CN107478997A - A kind of base station storage batteries appraisal procedure and device - Google Patents

A kind of base station storage batteries appraisal procedure and device Download PDF

Info

Publication number
CN107478997A
CN107478997A CN201710647180.6A CN201710647180A CN107478997A CN 107478997 A CN107478997 A CN 107478997A CN 201710647180 A CN201710647180 A CN 201710647180A CN 107478997 A CN107478997 A CN 107478997A
Authority
CN
China
Prior art keywords
base station
storage batteries
station storage
discharge
duration
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710647180.6A
Other languages
Chinese (zh)
Other versions
CN107478997B (en
Inventor
胡翔
巫进明
余冰洁
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Tower Co Ltd
Original Assignee
China Tower Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Tower Co Ltd filed Critical China Tower Co Ltd
Priority to CN201710647180.6A priority Critical patent/CN107478997B/en
Publication of CN107478997A publication Critical patent/CN107478997A/en
Application granted granted Critical
Publication of CN107478997B publication Critical patent/CN107478997B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01RMEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
    • G01R31/00Arrangements for testing electric properties; Arrangements for locating electric faults; Arrangements for electrical testing characterised by what is being tested not provided for elsewhere
    • G01R31/36Arrangements for testing, measuring or monitoring the electrical condition of accumulators or electric batteries, e.g. capacity or state of charge [SoC]
    • G01R31/385Arrangements for measuring battery or accumulator variables

Landscapes

  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Secondary Cells (AREA)

Abstract

The invention provides a kind of base station storage batteries appraisal procedure and device, wherein method includes:Obtain the discharge parameter of base station storage batteries;According to the discharge parameter of base station storage batteries, actual discharge duration and theoretical discharge duration corresponding to base station storage batteries are obtained;Actual discharge duration and theoretical discharge duration, determine base station storage batteries efficiency value according to corresponding to base station storage batteries;Base station storage batteries are assessed according to base station storage batteries efficiency value, obtain assessment result.Base station storage batteries appraisal procedure provided by the invention, on the premise of internet security is met, realized by way of remote control and accurate discharge test is loaded in net to battery, safe ready quickly obtains battery really in net battery online hours efficiency, the evaluation to battery is made, serves the project management of engineering.

