shaped, and it is provided with the connection matched with the side wall that the pit monomer 91 splices Key 93 and keyway 94.Connector includes cross bar construction 83, the concrete seven being coated on outside cross bar construction 83.Modularization Pit body, be advantageous to transport and can according to pit excavate situation it is flexibly assembled.
Example IV, as shown in fig. 7, the side wall 3 and the column 2 form side wall body, the side wall body is by more The individual side wall monomer 95 being coaxially disposed is socketed formation successively, and the lower surface of each monomer is provided with set access slot and upper surface is provided with Coupling.Modularization side wall body, be advantageous to transport and can according to pit excavate situation it is flexibly assembled.
Elevator hoistways pit method of construction comprises the following steps, and civil engineerings are excavated;Two, rammed earths;Three, moldings;Four, Prefabricated pit is marched into the arena fixation;Five, hoistways are marched into the arena construction, and the prefabricated pit is the prefabricated pit of above-mentioned elevator hoistways, the elevator The prefabricated pit of hoistway is completed to construct inside, including its side waterproof layer and lower waterproof layer are also to complete construction inside, can be greatly Shortening construction the time limit.
Installing elevator additional includes hoistway, the elevator body being installed in the hoistway, and the hoistway includes pit, the pit For the prefabricated pit of above-mentioned elevator hoistways.
The above embodiments merely illustrate the technical concept and features of the present invention, and its object is to allow person skilled in the art Scholar can understand present disclosure and implement according to this, and it is not intended to limit the scope of the present invention.It is all according to the present invention The equivalent change or modification that spirit is made, should all be included within the scope of the present invention.

Claims (9)

1. a kind of prefabricated pit of elevator hoistways, it includes bottom plate, pours on bottom plate and positioned at four corners column, is located at Side wall between column, the lower waterproof layer and side waterproof layer being respectively arranged on around the bottom base plate and side wall, its feature It is:The lower waterproof layer includes being layed in waterproof mortar dry batch below the bottom plate, coated on the bottom plate lower surface On waterproof coating layer, the side waterproof layer includes coated on the waterproof coating layer on the side wall lateral surface, located at described anti- The protective layer of water paint layer periphery.
2. the prefabricated pit of elevator hoistways according to claim 1, it is characterised in that:Applied coated on the waterproof on the bottom plate The bed of material includes elastomer asphalt waterproofing paint layer and dry spreads cement-based capillary crystalline waterproof coating layer, the high-elastic rubber successively Glue asphalt waterproofing paint layer is close on the bottom surface of the bottom plate.
3. the prefabricated pit of elevator hoistways according to claim 1, it is characterised in that:Coated on the side wall lateral surface Waterproof coating layer is elastomer asphalt waterproofing paint layer.
4. the prefabricated pit of elevator hoistways according to claim 1, it is characterised in that:The bottom plate includes bottom reinforcement bars structure With the concrete being coated on bar construction, the side wall includes sidepiece bar construction and the coagulation being coated on bar construction Soil, the bottom reinforcement bars structure include to bottom plate peripheral direction extend bottom lapping plate, the sidepiece bar construction include to The side lapping plate of lower section extension, the bottom lapping plate are interlockingly connected with the side lapping plate.
5. the prefabricated pit of elevator hoistways according to claim 1, it is characterised in that:The bottom plate forms bottom with the side wall Body is cheated, the pit body is by four part pit monomer compositions of decile, and the prefabricated pit is also including being connected to the bottom The connector between monomer, the connector across connecting plate are cheated, its side wall spliced with the pit monomer is provided with The connecting key and keyway of matching.
6. the prefabricated pit of elevator hoistways according to claim 1, it is characterised in that:The side wall forms side with the column Wall body, the side wall body are socketed and formed, set on the lower surface of each monomer successively by multiple side wall monomers being coaxially disposed There is set access slot and upper surface is provided with Coupling.
7. the prefabricated pit of elevator hoistways according to claim 1, it is characterised in that:The protective layer is plastic foamboard, Its thickness is not less than 20mm.
8. a kind of elevator hoistways pit method of construction, it comprises the following steps,
One, civil engineerings are excavated;
Two, rammed earths
Three, moldings;
Four, casting concrete cushion constructions on the element soil of compacting;
The prefabricated pits of five, are marched into the arena on fixed and concrete cushion;
Six, hoistways are marched into the arena construction,
It is characterized in that:The prefabricated pit be claim 1~7 in any prefabricated pit of elevator hoistways, the elevator The prefabricated pit of hoistway is completed to construct inside.
9. one kind installs elevator additional, it includes hoistway, the elevator body being installed in the hoistway, and the hoistway includes pit, its It is characterised by:The pit is any prefabricated pit of elevator hoistways in claim 1~7.
CN201710689794.0A 2017-08-14 2017-08-14 The prefabricated pit of elevator hoistways, elevator hoistways pit method of construction and installation elevator Pending CN107489258A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710689794.0A CN107489258A (en) 2017-08-14 2017-08-14 The prefabricated pit of elevator hoistways, elevator hoistways pit method of construction and installation elevator

