CN107447722A - A kind of river levee assembled material - Google Patents

A kind of river levee assembled material Download PDF

Info

Publication number
CN107447722A
CN107447722A CN201710686492.8A CN201710686492A CN107447722A CN 107447722 A CN107447722 A CN 107447722A CN 201710686492 A CN201710686492 A CN 201710686492A CN 107447722 A CN107447722 A CN 107447722A
Authority
CN
China
Prior art keywords
river levee
plate
groove
assembled material
main boards
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710686492.8A
Other languages
Chinese (zh)
Other versions
CN107447722B (en
Inventor
胡光福
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Yedun Fire Safety Technology Co ltd
Original Assignee
Yue Dao Industrial (shanghai) Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yue Dao Industrial (shanghai) Co Ltd filed Critical Yue Dao Industrial (shanghai) Co Ltd
Priority to CN201710686492.8A priority Critical patent/CN107447722B/en
Publication of CN107447722A publication Critical patent/CN107447722A/en
Application granted granted Critical
Publication of CN107447722B publication Critical patent/CN107447722B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/06Moles; Piers; Quays; Quay walls; Groynes; Breakwaters ; Wave dissipating walls; Quay equipment
    • E02B3/066Quays

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Revetment (AREA)

Abstract

A kind of river levee assembled material, including two parallel main boards, connected between the both ends of two main boards by connecting plate, at least one hole is provided with connecting plate, at least one supporting plate is connected with two main boards, the bearing of trend of supporting plate is consistent with the direction of main board, and at least one hole is provided with supporting plate;A first groove is respectively provided with one end outer surface of two main boards, first fixture block, the first fixture block energy clamping first groove are respectively provided with the other end inner surface of two main boards.Beneficial effects of the present invention:River levee is constructed flexibly simply, and product weight is light, is reduced construction manpower, is shortened the engineering time, cost is low, safe;River levee has very high steadiness, prevents soil loss, and can beautify river course, convenient to clean river levee;Solve the problems, such as damage hill exploitation rock and fall trees to make template, protect ecological environment.