Description

A kind of base station storage batteries appraisal procedure and device
Technical field
The present invention relates to station technology field, more particularly to a kind of base station storage batteries appraisal procedure and device.
Background technology
The storage base station number of current three operators is huge, substantial amounts of storage and newly-built site in existing network be present.Base station Backup guarantee of the middle battery as base station equipment, is directly connected to the quantity of operation of network, early stage each operator Respective configuration guide opinion all is proposed to battery configuration, but equipping rules have larger difference, are stored in addition in existing network Numerous influence factors such as battery producer is numerous, the time of being on active service is different, loss situation difference, each base station storage batteries are in civil power The judgement presence of the situation support duration of power failure is definitely difficult, and then judges which battery needs to carry out transformation replacement again When, do not form a perfect judgment criteria.
It is existing mainly to have three kinds of assessment modes in order to evaluate accumulator capacity:The first is that battery off-grid carries out electric power storage Tankage tester detects, very big to internet security, stability influence, and needs upper station on-the-spot test, wastes time and energy;Second It is that the thick assessment mode of the battery carried according to Switching Power Supply assesses battery performance, often deviation is very big;The third is to utilize conductance Instrument tests the internal resistance of battery, substantially judges the quality of battery, and deviation is also very big.Three of the above mode is all because testing cost is huge , often can only be with battery in Practical Project or the battery that accuracy deficiency can not be directly applied in existing network operation is evaluated Active time is that foundation is replaced, but the operating mode of battery is powered off frequent degree by our station, local environment temperature conditions, is filled Discharge administrative situation, battery behavior pattern itself, and active time situation influence, only with active time as judge according to According to, hence it is evident that it is not accurate enough.
The content of the invention
The embodiment of the present invention provides a kind of base station storage batteries appraisal procedure and device, is held with solving battery in the prior art It can not be directly applied in existing network operation in the appraisal procedure of amount because testing cost is high or accuracy is insufficient, and actual work When being replaced in journey using active time as judgment basis the problem of accuracy deficiency.
The embodiment of the present invention provides a kind of base station storage batteries appraisal procedure, applied to mobile terminal, including:
Obtain the discharge parameter of base station storage batteries;
According to the discharge parameter of the base station storage batteries, actual discharge duration and reason corresponding to the base station storage batteries are obtained By electric discharge duration;
According to actual discharge duration corresponding to the base station storage batteries and theoretical discharge duration, the base station storage batteries are determined Efficiency value;
The base station storage batteries are assessed according to the base station storage batteries efficiency value, obtain assessment result.
Wherein, the step of discharge parameter for obtaining base station storage batteries, includes:
Connected by O&M monitor supervision platform and the data acquisition unit of base station side, instruction letter is sent to the data acquisition unit Breath so that the data acquisition unit sets the parameter of the base station storage batteries according to the command information and makes the base station electric power storage Discharged in pond;
Receive discharge parameter of the base station storage batteries of the data acquisition unit transmission in discharge process;
The discharge parameter comprises at least:Corresponding duration, the base when base station storage batteries discharge into setting voltage Stand temperature value t corresponding to capacity Q, load total current I and the base station storage batteries of battery.
Wherein, according to the discharge parameter of the base station storage batteries, when obtaining actual discharge corresponding to the base station storage batteries The step of long and theoretical discharge duration, includes:
Determine a length of actual discharge duration T1 when the base station storage batteries discharge into corresponding during setting voltage;
According to temperature value t corresponding to the capacity Q, load total current I and the base station storage batteries of base station storage batteries, it is determined that The theoretical discharge duration T2.
Wherein, the temperature value according to corresponding to the capacity Q, load total current I and the base station storage batteries of base station storage batteries T, the step of determining the theoretical discharge duration T2, include:
The theoretical discharge duration T2 is determined using default calculation formula:
T2=Q η [1+ α (t-25)]/KI
Wherein η is capacity coefficient of discharging, and corresponding value is between 0.4~1;α is temperature coefficient, and corresponding value is 0.01st, 0.006 or 0.008;K represents safety coefficient, is certain value.
Wherein, actual discharge duration and theoretical discharge duration according to corresponding to the base station storage batteries, determine the base station The step of battery efficiency value, includes:
The ratio of the actual discharge duration and the theoretical discharge duration is obtained, the ratio is defined as the base station Battery efficiency value.
Wherein, the base station storage batteries are assessed according to the base station storage batteries efficiency value, obtains assessment result Step includes:
In the efficiency value previously generated with assessing in information corresponding relation, obtain corresponding to the base station storage batteries efficiency value Assessment result.
Wherein, methods described also includes:
Obtain discharge curve sample corresponding to a critical condition of the base station storage batteries;
According to the relevant parameter of the base station storage batteries and the discharge curve sample, the base station storage batteries are carried out Assess.
Wherein, the step of obtaining discharge curve sample corresponding to a critical condition of the base station storage batteries includes:
Set the first efficiency value corresponding to the base station storage batteries of a critical condition;
Discharge curve corresponding to first efficiency value is obtained, is determined according to discharge curve corresponding to first efficiency value Efficiency characteristic voltage curve under each discharge-rate, the efficiency characteristic voltage curve under each discharge-rate is defined as described Discharge curve sample.
Wherein, according to the relevant parameter of the base station storage batteries and the discharge curve sample, to the base station electric power storage The step of pond is assessed includes:
Discharge-rate corresponding to the base station storage batteries is obtained, and obtains in preset duration and is corresponded under present discharge multiplying power Each testing time point magnitude of voltage;
It is determined that the first electric discharge sample curve corresponding with present discharge multiplying power;
Magnitude of voltage at each testing time point is compared with corresponding magnitude of voltage in the described first electric discharge sample curve Compared with according to the assessment result of the comparative result acquisition base station storage batteries;
Corresponding test interval duration is equal between wherein adjacent testing time point, described in the acquisition of each testing time point Magnitude of voltage corresponding to first electric discharge sample curve.
Wherein, the magnitude of voltage at each testing time point is entered with corresponding magnitude of voltage in the described first electric discharge sample curve Row compares, and is included according to the step of assessment result of the comparative result acquisition base station storage batteries:
In each testing time point, when corresponding magnitude of voltage is less than corresponding voltage in the described first electric discharge sample curve When the quantity of the testing time point of value is more than 1/2 with the ratio of number of total testing time point, the effect of the base station storage batteries is determined It can be worth and be less than the first efficiency value corresponding to critical condition;
In each testing time point, when corresponding magnitude of voltage is more than corresponding voltage in the described first electric discharge sample curve When the quantity of the testing time point of value is more than 1/2 with the ratio of number of total testing time point, the effect of the base station storage batteries is determined It can be worth and be more than the first efficiency value corresponding to critical condition.
The embodiment of the present invention also provides a kind of base station storage batteries appraisal procedure, applied to base station, including:
Obtain the discharge parameter of base station storage batteries;
The discharge parameter of the base station storage batteries is transmitted to mobile terminal so that the mobile terminal determines the base station Battery efficiency value, and the base station storage batteries are assessed.
Wherein, the step of discharge parameter for obtaining base station storage batteries, includes:
Receive the command information that the mobile terminal is sent;
The parameter of the base station storage batteries is set according to the command information, and triggers the base station storage batteries electric discharge;