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710689794.0A CN107489258A (en) 2017-08-14 2017-08-14 The prefabricated pit of elevator hoistways, elevator hoistways pit method of construction and installation elevator

Publications (1)

Publication Number Publication Date
CN107489258A true CN107489258A (en) 2017-12-19

Family

ID=60644098

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710689794.0A Pending CN107489258A (en) 2017-08-14 2017-08-14 The prefabricated pit of elevator hoistways, elevator hoistways pit method of construction and installation elevator

Country Status (1)

Country Link
CN (1) CN107489258A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111576432A (en) * 2020-05-26 2020-08-25 山东省建筑科学研究院有限公司 Prefabricated foundation pit additionally provided with elevator and construction method
CN111997304A (en) * 2020-07-29 2020-11-27 清华大学 Elevator shaft structure and construction method thereof

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202245617U (en) * 2011-01-04 2012-05-30 张向阳 Elevator well wall assembled by adopting combined type derricks
CN202519693U (en) * 2012-03-16 2012-11-07 刘涛 Anti-seep structure for bottom pit and side walls of elevator
CN104358275A (en) * 2014-11-19 2015-02-18 武汉一冶建筑安装工程有限责任公司 Construction method for deeper elevator well or water collecting well
CN205712463U (en) * 2016-04-27 2016-11-23 苏州市德威防水科技有限公司 A kind of waterproof slab protection structure
CN106703367A (en) * 2017-03-09 2017-05-24 广东易佳梯科技有限公司 Method for constructing additional elevator shaft ways of existing buildings
CN207079869U (en) * 2017-08-14 2018-03-09 东南电梯股份有限公司 The prefabricated pit of elevator hoistways and installation elevator

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202245617U (en) * 2011-01-04 2012-05-30 张向阳 Elevator well wall assembled by adopting combined type derricks
CN202519693U (en) * 2012-03-16 2012-11-07 刘涛 Anti-seep structure for bottom pit and side walls of elevator
CN104358275A (en) * 2014-11-19 2015-02-18 武汉一冶建筑安装工程有限责任公司 Construction method for deeper elevator well or water collecting well
CN205712463U (en) * 2016-04-27 2016-11-23 苏州市德威防水科技有限公司 A kind of waterproof slab protection structure
CN106703367A (en) * 2017-03-09 2017-05-24 广东易佳梯科技有限公司 Method for constructing additional elevator shaft ways of existing buildings
CN207079869U (en) * 2017-08-14 2018-03-09 东南电梯股份有限公司 The prefabricated pit of elevator hoistways and installation elevator

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111576432A (en) * 2020-05-26 2020-08-25 山东省建筑科学研究院有限公司 Prefabricated foundation pit additionally provided with elevator and construction method
CN111997304A (en) * 2020-07-29 2020-11-27 清华大学 Elevator shaft structure and construction method thereof
CN111997304B (en) * 2020-07-29 2021-10-26 清华大学 Elevator shaft structure and construction method thereof

Similar Documents

Publication Publication Date Title
CN205653820U (en) Basement post -cast strip advances plugging device
CN105804410A (en) Sub-cabin pressure grouting method for vertical connection of prefabricated concrete structure
CN209227580U (en) The tower-crane foundation structure of raft foundation is placed under a kind of
CN106930777A (en) The construction method of the lining of Bored Section of Metro main track assembled two
CN203034494U (en) Water draining structure for basement bottom plate back watering belt
CN106320120A (en) Construction process for pile slab type non-soil roadbed highway
CN104652417A (en) High-performance concrete corrugated sheet pile, forming die and production method for high-performance concrete corrugated sheet pile
CN106759474A (en) The construction method of flexible spigot-and-socket common pipe trench
CN110439036A (en) A kind of poured band of outer wall of basement advance water stop construction method
CN206844275U (en) Mutual buckle type precast concrete cover ditch and its suspender
CN107489258A (en) The prefabricated pit of elevator hoistways, elevator hoistways pit method of construction and installation elevator
CN108396761A (en) The non-fully pile foundation cushion cap and production method under precipitation state inside a kind of foundation pit
CN108612233A (en) A kind of cast-in-place fair-faced concrete wall construction method
CN214784228U (en) Prefabricated plate advanced closing structure of outer wall post-cast strip
CN207079869U (en) The prefabricated pit of elevator hoistways and installation elevator
CN206529712U (en) Assembled steel reinforced concrete aliform type culvert opening
CN206859272U (en) The interim block structure of outer wall of basement pouring after settlement
CN206693272U (en) Control the shaft bottom structure of inspection shaft sedimentation
CN103306439A (en) Pouring technology for implanting high anti-leakage and anti-crack protective layer into roof structure layer
CN105756100A (en) Basement post-pouring belt system and making method thereof
CN106801384A (en) Assembled steel reinforced concrete aliform type culvert opening and construction method
CN105244835A (en) L-shaped concrete cable trench prefabricated component and production technology
CN205116220U (en) Pour cable pit after assembly of L type precast concrete spare
CN208701690U (en) Foundation pit of elevator shaft
CN210507502U (en) Prefabricated assembled concrete slab bed structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20171219