Description

A kind of river levee assembled material
Technical field
The present invention relates to a kind of river levee assembled material, belong to hydraulic engineering technical field.
Background technology
River levee filling Construction Technique is the key technology in water conservancy construction, the surveying setting-out of GPRS river levee filling construction, Do foundation excavation well emphatically, flood dam fills, the innovation of slope trimming key technology, only in this way river levee could be filled conscientiously Construction technology is fulfilled, and reaches the purpose brought benefits to the people.
China is built using soil property river levee or the concrete river levee of large rock mass and wooden model as river course dash more at present Thing.In existing river levee work progress, it usually needs river is drained.Made using the concrete river levee of large rock mass and wooden model For river course water retaining structure when, exploitation rock failure mechanism of rock massif, in order to make the template felling woods, destroy ecological environment, together When expend a large amount of manpower and materials, cost is high, and river levee landslide easily occurs in existing river levee large rock mass, easily sends out security incident. Soil property river levee has the features such as to ground strong adaptability, application safety and less investment.But soil property river levee is constructed using measurement Unwrapping wire-foundation excavation-constructs the mode of dykes and dams, and process is complicated, and consumption manpower is big.To be laid during surveying setting-out before engineering construction Good SURVEYING CONTROL NETWORK, permanent coordinate stake and horizontal reference point stake are made into each control point, and take corresponding safeguard measure, with It is tamper-proof.Three supplies and one leveling are carried out, terminate water supply and drainage pipeline, temporary electricity route arrangement before engineering construction, to ensure Meet construction production, living needs.Live temporary construction road will be arranged along Around, ensure levee foundation not ponding, and carrying out The corresponding measure of draining.The foundation excavation stage needs staged and layered is averagely lower to dig, and deburring and clear bottom, whether to check position repeatedly Accurately, it is impossible to which mistake is dug or backbreak, it is desirable to high, labor intensive and time.
The content of the invention
The present invention is filled with solving existing river levee in view of the deficienciess of the prior art, provide a kind of river levee assembled material Ecological environment to be destroyed in construction, expends a large amount of manpower and materials, cost is high, and the problem of easy hair security incident.
The technical scheme that the present invention solves above-mentioned technical problem is as follows:A kind of river levee assembled material, including two parallel Main board, connected by connecting plate between the both ends of two main boards, at least one hole is provided with the connecting plate, At least one supporting plate is connected with two main boards, the bearing of trend of the supporting plate is consistent with the direction of main board, At least one hole is provided with the supporting plate;It is respectively provided with a first groove on one end outer surface of two main boards, two First fixture block, the first fixture block energy clamping first groove are respectively provided with the other end inner surface of the individual main board.
Beneficial effects of the present invention:The river levee assembled material is easy to assembly quick, according to terrain or can use needs Assembled, it is not necessary to river is drained, directly may be inserted into river and then concrete perfusion.Specifically utilize the first fixture block card First groove on tight adjacent body plate is combined.Main board provides the stop supported for constructing for river bed, can be to main body Joints cement or concrete in plate, river levee are built quick and convenient.The height and thickness of assembled material can construct according to actual river course Need to be produced, there is very high flexibility.Supporting plate can further provide for supporting, and improve durability, the stability of river levee And service life.Concrete can carry out shunting from the hole in supporting plate and reach overall filling, reach and be integrally formed, river levee is more firm Gu.The inner space of whole river levee assembled material is sized for, and carries out pouring for appropriate concrete, and ensure that whole construct The stability and fastness of system.
The present invention is further arranged to, and support bar is connected between two adjacent supporting plates.
Pass through above-mentioned technical proposal, internal structure of the support bar further for the river levee assembled material provide support, enter one Step ensures structural stability during casting concrete.
The present invention is further arranged to, and the cross section of the supporting plate is plane, V-shape or arc, preferably V-shape or Arc.
When the supporting plate of Pass through above-mentioned technical proposal, V-shape or arc is beneficial to later stage casting concrete, concrete perfusion arrives Other spaces, it ensure that concreting fully and be uniformly distributed, the firm river levee being integrally formed.
The present invention is further arranged to, in addition to cover plate, and cover plate includes sealing plate and is connected to sealing plate same side two The clamp at end, latch, latch energy clamping first groove are provided with the inside of clamp.
Pass through above-mentioned technical proposal, due to being provided with hole on the connecting plate at the both ends of main board, sealed when pouring using cover plate Block end.Cover plate is stuck in one end of two main boards, passes through latch and first groove clamping fixed.
The present invention is further arranged to, in addition to Corner Link, and the Corner Link is parallelepiped, wherein two Individual adjacent surface is sealing, and another two is provided with hole on surface;The second fixture block is provided with the both sides for opening a porose surface, Second fixture block energy clamping first groove;Second groove is provided with the both sides for opening another porose surface, second groove is by first Fixture block clamping.
Pass through above-mentioned technical proposal, the adjacent surface of two of which are arranged to sealing, and one is to provide support, second, envelope Stifled concrete.Another two is provided with hole on surface, for into concrete, the Corner Link and connecting material being fixed and formed surely Fixed one.Corner Link realizes the angled connection of multiple river levee assembled materials, and the big I of connection angle is connected by corner The angle-determining of fitting.
The present invention is further arranged to, and is connected between two adjacent sealing surfaces consistent with Corner Link bearing of trend Baffle plate, form triangular prism between the baffle plate and two sealing surfaces.
Pass through above-mentioned technical proposal, triangular prism have good stability, can according to be actually needed choose whether to pour it is mixed Solidifying soil.Making for concrete can not be saved when the pressure that dike assembled material needs to bear is smaller to being poured in triangular prism Dosage.
The present invention is further arranged to, and the quantity of the baffle plate is 1-3.
Pass through above-mentioned technical proposal, the quantity for increasing baffle plate add support force and stability, can without or reduce Concrete pours.
The present invention is further arranged to, each part of the river levee construction material, such as supporting plate, the first fixture block, Two fixture blocks, support bar, the material of latch can be various materials, preferably PVC material, and environment-protecting and non-poisonous, product quality is light, can save Manpower, shorten the engineering time.
In summary, the invention has the advantages that:
(1) construction material height and thickness can according to actual river course construct needs be produced, this for actual production not Stack pile, the product of different length have very high flexibility;
(2) product weight can gently substantially reduce construction manpower, and shorten the engineering time, substantially reduce cost, Reduce the generation of security incident;
(3) river levee has very high steadiness, prevents soil loss, has beautification function to river course, is not in weathering Phenomenon, river levee can be cleaned conveniently;
(4) Construction Mode of the concrete river levee of original large rock mass and wooden model is changed, solves damage hill Exploitation rock and the problem of making template of falling trees, protect ecological environment.
Brief description of the drawings
Technical scheme in order to illustrate the embodiments of the present invention more clearly, it will use below required in embodiment Accompanying drawing is briefly described, it should be apparent that, drawings in the following description are only some embodiments of the present invention, for this area For those of ordinary skill, on the premise of not paying creative work, other accompanying drawings can also be obtained according to these accompanying drawings.
Fig. 1 is the structural representation of the embodiment of the present invention;
Fig. 2 is the structural representation of the embodiment of the present invention;
Fig. 3 is the structural representation of Corner Link;
Fig. 4 is the structural representation of cover plate;
Fig. 5 is the structural representation after the present invention is assembled in embodiment.
Wherein, 1, main board;2nd, baffle plate;3rd, connecting plate;4th, supporting plate;5th, first groove;6th, the first fixture block;7th, support Bar;8th, cover plate;9th, sealing plate;10th, clamp;11st, latch;12nd, Corner Link;13rd, the second fixture block;14th, second groove.
Embodiment
Below in conjunction with the accompanying drawing in the embodiment of the present invention, the technical scheme in the embodiment of the present invention is carried out clear, complete Site preparation describes, it is clear that described embodiment is only part of the embodiment of the present invention, rather than whole embodiments.It is based on Embodiment in the present invention, those of ordinary skill in the art are obtained every other under the premise of creative work is not made Embodiment, belong to the scope of protection of the invention.
As shown in figure 1, a kind of river levee assembled material, including two parallel main boards 1, the both ends of two main boards 1 it Between connected by connecting plate 3, at least one hole is provided with connecting plate 3, at least one support is connected with two main boards 1 Plate 4, the bearing of trend of supporting plate 4 is consistent with the direction of main board 1, and at least one hole is provided with supporting plate 4;Two main boards 1 One end outer surface on be respectively provided with a first groove 5, one first card is respectively provided with the other end inner surface of two main boards 1 Block 6, the first fixture block 6 can clamping first grooves 5.
In order to further improve the inside fastness of river levee assembled material, in one embodiment of the invention, such as Fig. 2 institutes Show, support bar 7 is connected between two adjacent supporting plates 4.Supporting plate 4 is shaped as plane, V-shape or arc, excellent Select V-shape or arc.
For blocking concrete, in one embodiment of the invention, in addition to cover plate 8, as shown in figure 4, cover plate 8 includes Sealing plate 9 and the clamp 10 for being connected to the same side both ends of sealing plate 9, latch 11 is provided with the inner side of clamp 10, latch 11 can block Tight first groove 5.
In order to adapt to the use needs of the different angle of different terrain, using Corner Link 12 by river levee assembled material group Dress, as shown in figure 3, Corner Link 12 is parallelepiped, the adjacent surface of two of which is the structure of Corner Link 12 Sealing, another two is provided with hole on surface;The second fixture block 13, the energy of the second fixture block 13 are provided with the both sides for opening a porose surface Clamping first groove 5;Second groove 14 is provided with the both sides for opening another porose surface, second groove 14 is by the first fixture block 6 Clamping.In another embodiment of the present invention, it is connected between two adjacent sealing surfaces and the side of extension of Corner Link 12 To consistent baffle plate 2, keep off between 2 plates and two sealing surfaces and form triangular prism.The quantity of baffle plate 2 is 1-3.
As an example, Fig. 5 is the structural representation after the present invention is assembled, using multiple river levee assembled materials Progress linearly constructs river levee, and the river levee that can carry out with reference to Corner Link 12 different bending angles is constructed.
The existing efficiency constructed with large rock mass is very low, can only be constructed 10 meters per work daily, and utilizes quick group The New Building Materials of river levee are filled, can be constructed for each person every day 50 meters.
Presently preferred embodiments of the present invention is these are only, is not intended to limit the invention, it is all in the spirit and principles in the present invention Within, any modification, equivalent substitution and improvements made etc., it should be included in the scope of the protection.