Gather discharge parameter of the base station storage batteries in discharge process.
The embodiment of the present invention also provides a kind of base station storage batteries apparatus for evaluating, applied to mobile terminal, including:
First acquisition module, for obtaining the discharge parameter of base station storage batteries;
Second acquisition module, for the discharge parameter according to the base station storage batteries, it is corresponding to obtain the base station storage batteries Actual discharge duration and theoretical discharge duration;
Determining module, for the actual discharge duration according to corresponding to the base station storage batteries and theoretical discharge duration, it is determined that The base station storage batteries efficiency value;
First evaluation module, for being assessed according to the base station storage batteries efficiency value the base station storage batteries, obtain To assessment result.
The embodiment of the present invention also provides a kind of base station storage batteries apparatus for evaluating, applied to base station, including:
4th acquisition module, for obtaining the discharge parameter of base station storage batteries;
Transport module, for the discharge parameter of the base station storage batteries to be transmitted to mobile terminal so that described mobile whole End determines the base station storage batteries efficiency value, and the base station storage batteries are assessed.
The beneficial effect of technical scheme of the embodiment of the present invention comprises at least:
Technical solution of the present invention, by obtaining the discharge parameter of base station storage batteries, base station electric power storage is obtained according to discharge parameter The actual discharge duration and theoretical discharge duration in pond, determine that base station storage batteries are imitated based on actual discharge duration and theoretical discharge duration It can be worth, the assessment of base station storage batteries is carried out according to the base station storage batteries efficiency value of acquisition, can be before internet security be met Put, realized by way of remote control and accurate discharge test is loaded in net to battery, safe ready quickly obtains Battery really in net battery online hours efficiency, draws the evaluation result to battery, and work is served according to evaluation result Journey project management.
Brief description of the drawings
Below in conjunction with the accompanying drawing in the embodiment of the present invention, the technical scheme in the embodiment of the present invention is carried out clear, complete Site preparation describes, it is clear that described embodiment is part of the embodiment of the present invention, rather than whole embodiments.Based on this hair Embodiment in bright, the every other implementation that those of ordinary skill in the art are obtained under the premise of creative work is not made Example, belongs to the scope of protection of the invention.
Fig. 1 represents the base station storage batteries appraisal procedure schematic diagram one of the embodiment of the present invention;
Fig. 2 represents voltage, the current curve schematic diagram of the base station storage batteries electric discharge of the embodiment of the present invention;
Fig. 3 represents the test point and efficiency target curve comparison schematic diagram of the embodiment of the present invention;
Fig. 4 represents the base station storage batteries appraisal procedure schematic diagram two of the embodiment of the present invention;
Fig. 5 a represent the base station storage batteries apparatus for evaluating schematic diagram one applied to end side of the embodiment of the present invention;
Fig. 5 b represent the base station storage batteries apparatus for evaluating schematic diagram two applied to end side of the embodiment of the present invention;
Fig. 6 represents the base station storage batteries apparatus for evaluating schematic diagram applied to base station side of the embodiment of the present invention;
Fig. 7 represents the base station storage batteries assessment system schematic diagram of the embodiment of the present invention.
Embodiment
Below in conjunction with the accompanying drawing in the embodiment of the present invention, the technical scheme in the embodiment of the present invention is carried out clear, complete Site preparation describes, it is clear that described embodiment is part of the embodiment of the present invention, rather than whole embodiments.Based on this hair Embodiment in bright, the every other implementation that those of ordinary skill in the art are obtained under the premise of creative work is not made Example, belongs to the scope of protection of the invention.
The embodiment of the present invention provides a kind of base station storage batteries appraisal procedure, applied to mobile terminal, as shown in figure 1, including:
Step 101, the discharge parameter for obtaining base station storage batteries.
Radio communication connects wherein between mobile terminal and base station, by the connection between mobile terminal and base station, can obtain Take discharge parameter of the base station storage batteries in discharge process.
Obtain base station storage batteries discharge parameter process be:Connected by O&M monitor supervision platform and the data acquisition unit of base station side Connect, send command information to data acquisition unit so that data acquisition unit sets the parameter of base station storage batteries simultaneously according to command information Base station storage batteries are made to be discharged;Receive discharge parameter of the base station storage batteries of data acquisition unit transmission in discharge process;Put Electrical parameter comprises at least:Corresponding duration, capacity Q, the load of base station storage batteries are total when base station storage batteries discharge into setting voltage Temperature value t corresponding to electric current I and base station storage batteries.
Mobile terminal is connected with O&M monitor supervision platform first, the data acquisition unit connection of O&M monitor supervision platform and base station side, Wherein here data acquisition unit is FSU (Field Supervision Unit, end station data acquisition unit).Mobile terminal with After O&M monitor supervision platform, O&M monitor supervision platform are connected with data acquisition unit, the connection of mobile terminal and base station is realized.
Now mobile terminal sends command information to the data acquisition unit of base station side, and data acquisition unit is obtaining command information Afterwards, the float charge voltage of base station storage batteries is set according to command information, and float charge voltage here is that the base station that user sets stores The termination discharge voltage of battery.Data acquisition unit needs triggering base station storage batteries to be discharged simultaneously.Discharged in base station storage batteries During, data acquisition unit obtains the discharge parameter of base station storage batteries.Data acquisition unit will be put after discharge parameter is obtained Electrical parameter is sent to mobile terminal.The discharge parameter of wherein data acquisition unit collection comprises at least:Base station storage batteries, which discharge into, to be set Determine corresponding duration during voltage, the capacity Q of base station storage batteries, load total current I and temperature value t corresponding to base station storage batteries.
It should be noted that for the actual performance of accurate evaluation base station storage batteries, needed before data acquisition is carried out Regulatory requirements are made to the data of collection, unification is made to the evaluation mark post of data analysis.In order to meet subsequent data analysis The accurate of evaluation is determined, and the granularity of O&M monitor supervision platform data acquisition is 30 minutes points at present, for evaluation analysis demand And hardware running environment, we compromise, and to take 2 minutes be measurement period, and the data of collection are system time, battery tension, storage Battery current etc..
After the discharge parameter of base station storage batteries is obtained, step 102 is performed.
Step 102, the discharge parameter according to base station storage batteries, obtain actual discharge duration and reason corresponding to base station storage batteries By electric discharge duration.
It is real according to corresponding to discharge parameter determines base station storage batteries after the discharge parameter of data acquisition unit collection is obtained Discharge duration on border.Wherein discharge parameter includes corresponding duration when base station storage batteries discharge into setting voltage, actual obtaining During electric discharge duration, a length of actual discharge duration T1 when base station storage batteries discharge into corresponding during setting voltage is determined.Data acquisition Device opens timing when base station storage batteries are opened and discharged, and stops timing at the end of base station storage batteries, obtains base station storage batteries and puts Corresponding duration during the electric voltage to setting.
When obtaining theoretical discharge duration corresponding to base station storage batteries, according to the capacity Q of base station storage batteries, load total current Temperature value t corresponding to I and base station storage batteries, to determine theoretical discharge duration T2.
The temperature value t wherein according to corresponding to the capacity Q, load total current I and base station storage batteries of base station storage batteries, it is determined that The step of theoretical discharge duration T2, includes:Theoretical discharge duration T2 is determined using default calculation formula:
T2=Q η [1+ α (t-25)]/KI
