CN107461205A - A kind of construction method for expanding brush day drop shaft - Google Patents

A kind of construction method for expanding brush day drop shaft Download PDF

Info

Publication number
CN107461205A
CN107461205A CN201710873405.XA CN201710873405A CN107461205A CN 107461205 A CN107461205 A CN 107461205A CN 201710873405 A CN201710873405 A CN 201710873405A CN 107461205 A CN107461205 A CN 107461205A
Authority
CN
China
Prior art keywords
brush
drop shaft
day drop
construction method
reaming
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710873405.XA
Other languages
Chinese (zh)
Inventor
牛金廷
泮志亮
夏春忠
崔庆凯
黄正全
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Huaye Group Co Ltd
Original Assignee
China Huaye Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Huaye Group Co Ltd filed Critical China Huaye Group Co Ltd
Priority to CN201710873405.XA priority Critical patent/CN107461205A/en
Publication of CN107461205A publication Critical patent/CN107461205A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/10Making by using boring or cutting machines

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Environmental & Geological Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Earth Drilling (AREA)

Abstract

The invention discloses a kind of construction method for expanding brush day drop shaft, comprise the following steps:The first step, pilot hole is outputed vertically along day drop shaft center line;Second step, reaming is carried out by anti-well rig from below to up to the counterbored area around the pilot hole;3rd step, after reaming, blasthole is arranged in the expansion brush region around the counterbored area, by the way that blasthole to be carried out to explosion from below to up to carry out expansion brush to the brush region of expanding, the borehole wall for brushing the day drop shaft is expanded in the brush region of expanding.The construction method solve expand brush speed it is slow, Pass blocks problem, ensure that working security, reduce construction cost.