Claims (7)

  1. A kind of 1. river levee assembled material, it is characterised in that:Including two parallel main boards, the both ends of two main boards it Between connected by connecting plate, at least one hole is provided with the connecting plate, at least one is connected with two main boards Individual supporting plate, the bearing of trend of the supporting plate is consistent with the direction of main board, and at least one hole is provided with the supporting plate;Two It is respectively provided with a first groove on one end outer surface of the individual main board, it is each on the other end inner surface of two main boards Provided with first fixture block.
  2. A kind of 2. river levee assembled material according to claim 1, it is characterised in that:Between two adjacent supporting plates It is connected with support bar.
  3. A kind of 3. river levee assembled material according to claim 1 or 2, it is characterised in that:The cross section of the supporting plate is Plane, V-shape or arc.
  4. A kind of 4. river levee assembled material according to claim 1, it is characterised in that:Also include cover plate, cover plate includes sealing Plate and the clamp for being connected to sealing plate same side both ends, are provided with latch, latch energy clamping first groove on the inside of clamp.
  5. A kind of 5. river levee assembled material according to claim 1, it is characterised in that:Also include Corner Link, described turn Angle connector is parallelepiped, and the adjacent surface of two of which is sealing, and another two is provided with hole on surface;It is porose opening The both sides on one surface are provided with the second fixture block, the second fixture block energy clamping first groove;Opening the both sides on another porose surface Provided with second groove, second groove is by the first fixture block clamping.
  6. A kind of 6. river levee assembled material according to claim 5, it is characterised in that:Connected between two adjacent sealing surfaces There is the baffle plate consistent with delivering connector bearing of trend, triangular prism is formed between the baffle plate and two sealing surfaces.
  7. A kind of 7. river levee assembled material according to claim 6, it is characterised in that:The quantity of the baffle plate is 1-3.
CN201710686492.8A 2017-08-11 2017-08-11 River levee assembly device Expired - Fee Related CN107447722B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710686492.8A CN107447722B (en) 2017-08-11 2017-08-11 River levee assembly device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710686492.8A CN107447722B (en) 2017-08-11 2017-08-11 River levee assembly device