Wherein η is capacity coefficient of discharging, and corresponding value is between 0.4~1;α is temperature coefficient, and corresponding value is 0.01st, 0.006 or 0.008;K represents safety coefficient, is certain value.
When computational theory discharges duration, the capacity Q, load total current I and base station of the base station storage batteries of acquisition are stored Temperature value t brings into default calculation formula and calculated corresponding to battery.Discharge capacity system in wherein default calculation formula Number η corresponds to a span, it is necessary to discharge duration according to corresponding to base station storage batteries to determine the value of capacity coefficient of discharging. K represents safety coefficient, and corresponding value is 1.25.Temperature coefficient α is according to electric discharge duration come value corresponding to determining.
For capacity coefficient of discharging η, correspond to different values, capacity coefficient of discharging under different electric discharge durations η and electric discharge duration corresponding relation can be found in table 1.
Base station storage batteries electric discharge duration (hour) Capacity coefficient of discharging η
0.5 0.4
1 0.45
2 0.61
3 0.75
4 0.79
5 0.83
6 0.87
7 0.91
8 0.94
9 0.98
10 1
More than 20 1
Table 1
When can be seen that base station storage batteries actual discharge duration increase according to table 1, capacity coefficient of discharging η gradually increases, i.e., Capacity coefficient of discharging η increases with the increase of base station storage batteries actual discharge duration, and capacity coefficient of discharging η is real with base station storage batteries Border electric discharge duration positive correlation, capacity coefficient of discharging η is between 0.4~1.It is more than or equal to 10 in the electric discharge duration of base station storage batteries When, corresponding capacity coefficient of discharging is definite value 1.When being calculated using default calculation formula, it is necessary to according to base station storage batteries Corresponding actual discharge duration, capacity coefficient of discharging η value is determined according to the corresponding relation in table 1.
When obtaining temperature value t corresponding to base station storage batteries, for single base station battery, its corresponding temperature is Determine, choose the actual temperature value of test station and calculated.
For temperature coefficient α, its value is needed depending on the actual discharge duration of base station storage batteries, temperature coefficient α reduces with the increase of base station storage batteries actual discharge duration, temperature coefficient α and base station storage batteries actual discharge duration negative Close.When the actual discharge duration of base station storage batteries is less than or equal to 1h, temperature coefficient α value is 0.01;In base station storage batteries Actual discharge duration when being less than or equal to 10h more than 1h, temperature coefficient α value is 0.008;In actually putting for base station storage batteries When electric duration is more than 10h, temperature coefficient α value is 0.006.
It is determined that after the actual discharge duration and theoretical discharge duration of base station storage batteries, step 103 is performed.
Step 103, actual discharge duration and theoretical discharge duration according to corresponding to base station storage batteries, determine base station storage batteries Efficiency value.
It should be noted that the measuring battery capacity of main flow is all determined with 0.1C standards at present, but stood in existing network Point static current of lcd is different, situation can not be lost directly to evaluate battery efficiency by measuring the accumulator capacity released, In order to there is the appraisal tool of a standard, therefore electric discharge duration latitude is selected to evaluate the efficiency value of existing network battery, this is also The parameter being most closely associated with engineering, so far determines evaluating, i.e., base station storage batteries efficiency value=actual discharge duration/ Theoretical discharge duration.
After actual discharge duration corresponding to base station storage batteries and theoretical discharge duration is obtained, actual discharge duration is obtained With the ratio of theoretical discharge duration, ratio is defined as base station storage batteries efficiency value.
Determine that the process of base station storage batteries efficiency value is according to actual discharge duration T1 and theoretical discharge duration T2:Base station stores Battery efficiency value=actual discharge duration T1/ theoretical discharge durations T2.
After base station storage batteries efficiency value is obtained, step 104 is performed.
Step 104, according to base station storage batteries efficiency value the base station storage batteries are assessed, obtain assessment result.
After base station storage batteries efficiency value is obtained, in the efficiency value previously generated with assessing in information corresponding relation, obtain Assessment result corresponding with base station storage batteries efficiency value is taken, realizes the assessment to base station storage batteries.
In embodiments of the present invention, according to online battery duration efficiency, the matching with the discharge performance of actual battery, It can intuitively judge that situation is lost in battery efficiency, because electric discharge is the actual discharge that is obtained according to actual existing network load testing Duration, therefore our station electric discharge standby duration ability has also directly been reacted, it is to have very strong data convincingness.
Now with the online discharge test data instance of base station storage batteries, apply the technical scheme of the present invention and made a concrete analysis of, As shown in Figure 2.
The specification of base station storage batteries is 150AH/48V, and the average current of test is 10.54A, discharges into the 47V electricity of setting Pressure, take 667 minutes (11.1 hours), therefore a length of 11.1 hours during the actual discharge of current base station battery.Due to current For a certain certain base station battery, environment temperature corresponding to base station storage batteries is 25 DEG C, then t value is 25 DEG C, and η takes It is set to 1, α and takes fixed 0.006, Q 150AH, be calculated during theoretical discharge a length of 11.38 hours, then base station storage batteries efficiency value =actual discharge duration (11.1h) ÷ theoretical discharges duration (11.38h), it is 0.9766 to draw base station storage batteries efficiency value.
Technical solution of the present invention, based on existing network Internet resources and monitoring system, on the premise of network operation safety is met, By implementing remote auto discharge test to battery, by the data collection and analysis of science, output really exists in net battery Line duration efficiency, endurance of storage battery assessment is obtained, battery can be made full use of, and then improve network stabilization, reduced Operation cost, preferably serve project management and commodity network operation.
In the such scheme of the embodiment of the present invention, base station storage batteries efficiency value can truly reflect the loss feelings of battery Condition, but this is based on the parameter for battery draw after deep discharge in 47V, in the real work of battery asset management Middle manager only may only wonder whether this battery pack efficiency situation is less than some given critical condition, rather than accurately Some numerical value, quickly to judge whether that needs scrap replacement.Therefore the method for the embodiment of the present invention also includes:
Obtain discharge curve sample corresponding to a critical condition of base station storage batteries;According to the relevant parameter of base station storage batteries And discharge curve sample, base station storage batteries are assessed.
Wherein the critical condition of base station storage batteries can scrap state to be critical, and the critical state of scrapping here can be this Art personnel setting.When obtaining discharge curve sample corresponding to critical condition, it is necessary first to set a critical condition Base station storage batteries corresponding to the first efficiency value;Discharge curve corresponding to the first efficiency value is obtained, it is corresponding according to the first efficiency value Discharge curve determine efficiency characteristic voltage curve under each discharge-rate, by the efficiency characteristic voltage under each discharge-rate Curve is defined as discharge curve sample.
Specifically, according to the needs in engineering management, setting one is critical to scrap the first efficiency value corresponding to state, collects And the discharge curve (voltage and electric current) of this critical the first efficiency value for scrapping state is accumulated, analyze under various discharge-rates Typical efficiency characteristic voltage curve as efficiency characteristic voltage curve, by the efficiency characteristic voltage curve under each discharge-rate A database is formed, the efficiency characteristic voltage curve under each discharge-rate stored in database is defined as the sample that discharges Curve.
It is determined that electric discharge sample curve after, according to the relevant parameter of base station storage batteries and discharge curve sample, to base The step of battery is assessed of standing includes:
Discharge-rate corresponding to base station storage batteries is obtained, and it is corresponding each under acquisition present discharge multiplying power in preset duration The magnitude of voltage of individual testing time point;It is determined that the first electric discharge sample curve corresponding with present discharge multiplying power;By each testing time Magnitude of voltage at point obtains base station electric power storage compared with corresponding magnitude of voltage in the first electric discharge sample curve according to comparative result The assessment result in pond;Corresponding test interval duration is equal between wherein adjacent testing time point, is obtained in each testing time point Take magnitude of voltage corresponding to the first electric discharge sample curve.
, it is necessary to obtain corresponding discharge-rate for base station storage batteries to be assessed, and selected in preset duration Several testing time points, the interval duration between adjacent testing time point is equal, is obtained for each testing time point corresponding Magnitude of voltage, wherein the interval duration between point of adjacent testing time is equal.
According to the discharge-rate of base station storage batteries to be assessed, determined and current base station battery in the sample curve that discharges Discharge-rate corresponding to first electric discharge sample curve, by the magnitude of voltage at each testing time point of acquisition with first electric discharge mark In this curve at corresponding testing time point corresponding to magnitude of voltage be compared, battery to be assessed and critical report can be judged quickly The magnitude of voltage height difference of useless condition curve sample, by the evaluation to magnitude of voltage corresponding at these testing time points, no Need when battery discharging is completed, it is possible to evaluate base station storage batteries and scrap condition curve sample battery efficiency height with critical Low correction data, and then the more critical evaluation for scrapping state sample battery efficiency height is made to battery.
Wherein, the magnitude of voltage at each testing time point is compared with corresponding magnitude of voltage in the first electric discharge sample curve Compared with when obtaining the assessment result of base station storage batteries according to comparative result:In each testing time point, when corresponding magnitude of voltage is small The quantity of the testing time point of corresponding magnitude of voltage and the ratio of number of total testing time point are big in the first electric discharge sample curve When 1/2, determine that the efficiency value of base station storage batteries is less than the first efficiency value corresponding to critical condition;In each testing time point In, when corresponding magnitude of voltage is more than the quantity of the testing time point of corresponding magnitude of voltage and total test in the first electric discharge sample curve When the ratio of number at time point is more than 1/2, determine that the efficiency value of base station storage batteries is more than the first efficiency value corresponding to critical condition.
Specifically, in each testing time point of battery to be assessed, it is corresponding at the testing time point more than half Magnitude of voltage when being all higher than corresponding magnitude of voltage in the first electric discharge sample curve, it may be determined that the efficiency value of base station storage batteries is more than First efficiency value corresponding to critical condition, now the state of base station storage batteries scrap state better than critical.In battery to be assessed Each testing time point in, magnitude of voltage corresponding at the testing time point more than half is respectively less than the first electric discharge sample curve In corresponding magnitude of voltage when, it may be determined that the efficiency value of base station storage batteries is less than the first efficiency value corresponding to critical condition, now The state of base station storage batteries is inferior to critical scrap state.
As shown in figure 3, it is that the critical battery for scrapping state is imitated to set discharge-rate as the 52% of 0.03C efficiency battery Can curve, the discharge-rate of tested batteries is also 0.03C, often by 30 minutes we compare once with target curve Difference, as shown in table 2, it can be found that the voltage at 6 test points is below target curve, then can be determined that the batteries Efficiency is the object that innovation is needed in our engineerings under 52%.
Table 2
Technical scheme provided in an embodiment of the present invention, in order to meet measuring stability, long-range discharge test data are realized, The data of data acquisition unit memory storage collection, extract reporting terminal after test terminates, are analyzed.It is and provided by the invention complete The method that battery capacity is assessed in new measurement, is assessed according to the ratio of actual discharge duration and theoretical discharge duration, due to Actual discharge duration is to carry out discharge test in linear load according to reality to obtain the duration under true service condition, can more be assessed The actual time of base station operation when actual power-off.
The present invention carries out the discharge test under various discharge-rates for the critical battery for scrapping state, draws critical report Useless condition curve sample.To net battery carry out in net discharge test when, by select several time cycle points, by with facing The voltage-contrast analysis of the same periodic point of condition curve sample is scrapped on boundary, judges the height situation with sample curve, is made quick Judge, meet the demand of technical staff.
The embodiment of the present invention also provides a kind of appraisal procedure of base station storage batteries, applied to base station, as shown in figure 4, including:
Step 401, the discharge parameter for obtaining base station storage batteries.
Wherein when obtaining the discharge parameter of base station storage batteries, it is necessary to receive the command information of mobile terminal transmission;According to Command information sets the parameter of base station storage batteries, and triggers base station storage batteries electric discharge;Base station storage batteries are gathered in discharge process Discharge parameter.
Specifically, when obtaining discharge parameter, base station is configured according to the command information of acquisition to battery, and is being set Base station storage batteries electric discharge is triggered after the completion of putting, the discharge parameter corresponding to collection during base station storage batteries discharge.Wherein, base Stand when being configured according to command information to battery, it is necessary to set the float charge voltage of battery, float charge voltage here is Corresponding termination discharge voltage when stopping discharging for the base station storage batteries of user's setting.Base station side is received by data acquisition unit and moved The command information that dynamic terminal is sent, for the actual performance of accurate evaluation base station storage batteries, needs before data acquisition is carried out Regulatory requirements are made to the data of collection, unification is made to the evaluation mark post of data analysis.In order to meet subsequent data analysis The accurate of evaluation is determined, and the granularity of O&M monitor supervision platform data acquisition is 30 minutes points at present, for evaluation analysis demand And hardware running environment, can compromise take 2 minutes be measurement period.
The discharge parameter of wherein data acquisition unit collection comprises at least:Base station storage batteries discharge into corresponding during setting voltage Duration, the capacity Q of base station storage batteries, load total current I and temperature value t corresponding to base station storage batteries.
Step 402, the discharge parameter of base station storage batteries transmitted to mobile terminal so that mobile terminal determines base station electric power storage Pond efficiency value, and base station storage batteries are assessed.
After the discharge parameter of base station storage batteries is obtained, the discharge parameter of acquisition is sent to mobile terminal so that move Dynamic terminal is assessed according to the efficiency value of the discharge parameter calculation base station battery of acquisition according to efficiency value.
The technical scheme of the embodiment of the present invention, the side of remote control can be passed through on the premise of internet security is met Formula is realized loads accurate discharge test to battery in net, and safe ready quickly obtains battery and really existed in net battery Line duration efficiency, the evaluation result to battery is drawn, project management is served according to evaluation result.
The embodiment of the present invention also provides a kind of base station storage batteries apparatus for evaluating, applied to mobile terminal, as shown in Figure 5 a, bag Include:
First acquisition module 10, for obtaining the discharge parameter of base station storage batteries;
Second acquisition module 20, for the discharge parameter according to base station storage batteries, obtain actual corresponding to base station storage batteries Discharge duration and theoretical discharge duration;
Determining module 30, for the actual discharge duration according to corresponding to base station storage batteries and theoretical discharge duration, determine base Stand battery efficiency value;
First evaluation module 40, for being assessed according to base station storage batteries efficiency value base station storage batteries, assessed As a result.
Wherein, the first acquisition module 10 includes:
Sending submodule 11, for being connected by the data acquisition unit of O&M monitor supervision platform and base station side, to data acquisition Device sends command information so that data acquisition unit sets the parameter of base station storage batteries according to command information and enters base station storage batteries Row electric discharge;