Description

A kind of construction method for expanding brush day drop shaft
Technical field
The present invention relates to orebody mining technical field, more particularly to a kind of construction method for expanding brush day drop shaft.
Background technology
In mine construction and production phase, people from mine row ventilation shaft, Stope chute, stage casing drop shaft are all a lot.In order to ensure Construction safety is generally constructed using anti-well rig.
When being constructed using mine shaft rising boring, typically can not once it construct to day drop shaft design section, it is also necessary to which forward direction expands brush, will Enlarged-diameter is to design section.As depicted in figs. 1 and 2, job platform 31 is located at the rig cave of the top of day drop shaft 30 to prior art In room 10, using the positive expansion brush region 34 for expanding brush day drop shaft 30, blasthole 35 is arranged vertically on day drop shaft borehole wall;When expanding brush, Inspection sled will be carried out to the float stone of the borehole wall by often expanding one big gun of brush, and need interim spray concrete supporting;Drilling depth is in 3-4m, circulation time Number is more;Therefore prior art is positive expands the brush borehole wall, expand brush speed causes that speed of application is slow, and cyclic advance is limited slowly, and is constructing During bulk rubble it is more, debris is transferred by the pit shaft of minor diameter, it is easy to causes a day Pass blocks, it is hidden to produce safety Suffer from.
The content of the invention
Based on drawbacks described above, solving day drop shaft it is an object of the invention to provide one kind, to expand brush speed slow, is expanding swiped through journey The construction method of the quick expansion brush day drop shaft of middle Pass blocks, this method are quickly expanded from bottom to top using brush is reversely expanded Brush, ensure that speed of application, avoids potential safety hazard caused by Pass blocks, while reduce construction cost.
Above-mentioned purpose is achieved through the following technical solutions:
A kind of construction method for expanding brush day drop shaft, this method comprise the following steps:
The first step, pilot hole is outputed vertically along day drop shaft center line;
Second step, reaming is carried out by anti-well rig from below to up to the counterbored area around the pilot hole;
3rd step, after reaming, blasthole is arranged in the expansion brush region around the counterbored area, by by blasthole from it is lower and To carry out expansion brush to expanding brush region, the borehole wall for brushing the day drop shaft is expanded in the brush region of expanding for upper progress explosion.
Preferably, the top of day drop shaft is rig chamber, and rig chamber connects with brattice way, is lower section below day drop shaft Chamber, in the second step, the workbench of the anti-well rig is placed in the lower section chamber, from bottom to top to be expanded Hole, a large amount of float stones are produced so as to avoid to damage the borehole wall.
Preferably, in the first step, the anti-well rig that is placed in the rig chamber is along day drop shaft center line The lower section chamber is drilled into from top to down, outputs pilot hole, so that the anti-well rig being drilled into the lower section chamber is under And upper carry out second step.Boring direction is must be noted that during drilling, it is impossible to bore folk prescription to.
Preferably, after the drilling rod of the anti-well rig is drilled into lower section chamber, in the second step, in the anti-well rig Drilling rod bottom installation reaming cutterhead, the rock in the counterbored area is shredded by cornish bit disc spins, with from bottom to top Reaming is carried out to counterbored area, at the upper aperture of reaming to the pilot hole.
Preferably, in the second step and the 3rd step, after reaming and expansion brush, waste residue falls into the lower section chamber, passes through Mucking machine transports spoil area to.
Preferably, in the 3rd step, horizontally disposed blasthole in brush region is expanded described from below to up, with from below to up Carry out explosion.
Preferably, the blasthole is horizontally disposed a row or multi-row.
Preferably, explosion is carried out using short-delay blasting method.Short-delay blasting method can reduce explosion to job platform, the borehole wall Destroy, cyclic advance is unrestricted.
It is highly preferred that multiple rows of blasthole uses short-delay blasting, the cyclic advance in vertical direction is unrestricted, circulate into Chi can be 4-10m.
Preferably, pilot hole internal diameter is determined by anti-well rig used, can be 250mm, and day drop shaft external diameter is 2.5-3.5m, The anti-well rig carries out a diameter of 1.2-1.5m of the counterbored area of reaming formation.Using the borehole wall of anti-well drilling machine construction Smooth, float stone is less.
Preferably, in the 3rd step, stable car is arranged in the brattice way, stable car operating side is suspended in the day It is used to arrange blasthole in drop shaft.
Beneficial effect:
The construction method that the present invention expands brush day drop shaft is brushed using reversely expansion, is carried out expansion brush to the borehole wall from bottom to top, safety, is expanded Brush speed is fast, and expands every time after the completion of brush, and mineshaft diameter becomes big, and the debris expanded after brush is transferred by the pit shaft of major diameter, can To release in time, it is not easy to block pit shaft;Reaming is carried out from bottom to top, carries out expansion brush from bottom to top, and level can arrange multiple rows of Blasthole, multiple rows of blasthole carry out a short-delay blasting, and cyclic advance is unrestricted, and drilling depth can reach 10m or so, and step is simple, It ensure that speed of application;And expanding brush construction every time all to carry out in the former borehole wall, the former general smoother of the borehole wall, float stone is less, Security is higher;Reduce gib process during brush is expanded simultaneously, save cost.