Publications (2)

Publication Number Publication Date
CN107447722A true CN107447722A (en) 2017-12-08
CN107447722B CN107447722B (en) 2021-01-19

Family

ID=60492099

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710686492.8A Expired - Fee Related CN107447722B (en) 2017-08-11 2017-08-11 River levee assembly device

Country Status (1)

Country Link
CN (1) CN107447722B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108505687A (en) * 2018-06-05 2018-09-07 江苏凤腾塑料有限公司 A kind of concrete strengthening device of PVC extrusion moldings

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5508306B2 (en) * 2011-02-01 2014-05-28 大成建設株式会社 Levitation breakwater
CN105464271A (en) * 2015-01-17 2016-04-06 刘绮琪 Section connecting and assembling mechanism
CN106368167A (en) * 2016-09-22 2017-02-01 杭州中车车辆有限公司 Anti-flood combined type baffle mechanism
CN206408583U (en) * 2016-12-01 2017-08-15 天津港第四港埠有限公司 A kind of ground anti-skid structure

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5508306B2 (en) * 2011-02-01 2014-05-28 大成建設株式会社 Levitation breakwater
CN105464271A (en) * 2015-01-17 2016-04-06 刘绮琪 Section connecting and assembling mechanism
CN106368167A (en) * 2016-09-22 2017-02-01 杭州中车车辆有限公司 Anti-flood combined type baffle mechanism
CN206408583U (en) * 2016-12-01 2017-08-15 天津港第四港埠有限公司 A kind of ground anti-skid structure

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108505687A (en) * 2018-06-05 2018-09-07 江苏凤腾塑料有限公司 A kind of concrete strengthening device of PVC extrusion moldings

Also Published As

Publication number Publication date
CN107447722B (en) 2021-01-19

Similar Documents

Publication Publication Date Title
CN202466604U (en) Self-locking protection brick
CN103422501B (en) Anti-floating anchor rod structure in sand seam geology and construction method thereof
CN210482200U (en) Ecological bank protection structure of high and steep river course bank slope
CN108661069A (en) Close on the wall piled anchor composite structure and method of old Retaining Wall Reinforcement under the load of river road surface
CN102304926B (en) Method for fixing telegraph pole on wetland
CN210975741U (en) Reinforced structure of earth and rockfill dam
CN210857112U (en) Hidden water conservancy slope protection structure
CN111576454A (en) Combined protective structure for side slope retaining wall and steel pipe pile and construction method thereof
CN113250240A (en) Combined side slope protection structure and process of layered net type gabion and concrete
CN112281868A (en) Support system and method combining temporary foundation pit support and permanent slope support
CN103334450B (en) Construction method of pile precast slab retaining wall with drainage ditch
CN204491641U (en) Waterwall unit and self-balancing cofferdam structure
CN107447722A (en) A kind of river levee assembled material
CN203429645U (en) Slope support structure assembly
CN203821306U (en) Flexible anti-scour protection pad
CN110295573A (en) Adapt to the channel revetment project post-evaluation structure of construction time severe hydrometeorological condition
CN213682159U (en) Ecological compound slope protection
CN209084162U (en) A kind of Large Underground pipeline anchor block
CN209066483U (en) A kind of assembled ecology retaining wall
CN203145011U (en) Anchor rod structure with anti-floating capacity
CN206245321U (en) Cut slope composite supporting construction
CN217078853U (en) Retaining wall for hydraulic engineering
CN206385502U (en) A kind of assembling-type precast channel revetment of rapid construction
CN211060926U (en) A work base observation mound for deep overburden
CN219753135U (en) Gardens waterscape revetment structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20210205

Address after: 201700 room 586, area F, 5 / F, building 1, 1288 Huateng Road, Huaxin Town, Qingpu District, Shanghai

Patentee after: Shanghai yedun Fire Safety Technology Co.,Ltd.

Address before: 201799 room 701, 7 / F, block B, building 4, 1777 Hualong Road, Huaxin Town, Qingpu District, Shanghai

Patentee before: YUEDAO INDUSTRY (SHANGHAI) Co.,Ltd.

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20210119

Termination date: 20210811