First receiving submodule 12, for receiving electric discharge of the base station storage batteries of data acquisition unit transmission in discharge process Parameter;
Discharge parameter comprises at least:Corresponding duration, the appearance of base station storage batteries when base station storage batteries discharge into setting voltage Measure Q, load total current I and temperature value t corresponding to base station storage batteries.
Wherein, the second acquisition module 20 includes:
First determination sub-module 21, a length of actually put when corresponding during for determining that base station storage batteries discharge into setting voltage Electric duration T1;
Second determination sub-module 22, for the capacity Q according to base station storage batteries, load total current I and base station storage batteries Corresponding temperature value t, determine theoretical discharge duration T2.
Wherein, the second determination sub-module 22 is further used for:
Theoretical discharge duration T2 is determined using default calculation formula:
T2=Q η [1+ α (t-25)]/KI
Wherein η is capacity coefficient of discharging, and corresponding value is between 0.4~1;α is temperature coefficient, and corresponding value is 0.01st, 0.006 or 0.008;K represents safety coefficient, is certain value.
Wherein, the first determining module 30 is further used for:
The ratio of actual discharge duration and theoretical discharge duration is obtained, ratio is defined as base station storage batteries efficiency value.
Wherein, the first evaluation module 40 is further used for:
In the efficiency value previously generated with assessing in information corresponding relation, obtain and assessed corresponding to base station storage batteries efficiency value As a result.
Wherein, as shown in Figure 5 b, the device also includes:
3rd acquisition module 50, for obtaining discharge curve sample corresponding to a critical condition of base station storage batteries;
Second evaluation module 60, for the relevant parameter according to base station storage batteries and discharge curve sample, base station is stored Battery is assessed.
Wherein, the 3rd acquisition module 50 includes:
Submodule 51 is set, for setting the first efficiency value corresponding to the base station storage batteries of a critical condition;
First processing submodule 52, it is corresponding according to the first efficiency value for obtaining discharge curve corresponding to the first efficiency value Discharge curve determine efficiency characteristic voltage curve under each discharge-rate, by the efficiency characteristic voltage under each discharge-rate Curve is defined as discharge curve sample.
Wherein, the second evaluation module 60 includes:
Acquisition submodule 61, for obtaining discharge-rate corresponding to base station storage batteries, and obtained currently in preset duration The magnitude of voltage of corresponding each testing time point under discharge-rate;
3rd determination sub-module 62, for determining the first electric discharge sample curve corresponding with present discharge multiplying power;
Second processing submodule 63, for by the magnitude of voltage at each testing time point with first electric discharge sample curve in it is right The magnitude of voltage answered is compared, and the assessment result of base station storage batteries is obtained according to comparative result;
Corresponding test interval duration is equal between wherein adjacent testing time point, in survey corresponding to each testing time point Try magnitude of voltage corresponding to moment acquisition the first electric discharge sample curve.
Wherein, second processing submodule 63 is further used for:
In each testing time point, when corresponding magnitude of voltage is less than corresponding magnitude of voltage in the first electric discharge sample curve When the quantity of testing time point is more than 1/2 with the ratio of number of total testing time point, determine that the efficiency value of base station storage batteries is less than First efficiency value corresponding to critical condition;
In each testing time point, when corresponding magnitude of voltage is more than corresponding magnitude of voltage in the first electric discharge sample curve When the quantity of testing time point is more than 1/2 with the ratio of number of total testing time point, determine that the efficiency value of base station storage batteries is more than First efficiency value corresponding to critical condition.
The embodiment of the present invention also provides a kind of base station storage batteries apparatus for evaluating, applied to base station, as shown in fig. 6, including:
4th acquisition module 70, for obtaining the discharge parameter of base station storage batteries;
Transport module 80, for the discharge parameter of base station storage batteries to be transmitted to mobile terminal so that mobile terminal determines Base station storage batteries efficiency value, and base station storage batteries are assessed.
Wherein the 4th acquisition module 70 includes:
Second receiving submodule 71, the command information sent for receiving the mobile terminal;
Submodule 72 is set, for setting the parameter of base station storage batteries according to command information, and base station storage batteries is triggered and puts Electricity;
Submodule 73 is gathered, for gathering discharge parameter of the base station storage batteries in discharge process.
Base station storage batteries apparatus for evaluating provided in an embodiment of the present invention, by obtaining the discharge parameter of base station storage batteries, root The actual discharge duration and theoretical discharge duration of base station storage batteries are obtained according to discharge parameter, is put based on actual discharge duration and theory Electric duration determines base station storage batteries efficiency value, and the assessment of base station storage batteries is carried out according to the base station storage batteries efficiency value of acquisition, can On the premise of internet security is met, to realize that loading accurate electric discharge in net to battery surveys by way of remote control Examination, safe ready quickly obtain battery really in net battery online hours efficiency, draw the evaluation result to battery, Project management is served according to evaluation result.
The embodiment of the present invention also provides a kind of base station storage batteries assessment system, as shown in fig. 7, base station storage batteries assessment system It is application layer, key-course, transport layer respectively including three layers.Wherein base station storage batteries assessment system can be arranged at mobile terminal It is interior, mobile terminal, base station storage batteries assessment system and base station information interaction process can also be formed independently of mobile terminal Framework.It is integrated in the embodiment of the present invention with base station storage batteries assessment system in mobile terminal, to be illustrated.
Application layer includes user interactive module, data memory module, data analysis module, data transmit-receive module, key-course Comprising rule-definition module, testing control module and interface protocol, transport layer is mainly network foundation communication module.Application layer mould Block mainly realizes the interactive operation of user and the processing function of data;Key-course mainly realizes the test to remote testing object The definition for protocol integrated test system and the test analysis rule docked between control, object unit;Transport layer mainly realize unit it Between control signal and data-signal transmission.
Currently we are mainly based upon mobile terminal (user interactive module) by network O&M monitor supervision platform, to realize pair Remote base stations battery (remote testing object) carries out discharge test, and in order to make stable testing reliable, we are by upgrading FSU work( Energy (testing control module), FSU is allowed to support the record data of test process being stored in FSU storage (data with the self-defined cycle Memory module) in, after test terminates, data analysis is carried out by data analysis module, data analysis module is operated in user and matched somebody with somebody Put and be operated under guide (rule-definition module), user interactive module is output to finally by data transmit-receive module.Specific step It is rapid as follows:Using mobile terminal by O&M monitor supervision platform connect upper base station end FSU (Field Supervision Unit, End station data acquisition unit), Switching Power Supply relevant parameter is adjusted, the float charge voltage of battery is adjusted to 47V, enters battery Discharge condition, in discharge process, pass through discharge process data (record time, voltage, electric current that base station end FSU gathers battery Parameter, record granularity are adjusted according to fineness requirement, and this test was mainly got ready using 2 minute cycle), by electric discharge The analysis of curve can draw battery backup duration and battery online hours efficiency situation, make and the synthesis of battery is commented Estimate.
When network hardware condition is more improved, service can be realized to long-range, automation, intelligent development evolution The multithreading discharge test management that device is carried out simultaneously to more base stations, realizes the long-range control of discharge of battery, long-range FSU or data, services Device data record, test report such as automatically generate at the function, so as to serve the management of huge power supply assets.
Above-described is the preferred embodiment of the present invention, it should be pointed out that is come for the ordinary person of the art Say, some improvements and modifications can also be made under the premise of principle of the present invention is not departed from, and these improvements and modifications also exist In protection scope of the present invention.