Brief description of the drawings
Fig. 1 is the positive construction schematic diagram for expanding brush day drop shaft of prior art;
Fig. 2 is the diagrammatic cross-section at A-A in Fig. 1;
Use state figure when Fig. 3 is drop shaft of the present invention anti-well rig reaming;
Fig. 4 is the diagrammatic cross-section at A-A in Fig. 3;
Fig. 5 is the construction schematic diagram of the invention for reversely expanding brush day drop shaft;
Fig. 6 is the diagrammatic cross-section at A-A in Fig. 5.
Embodiment
Below in conjunction with the accompanying drawing in the embodiment of the present invention, the technical scheme in the embodiment of the present invention is carried out clear, complete Site preparation describes:
As seen in figures 3-6, the present invention provides a kind of construction method for expanding brush day drop shaft, and this method comprises the following steps:The One step, as shown in Figure 3-4, pilot hole 32 is outputed vertically downwards along the center line of day drop shaft 30;Second step, as shown in Figure 3-4, pass through Anti- well rig 80 carries out reaming from below to up to the counterbored area 33 around the pilot hole 32;3rd step, as seen in figs. 5-6, After reaming, blasthole 35 is arranged in the expansion brush region 34 around counterbored area 33, by the way that blasthole 35 is carried out into explosion from below to up To carry out expansion brush to expanding brush region 34, expand the borehole wall for brushing day drop shaft 30 from expansion brush region 34.
The present invention is used reversely to expand and brushed, and carries out expansion brush to the borehole wall from bottom to top, and safety, expansion brush speed is fast, and expands every time After the completion of brush, mineshaft diameter becomes big, and the debris expanded after brush is transferred by the pit shaft of major diameter, it is not easy to blocks pit shaft.
The present embodiment, the top of day drop shaft 30 is rig chamber 10, and rig chamber 10 connects with brattice way 11, day drop shaft 30 lower sections are lower section chamber 20, in second step, in the workbench chamber 20 placed below of anti-well rig 80, with from bottom to top Carry out ream operation.In the present embodiment, the design external diameter of day drop shaft 30 is 3.0m, and the design internal diameter of day drop shaft 30 is 2.5m; The anti-well rig 80 that counter bore diameter is 1.2-1.5m is employed during construction day drop shaft 30, further, counter bore diameter 1.2m, is expanded After hole, using the reverse brush drop shaft that expands to intended diameter 2.5m, the pit shaft borehole wall that anti-well rig 80 is constructed is smooth, float stone compared with Few, waste residue 60 falls directly into lower section chamber 20, and spoil area is transported to by mucking machine.
First, in the first step, the anti-well rig 80 being placed in rig chamber 10 is along the center line of day drop shaft 30 to next time Property get into lower section chamber 20, output internal diameter be 250mm pilot hole 32, bore pilot hole 32 when must be noted that boring direction, it is impossible to Bore folk prescription to;In second step, after the drilling rod 81 of anti-well rig 80 is drilled into lower section chamber 20, reaming is installed in the bottom of drilling rod 81 Cutterhead 82, the rock in chopping counterbored area 33 is rotated by reaming cutterhead 82, to the counterbored area around the pilot hole 32 33 carry out reaming from bottom to top, and reaming is at aperture, the waste residue 60 after reaming falls into lower section chamber 20, leads on the pilot hole 32 Cross mucking machine and transport spoil area to;After reaming, then region 34 is brushed to expansion in brush region 34 is expanded from below to up and carries out expanding brush simultaneously cloth Horizontal blasthole 35 is put, stable car 90 is fixed in brattice way 11, the operating side of stable car 90 is suspended in day drop shaft 30, carries out blasthole Arrangement, be easy to expand brushing and put blasthole 35 and operate.
In the present embodiment, expansion brush is carried out using region 34 is brushed to expansion from below to up, from below to up horizontally disposed blasthole 35, from Lower and upper carry out explosion;The blasthole 35 can once arrange a row or multi-row;Job platform, the borehole wall are broken to reduce explosion It is bad, explosion is carried out using short-delay blasting method, blasting sequence is carried out successively from below to up, and cyclic advance is unrestricted;It is multiple rows of described Blasthole 35 uses short-delay blasting so that cyclic advance is up to 10m or so.The embodiment step is simple, and expansion brush speed is fast, security It is higher, and expand every time after the completion of brush, mineshaft diameter becomes big, and the debris expanded after brush is transferred by the pit shaft of major diameter, it is not easy to Block pit shaft;Reduce gib process during brush is expanded simultaneously, save cost.
The preferred embodiment of the present invention is described above in association with accompanying drawing, but the invention is not limited in above-mentioned specific Embodiment, above-mentioned embodiment is only schematical, is not restricted, one of ordinary skill in the art Under the enlightenment of the present invention, in the case of present inventive concept and scope of the claimed protection is not departed from, it can also make very Multi-form, these are belonged within the scope of the present invention.

Claims (10)

1. a kind of construction method for expanding brush day drop shaft, comprises the following steps:
The first step, pilot hole is outputed vertically along day drop shaft center line;
Second step, reaming is carried out by anti-well rig from below to up to the counterbored area around the pilot hole;
3rd step, after reaming, blasthole is arranged in the expansion brush region around the counterbored area, by the way that blasthole is entered from below to up To carry out expansion brush to the brush region of expanding, the borehole wall for brushing the day drop shaft is expanded in the brush region of expanding for row explosion.
2. expand the construction method of brush day drop shaft as claimed in claim 1, it is characterised in that the top of day drop shaft is rig cave Room, rig chamber connect with brattice way, are lower section chamber below day drop shaft, in the second step, the anti-well rig Workbench is placed in the lower section chamber, from bottom to top to carry out reaming.
3. expand the construction method of brush day drop shaft as claimed in claim 2, it is characterised in that in the first step, be placed in institute The anti-well rig stated in rig chamber is drilled into the lower section chamber from top to down along day drop shaft center line, outputs pilot hole, So that the anti-well rig being drilled into the lower section chamber carries out second step from below to up.
4. expand the construction method of brush day drop shaft as claimed in claim 3, it is characterised in that the drilling rod of the anti-well rig is drilled into After the chamber of lower section, in the second step, the bottom installation reaming cutterhead of the drilling rod of the anti-well rig, spiraled by cornish bit Turn the rock in the chopping counterbored area, to carry out reaming to counterbored area from bottom to top, reaming is upper to the pilot hole At aperture.
5. expand the construction method of brush day drop shaft as claimed in claim 4, it is characterised in that in the second step and the 3rd step In, after reaming and expansion brush, waste residue falls into the lower section chamber, and spoil area is transported to by mucking machine.
6. expand the construction method of brush day drop shaft as claimed in claim 1, it is characterised in that in the 3rd step, from lower On it is described expand brush region in horizontally disposed blasthole, to carry out explosion from below to up.
7. expand the construction method of brush day drop shaft as claimed in claim 6, it is characterised in that the horizontally disposed row of the blasthole or It is multiple rows of.
8. expand the construction method of brush day drop shaft as claimed in claim 7, it is characterised in that multiple rows of blasthole is quick-fried using elementary errors It is broken, cyclic advance 4-10m.
9. the construction method for expanding brush day drop shaft as described in claim any one of 1-8, it is characterised in that the anti-well rig enters The a diameter of 1.2-1.5m for the counterbored area that row reaming is formed.
10. expand the construction method of brush day drop shaft as claimed in claim 2, it is characterised in that in the 3rd step, on top Stable car is arranged in tunnel, stable car operating side, which is suspended in the day drop shaft, to be used to arrange blasthole.
CN201710873405.XA 2017-09-25 2017-09-25 A kind of construction method for expanding brush day drop shaft Pending CN107461205A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710873405.XA CN107461205A (en) 2017-09-25 2017-09-25 A kind of construction method for expanding brush day drop shaft

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710873405.XA CN107461205A (en) 2017-09-25 2017-09-25 A kind of construction method for expanding brush day drop shaft

Publications (1)

Publication Number Publication Date
CN107461205A true CN107461205A (en) 2017-12-12

Family

ID=60553108

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710873405.XA Pending CN107461205A (en) 2017-09-25 2017-09-25 A kind of construction method for expanding brush day drop shaft

Country Status (1)

Country Link
CN (1) CN107461205A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108331612A (en) * 2018-01-31 2018-07-27 山东烟台鑫泰黄金矿业有限责任公司 A kind of cutting method of ore pass
CN108343455A (en) * 2017-12-28 2018-07-31 浙江省隧道工程公司 Binary channels underground chamber construction method
CN108915693A (en) * 2018-06-25 2018-11-30 贵州开磷集团股份有限公司 A kind of construction method of the ladder pipeline well on inclined orebody
CN110107301A (en) * 2019-04-09 2019-08-09 北京中煤矿山工程有限公司 A kind of mechanical rock breaking sinking method of positive-reversed-positive three-level drilling
CN110541711A (en) * 2019-09-03 2019-12-06 山东唐口煤业有限公司 method for strengthening underground chamber brush
CN112412502A (en) * 2020-12-16 2021-02-26 中铁四局集团有限公司 Excavation method for one-step blasting forming of cave depot tank body

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103184872A (en) * 2013-03-20 2013-07-03 中国水利水电第十四工程局有限公司 Construction method of one-time excavation for large-section vertical well
CN103835661A (en) * 2013-11-06 2014-06-04 北京中煤矿山工程有限公司 Local excavation pre-supporting raise boring technology
CN104110261A (en) * 2014-06-13 2014-10-22 中国水利水电第十二工程局有限公司 Construction method for expanding excavation of shaft at one time in reverse mode
CN104747195A (en) * 2015-01-21 2015-07-01 安徽金日盛矿业有限责任公司 Ore pass enlargement construction method
CN105401946A (en) * 2015-10-27 2016-03-16 中国水利水电第三工程局有限公司 Reverse blasting excavation method of shaft and pilot shaft

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103184872A (en) * 2013-03-20 2013-07-03 中国水利水电第十四工程局有限公司 Construction method of one-time excavation for large-section vertical well
CN103835661A (en) * 2013-11-06 2014-06-04 北京中煤矿山工程有限公司 Local excavation pre-supporting raise boring technology
CN104110261A (en) * 2014-06-13 2014-10-22 中国水利水电第十二工程局有限公司 Construction method for expanding excavation of shaft at one time in reverse mode
CN104747195A (en) * 2015-01-21 2015-07-01 安徽金日盛矿业有限责任公司 Ore pass enlargement construction method
CN105401946A (en) * 2015-10-27 2016-03-16 中国水利水电第三工程局有限公司 Reverse blasting excavation method of shaft and pilot shaft

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
王惠庆等: "铜厂埂磷矿大断面高溜井人机结合施工工艺", 《现代矿业》 *

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108343455A (en) * 2017-12-28 2018-07-31 浙江省隧道工程公司 Binary channels underground chamber construction method
CN108331612A (en) * 2018-01-31 2018-07-27 山东烟台鑫泰黄金矿业有限责任公司 A kind of cutting method of ore pass
CN108915693A (en) * 2018-06-25 2018-11-30 贵州开磷集团股份有限公司 A kind of construction method of the ladder pipeline well on inclined orebody
CN110107301A (en) * 2019-04-09 2019-08-09 北京中煤矿山工程有限公司 A kind of mechanical rock breaking sinking method of positive-reversed-positive three-level drilling
CN110541711A (en) * 2019-09-03 2019-12-06 山东唐口煤业有限公司 method for strengthening underground chamber brush
CN112412502A (en) * 2020-12-16 2021-02-26 中铁四局集团有限公司 Excavation method for one-step blasting forming of cave depot tank body

Similar Documents

Publication Publication Date Title
CN107461205A (en) A kind of construction method for expanding brush day drop shaft
CN104847355B (en) Continuous mining method for hollow ground of medium-thickness steeply inclined ore body
CN109341449B (en) Sectional control blasting well completion method for one-time rock drilling of large-section high raise
CN104153780B (en) Lean ore body sublevel caving stays ore deposit continuous stoping technique
Liu et al. Key technologies of drilling process with raise boring method
CN113153292B (en) Method for quickly crossing hard rock fault by hydraulic fracturing of underground coal face of coal mine
CN111364997A (en) Upward drift-caving combined mining method
US20230134275A1 (en) Mining method
CN106285731A (en) The little courtyard radiant type of a kind of high Large chamber and the mixed construction method of step
CN114233295B (en) One-lane multi-purpose mining method
CN109630131B (en) Underground chamber construction method
CN111005721A (en) Mining method of steeply inclined medium-thickness ore body
CN104612692A (en) Following-forming continuous-filling mining method for segmented ore-caving bottom structure
CN104632224B (en) Shortwall hydraulic mining method along strike
CN101737051A (en) Covering layer forming method of blind ore bodies
CN113653490A (en) Ground control method for rock burst of close-distance coal seam group
US20130127231A1 (en) Hydraulic Mining System for Tabular Orebodies Utilising Directional Drilling
CN104343454A (en) Mechanical point-column type chamber and pillar method
CN113847029B (en) Surrounding column extraction method for underground mine high and large point column
Paredes et al. Undercutless caving at Newcrest: towards the next generation of cave mining
CN114856563B (en) Dead-weight ore-falling mining method for deep-hole pre-cracked ore in downward stage of broken ore rock
CN103982184A (en) Falling ore directional slip control method adopting underground mine bottom-pillar-free caving mining method
CN111749693B (en) Method for constructing and blocking deep hole in large fault section by sill pillar-free sublevel caving method
CN108547615B (en) Method for mining in complex ore body group by using trackless equipment
RU2312990C1 (en) Method to protect rock bump hazardous flat-lying seams against impacts

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20171212

RJ01 Rejection of invention patent application after publication