Claims (14)

  1. A kind of 1. base station storage batteries appraisal procedure, applied to mobile terminal, it is characterised in that including:
    Obtain the discharge parameter of base station storage batteries;
    According to the discharge parameter of the base station storage batteries, obtain actual discharge duration and theory corresponding to the base station storage batteries and put Electric duration;
    According to actual discharge duration corresponding to the base station storage batteries and theoretical discharge duration, the base station storage batteries efficiency is determined Value;
    The base station storage batteries are assessed according to the base station storage batteries efficiency value, obtain assessment result.
  2. 2. base station storage batteries appraisal procedure according to claim 1, it is characterised in that obtain the electric discharge ginseng of base station storage batteries Several steps include:
    Connected by O&M monitor supervision platform and the data acquisition unit of base station side, send command information to the data acquisition unit, make The data acquisition unit is obtained to set the parameter of the base station storage batteries according to the command information and enter the base station storage batteries Row electric discharge;
    Receive discharge parameter of the base station storage batteries of the data acquisition unit transmission in discharge process;
    The discharge parameter comprises at least:Corresponding duration, the base station store when the base station storage batteries discharge into setting voltage Temperature value t corresponding to capacity Q, the load total current I of battery and the base station storage batteries.
  3. 3. base station storage batteries appraisal procedure according to claim 2, it is characterised in that according to putting for the base station storage batteries Electrical parameter, the step of obtaining actual discharge duration corresponding to the base station storage batteries and theoretical discharge duration, include:
    Determine a length of actual discharge duration T1 when the base station storage batteries discharge into corresponding during setting voltage;
    According to temperature value t corresponding to the capacity Q, load total current I and the base station storage batteries of base station storage batteries, it is determined that described Theoretical discharge duration T2.
  4. 4. base station storage batteries appraisal procedure according to claim 3, it is characterised in that according to the capacity Q of base station storage batteries, Temperature value t corresponding to load total current I and the base station storage batteries, the step of determining the theoretical discharge duration T2, include:
    The theoretical discharge duration T2 is determined using default calculation formula:
    T2=Q η [1+ α (t-25)]/KI
    Wherein η is capacity coefficient of discharging, and corresponding value is between 0.4~1;α is temperature coefficient, corresponding value be 0.01, 0.006 or 0.008;K represents safety coefficient, is certain value.
  5. 5. base station storage batteries appraisal procedure according to claim 1, it is characterised in that corresponding according to the base station storage batteries Actual discharge duration and theoretical discharge duration, the step of determining the base station storage batteries efficiency value includes:
    The ratio of the actual discharge duration and the theoretical discharge duration is obtained, the ratio is defined as the base station electric power storage Pond efficiency value.
  6. 6. base station storage batteries appraisal procedure according to claim 5, it is characterised in that according to the base station storage batteries efficiency Value is assessed the base station storage batteries, and the step of obtaining assessment result includes:
    In the efficiency value previously generated with assessing in information corresponding relation, obtain and assessed corresponding to the base station storage batteries efficiency value As a result.
  7. 7. base station storage batteries appraisal procedure according to claim 1, it is characterised in that methods described also includes:
    Obtain discharge curve sample corresponding to a critical condition of the base station storage batteries;
    According to the relevant parameter of the base station storage batteries and the discharge curve sample, the base station storage batteries are commented Estimate.
  8. 8. base station storage batteries appraisal procedure according to claim 7, it is characterised in that obtain the one of the base station storage batteries Include corresponding to critical condition the step of discharge curve sample:
    Set the first efficiency value corresponding to the base station storage batteries of a critical condition;
    Discharge curve corresponding to first efficiency value is obtained, is determined according to discharge curve corresponding to first efficiency value each Efficiency characteristic voltage curve under discharge-rate, the efficiency characteristic voltage curve under each discharge-rate is defined as the electric discharge Curve sample.
  9. 9. base station storage batteries appraisal procedure according to claim 7, it is characterised in that according to the phase of the base station storage batteries Related parameter and the discharge curve sample, the step of assessing the base station storage batteries, include:
    Discharge-rate corresponding to the base station storage batteries is obtained, and it is corresponding each under acquisition present discharge multiplying power in preset duration The magnitude of voltage of individual testing time point;
    It is determined that the first electric discharge sample curve corresponding with present discharge multiplying power;
    By the magnitude of voltage at each testing time point compared with corresponding magnitude of voltage in the described first electric discharge sample curve, root The assessment result of the base station storage batteries is obtained according to comparative result;
    Corresponding test interval duration is equal between wherein adjacent testing time point, and described first is obtained in each testing time point Discharge magnitude of voltage corresponding to sample curve.
  10. 10. base station storage batteries appraisal procedure according to claim 9, it is characterised in that at each testing time point Magnitude of voltage obtains the base station compared with corresponding magnitude of voltage in the described first electric discharge sample curve, according to comparative result and stored The step of assessment result of battery, includes:
    In each testing time point, when corresponding magnitude of voltage is less than corresponding magnitude of voltage in the described first electric discharge sample curve When the quantity of testing time point is more than 1/2 with the ratio of number of total testing time point, the efficiency value of the base station storage batteries is determined Less than the first efficiency value corresponding to critical condition;
    In each testing time point, when corresponding magnitude of voltage is more than corresponding magnitude of voltage in the described first electric discharge sample curve When the quantity of testing time point is more than 1/2 with the ratio of number of total testing time point, the efficiency value of the base station storage batteries is determined More than the first efficiency value corresponding to critical condition.
  11. A kind of 11. base station storage batteries appraisal procedure, applied to base station, it is characterised in that including:
    Obtain the discharge parameter of base station storage batteries;
    The discharge parameter of the base station storage batteries is transmitted to mobile terminal so that the mobile terminal determines the base station electric power storage Pond efficiency value, and the base station storage batteries are assessed.
  12. 12. base station storage batteries appraisal procedure according to claim 11, it is characterised in that obtain the electric discharge of base station storage batteries The step of parameter, includes:
    Receive the command information that the mobile terminal is sent;
    The parameter of the base station storage batteries is set according to the command information, and triggers the base station storage batteries electric discharge;
    Gather discharge parameter of the base station storage batteries in discharge process.
  13. A kind of 13. base station storage batteries apparatus for evaluating, applied to mobile terminal, it is characterised in that including:
    First acquisition module, for obtaining the discharge parameter of base station storage batteries;
    Second acquisition module, for the discharge parameter according to the base station storage batteries, obtain real corresponding to the base station storage batteries Discharge duration and theoretical discharge duration on border;
    Determining module, for the actual discharge duration according to corresponding to the base station storage batteries and theoretical discharge duration, it is determined that described Base station storage batteries efficiency value;
    First evaluation module, for being assessed according to the base station storage batteries efficiency value the base station storage batteries, commented Estimate result.
  14. A kind of 14. base station storage batteries apparatus for evaluating, applied to base station, it is characterised in that including:
    4th acquisition module, for obtaining the discharge parameter of base station storage batteries;
    Transport module, for the discharge parameter of the base station storage batteries to be transmitted to mobile terminal so that the mobile terminal is true The fixed base station storage batteries efficiency value, and the base station storage batteries are assessed.
CN201710647180.6A 2017-08-01 2017-08-01 Base station storage battery evaluation method and device Active CN107478997B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710647180.6A CN107478997B (en) 2017-08-01 2017-08-01 Base station storage battery evaluation method and device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710647180.6A CN107478997B (en) 2017-08-01 2017-08-01 Base station storage battery evaluation method and device

Publications (2)

Publication Number Publication Date
CN107478997A true CN107478997A (en) 2017-12-15
CN107478997B CN107478997B (en) 2020-08-18

Family

ID=60598612

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710647180.6A Active CN107478997B (en) 2017-08-01 2017-08-01 Base station storage battery evaluation method and device

Country Status (1)

Country Link
CN (1) CN107478997B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109660360A (en) * 2019-01-31 2019-04-19 中国铁塔股份有限公司 A kind of method of network entry and OMC cloud platform of power & environment supervision equipment
CN111385943A (en) * 2020-04-20 2020-07-07 山东省产品质量检验研究院 Method for testing overall performance of solar LED street lamp system
CN111834677A (en) * 2019-04-18 2020-10-27 东莞新能德科技有限公司 Battery management method, battery management device, battery management system and terminal equipment
CN117452273A (en) * 2023-12-07 2024-01-26 中通维易科技服务有限公司 Battery charge-discharge performance test system for simulating actual use process

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102243724A (en) * 2010-05-10 2011-11-16 宏境科技股份有限公司 Module of automatically calculating storage battery usage times
CN103135063A (en) * 2012-12-21 2013-06-05 郝勇 Detection and monitoring method of lead-acid storage battery
CN104849665A (en) * 2014-02-19 2015-08-19 ***通信集团河北有限公司 Method and device for determining safe discharging time length of storage battery
US20160187428A1 (en) * 2014-12-26 2016-06-30 Samsung Electronics Co., Ltd. Method and apparatus for estimating state of health (SOH) of battery
CN106501735A (en) * 2016-12-29 2017-03-15 北京金风科创风电设备有限公司 Method and device for monitoring battery in uninterruptible power supply
CN106796270A (en) * 2014-10-13 2017-05-31 萨基姆通讯能源及电信联合股份公司 The method of the health status of battery for being estimated as in the equipment of system power supply

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102243724A (en) * 2010-05-10 2011-11-16 宏境科技股份有限公司 Module of automatically calculating storage battery usage times
CN103135063A (en) * 2012-12-21 2013-06-05 郝勇 Detection and monitoring method of lead-acid storage battery
CN104849665A (en) * 2014-02-19 2015-08-19 ***通信集团河北有限公司 Method and device for determining safe discharging time length of storage battery
CN106796270A (en) * 2014-10-13 2017-05-31 萨基姆通讯能源及电信联合股份公司 The method of the health status of battery for being estimated as in the equipment of system power supply
US20160187428A1 (en) * 2014-12-26 2016-06-30 Samsung Electronics Co., Ltd. Method and apparatus for estimating state of health (SOH) of battery
CN106501735A (en) * 2016-12-29 2017-03-15 北京金风科创风电设备有限公司 Method and device for monitoring battery in uninterruptible power supply

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
中华人民共和国***: "《通信电源设备安装工程设计规范YD/T 5040-2005》", 25 July 2006, 北京邮电大学出版社 *
胡元清: "通信基站蓄电池远程实际负载在线核对性容量测试", 《通信电源技术》 *

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109660360A (en) * 2019-01-31 2019-04-19 中国铁塔股份有限公司 A kind of method of network entry and OMC cloud platform of power & environment supervision equipment
CN111834677A (en) * 2019-04-18 2020-10-27 东莞新能德科技有限公司 Battery management method, battery management device, battery management system and terminal equipment
CN111834677B (en) * 2019-04-18 2022-02-22 东莞新能德科技有限公司 Battery management method, battery management device, battery management system and terminal equipment
CN111385943A (en) * 2020-04-20 2020-07-07 山东省产品质量检验研究院 Method for testing overall performance of solar LED street lamp system
CN117452273A (en) * 2023-12-07 2024-01-26 中通维易科技服务有限公司 Battery charge-discharge performance test system for simulating actual use process
CN117452273B (en) * 2023-12-07 2024-05-24 中通维易科技服务有限公司 Battery charge-discharge performance test system for simulating actual use process

Also Published As

Publication number Publication date
CN107478997B (en) 2020-08-18

Similar Documents

Publication Publication Date Title
CN107478997A (en) A kind of base station storage batteries appraisal procedure and device
CN106443461B (en) Battery energy storage system state evaluating method
US9201120B2 (en) Electronic battery tester for testing storage battery
CN101067645B (en) Method for analysing valve control type lead-acid accumulator battery performance
CN104794206B (en) A kind of substation data QA system and method
CN108254696A (en) The health state evaluation method and system of battery
US20170207818A1 (en) Method for differentiating power distribution areas and phases by using voltage characteristics
CN110046145A (en) Expert intelligence Analysis Service platform based on electric flux big data research
CN109061518A (en) A kind of communication storage battery health degree on-line monitoring method
US9910081B2 (en) Performance analysis of power grid monitors
CN106353689A (en) System and method capable of rapidly screening ex-service storage batteries
CN111586729A (en) Three-network signal detection method and system based on metering terminal communication
CN105182122A (en) Fault early warning method of random power supply access equipment
CN203909253U (en) Device for rapidly testing and evaluating storage battery quality state
CN111679215A (en) Lithium battery real-time sorting method, device, equipment and storage medium
CN110908360A (en) Communication power supply monitoring system and high-frequency switching power supply charging module self-checking method
CN115002166B (en) Intelligent battery monitoring and leasing management system and method based on Internet of things
CN104076291A (en) Device and method for rapidly testing and evaluating quality state of storage battery
CN105866726A (en) Portable assessment device based on reliable data of electric energy meter
CN115967169A (en) Test system and method for intelligent distribution transformer terminal
Guo et al. Traffic forecasting for mobile networks with multiplicative seasonal ARIMA models
CN102156260A (en) System and method for evaluating status of oscillation circuit of active high-voltage direct-current switch
CN111308259A (en) Portable evaluation device based on electric automobile fills electric pile reliability data
CN107843870A (en) A kind of method and system for detecting ammeter metering load curve and correcting errors
CN116500451B (en) Online monitoring system for storage battery

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant